Professional Documents
Culture Documents
Abstract: In this paper, using probabilistic evaluation based on Monte Carlo method, back flashover rate and shielding failure
flashover rate of 230kV overhead transmission lines in the west regions of Iran are evaluated. To such aim, first, number of
thunderstorm days per year are collected from the reported weather information in order to determine ground flash density.
Then, using MRU-200 equipment, tower-footing resistance of several towers are measured. Matlab® software is used in order
to produce lightning surges considering its probabilistic nature and randomly distribution on ground to evaluate striking
distance based on geometric model. Calculated distances are transferred to EMTP-RV software by establishing a link to
perform transient simulation and report the results for modelled 230kV transmission line. Finally, considering IEEE-1243
standard, it is shown that due to high ground flash density, using tower with one shield wire is not sufficient to protect the
line against lightning phenomena.
1
ZS1-3 ZS1-2
35
Number of thunderstorm days per
30
25 ZT3 ZT1 ZT2
20
15 ZEq
year
Generator
10 RT3 RT1 RT2
Pulse
5
0
Fig. 2. Measuring tower-footing resistance.
Resistance ( )
2
Resistance ( )
TABLE 1 Ground flash density using Eriksson equation
2
Kermanshah NG Kurdistan NG Ilam NG
0
Javanrud 2.16 Saqqez 1.46 Ilam 2.85 180 182 184 186 188 190 192 194 196 198 200
Sarpol-e Resistance ( )
2.69 Sanandaj 2.42 Mehran 0.91 4
Zahab
Eslam Abad-e
2.59 Bijar 1.82 Dehloran 1.28 2
Gharb
Dareh
Harsin 1.03 Zarineh 1.93 0.57 0
Shahr 220 222 224 226 228 230 232 234 236 238 240
Tower Number
Ravansar 2.14 Marivan 2.99 Ivan 1.24
Ghasr-e Fig. 3. Measured tower-footing resistance.
0.52 Ghorveh 1.75 Lomar 1.26
Shirin
Somar 0.19 Baneh 4.33 Sarableh 1.01 3. Measuring of Tower-Footing Resistance
Tazeh Abad 2.61 Kamyaran 0.89 Abdanan 1.65 In order to measure tower-footing resistance, 4 pole
Hezar method is used. This method is recommended in the case of
Kangavar 1.81 1.61
Kanian measurements of earth resistance with very low values. It
Kermanshah 2.35 permits to eliminate the influence of the test leads resistance
over the result of the measurement [16]. The measurements
are conducted by using MRU-200 device. It is worth noting
2. Meteorological Studies and Determination of that sine under study 230kV transmission lines were in
Isochronic Level operation, earth impedance measurement was used to
West Regional Electric Company in Iran is responsible measure tower-footing resistance accurately while
for design, operation and maintenance of electrical system in minimizing effects of shield wires. In this case, 4µs/10µs
Kermanshah, Kurdistan and Ilam provinces. Total length of surge is produced by the device and due to low impedance
230kV transmission lines in these provinces is equal to 2646 path through tower-footing resistance shown in Fig. 2,
Km and according to the reports, in period of 2012-2017, approximately. all current flows through this path since
average value of these lines outage due to shielding failure is 𝑅𝑇1 ≪ 𝑍𝐸𝑞 . Impedance is measured according to the ratio of
1.17/100 Km-years. Fig. 1 shows average value number of peak value of voltage and current. It should be noted that
thunderstorm days per year in different cities of Kermanshah effect of the parallel paths is negligible since the produced
province during 2012-2017 according to the reported weather surge is eliminated in shield wires due to damping.
information. These data are also available for Kurdistan and In this study, 63 towers were selected in Sanandaj-
Ilam provinces. Considering Eriksson equation, ground flash Chamran-Cheshmeh Sefid 230kV transmission line in order
density is calculated as follows: to measure tower footing resistance. Fig. 3 depicts numerical
𝑁𝐺 = 0.04𝑇𝑑1.25 (1) measurement results for different towers. According to the
where, 𝑇𝑑 is number of thunderstorm days per year. Table 1 measurement results, the maximum value of tower footing
lists ground flash density for different provinces based on (1). resistance is equal to 4Ω which is used in the simulations.
As it can be seen in Table 1, ground flash density in 10 cities Moreover, it is worth noting that in IEC 62305-3, it is
is greater than 2 which is known as a high value [15]. It should mentioned that 10Ω is appropriate earth resistance; however,
be noted that number of line outages is 7/year for both this value is very general and it is not limited to transmission
Kermanshah and Ilam while this value is equal to 17/year for lines.
Kurdistan.
2
TABLE 2 Lightning Parameters [19] 11m
9m
Average Standard
Parameter 2m
Value Deviation
Maximum Current
1.3
31.1 0.48
(kA)
1.3
Front Time (µs) 3.83 0.55
6
a c
14.3m
Time to Half Value (µs) 77.5 0.58
1.3
b b
1.3
4. Monte Carlo
Monte Carlo simulation is a type of simulation which c a
relies on repeated random sampling and statistical analysis in
17.6m
49.8m
order to compute the results. It should be noted that this
simulation method is closely related to random experiments,
experiments for which the specific result is not known in
advance. In this context, Monte Carlo simulation can be
considered as a methodical way of doing so-called what-if
9m
analysis. In summary, Monte Carlo simulation is a very useful
1.5
mathematical technique for analyzing uncertain scenarios and
providing probabilistic analysis of different situations [17].
9m
The main assumption is that population mean of 𝑔(𝑋) is
estimated by sample mean as follows:
𝑛
1
𝐸[𝑔(𝑋)] ≈ ∑ 𝑔(𝑋𝑡 ) (2) 11.5m
𝑛 Fig. 4. The used tower in Sanandaj-Chamran-Cheshmeh Sefid 230
𝑡=1
here, n is number of samples and it is under control. If the kV transmission line.
samples are independent, laws of large numbers ensure that 𝑁
𝑟𝑚
the approximation can be made as accurate as desired by 𝑓(𝑠) = ∑ ( ) + 𝑑 + 𝑠𝑒 (3)
𝑠 − 𝑎𝑚
increasing the sample size. In this paper, Monte Carlo 𝑚=1
simulation method considering 30000 samples is used to Moreover, frequency representation in the form of (3) is
include statistical characteristics of lightning phenomena into converted to state-space equation. In (3), 𝑑 and 𝑒 are optional
the performed analysis [18]. [21]. Unknown coefficients are identified so that the least-
squares distance between 𝑓(𝑠) and the data samples is
achieved which requires an iterative process by replacing
5. System Modelling
initial poles by the relocated poles until convergence is
EMTP-RV software as a very powerful and flexible tool
reached. It is worth noting that line span is 402 m and its
is used in order to simulate 230kV transmission line. It should
length is 187.2Km. Conductor type is Canary in which
be noted that 80MW load with power factor of 0.9 lag flows
diameter is 29.51mm and its resistance at 20º C is 0.06332
through transmission line. Moreover, upstream and
Ω/Km. The same conductor is used for shield wire.
downstream networks are modelled using ideal source with
balanced voltages. In addition, a variable uniformly
5.3. Tower
distributed in the range 0º–360º simulates the phase angle of
In this paper, each segment of the tower between
the impressed power frequency voltages.
crossarms (four sections) is represented by using lossless line
model [22]. The used tower in the under study transmission
5.1. Lightning Surge line is depicted in Fig. 4 in which all numerical values are in
In EMTP software, I CIGRE device is used to model meter. Moreover, considering [22], tower surge impedance is
current shape of a lightning stroke for accurate calculations 2
of the lightning performance. Current source which is used to calculated by 60𝑙𝑛(√2√(ℎ𝑟) + 1). According to this equation,
model lightning surge is in parallel with a 1kΩ resistance to noting that h (tower height) and r (tower base radius) are
consider channel impedance. In this paper, 30000 lightning 49.9m and 5.75m, respectively, surge impedance of the tower
surges are produced considering statistical characteristics is equal to 150.84Ω. More details regarding tower grounding
reported in [19] which are also listed in Table 2. system and number of included towers and line lengths at two
ends are provided in appendix.
5.2. Transmission Line
Frequency dependent line model is used to accurately 5.4. Insulator
model Sanandaj-Chamran-Cheshmeh Sefid 230kV One of the most suitable methods for the evaluation of the
transmission line by taking into account the frequency moment and level of arcing of spark gaps after a lightning
dependence of series resistance and inductance of the line per strike, is the integral method. The insulation is modeled by:
unit length [19]. In this model, data of phase and shield 𝑡
conductors along with physical distances are used as required ∫ [|𝑣𝑔𝑎𝑝 (𝑡)| − 𝑣0 ]𝑘 > 𝐷 (4)
𝑡0
input data. It should be noted that vector fitting method is
used to approximate the simulated frequency response with a
rational model as follows:
3
Start
Downward
Leader
Shield Random Generation of
Conductor Dc Lightning Current Magnitude
Performing in MATLAB
O rc M Determining Striking Distance Based
rc N on IEEE-1243
i=i+1
Fig. 5. Exposed distance for final jump in electro-geometric
model. Simulation by EMTP-RV Software
Performing in
EMTP-RV
Flashover occurs when the above integral becomes greater or
equal to D. t0 is the time-point from which 𝑣𝑔𝑎𝑝 became
Transferring Simulation Results to
greater than 𝑣0 . When the voltage 𝑣𝑔𝑎𝑝 goes below 𝑣0 the MATLAB and Saving the Results
integral is reset. The gap is an ideal open switch before
flashover and becomes an ideal closed switch after flashover.
More information are provided in [23]. Considering height of Yes
the insulator is about 300cm and modifying the reported i 30000
values in [24], in the under study transmission system,
No
numerical values for 𝑣0 , k and D are 1300kV, 1.02 and
0.036506, respectively. End
Fig. 6. Simulation procedure.
6. Striking Distance
Several researchers have contributed to the electro- present in the channel. Matlab® software is used in order to
geometric model of the last step or striking distance of the produce lightning waveforms with characteristics listed in
lightning flash [25]. As the downward leader approaches the Table 2, determining the strike distances according to IEEE-
earth, a point of discrimination is reached for a final leader 1243 and also produce phase angle of the source. These
step. The electro-geometric model portrays this concept with parameters are then transferred to the EMTP-RV software to
the use of striking distances. Other models, model the perform transient simulation and investigate performance of
upward-directed leaders from objects. In IEEE-1243 [15], the the transmission line against lightning overvoltages
following striking distance equations are recommended: considering models described for each equipment in Section
𝑟𝑐 = 10𝐼0.65 V. Flowchart of the simulation procedure is illustrated in Fig.
[3.6 + 1.7𝐿𝑛(43 − ℎ)]𝐼0.65 ℎ < 40 (5) 6. As shown in this figure, at first, output results of Matlab ®
𝑟𝑔 = { 0.65 are used in EMTP-RV. Then, results of EMTP-RV are
5.5𝐼 ℎ ≥ 40
where, 𝑟𝑐 is striking distance to the phase conductor, 𝑟𝑔 is analyzed to investigate the line outages. It is worth noting that
striking distance to the ground, I is stroke current and h is the simulation time in EMTP-RV is 1ms with time step of 1ns.
average conductor height in meters, given by the height at the
tower minus two-thirds of the midspan sag. These distances 8. Calculation of Shielding Failure Flashover Rate
are depicted in Fig. 5. and Back Flashover Rate
If a downward leader (having a prospective current I for In this paper, considering the described procedure in Fig.
which the arcs were drawn) touches the arcs between M and 6, Shielding Failure Flashover Rate (SFFOR) per 100 Km-
N, the leader will strike the phase conductor. If the leader year is calculated as follows [3]:
𝐹𝑃
touches between M and O, it will strike the shield wire. If all 𝑆𝐹𝐹𝑂𝑅 = 𝑁𝐺 × 100 × 𝑑 × (6)
𝑁
leaders are considered vertical, the exposure distance for a N is number of runs, d is the maximum width of impact area
shielding failure is Dc. In the two-conductor case shown, there that corresponds to the maximum peak current magnitude of
would only be a shielding-failure rate (SFR) on one side equal the first stroke generated by the Monte Carlo simulation.
to NG ×Dc ×L, given for specific value of current for a line of Moreover, FP is the number of flashovers caused by strokes
length L. to the phase conductor.
In this paper, Back Flashover Rate (BFR) per 100 Km-
7. Simulation Procedure year is calculated as follows [3]:
In order to investigate performance of Sanandaj- 𝐹𝐺
Chamran-Cheshmeh Sefid 230kV transmission line against 𝐵𝐹𝑅 = 𝑁𝐺 × 100 × 𝑑 × (7)
𝑁
lightning with only one shield wire, a channel with length of In this equation, FG is the number of flashovers caused by
450m and width of 712m is used. Moreover, for considering strokes to the shield wire.
the worst case, it is assumed that all the lightning strokes are
4
TABLE 3 Required parameters to calculate line outages (one shield wire) 9. Tests and Results
Parameter Value Parameter Value 9.1. Using One Shield Wire
Ic BFR 38.84 kA DCC* 8.0548 Considering Fig. 4 and flowchart in Fig. 6, 30000
Ic SFFOR 8.03 kA Imax 48.81 kA
lightning strokes are produced with characteristics listed in
Isochronic
h 49.9 m 26.5 Table 2. Under this condition, 6774 lightning strokes strike to
Level
L 182.7 Km NG 1.4 shield wire (22.58%), 643 lightning strokes terminate on
*
DCC is DC for IC upper phase conductors (2.14%) and the rest strike to the
ground. It is worth noting that minimum and maximum
1000 951.93 950.11
912.03 915.08 lightning currents that strike to the shield wire are 5.66 kA
900 and 215.51 kA, respectively. Moreover, minimum lightning
790.16 791.53
800 current (or critical current IC) and maximum current (IMax)
700 that strike to the phase conductors are 8.03 kA and 48.81 kA,
Voltage (kV)
5
TABLE 4 Required parameters to calculate line outages (two shield wires)
Parameter Value Parameter Value
400
Ic BFR 91.41 kA DCC* 1.7211
Ic SFFOR 8.03 kA Im 25.10 kA 200
h 49.9 m Isochronic Level 26.5
0
L 182.7 Km NG 1.4
* -200
DCC is DC for IC
Voltage (kV)
-400
-800 Tower
700 Phase "a"
609.33 609.01
-1000 Phase "b"
600 Phase "c"
-1200 Phase "a '"
Voltage (kV)
0
400
a c' b b' c a'
200
Average Standard deviation
0
-400
160
-600
137.68 136.42 Tower
140 Phase "a"
-800
Phase "b"
120 105.67 105.01 Phase "c"
-1000
Phase "a '"
Voltage (kV)
100
-1200 Phase "b '"
80 Phase "c'"
-1400
0 5 10 15 20
60 Time (us)
40 29.68 29.97 Fig. 13. Overvoltage of different conductors – 35kA lightning -
22.87 22.94
15.76 16.04 13.05 two shield wires
20 12.74
0
between two shield wires is 5.6 m and shielding angle of
a c' b b' c a' 14.98º is provided which is much less than 34.69º [26].
Following the same procedure performed in Section 9.1,
Average Standard deviation it is concluded that 7818 lightning strokes terminate on shield
wires (26.06%), 163 lightning strokes terminate on upper
Fig. 11. Reduction in average and standard deviation of
phase conductors (0.54%) and the rest strike to the ground
overvoltages – striking to shield conductors.
which shows significant improvement in protection of the
line against lightning. It is worth noting that in this case, as
9.2. Using Two Shield Wires expected, IMax significantly reduces and it is equal to 25.10
As mentioned before, using one shield conductor does kA which shows more than 90% reduction in comparison
not provide appropriate protection against lightning surges with IMax when only one shield wire is used. Consequently,
due to high value of ground flash density in the under study reduction in overvoltages for striking lightning to the shield
area. Therefore, one of the best solutions in order to reduce wires especially for upper conductors is expected. Fig. 10
outages because of lightning is employing more shield wires depicts average and standard deviation values of produced
which should be considered during the design process. overvoltages when two shield wires are used. As it can be
Otherwise, adding new shield wires after construction is seen in this figure, reduction in produced overvoltages for
almost impossible and other solutions like reduction of tower- terminating on shield wires is obvious due to providing
footing resistance (if possible) or using line surge arrester parallel path for lightning current to flow. Further details
should be considered. regarding mathematical description of reduction in
Generally speaking, for constant height of shield wire, if overvoltages are represented in Fig. 11 for each phase
another shield wire is added to the tower structure, shielding individually.
angle reduces and for the same value of critical current, Results are summarized in Table 4. Under this condition,
SFFOR also reduces. In this case, significant reduction in by using (6) and (7), SFFOR is equal; therefore, it is
value of IMax is expected. To such aim, it is assumed that concluded that SFFOR is 0.2494/100 km-year which is much
another shield wire is added to the tower so that the distance less than SFFOR for one shield wire and closer to
recommended value by IEEE-1243.
6
case, is 83kA with probability of 7.17%. Results of this case
1600
are shown in Fig. 15. According to this figure, at the time of
Phase "a" 1.405µs, short circuit occurs in phase a when its voltage
1400 Phase "b"
Phase "c"
reaches 1469kV. It is worth noting that while the required
1200
Phase "a '" current for flashover significantly increases, occurrence
1000 Phase "b '" probability of lightning with bigger magnitude reduces.
Phase "c'" According to results of this section, it is concluded that
Voltage (kV)
800
using two shield wires for under study 230kV transmission
600
line, significantly reduces overvoltages in different parts of
400 the tower and the required lightning magnitude considerably
200
increases.
0
11. Conclusion
-200
In this paper, using Monte Carlo simulation method for
-400 considering statistical features of the lightning phenomena,
0 5 10 15 20
Time (us) outages of 230kV transmission line in the west regions of Iran
Fig. 14. Overvoltage of different Insulators – 54kA lightning - was investigated based on the reported weather information.
one shield wire Moreover, using MRU-200 device, footing-resistance of
towers were measured for 63 towers. Then, by determining
1600 the strike distances along with characteristics of lightning
Phase "a"
1400 Phase "b" surge in Matlab®, results were transferred to EMTP-RV in
Phase "c" order to investigate performance of the system. As expected
1200
Phase "a '" and according to the results, using one shield wire does not
1000 Phase "b '"
provide appropriate protection for the line against lightning
Phase "c'"
surges since ground flash density in the under study regions
Voltage (kV)
800
600
is a high value. Moreover, calculated SFFOR was compared
with recommended values by IEEE-1243. Also, performance
400
of the two shield wires were investigated which showed that
200 in this case, reduction in value of SFFOR is significant and it
0 is closer to the recommended value by IEEE-1243.
-200
12. Acknowledgments
-400
0 5 10 15 20 This research was supported by the West Regional
Time (us)
Electric Company, Iran, Kermanshah. The authors would like
Fig. 15. Overvoltage of different conductors – 83kA lightning - to thank their colleagues who provided insight and expertise
two shield wire
that greatly assisted the research.
1.4m
90Km
Fig. 16. Tower grounding system
[6] M. S. Banjanin, M. S. Savić, Z. M. Stojković, ‘Lightning protection of
overhead transmission lines using external ground wires’, Electric
Power Systems Research., 2015, 127, pp. 206-212.
[7] F. Mahmood, A. S. Nehmdoh, M. Lehtonen, ‘Effect of combined AC
and lightning-induced overvoltages on the risk of MV insulator
flashovers above lossy ground’, Electric Power Systems Research,
402m
2015, 127, pp. 101-108.
[8] K. Sheshyekani, M. Akbari, B. Tabei, R. Kazemi: ‘Wide-band
modeling of large grounding systems to interface with electromagnetic
transient solvers’, IEEE Trans. Power Del., 2014, 29, (4), pp. 1868–
1876.
[9] M. R. Alemi, K. Sheshyekani: ‘Wide-Band Modeling of Tower-
Footing Grounding Systems for the Evaluation of Lightning
Performance of Transmission Lines’, IEEE Trans. Electromagn.
402m
Compat. 2015, 57, (6), pp. 1627-1636.
[10] Young, F.S., Clayton, J.M., Hileman, A. R., ‘Shielding of transmission
lines’, IEEE Transaction on Power Apparatuses and Systems, 1963,
S82, pp. 132-154.
[11] Brown, G.W., Whitehead, E.R.: ‘Field and analytical studies of
transmission line shielding: part II’, IEEE Transaction on Power
Apparatuses and Systems, 1969, PAS-88, (5), pp. 617-626.
[12] Hamed Ahmadi, Mažana Armstrong, Arash Tavighi, ‘Quantifying the
Shielding Effect of Trees Against Lightning Strikes for Power
402m
Transmission Lines’, Electrical & Computer Engineering (CCECE)
2018 IEEE Canadian Conference on, pp. 1-5, 2018.
[13] P. Hashemian, B. Vahidi, A. Rahiminezhad, ‘Improved electro-
geometric model for shielding failure analysis of transmission lines’,
IET Gener. Transm. Distrib., 2018, 12, (4), pp. 542-547.
[14] CIGRE Working Group C4.26. ‘Evaluation of Lightning Shielding
Analysis Methods for EHV and UHV DC and AC Transmission Lines’,
2017.
402m
8
14. Appendix
Tower grounding system consisting of four horizontal
branches made of strap iron buried at about 0.8 m is shown in
Fig. 16. This grounding system is suitable for soil resistivity
of 150Ωm - 250Ωm.
The used network in EMTP-RV is depicted in Fig. 17.
As shown in this figure, seven towers and six spans with the
length of 402m are used to analyze the system performance.
Moreover, two 90Km transmission lines are considered to
terminate on both ends. It should be noted that since under
study transmission line is double ended, two voltage sources
are connected to each end. Moreover, parameters of the
voltage sources are determined based on load flow solution.
As mentioned in the paper, 80MW with power factor of 0.9
Lag is transferred through transmission line.