Professional Documents
Culture Documents
ENRICHMENT 3
FUEL FOR THOUGHT 5
NUCLEAR EVENTS 7
No. 5
NUCLEUS 1
Improving Cybersecurity at Nuke Plants 8
Volume 8
NUCLEUS 2
Bridge Crane Installed
Ahead of Planned Outage
14
SEPTEMBER/OCTOBER 2015
NUCLEUS 3
Rethinking Steel-Plate
Composite Construction
16
NUCLEUS 4
What’s Happening at
POWER-GEN International
23
NUCLEAR NEWS 26
A Publication
N
uclear power plants around the world are shutting down
and operating longer. Electricity prices either benefit If you ask around, talk to peers,
plant operators or can be the reason a plant closes. The and study the total life cycle of N-stamp valves,
industry is in a state of extremes and experts from around the ConvalÆ truly is the smartest choice.
world will be in Las Vegas to discuss what the industry must do
to overcome the setbacks as well as continue the momentum. Thatís not marketing hype.
Thatís based on decades of dramatic,
NUCLEAR POWER International 2015 runs December real-life experience in various nuclear power
generation applications around the world.
8-10 at the Las Vegas Convention Center. The conference and Check out User Group feedback, and see
if our claims are valid.
expo will feature three conference sessions and one mega-ses-
We also offer references, case studies,
sion sure to inform attendees about different issues affecting a 900-page Engineering Binder, world
class engineering and technical support.
the nuclear power generation industry.
Please contact us today at P.O. Box 1049,
The conference begins Tuesday, December 8 with the ClampsealÆ globe valves (above),
SwivldiscÆ gate valves (below left) and Somers CT 06071; phone 860.749.0761;
CamsealÆ zero-leakage, top-entry ball valves fax 860.763.3557; sales@Conval.com;
POWER-GEN International 2015 Keynote Address titled (below center and right) are global favorites.
shut down? day afternoon. It is a panel discussion Thursday. Topics include the outlook
Wednesday morning is the session that looks at the transitioning of the for nuclear in 2016, policy & regula-
titled “60 Years and Beyond.” Nuclear power generation industry. tion, challenges facing renewables, en-
Scan the QR Code for more information
power plants are being designed to There are also plenty of opportu- ergy storage and more. (877-4SI-POWER)
operate beyond the 40- and even 60- nities to network with other attend- I hope to see you at NUCLEAR NEW 8 7 7 - 4 7 4 - 7 6 9 3
www.structint.com/NPI
year timeframe, and experts will take ees. Monday, Dec. 7 is the Projects POWER International 2015!
Y
ou may not see them, but many tents are being pitched around the world. A number of by participating countries through the Kyoto
climate-related “circuses” are on the docket this year, and it’s an open question whether Protocol in 2000, run out in 2020.
the circus strong men will let nuclear completely under the tent or if nuclear will be Interestingly, the Paris organizers are calling
peaking in from the outside. for “contributions” rather than “commitments”
Circus No. 1 is the United Nations’ Sustainability Summit in New York in September, this time around, but the contributions have
which will establish sustainable development goals to guide policy and funding for the next to go further than existing commitments. In
15 years. The sustainable development goals are a follow-on to the millennium development somewhat of a marketing ploy, the Paris con-
goals formulated in 2000. ference is intended to spark a “race to the top.”
Energy is a core element of the proposed sustainable development goals: “Ensure access to While COP21 appears to be taking a relative-
affordable, reliable, sustainable, and modern energy for all.” And climate change gets prime bill- ly agnostic view on solution pathways, nuclear
ing as well: “We are determined to address decisively the threat posed by climate change and is not overtly part of the race. I didn’t find any
environmental degradation. The global nature of climate change calls for the widest possible mention of nuclear on the COP21 web site.
international cooperation aimed at accelerating the reduction of greenhouse gas emissions.” So I guess we can say Tent No. 2 is open,
Clearly, nuclear would have a role in this call for the “widest possible international coopera- but prime seating may not be available.
tion,” right? Apparently not. As part of the targets laid out in a draft document published ahead Circus No. 3 is the Clean Power Plan, the
of this year’s meetings, there is no mention of nuclear, although fossil energy gets a nod: “By pending U.S. regulation that would cut carbon
2030, enhance international cooperation to facilitate clean energy research and technology, in- pollution from the power sector by 30% from
cluding renewable energy, energy efficiency and advanced and cleaner fossil-fuel technology….” 2005 levels. The proposed regulation lays out
Tent No. 1 is looking rather exclusive. four building blocks for achieving this goal.
Circus No. 2 is the 21st meeting of the Conference of the Parties (COP21), or more simply, Nuclear qualifies under the third building
the Paris Climate Talks, scheduled for late November/early December. The goal of this gather- block – using more zero and low-emitting pow-
ing is to develop a new international agreement on climate – applicable to all countries – with er sources – but the extent of the contribution
an aim to keep global warming below 2 degrees C above pre-industrial levels. The current slate may be limited. In setting the carbon intensity
goal for each state, the proposed guideline treatment to some extent, for now at 12
already includes those nuclear plants in least, the flaps on Tent #3 are up, but
operation and those under construction. maybe only a few inches.
And for those plants under construction Some entities are trying to cast the
in Tennessee, Georgia and South Caro- tent support poles wider and raise the
lina, it assumes they are already operating flaps further. In early May, for example,
at 90% capacity factor, making the state’s the presidents of almost 40 scientific
carbon intensity goal more stringent than and international societies – represent-
it otherwise would be. ing 50,000 members and 36 countries
In a nod to the importance of nuclear, – signed the “Nuclear for Climate Dec-
the proposed rule recognizes that some laration” at the International Congress
nuclear plants are at risk of retiring due on Advances in Nuclear Power Plants in
to economic or other forces. The carbon Nice, France. The declaration calls on
intensity target, therefore, enables states all nations to deploy the “widest pos-
to add 6% of current nuclear electricity sible portfolio of low-carbon technolo-
generation to the denominator of each gies available, including nuclear energy,
state’s target. But at-risk plants are not in order to reduce carbon dioxide emis-
evenly distributed across states, and sions and meet other energy goals.” NuScale Power has created a new kind of nuclear power plant: one that is safe, reliable, and
economical. The innovative design incorporates all of the components for steam generation and
the at-risk factor may have other unin- Will that help? Theoretically, yes, heat exchange into a single integrated unit, the NuScale Power Module™ (NPM). Using up to
tended consequences. For example, if but the scientific community making 12 of these 50MWe (gross) NPMs, a NuScale nuclear power plant can provide 600 MWe (gross)
of safe, carbon-free, electrical generation. The compact design of the NPM allows it to be built and
a state lost all its nuclear generation, it such proclamations does not equate assembled in a U.S. factory, then shipped to a prepared site for easy deployment. The design
eliminates many costly, complex systems while cutting-edge manufacturing cuts time and cost
could replace only 6% of it with other to political action. We need those in
of production. The result: a power source that is simultaneously safe, reliable, scalable, carbon-free,
zero-carbon resources and still meet charge to understand one of the subtle and economical. Innovation: the Element of Nu™.
the intensity target, but total carbon attractions of the circus: that all the
emissions would increase. participants have their own acts, but
While there is reason to believe all are welcome under the big tent if NuScale Powerr
the final rule will modify the nuclear they can perform. wer
nuscalepower.com
m
© 2015 NuScale Power, LLC. All Rights Reserved.
S M T W TH F S
1 2 3
OCTOBER 2015 4-7
International Uranium Fuel Seminar
19-23
International Conference on Global
4 5 6 7 8 9 10
Park Hyatt Beaver Creek Emergency Preparedness and Response
11 12 13 14 15 16 17 Beaver Creek, CO Vienna, Austria
http://www.nei.org/Conferences/ http://www-pub.iaea.org/iaeameet-
18 19 20 21 22 23 24 International-Uranium-Fuel-Seminar ings/46533/International-Conference-on-
Research-Reactors-Safe-Management-and-
25 26 27 28 29 30 31 Effective-Utilization
15
Organizational Meeting of the Convention
on Nuclear Safety
Vienna, Austria
http://www-pub.iaea.org/iaeameet-
ings/50405/Organizational-Meeting-of-the-
Convention-on-Nuclear-Safety
S M T W TH F S
1 2 3 4 5 6 7 8-12 18-20
NOVEMBER 2015 ANS 2015 ANS Winter Meeting
and Nuclear Technology Expo
Licensing Forum
8 9 10 11 12 13 14 Omni Shoreham Hotel
Marriott Warman Park Washington, DC
15 16 17 18 19 20 21 Washington DC http://answinter.org/
http://answinter.org/
22 23 24 25 26 27 28
29 30 18-20
Workshop on Best Practices in Physics-Based Fault
Rupture Models for Seismic Hazard Assessment of
Nuclear Installations
Vienna, Austria
http://www-pub.iaea.org/iaeameetings/50896/Workshop-
on-Best-Practices-in-Physics-Based-Fault-Rupture-Models-
for-Seismic-Hazard-Assessment-of-Nuclear-Installations
Fundamental Issues:
Nuclear Generators Lead Cyber Security
ANDREW GINTER, VP INDUSTRIAL SECURITY, WATERFALL SECURITY SOLUTIONS
W
e have all heard the phrase “oh that’s for nuclear – they’re different.”
While nuclear is “different” in many realms, it is not so different in the
realm of industrial cyber security. Cyber-attacks, attack tools and the
attackers themselves only become more sophisticated over time. The risk of physi-
cal sabotage using a cyber-attack is common to nuclear and non-nuclear sites.
Yes, nuclear generators are more concerned than most about both physical and cyber
Waterfall Security’s unidirectional gateway is one
security, but the “sophisticated cyber-attacks” that nuclear generators were talking about of many ways businesses can keep computers and
five years ago are today encoded into publicly available, powerful and easy-to-use attack other technology safe from outside threats.
Courtesy: Waterfall Security
tools. These tools make yesterday’s “sophisticated attacks” accessible to large numbers of
hackers of modest talents, and even to unskilled “script kiddies.”
Nuclear generator security people have been talking about issues that are becoming integrity. Finally, try hard not to shut the the control system running correctly) and
equally troubling for the entire electric sector and for industrial control systems in all site down at all. Protect the site’s availabil- the third priority was confidentiality. In
industries. ity, because every hour the site is running the world of nuclear generators, though,
the bank reaps millions of dollars in trans- we never hear any of this “CIA vs. AIC”
SECURITY IS ALL ABOUT SAFETY action fees. terminology.
We can start with priorities. Industrial security standards and guidance published in the Common wisdom among control- The first priority at nuclear generators
early 2000s, such as the National Institute of Standards and Technology (NIST) 800- system security practitioners in the early was, is and always will be safety. Cyber
82r1 and International Electrotechnical Commission (IEC) 62443-1-1, all talk about 2000s was that, in the ICS world, this security breaches are systematic failures
“CIA” versus “AIC.” Conventional IT security priorities tend to be, in this specific or- triad is reversed. The highest priority for of safety equipment, not random fail-
der, confidentiality, integrity and availability (CIA). If the banking website starts leaking control systems was thought to be avail- ures, and so cannot be modeled by stan-
credit card numbers to the Internet, shut it down to protect confidentiality. If the site ability (keep the control system running), dard safety calculations. Cyber security is
starts letting people transfer money they don’t have, shut it down to protect database the second priority was integrity (keep therefore essential to safety; digital safety
systems are worthless if they are compro- compromised state, the compromise had American nuclear generators from deploy- nations, as well, either because of a similar
mised. The second nuclear security prior- to originate somewhere. Compromise al- ing firewalls to connect generating-unit regulatory imperative, or simply because
ity is always reliability: prevent damage to ways comes from “the outside.” It comes safety and control networks, directly or the technology provides such dramatic
the generating unit, and keep the lights from network attacks, software/malware indirectly, to any less-trusted network. As threat reduction benefits. Unidirectional
on. And yes, the third priority is confiden- coming into the control system, people a result, to balance between security and gateways permit information to leave in-
tiality. with malicious intent entering the secure operational needs, all American nuclear dustrial networks and are physically inca-
This “safety and reliability” wording is area to mis-operate the control system generators deployed unidirectional secu- pable of sending any message or any infor-
being discussed in a number of control- and hardware components with embed- rity gateway technology. Unidirectional mation back into protected networks to
system standards forums. Revision 2 of ded software crossing through the pe- gateways are deployed widely in other put those networks at risk. Unidirectional
the NIST 800-82 “Guide to Industrial rimeter.
Control Systems (ICS) Security” is the Classic network perimeter protection
first major standard to pick up the new in old-school ICS security standards is all
wording. Several other draft standards about firewalls. The problem with fire- NEED POWER FAST?
from different organizations are looking at walls is that they are porous by design.
this new wording, as well. It is the safety At their core, all firewalls are routers,
and reliability of the physical processes because all firewalls forward messages.
that are the cyber-security focus at most Some of the forwarded messages contain
industrial sites, not abstract CIA/AIC at- attacks, in spite of every firewall ven-
tributes of the industrial control-system dor’s best efforts to filter “good” packets
computers and networks. from “bad.” Fundamentally, every path
through a firewall intended to permit
1MW
1MW Emergency
Emer
Em erge
errgenc
genc
gency Ge
ncy G
Gene
Generator
ene
nera
era
r to
torr
SECURITY STARTS AT THE PERIMETER data to flow out of a control system net- Compact,
C lightweight,
t li ht i ht Flex
Fl 2 andd 3 compatible
tibll
ti
In a real sense, all cyber security starts work also allows attacks back into that Flex 2 - 9500 lbs., 14.5’ L. x 5.7’ W. x 8’ H.
Flex 3 - 8250 lbs., 14.5’ L. x 3.5’ W. x 7.5’ H. without trailer
at the cyber/physical security perim- “protected” network.
Portable by standard truck or helicopter, and sized
eter. If a control system ever makes the In 2010, the Nuclear Regulatory for commercial airfreight
transition from a trustworthy state to a Commission (NRC) effectively forbade Available in many Hz and Voltage configurations.
gateway hardware makes the gateways se- Security Agency (ENISA) control-system remote access to industrial sites echoed other nuclear generation jurisdictions
cure, and unidirectional server replication standards also recognize the strength of standard guidance for IT systems: use throughout the world.
software makes the gateways plug-and- unidirectional gateways. encryption, firewalls, two-factor au-
play replacements for firewalls. The 2014 French Agence nationale thentication and “jump hosts” – ma-
Since 2010, unidirectional gateways de la sécurité des systems d’information chines to terminate remote desktop
have been deployed widely outside the (ANSSI) ICS security standards go even or other interactive sessions outside
nuclear generation industry, and have ap- further. ANSSI groups control systems of the control system, and permit DEDICATED TO DELIVERING
peared in many ICS security standards into three classes, based on the impor- only connections from the “jump
and guidance documents. For example, tance of the industrial site. The standards host” machines to control networks.
CRITICAL POWER WHERE
the 2013 North American Electric Reli- permit the use of firewalls for only the The thinking was that if these mea- WE’RE NEEDED MOST.
ability Corporation Critical Infrastructure least important Class 1 networks. AN- sures were secure enough for corpo-
Protection Version 5 (NERC CIP V5) SSI states that all connections between rate networks, they should be enough
standards recognize the security of uni- the more important Class 2 networks and for control networks, as well. Bluntly
directional gateways in the definition of any less-trusted networks “should be uni- though, the problem with this ap-
the NERC term “External Routable Con- directional” toward the less-trusted net- proach is that corporate networks are
nectivity.” The standards relax roughly works. For the most important Class 3 not particularly secure.
one-third of the CIP V5 requirements for networks, ANSSI outright forbids the use In 2010, the United States’ Nu-
medium impact power plants with unidi- of firewalls. clear Energy Institute (NEI) NEI-
rectional gateways deployed, in recogni- The ANSSI standards make this point 08-09 guidance and the NRC-5.71
tion of the superior security provided by very clearly: firewalls are permitted for rules effectively banned interac-
the gateways. The proposed 2015 NERC partitioning networks at the same level of tive remote access to nuclear gen-
CIP V6 standards also include all of these trust, but may not be used to connect net- erator safety and control-system Custom engineered to meet each application’s
requirements, Fairbanks Morse engines provide Power Gen
exemptions and introduce additional ones. works at different trust levels. networks. Today, no American reliable, efficient power generation with low emissions.
Backed by genuine OEM parts and comprehensive,
The NIST 800-82r2, International Soci- nuclear generator permits such responsive service, Fairbanks Morse engines deliver
critical backup and primary power when and where it’s
ety of Automation (ISA)/IEC 62443-3-3, REMOTE ACCESS access. And again, similar rules needed most.
and European Network and Information Historically, guidance for interactive and practices are in effect in many See how we’re generating power and progress around
the globe at www.fairbanksmorse.com.
The rationale for banning remote ac- permit remote access, provided that IT- time, any medium that can store informa- • once files have been identified as prob-
cess is simple: there is no way to assure standard encryption, two-factor and oth- tion, can also store attacks and malware. ably “clean,” copy those files to a new
the trustworthiness of remote endpoints. er security controls are deployed, but this This is a serious problem. CD-ROM, and carry the CD-ROM
Modern attack tools and techniques rou- may change. The American Federal Ener- Nuclear generators have discussed this into the trusted network; and
tinely defeat anti-virus, security updates gy Regulatory Commission (FERC), in its risk at length, and, for now, have settled • as much as possible, try to load these
and other IT-centric protections. If a re- Notice of Proposed Rulemaking (NOPR) on a handful of security controls to deal CD-ROMs onto an isolated test-bed
mote laptop or workstation is compro- for the proposed CIP V6 standards, has with the risks of removable media: for functionality and security testing,
mised, no two-factor authentication, en- expressed concern about the adequacy of • When moving information from con- before loading them into live equip-
cryption or jump hosts will save us. A CIP V5/V6 controls for interactive remote trol systems to less-trusted networks, ment.
compromised endpoint computer is no access, and has invited comments from all use only brand new media – no excep- This entire process is viewed as high
longer running trusted software. Such a stakeholders as to what might be done to tions. The thinking is that any medi- risk, and nuclear sites strongly discourage
machine is going to do whatever its at- address these concerns. um exposed to a corporate network or use of this process at all. That said, though,
tacker wants the machine to do, not what Given the clear direction on the part other untrusted network is potentially sometimes the process is unavoidable,
the owner or operator wants the machine of the nuclear industry, and the strong in- compromised, and so untrustworthy. such as when control-system software
to do. If we trust a compromised machine dications outside of nuclear, the future of • When moving information from “out- components are being enhanced or up-
to operate any part of our control system remote access seems clear. Within a hand- side” networks into trusted networks: graded. Many in the nuclear community
remotely, we have handed our control sys- ful of years, expect remote access to be • use brand new media and expose it to view these current measures as interim
tem over to our attacker. permitted or recommended only for un- a minimum number of “outside” ma- measures and are evaluating alternatives,
What is the state of remote access out- important, expendable networks and ex- chines; such as unidirectional FLIP technology.
side of nuclear generation? ISA ICS secu- pendable industrial processes. • prefer to use CD-ROMS to USB Flash FLIP operates as a unidirectional security
rity training material describes remote ac- sticks, because of the risk of USB firm- gateway, except that it switches the ori-
cess technology as “high risk.” The 2014 REMOVABLE MEDIA ware compromise; entation on a scheduled, basis to enable
ANSSI standards “strongly discourage” Sometimes, removable media, such as • scan the media on at least one dedi- information to flow unidirectionally into
remote access for Class 2 networks, and USB Flash sticks and CD-ROMs, are es- cated anti-malware scanning machine, the protected network from time to time.
forbid such access for Class 3 networks. sential to the configuration and operation with at least four different anti-mal- In the wider world, concerns over the
The current NERC CIP V5 standards of industrial control systems. At the same ware engines; safety of removable media are only starting
to be discussed. The ISA/IEC 62443-3-3 2 and Class 3 networks are required to do security concerns include recent reports security provisions for a future revision of
and the proposed NERC CIP V6 stan- what nuclear generators do today. Individ- that nation-state intelligence agencies had the CIP standards. FERC’s stated reason
dards contain only vague IT-like provisions ual sites are also deploying unidirectional inserted remote control radio components for the coming order is “recent malware
for managing removable media, roughly FLIP technology to automate these anti- into brand new computers that were in- campaigns targeting supply-chain ven-
amounting to “use removable media only virus checks and other security controls tercepted in transit between a distributor dors.” This is presumably a reference to
on systems with anti-virus software in- and even further reduce the use of remov- and a customer, and concerns about CPUs recent “watering hole” attacks, where con-
stalled.” The 2014 ANSSI standards are able media on industrial systems. and vulnerable firmware embedded in trol-system vendor websites were hacked
more specific. ANSSI encourages Class Thus, it seems that stronger controls for USB devices. to distribute malware, as well as legiti-
1 networks to do what nuclear genera- removable media on non-nuclear control The 2010 NEI and NRC rules require mate control-system software updates. In
tors do today. The less-expendable Class systems are coming, but are somewhat “measures to protect against supply-chain addition, while NIST 800-82r2 provides
further in the future than remote access threats,” including trusted distribution
REGISTER TODAY!
WWW.NUCLEARPOWERINTERNATIONAL.COM
and unidirectional gateway controls. paths, vendor validation and tamper-proof
seals. These measures are more easily re-
SUPPLY-CHAIN PROTECTION quired than delivered, though, especially
Historically, industrial supply-chain for cheap, high-volume USB components,
concerns were focused on safety. There including Flash sticks, keyboards and
have been cases where distributors were mice. How to maximize the effectiveness
found to be selling, deliberately or inad- and minimize the cost of addressing sup- ESI-Energy Consultants’ (ENERCON’s) in-house staff numbers more
ADVANCING CLEAN ENERGY vertently, equipment that claimed a high ply-chain risks are open issues and topics
than 1,600 including experienced professionals with advanced
degrees, professional licenses and certifications. Our key personnel
and associates average over 20 years of experience in project
Safety Integrity Level rating, when the of frequent discussion in nuclear security engineering and regulatory compliance. When operating experience
In nuclear generators, supply-chain in- in the non-nuclear world are only just be-
OWNED & PRODUCED BY: PRESENTED BY: SUPPORTED BY:
ESI-Energy Consultants
tegrity discussions have expanded in recent ginning. In the FERC NOPR for NERC
Enercon Services, Inc. (USA), doing business internationally as ESI-Energy Consultants
years to include control-system computer CIP V6, FERC gives notice of its intent
500 TownPark Lane Kennesaw, GA 30144
components of all types. Supply-chain to order NERC to develop supply-chain t +1 770.919.1930 f +1 770.919.1932
enercon.com
no specific measures for ICS supply-chain and supply-chain protection are issues
protection, the standard does refer read- are on the horizon for all “important”
ers to supply-chain security controls listed industrial sites. In short, control-system
in the IT-focused NIST 800-53. security standards from many authori-
ties are evolving rapidly to reflect and
LOOKING FORWARD address modern attack capabilities that
Once again, because cyber-attack tools nuclear generators have been dealing
and cyber-sabotage tools only become with for years.
more powerful and easier to use over time, Today, the real questions facing all
what was regarded yesterday as a sophisti- electric-sector owners and operators are
cated attack that only the most important
nuclear control systems must address, is
“which of our sites are important enough
to protect with modern security mea-
ADVANCING CLEAN ENERGY
likely to be regarded tomorrow as a perva- sures?” and “which of our sites are ex-
sive, universally available attack capability pendable enough to continue protecting
that all industrial sites must consider. against only yesterday’s attacks?”
Today, in many industries, safety, reli- Really – are any of our industrial sites
ability and equipment protection priorities expendable?
against remote access. Unidirectional lutions, a provider of Unidirectional Securi- DECEMBER 8–10, 2015 provides for our health, economy and environment.
p
munications that are so valuable to mod- of control system software products, control
ern enterprises. system middleware products and industrial
In addition, removable-media controls cybersecurity products.
R
etrofitting nuclear power plant turbines has a positive impact The AEP team was keenly aware of the
on long-term plant reliability and performance. In the case of 2013 accident at Arkansas Nuclear 1 in
the Donald C. Cook Nuclear Generating Station in Michi- which the stator of the unit’s old genera-
gan, a retrofit has been scheduled to support plant operation beyond tor fell during a maintenance procedure.
the current license period. Achieving the long-term benefits of this To prevent a similar incident during the
retrofit presented some short-term challenges. Turbine retrofit proj- bridge crane installation, AEP began
ects are costly, complex and, when not properly managed, can result planning for this project in 2012.
in lengthy outages. Knowing this, American Electric Power (AEP) AEP and its engineering partner de-
employees at the plant were looking for ways to minimize outage veloped an installation solution using a
time for the upcoming retrofit scheduled for 2016. unique method for component rotation
Among the projects to effectively execute the retrofit was the in- in an operating plant that was less in-
stallation of a second bridge crane in the turbine building. The crane vasive to plant structures. The innova-
would be used to move much of the heavy material needed to per- tive approach used multiple telescoping
form maintenance on the turbine, while allowing the existing large gantry systems and a hydraulic turn-
Day & Zimmermann and AEP installed a second bridge crane in the operating Cook turbine crane to be free to support other outage activities. Typically, table to safely lift and rotate compo-
nuclear plant in advance of a planned maintenance outage.
this installation would be planned into the outage and could take up nents for the 250-ton bridge crane. The
to 10 days to complete. Additionally, standard industry practices include a labor-intensive solution that would involve either the par- configuration of the gantry system used in
tial removal of the turbine building roof or the removal of the end wall to allow for materials to be brought into the turbine building. this project was an engineered temporary
AEP Manager of Projects Scott Dailey and his team wanted to see if they could find a way to eliminate this extra outage time lift assembly. Two 88-foot girders weigh-
by installing the additional crane while the plant remained online. To do this, they would have to develop a unique approach ing as much as 110,000 pounds each were
that minimized risk to the station and maximized efficiency. In 2012, with the retrofit outage still years away, AEP turned to its lifted 60 feet above the turbine floor and
engineering and crane partners and to its on-site maintenance contractor Day & Zimmermann for solutions. placed in position on the existing crane
LAS VEGAS, NV
rails between two operating units. The gantry lifts were constantly
#POWERGEN
Because this was a first-of-its-kind ap- monitored by LED levels and survey-
plication, a proof of concept was required. ors at multiple stations to confirm the
THE WORLD’S
In January 2014, about six months be- operation remained within established
fore the crane’s scheduled installation, limits. The stability of the configured
LARGEST
the project team, which included AEP, system was validated along with the
various crane and installation vendors, operating team’s ability to control the
and Day & Zimmermann, worked with loads within levelness criteria.
the utility to perform an off-site lifting Following the planning phase, AEP
demonstration. The team simulated
each major component lift and position-
worked with its vendors to complete
the actual installation. The project was POWER GENERATION EVENT
ing movement. The demonstration was completed on time and under budget
done outside which added weather ele- with no safety incidents. Collabora-
ments to a process that would ultimately tion between Day & Zimmermann,
be completed indoors. Additionally, the AEP and the other project vendors NETWORK WITH 22,000 ATTENDEES
load was intentionally taken beyond the
operational limits established to confirm
was a key component in delivering a
safe and efficient installation. From
VISIT WITH 1,400 EXHIBITORS
there was sufficient margin to manage start to finish, the project took 18,000
LEARN FROM 400+ INDUSTRY SPEAKERS
potential negative scenarios during in-
stallation. ASME NQA-1-2012 requires
work hours.
REGISTER TODAY!
a dynamic load test equal to 110 percent THE RESULTS
of the rated load, but the AEP team chose Keeping the plant online during the OWNED & PRODUCED BY: PRESENTED BY: SUPPORTED BY:
to proceed with a more conservative 125 installation saved AEP significant time
percent rated load test because of the risk and money. The second bridge crane is
involved with performing these lifts on now a permanent fixture in the turbine
the turbine deck between two operating building, and will help AEP save time
units. and money in future outages.
obvious benefits of modular construc- for also delivering increased resiliency the construction schedule has been tra- demonstrated that the total construction
tion leading to schedule contraction. As and sustainability benefits. ditionally prolonged due to extensive time can be reduced to about four years
illustrated in Figure 1, the steel face- and complex rebar cage fabrication, erec- for new plants (see 2001 DOE report en-
Figure 1a Reinforced Concrete
plates serve as formwork during con- tion, and disassembly of elaborate con- titled “A Roadmap to Deploy New Nuclear
crete placement, and through compos- crete formwork. A 2004 report by the Power Plants in the United States by 2010,
ite action enabled by shear connectors U.S. Department of Energy, “Study of Volume II”), compared to a typical dura-
they also serve as equivalent reinforcing Construction Technologies and Schedules, tion of five to six years. A four-year con-
rebar
steel (rebar) during the service life of the O&M Staffing and Cost, Decommission- struction duration is also the target for
concrete
structure. The use of faceplates thus ing Costs and Funding Requirements for the upcoming new generation of nuclear
form
eliminates formwork and rebar while Advanced Reactor Designs”, conserva- plants in the U.S.
facilitating fabrication of large empty tively estimates that use of SC Westinghouse Electric Corp. (WEC)
modules that can be brought to their fi- Figure 1b Steel- Plate Reinforced Concrete modules in place of conven- has incorporated SC modules for walls
nal location in the field for expeditious tional reinforced concrete can and floors of its AP1000 plant internal
steel plate headed stud
concrete placement (see Figure 2). Such tie bar reduce total construction time structures, and was the first to incor-
(e.g., 4.5-6.0mm)
modular composite construction ap- sleeve for piping by at least several months. SC porate them in a certified design (see
proach has already been incorporated by embedded plate modules typically have steel WEC’s design certification document,
some standard plant suppliers, and now on the outside to act as stay-in- DCD, for AP1000 standard plant).
concrete
with the impending issuance of the first place formwork and equivalent A typical wall module panel for the
(AISC-issued) US consensus standard rebar, thus eliminating the as- AP1000 plant containment internal
for its design, SC construction usage is Illustrations of RC and SC Construction for walls (from MPR-2610, a sociated labor and schedule-in- structures is shown in Figure 3. Figure
likely to expand further. report to DOE) tensive activities. Extensive use 4 shows a pre-assembled internal struc-
The schedule advantage of SC con- of prefabrication and modular ture SC module. WEC also extended
struction is well understood, and is the BACKGROUND construction in Asian power plants has the use of SC modules to the AP1000
prime reason for its expanding embrace Nuclear power plant construction in- already significantly expedited construc- shield building to make it resilient
in the nuclear industry. The use of large volves extensive use of reinforced con- tion times, reduced overall costs, and against aircraft impact, which is a stipu-
scale and well planned/executed SC con- crete (primarily because it is a cheap op- optimized energy and material use. In lated beyond-design-basis (BDB) event
struction offers a promising opportunity tion for radiation shielding). As a result, Japan, use of modular techniques has for new nuclear power plants.
during initial construction; minor pen- both faces; SC walls leverage these designed into the system by considering/ per hour will typically ensure that a 10
etrations can be handled relatively eas- liner plates by making them struc- stipulating the anticipated handling/rig- psi pressure limit will not be exceeded
ily during service life. tural steel reinforcement and leak- ging loads. Since large modules are very unless the concrete is a very slow-setting
• Major attachments (e.g., for large bore age barriers for the walls). heavy and have complex geometries, type and/or placement temperatures are
pipe supports) can be easily incorpo- There are several considerations that large crane capacity and specialized rig- low. Increased pour rate and/or design
rated during initial construction. are unique to SC construction. They are ging supervision is needed at the site to for slower setting concrete mixes (e.g.,
• Minor/moderate attachments to discussed below. ensure safe handling. due to cement substitutes such as fly
faceplates can be easily handled Degree of Modularization and Mod- Concrete Placement: Free-fall place- ash) can be accommodated by having
during service life (e.g., for small ule Fabrication Process: The full promise ment method works well for placing closer spacing of tie bars in the modules.
pipe and conduit supports) since the of SC construction is better realized if normal concrete between the faceplates. Concrete drop height is another
faceplates serve similar function as large modules are used. Prefabrication However, self-consolidating concrete consideration. The quickest method of
embed plates (unlike SC construc- of large modules is ideally accomplished (SCC) may need to be used for concrete concrete placement for modular wall
tion, they have to be specifically at a shipyard facility in preparation for placement in congested areas, such as in construction is use of a simple drop
provisioned in RC construction). module delivery by barge to the con- wall-to-floor and wall-to-basemat joint. technique that also ensures good con-
• High in-plane membrane (axial and struction site. Even if access to existing The rate of concrete placement, which solidation. A drop height of 10 to 20 feet
shear) strength and ductility are shipyards is available, delivery by barge affects the magnitude of wet concrete is recommended. Specially located pour
achieved. can difficult because many candidate pressure, is another parameter that must ports are needed if the module height
• Improved resistance to out-of-plane sites do not have barge access. In such be controlled (as in any other formwork exceeds 20 feet. Smaller aggregate size,
(bending and shear) loads. cases, an onsite fabrication shop could be design). Typically, the steel faceplates are made from hard rock, is preferable to
• No curing is needed for SC wall con- set up to further assemble truckable SC designed for 10 psi pressure when act- ensure good placement using the drop
struction since the faceplates prevent panels into larger modules. ing as forms. Excessive pressure not only technique. Specialized placement tech-
loss of moisture. Module Design for Construction Loads: causes high stresses in the plates, but can niques may be used in potentially con-
• Faceplates provide leaktightness, It is important that the modules be de- also lead to excessive permanent defor- gested areas, such as wall-to-floor and
which protects concrete during ser- signed for anticipated handling and rig- mation (bulging) that can be undesir- wall-to-basemat joint locations.
vice life (liner plates are already ging loads. Empty modules have lower able from both aesthetic and functional Fabrication/Welding/Field Fit-up: Mod-
needed for applications where a wall strength and stiffness; therefore, ade- standpoints (e.g., for making baseplate ules are formed by splicing adjoining SC
is in contact with water on one or quate strength and stiffness need to be attachments). A pour rate of 6 to 8 feet panels made from plates that may be
about 8-10 ft wide and 40-60 ft long. A 2004 report by the U.S. Depart- of steel faceplates divided by the total environment (e.g., interior v/s exte-
Module fabrication is generally accom- ment of Energy ... conservatively thickness of SC wall) is kept between rior walls and underground walls).
plished in a shop. Various modules are estimates that use of SC modules 2 percent to 4 percent. • Resiliency against Exposure to Fire:
then installed in the field and connected in place of conventional reinforced • Resiliency for Accident Thermal Loads: The faceplate that gets exposed to
with each other, or with other structural concrete can reduce total construc- The accident thermal load, resulting fire loses strength and stiffness; how-
elements such as basemat, using special from a loss-of-coolant or mains steam ever, similar to RC construction, the
tion time by at least several months.
connection methods. The field erection break event, leads to exposure to el- bulk of concrete and the opposite
and connection require dealing with fit- The presence of faceplates naturally evated temperature for sustained du- faceplate maintain good strength
up and tolerances, similar to tank and leads to increased missile and blast ration. This loading poses some more and stiffness. As such, SC structures
vessel construction. The fit-up issues resistance. These attributes can challenge to SC members since the have better fire resistance than pure
can be minimized using good weld- be enhanced with better design of faceplate is immediately exposed to steel structures; however, the fire re-
ing practices (even minimizing welding faceplate tying system in terms of the elevated temperature, i.e., there sistance can be enhanced if suitable
where possible) and through smarter de- strength, spacing, and ease of fabri- is no concrete cover. A seismic event fire protection coating is applied to
sign of connections. cation of tie-bars. could occur during such extended the faceplate(s) or fire-resistant steel
• Resiliency for External Hazard Loads: exposure, which is a BDB consider- is used. The member’s strength and
RETHINKING SC CONSTRUCTION IN SC construction generally results in ation. Performance against these sce- stiffness during fire exposure can
TERMS OF IMPROVED SUSTAINABILITY increased strength and ductility (for narios can be improved by using full also be improved by embedding an-
AND RESILIENCY comparable amount of rebar/steel strength connections, steel or fiber other steel plate within the concrete,
SC construction has certain natural ben- density per unit volume of concrete). reinforced concrete, or fire-resistant i.e., between the faceplates.
efits related to resiliency and sustainabil- This naturally leads to higher margins steel plates. The following considerations apply
ity. As discussed below, some of these against design basis external hazard • Durability and Long Service Life: The for improved sustainability of SC struc-
benefits can be further realized with ad- loads (e.g., seismic, high wind). This faceplates provide leaktight protec- tures:
ditional design features and construction benefit can be best realized if full tion for concrete. However, just • Field Labor Force Reduction: SC con-
planning. strength connections are used to join like any steel structure, the exposed struction requires smaller field labor
The following considerations apply SC elements with other connected steel surfaces need to be protect- force compared to conventional SC
for improved resiliency of SC structures: members (e.g., basemat) and if the ed from corrosion. The protection construction because of elimination
• Resiliency for Missile and Blast Loads: steel ratio (i.e., combined thickness scheme will depend on the service of activities related to formwork,
rebar election, and curing. As in any substitutes like fly ash, pozzolans, Figure 4
process during service life and
modular construction, the degree of or slag is always desirable from sus- after decommissioning. Faceplate
field labor reduction depends on the tainability standpoint. The slow surface treatment and material
extent of modularization and the size setting pace of cement substitutes selection can be especially based
of modules. Use of automated weld- can be easily handled in SC design on ease of decontamination. This
ing techniques, field bolting can help by ensuring that the faceplates are is a sustainability consideration
further in this regard. With maxi- adequately designed as formwork in terms of controlling potential
mization of field labor reduction, (the slow setting pace can be prob- spread of radioactive materials.
there is a commensurate reduction lematic in conventional RC con- • Potential for Recycling: Unlike rebar
in the carbon footprint associated struction in that the form stripping in RC construction, the steel face-
with mobilization, demobilization, and subsequent placement activi- plates can be more easily removed
and daily life of field labor force, etc. ties have to be delayed until the and recycled. Also, the concrete
• Reduction of Water Usage: SC con- concrete gains sufficient strength). can be pulverized and used in rub-
struction does not have rebar con- • Prolonged Service Life: SC struc- blized pavement construction.
gestion issues such that the amount tures will have long service life pro- • Reduced Energy Use during Construc-
of water used in concrete mix design vided that potential for steel plate tion: SC construction has reduced
Example of Large Pre-Assembled Module in AP1000
can be reduced without sacrificing corrosion is addressed. Depend- Plant (from AP1000 DCD) need for concrete compaction (con-
placement quality issues. Also, be- ing on the application (e.g., under- solidation using vibrators) since the
cause no curing is required, the as- ground wall or just exterior wall efficient in the long run. free fall placement method gener-
sociated water usage is eliminated. exposed to atmosphere or walls • Surface Decontamination: ally leads to well-consolidated con-
• Use of Green Concrete or Cement exposed to water), certain types of The ability to decontaminate the crete. Also options for field bolting
Substitutes: Cement is an energy- stainless steel can be used advan- exposed surfaces and the effort can be maximized to reduce energy
intensive ingredient of concrete. tageously. Compared to surface required to do so is an important consumption during construction.
Green concrete mixes, involving treatment options (e.g., cathodic consideration in any nuclear facil- • Material Savings in Steel and Con-
replacement of cementitious mate- protection or surface coatings), the ity. The presence of faceplates crete Quantity: Owing to their
rials or naturally occurring cement stainless option may be most cost lends for easy decontamination higher strength and radiation shield
capability, SC member design can the field (aside from the resulting LARGE SCALE
RENEWABLES TRACK UTILITY INTEGRATION TRACK
be optimized to produce reduced schedule contraction). Covers baseload and multi- Covers permitting, regulation,
megawatt-scale renewable energy interconnection and other grid
amount of steel and concrete com- • Use/Reinvigoration of Nation’s Ship- projects, policies and applications impacts of renewable energy
pared to comparable RC member. yard and Fabrication Facilities: Fabri-
This aspect has to be exploited dur- cation of SC modules could be per-
ing the design phase, which is often formed at a shipyard facility or at a
not done in SC design. The quanti- steel fabricator shop experienced
ty reductions have obvious sustain- in nuclear related steel fabrication.
ability implications. This will be a boost for idled or un-
• Elimination of Water-Stops and Rebar der-utilized fabrication facilities, and
Accessories: Unlike conventional RC will provide new job opportunities.
construction, SC construction has
no need for water-stops (because of CONCLUSION DISTRIBUTED ENERGY RENEWABLES IN THE
its inherent leaktightness) and ac- Resiliency and sustainability are highly RESOURCES (DER) TRACK DEVELOPING WORLD TRACK
Covers smaller commercial and Examines how renewable energy
cessories such as rebar chairs. This desired features for future nuclear pow- behind-the-meter renewable is uniquely positioned to bring
energy applications, technologies electricity to the millions of
results in reduction of the rubber er plant structures. There are a few con- and policies people worldwide who suffer
from energy poverty
and plastic based materials, which struction options to incorporate these
HYBRID SOLUTIONS TRACK
is good in terms of sustainability. considerations. The SC construction Looks at how different energy generation technologies
work together with a major focus on energy storage
• Increased Potential for Modular At- option provides certain inherent benefits
tachment of Supported Commodi- related to schedule and material savings,
Renewable Energy World Conference & Exhibition North America 2015
ties: The SC modules can be de- and provides strong promise for many December 8-10, 2015 / Las Vegas Convention Center, Las Vegas, Nevada
signed to further enhance the ability attributes related to resiliency and sus- www.renewableenergyworld-events.com
to support/attach piping/equipment tainability. The resiliency and sustain- Owned & Produced by: Presented by: Supported by: Media Sponsor:
I
t’s the largest annual forum for the power generation industry. features five conferences
More than 21,000 industry professionals from around the world will gather and four exhibitions under
in Orlando for POWER-GEN International 2015, where innovative and cost- one roof. All together, more
effective solutions for maintaining, operating and building new power generation will than 300 speakers will be
be shared Dec. 8-10 at the Las Vegas Convention Center. featured in nearly 80 confer-
More than 1,400 exhibiting companies from every sector of the industry will be ence sessions during Power
showcasing their products and services on the exhibit floor. The exhibition opens at Generation Week.
11:30 a.m. Tuesday following the keynote session. At POWER-GEN, 33
Steven Edwards Stuart Hemphill
POWER-GEN International offers a wealth of networking opportunities with conference sessions will be
leading professionals and key decision makers. More than 200 speakers will share their held under seven tracks:
thoughts on trends, technology and project development in 43 conference sessions. A Emissions Control; On-Site
wide range of topics, from emissions control to gas turbine design, will be discussed Power; Plant Performance;
by high-ranking regulators, developers, power producers and industry representatives. Gas Turbine Technologies;
The keynote session on Dec. 8 will feature five high-ranking executives: Steven L. Microgrids, Storage & Vir-
Edwards, chairman, president and CEO, Black & Veatch; Robert Flexon, president and tual Power Plants; Industry
CEO, Dynegy; Steve Berberich, president and CEO, California ISO; Stuart R. Hemp- Trends/Competitive Power
hill, senior vice president, Power Supply and Operational Services, Southern California Generation; and Power Proj-
Edison; and Victor Abate, president and CEO, Power Generation, GE Power & Water. ect Financing. Robert Flexon Victor Abate
in diameter) are used to condense the 1935, thousands of men and their fami- the Tour Center, where you can view Eligible attendees must take their en-
steam back into water to be reused in lies came to Black Canyon to tame the the river flow, the lake and the massive try card to the booths of the sponsoring
the plant. The Chuck Lenzie Generat- Colorado River. It took less than 5 years expanse of the Hoover Dam. companies, have it stamped by the spon-
ing Station is part of a 2,250-megawatt to build the largest dam of its time. soring exhibitors and return the card to
three-plant complex, which includes the Now, 70 years later, Hoover Dam PRE-CONFERENCE WORKSHOPS the PennWell booth prior to the drawing.
Harry Allen and Silverhawk Generating still stands as a world-renowned struc- Attendees of POWER-GEN and Renew- As always, you must be present to win.
Stations. ture. Hoover Dam is a National Historic able Energy World North America can
The plant can produce enough elec- Landmark and has been called one of also choose from 31 Competitive Power GOLF
tricity to serve approximately 665,000 the Seven Engineering Wonders of the College pre-conference workshops on Also, a golf tournament will be held
Nevada households. The dry-cooling Modern World. This engineering project Sunday Dec. 7 and Monday Dec. 9. Monday, Dec. 7, at the Desert Pines
system enables the combined-cycle plant not only enabled the industrial develop- Some of the workshop topics include Golf Club.
to make the same amount of electricity ment of the Pacific Southwest, but it also “Effective Project management for the Desert Pines Las Vegas was named a
with a mere 7 percent of water used by forms Lake Mead, the largest man-made Power Project Professional,” “Outage best upscale golf course in “Golf Digest
conventional water-cooled facilities. The reservoir in the Western Hemisphere. Management Processes, Skills and Tools Top 50 Resort Course.” Desert Pines also
facility uses a wastewater treatment sys- Before your guided tour of Hoover Improvement Workshop,” Distributed was host to the Golf Channel’s Big Break
tem that recaptures and recycles about Dam, you will have a short presentation Generation: Wining the Interconnec- II. From championship tees to three sets of
75 percent of the water used in the pow- on how the west was won with water and tion,” “Project Risk management in Pow- tee areas, Desert Pines Las Vegas offers a 71
er production process. give you some background history on er Construction,” “Quantitative Risk par course spread over 6,810 yards that is
the building of the magnificent Hoover Analysis in Power Construction,” and the perfect balance between challenge and
Hoover Dam Dam. Next, your guide will take you “How to Develop a Viable 316(b) Phase fun. The generous mounding separates the
Just a short drive from the glitter and over 500’ down one of our enormous el- II Compliance Approach.” fairways which can result in lucky breaks
glamour of Las Vegas, the Hoover Dam evators to the Nevada wing of the power from those errant shots and keep the game
is a testimony to America’s ability to plant, where you overlook the massive WIN A CORVETTE amusing and fun for all skill levels.
construct monolithic projects in the 7-story tall generators. A car will again be given away this year. For complete conference, exhibition
midst of adverse conditions. Built during From there you will go on your own The drawing for a 2016 Corvette will and registration information, visit www.
the Great Depression between 1931 and out to the Observation Deck on top of be Thursday, Dec. 10. Entering is easy. powergenerationweek.com.
NRC Issues White Finding ensure the plant would remain in safe shut-
down.
GNF Nuclear Reactor Fuel
for Entergy Nuclear Power NRC said Entergy officials failed to ensure Innovation Approved by NRC
Plant in Louisiana that a control room simulator used to train Sept. 11
Sept. 11 reactor operators was capable of reproducing The U.S. Nuclear Regulatory Commission
The U.S. Nuclear Regulatory Commission all of the challenges the operators might en- approved Global Nuclear Fuel’s (GNF) lat-
(NRC) issued a white finding to the River counter during a specific unplanned reactor est innovation for boiling water nuclear reac-
Bend nuclear power plant in Louisiana. shutdown scenario, an NRC official said in a tors (BWR). GNF is a joint venture with GE
River Bend was operating at 85 percent statement. As a result, operators took actions (NYSE: GE), Hitachi Ltd. (NYSE: HIT) and
capacity on Christmas 2014 when the plant that complicated the plant’s response. Toshiba Corp.
automatically shut down. After the shut- NRC conducted a special inspection to NSF channels are designed to reduce
down, there were issues with the plant’s better understand the circumstances sur- channel bow and control rod blade inter-
feedwater system, and several electrical cir- rounding the event and review corrective ac- ference, which reduces the need for opera-
cuit breakers also failed to operate proper- tions. NRC determined the finding as a white, tional testing. It was built with a propri-
ly. Operators took compensatory actions to or one of low to moderate safety significance. etary combination of zirconium, niobium,
Officials with plant operator Entergy (NYSE: tin and iron to be resistant to fluence gra-
ETR) agreed with the finding. dient bow and shadow corrosion induced
“The identified issues have been corrected bow.
to ensure that conditions in the simulator ac- NSF channels were first made available in
curately reflect conditions in the plant, and lead use assemblies in 2002. Since then, more
River Bend Station remains safe and secure,” than 300 NSF channels have been loaded into
Entergy said in a statement. “Entergy did not BWR plants. The channel material is available
request a regulatory conference and will not in reload quantities starting with outages in
contest the finding. This will not impact the spring 2016. NSF will be standard on GNF3
plant’s regulatory status in relation to the bundles, which are slated for full reloads in
NRC’s Action Matrix.” 2018.
EPRI Qualifies Areva power plant through May 2018 and the reliability of our electric system,” said 1,800 people directly, and are respon-
Nuclear
Sept. 10
Inspection Tools Byron nuclear plant through May 2019.
The utility said all of its nuclear plants
Chris Crane, Exelon president and CEO.
“However, these plants are long-lived as-
sible for an additional 7,500 indirect
jobs in the state,” said Richard Myers,
The U.S. Electric Power Research In- in the PJM market cleared the transition sets with decades of useful life left, and NEI’s Vice President for Policy Develop-
stitute (EPRI) qualified three of Areva’s capacity auction for the 2017-18 plan- today’s decision is only a short-term re- ment and Planning. “The two facilities
automated inspection tools for examin- ning year, and that it will defer any de- prieve. Policy reforms are still needed produce $3.1 billion a year in total eco-
ing nuclear steam generators. cisions about future operations of Quad to level the playing field for all forms of nomic value for the state, according to
Areva’s AIDA3, MIRA3, and WTT Cities and Byron, which the companies clean energy and best position the state an economic analysis conducted by NEI.
tools have all received EPRI’s Automat- considers economically challenged. The of Illinois to meet EPA’s new carbon re- In addition to this immense economic
ed Analysis Performance Demonstration auction results take effect in June 2017. duction rules.” value, these nuclear energy facilities are
Database (AAPDD) qualification and The decision to defer the retirements Exelon said it plans to bid all of its essential if Illinois hopes to reduce its
are now available to the U.S. nuclear en- comes after analysis of the present and eligible nuclear plants into the 2019-20 carbon emissions. Quad Cities and By-
ergy market. future economics of the plants, taking PJM capacity auction held next year. ron produce 34.6 billion kilowatt-hours
The tools are designed to mimic hu- into consideration the constructive mar- PJM holds a capacity auction each year of carbon-free electricity every year—
man data analysis at accelerated com- ket trends from the PJM capacity auc- to ensure enough power generating re- more than three times the state’s entire
puter speeds, which provides repeat- tion reforms. sources are available to meet demand in production from renewable energy.”
ability and reliability in nuclear steam All of the nuclear plants have also the region that covers 13 states and the
generator eddy current non-destructive cleared the transition capacity auction District of Columbia.
Former Nuclear Plant Site
to Host Solar Power Plant
examination. for the 2016-17 planning year, but Quad The Nuclear Energy Institue (NEI)
Cities, Oyster Creek and Three Mile Is- said in a release that, although the deci-
Exelon Defers Retirements land nuclear plants did not clear the ca- sion is temporary, it is a good step for the Sept. 10
Each nuclear power plant receives ei- in 2007 dollars, of which $539 million is the 1,405-MW third reactor at its Angra
ther a mid-cycle assessment or annual allotted for delays and other costs. Total nuclear power plant while the company
assessment letter along with an NRC in- project capital cost is now estimated at faces a corruption investigation.
spection plan. The reactors under con- $5.2 billion in 2007 dollars, which is the The stated-owned utility announced
struction at Summer, Vogtle and Watts portion to be covered by utility South it would suspend the contract for 60
Bar receive annual oversights. Carolina Electric & Gas. days. Construction firms Andrade Guti-
The two Westinghouse AP1000 re- errez and Techint Engenharia asked Ele-