Pile load testing
Ruwan Rajapakse, in Pile Design and Construction Rules of Thumb
(Second Edition), 2016
24.2 Pile load test procedure
+ Compute the ultimate pile capacity based on soil mechanics
theory.
* Compute the design load using a suitable factor of safety (FOS)
Ultimate pile capacity (U)
Design load (D) = a
* Generally, total test load is twice the design load (this could
change depending upon local building codes).
Total test load (Q) = 2 x Design load (D)
In some sites negative skin friction is expected. In that case the
following formula can be used:
Total test load (Q) = 2 x (Design load + Negative skin fricti
4 »
If negative skin friction is known with good accuracy, one can use
the following equation:
Total test load (Q) = 2 x (Design load) + Negative skin frict
4 »
* Apply 12.5% of the test load and record the settlement of the pile
every 2h.
* Readings should be taken until the settlement recorded is less
than 0.001 ft. during a period of 2 h. When the pile settlement
rate is less than 0.001 ft. per 2h, add another 12.5% of the test
load. Now the total load would be 25% of the test load. The
settlement is monitored as previously. When the settlement rate
is less than 0.001 ft. per 2 h, the next load is added.
+ The next load would be 259% of the test load. Now the total load is
50%. The load is increased to 75% and 100% and settlement
readings are taken.
* The load is removed in the same sequence and the settlement
readings are recorded. At least 1 h time period should elapse
during removal of loads.
* Final settlement reading should be recorded 48 h after removal of
the final load (Fig. 24.3).
Settlement (in)
Q=Test load
0250 03@ QO Load
Sign in to download full-size image
(24.3. Load versus settlement.
Q, maximum test load; and maximum test load (Q) is twice the
design load. Settlement is marked along the Y-axis. The settlement
would increase during application stage of the load and would
decrease during removal stage of the load.
Gross settlement = the total settlement at test load (in this case it is
1.55 in).
Gross settlement = settlement of pile into the soil + pile shortening
* tis obvious that the pile would compress due to the load and as
a consequence the pile would shorten.
Net settlement = settlement at the end after the load is fully
removed (in this case it is 0.4 in.).
Net settlement = settlement of pile into the soil after removal of
the load
* When the load is released the pile would return to its original
length. In a strict sense there may be a slight deformation even
after the load is removed. In most cases it is assumed that the pile
had come to its original length when the load is removed.
* The pile load test is considered to have failed, if the settlement
into the soil is greater than 1 in., at full test load, or the
settlement into the soil is greater than 0.5 in., at the end of the
test after removal of the load (Plate 24.1).