Millennium Erectors Corporation

9445 Retiro St., Guadalupe, Makati City

Project : Oriental Gardens Makati (Lilac Tower) Report No. : 062


Location : Don Chino Roces Ave. corner Export Drive, Makati City Date : March 5, 2014
Contract Package Shift : Day
Working Time : from 7:00AM to 4:00PM Weather : Sunny/Cloudy
Daily Construction Report
MANPOWER
Staff NO MH NO MH Equipments NO HRS.
1. Project Manager 1 8 1. Leadman 5 40 1. Cut off machine 1 8
2. QA/QC 2 16 2. Carpenter 1 8 2. Mini Dump Truck 1 8
3. Site Engineer 2 16 3. Mason 5 40 3. Circular Saw 1 8
4. Electrical Engineer 1 8 4. Tile Setter 3 24 4. Service Vehicle 1 8
5. Mechanical Coordinator 1 8 5. Welder 2 16 5. Power Washer 3 24

6. Cost Engineer 0 0 6. Laborer 68 544 6. Grinder 6 48


7. Safety Officer 1 13 Total 84 672 7. Auto level 1 8
8. Project Nurse 0 0 TRADECON 8. Mech.Concrete Vib. 2 16

9. CAD Operator 1 8 KALAYAAN 6 48 9. Transit 1 8


10. Timekeeper 1 10 ICC 29 232 10. Hammer Drill & Rotary 10 80

11. Foreman 1 8 ROSTRAM 7 56 11. Chipping Gun 1 8


Total 11 95 S&H 38 304 12. Welding machine 5 40
ARLO 16 128 13. Gondola 2 16

General Services NO MH YYD 4 32 14. Hand Drill 6 48

1. Spot Checker 2 26 V. ROQUE 10 80 15. Misting Machine 1 8


2. Electrician 1 13 G. S. GO 5 40 16. Cutting Tools 2 16
3. Electrical Aide 1 13 CARSON 6 48 17. Vacuum Cleaner 2 16

4. Line and Grade 0 0 CARDRIAN 10 80


5. L&G Helper 1 13 POLYGON 3 24

6. Warehouse Man 1 13 STELSEN 3 24


7. Warehouse Aide 1 13 SCHINDLER 6 48
8. Pump Tender 1 13 Total 143 1144
9. Utility 2 26 SUBCON
Total 10 130 FIVE STAR 3 24
CHER 65 520

Operator NO MH FRANCISCAN 2 16
1. Driver 1 13 BIO 101 3 24

Total 1 13 MIGHTY 49 392


FMPI 17 136

Total 425 3400 Prepared by :

NO MH Engr. June U. Patricio Jr.

Description of Activities Performed Today: MEC


GRAND TOTAL 531 4310
1. Masonry works @ GF to 33rd floor

2. Painting works Interior @ 29th/30th floor


3. Installation/Rectification of tiles @ 9th - 33rd floor Received by:

4.Puchlisting @ 9th-32nd floor

5. Ceiling works @ 9th - 32nd floor


DAAA
Millennium Erectors Corporation
9445 Retiro St., Guadalupe, Makati City

Project : Oriental Gardens Makati (Lilac Tower) Report No. : 002


Location : Don Chino Roces Ave. corner Export Drive, Makati City Date : August 24, 2011
Contract Package Shift : Night
Working Time : from to Weather :

Daily Construction Report


MANPOWER
Staff NO MH General Services NO MH Operator NO MH
1. Project Manager 1. Time Keeping 1. Driver

2. Superintendent 2. Warehouse 2. Tadano Oprt.


3. Site Engineer 3. Line & Grade 3. Backhoe Optr.

4. Quality Control 4. Electrician 4. Mini Loader Optr


5. Office Engineer 5. Utility 5. Genset Optr.

6. Autocad Operator 6. Leadman 6. Bulldozer Optr.

7. Safety Officer 7. Vibratory Roller Optr.


8. Project Nurse 8. Dumptruck Optr.

Total 0 0 Total 0 0 Total 0 0

Carpenter NO MH Welder NO MH Labor NO MH


1. Curanto 1. 1.

2. Total 2.

3. 3.
4. Steelman NO MH 4.

5. 1.

Total 0 0 Total 0 0 Total 0 0

Grand Total 0 0

Equipments NO HRS. Equipments NO HRS.


1. Backhoe
2. Mini Loader
3. L-300 FB

Description of Activities Performed Today:

Remarks:

Prepared by: Received by:

Jose P. Maaliw
MEC DAAA
\ NO MH
1. 5 87
Total 5 87