You are on page 1of 1
Pile load testing Ruwan Rajapakse, in Pile Design and Construction Rules of Thumb (Second Edition), 2016 24.2 Pile load test procedure + Compute the ultimate pile capacity based on soil mechanics theory. * Compute the design load using a suitable factor of safety (FOS) Ultimate pile capacity (U) Design load (D) = a * Generally, total test load is twice the design load (this could change depending upon local building codes). Total test load (Q) = 2 x Design load (D) In some sites negative skin friction is expected. In that case the following formula can be used: Total test load (Q) = 2 x (Design load + Negative skin fricti 4 » If negative skin friction is known with good accuracy, one can use the following equation: Total test load (Q) = 2 x (Design load) + Negative skin frict 4 » * Apply 12.5% of the test load and record the settlement of the pile every 2h. * Readings should be taken until the settlement recorded is less than 0.001 ft. during a period of 2 h. When the pile settlement rate is less than 0.001 ft. per 2h, add another 12.5% of the test load. Now the total load would be 25% of the test load. The settlement is monitored as previously. When the settlement rate is less than 0.001 ft. per 2 h, the next load is added. + The next load would be 259% of the test load. Now the total load is 50%. The load is increased to 75% and 100% and settlement readings are taken. * The load is removed in the same sequence and the settlement readings are recorded. At least 1 h time period should elapse during removal of loads. * Final settlement reading should be recorded 48 h after removal of the final load (Fig. 24.3). Settlement (in) Q=Test load 0250 03@ QO Load Sign in to download full-size image (24.3. Load versus settlement. Q, maximum test load; and maximum test load (Q) is twice the design load. Settlement is marked along the Y-axis. The settlement would increase during application stage of the load and would decrease during removal stage of the load. Gross settlement = the total settlement at test load (in this case it is 1.55 in). Gross settlement = settlement of pile into the soil + pile shortening * tis obvious that the pile would compress due to the load and as a consequence the pile would shorten. Net settlement = settlement at the end after the load is fully removed (in this case it is 0.4 in.). Net settlement = settlement of pile into the soil after removal of the load * When the load is released the pile would return to its original length. In a strict sense there may be a slight deformation even after the load is removed. In most cases it is assumed that the pile had come to its original length when the load is removed. * The pile load test is considered to have failed, if the settlement into the soil is greater than 1 in., at full test load, or the settlement into the soil is greater than 0.5 in., at the end of the test after removal of the load (Plate 24.1).

You might also like