STORM WATER DRAINAGE SCHEME FOR MUZAFFARPUR SMART CITY ABD AREA
DETAILED ESTIMATE
Name of the Work: Dismantling of Pavement
Sl No Description Unit Nos L B D Qty
Dismantling of flexible pavements and disposal
of dismantled materials up to a lead of 1000 m,
1 stacking serviceable and unserviseable materials
separately

Granular courses by Manual Means (For


a Bituminous Road)
For 145 mm Dia Pipe m3 1 5069.62 0.75 0.500 1901.1064
For 195 mm Dia Pipe m3 1 425.54 0.75 0.500 159.579
For 245 mm Dia Pipe m3 1 115.44 0.75 0.500 43.2915
For 294 mm Dia Pipe m3 1 76.25 0.80 0.500 30.5004
For 350 mm Dia Pipe m3 1 42.12 1.00 0.500 21.0595
For 400 mm Dia Pipe m3 1 23.42 1.05 0.500 12.292875
For 450 mm Dia Pipe m3 1 4.84 1.10 0.500 2.6642
For 500 mm Dia Pipe m3 1 12.93 1.15 0.500 7.434175
For 600 mm Dia Pipe m3 1 38.01 1.27 0.500 24.13635
For 700 mm Dia Pipe m3 1 82.54 1.37 0.500 56.537845
For 800 mm Dia Pipe m3 1 33.27 1.49 0.500 24.786895
For 900 mm Dia Pipe m3 1 5.47 1.60 0.500 4.3792
Total 2287.7683

b Granular courses by Mechanical Means (For


Concrete Road)
For 145 mm Dia Pipe m3 1 67353.48 0.75 0.200 10103.022
For 195 mm Dia Pipe m3 1 5653.66 0.75 0.200 848.0484
For 245 mm Dia Pipe m3 1 1533.76 0.75 0.200 230.0634
For 294 mm Dia Pipe m3 1 1013.05 0.80 0.200 162.08784
For 350 mm Dia Pipe m3 1 559.58 1.00 0.200 111.9162
For 400 mm Dia Pipe m3 1 311.09 1.05 0.200 65.32785
For 450 mm Dia Pipe m3 1 64.36 1.10 0.200 14.15832
For 500 mm Dia Pipe m3 1 171.77 1.15 0.200 39.50733
For 600 mm Dia Pipe m3 1 504.99 1.27 0.200 128.26746
For 700 mm Dia Pipe m3 1 1096.56 1.37 0.200 300.45826
For 800 mm Dia Pipe m3 1 442.03 1.49 0.200 131.72464
For 900 mm Dia Pipe m3 1 72.73 1.60 0.200 23.27232
Total 12157.854

c Bituminous courses by mechanical means


For 145 mm Dia Pipe m3 1 5069.62 0.75 0.080 304.17702
For 195 mm Dia Pipe m3 1 425.54 0.75 0.080 25.53264
For 245 mm Dia Pipe m3 1 115.44 0.75 0.080 6.92664
For 294 mm Dia Pipe m3 1 76.25 0.80 0.080 4.880064
For 350 mm Dia Pipe m3 1 42.12 1.00 0.080 3.36952
For 400 mm Dia Pipe m3 1 23.42 1.05 0.080 1.96686
For 450 mm Dia Pipe m3 1 4.84 1.10 0.080 0.426272
For 500 mm Dia Pipe m3 1 12.93 1.15 0.080 1.189468
For 600 mm Dia Pipe m3 1 38.01 1.27 0.080 3.861816
For 700 mm Dia Pipe m3 1 82.54 1.37 0.080 9.0460552
For 800 mm Dia Pipe m3 1 33.27 1.49 0.080 3.9659032
For 900 mm Dia Pipe m3 1 5.47 1.60 0.080 0.700672
Total 366.04293
480197212.xlsx

Name of the Work: Dismantling of Pavement


Sl No Description Unit Nos L B D Qty

Dismantling of cement concrete pavements by


mechanical means using pneumatic tools,
breaking to pieces not exceeding 0.02 m3 in
2 volume and stock pilling at designated locations
and disposal of dismantled materials up to a
lead of 1000 metres, stacking serviceable and
unserviceable material

For 145 mm Dia Pipe m3 1 67353.48 0.75 0.400 20206.045


For 195 mm Dia Pipe m3 1 5653.66 0.75 0.400 1696.0968
For 245 mm Dia Pipe m3 1 1533.76 0.75 0.400 460.1268
For 294 mm Dia Pipe m3 1 1013.05 0.80 0.400 324.17568
For 350 mm Dia Pipe m3 1 559.58 1.00 0.400 223.8324
For 400 mm Dia Pipe m3 1 311.09 1.05 0.400 130.6557
For 450 mm Dia Pipe m3 1 64.36 1.10 0.400 28.31664
For 500 mm Dia Pipe m3 1 171.77 1.15 0.400 79.01466
For 600 mm Dia Pipe m3 1 504.99 1.27 0.400 256.53492
For 700 mm Dia Pipe m3 1 1096.56 1.37 0.400 600.91652
For 800 mm Dia Pipe m3 1 442.03 1.49 0.400 263.44928
For 900 mm Dia Pipe m3 1 72.73 1.60 0.400 46.54464
Total 24315.709
480197212.xlsx

STORM WATER DRAINAGE SCHEME FOR MUZAFFARPUR SMART CITY ABD AREA
ABSTRACT ESTIMATE
Name of the Work: Dismantling of Pavement
S.No. Description Unit Quantity Rate (Rs) Amount in (Rs) SOR Reference
1
Dismantling of flexible pavements and disposal
of dismantled materials up to a lead of 1000 m,
stacking serviceable and unserviseable materials
separately
a Granular courses by Manual Means (For RCD SOR 2019, Item no 2.5 I
m3 14445.62 560.00 8089548.76
Bituminous Road) B
b RCD SOR 2019, Item no 2.5
Bituminous courses by mechanical means m3 366.04 359.00 131409.41
II A.
2
Dismantling of cement concrete pavements by
mechanical means using pneumatic tools,
breaking to pieces not exceeding 0.02 m3 in
volume and stock pilling at designated locations m3 24315.71 1584.00 38516082.97 RCD SOR 2019, Item no 2.6
and disposal of dismantled materials up to a lead
of 1000 metres, stacking serviceable and
unserviceable material

46737041.15
Total
467.37 in Lakhs