SHEET :

CALCULATION SHEET 1 OF

SUBJECT : Kebutuhan Issulation Armaflex & Jacketing SS 204 DATE 6/18/2020 BY :

PROJECT : Paket iv Phase 1 New SKM unit V Kediri CHECK'D BY :

DAFTAR JUMLAH PIPA, FITTING DAN ACCERORIS LINE PHE PAKET IV PHASE -1 NEW SKM YANG TERBUNGKUS ARMAFLEX
TABEL : 1 ###
BQ
NO MATERIAL SI TOTAL SAT KETERANGAN
SKM ANEX
A
1 PIPA BS Ø6" 32 32 LJR
2 PIPA BS Ø4" 117 117 LJR
3 PIPA BS Ø3" 77 10 87 LJR
4 PIPA BS Ø2-1/2" 27 27 LJR
5 PIPA BS Ø2" 26 26 LJR
6 PIPA BS Ø1-1/2" 6 58 64 LJR
7 PIPA BS Ø1-1/4" 5 5 LJR
8 PIPA BS Ø1" 71 17 88 LJR
9 PIPA BS Ø1/2" 1 1 LJR

B KERJA TAMBAH ( FITTING )


1 SO FLANGE ANSI 150 Ø6" 16 16 PCS
2 SO FLANGE ANSI 150 Ø 4" 21 21 PCS
3 SO FLANGE PN 16 Ø 3" 16 16 PCS
4 SO FLANGE PN 16 Ø 1--1/2" 168 168 PCS
5 SO FLANGE PN 16 Ø 1--1/4" 54 54 PCS
6 BUTTEFLY VALVE Ø6" 2 2 PCS
7 BUTTEFLY VALVE Ø4" 8 8 PCS
8 BUTTEFLY VALVE Ø3" 4 4 PCS
9 BUTTEFLY VALVE Ø1-1/2" 32 32 PCS
10 BUTTEFLY VALVE Ø1" 2 2 PCS
11 BUTTEFLY VALVE Ø1-1/4" 12 12 PCS
12 BALLANCING VALVE Ø1-1/2" 12 12 PCS
13 BALLANCING VALVE Ø1-1/4" 12 12 PCS
14 BALL VALVEØ 1" 30 30 PCS
15 BALL VALVEØ 1/2" 4 4 PCS
16 RED. TEE Ø3X 1.5" 16 16 PCS
17 RED. TEE Ø4X 1.5" 12 12 PCS
18 RED. TEE Ø4X 1" 12 12 PCS
19 ELBOW 45° BS Ø3" 28 28 PCS
20 ELBOW 45° BS Ø4" 12 12 PCS
21 ELBOW 45° BS Ø1" 24 24 PCS
22 ELBOW 90° BS Ø1" 11 11 PCS
23 EQUAL TEE Ø1" 11 11 PCS
24 Y-STRAINER 1-1/2" 32 32 PCS
25 Y-STRAINER 1" 2 2 PCS
26 Y-STRAINER 1-1/4" 12 12 PCS
27 CONRED BS Ø1X3/4" 24 24 PCS
28 END CAP Ø3" 2 2 PCS

Note
LINE RETURN 1 LAYER Thickness = 25 mm
LINE SUPPLY 2 LAYER Thickness = 50 mm
Ø<= 2" = menggunakan Armaflex 13mm
Ø> 2" Menggunakan Armaflex thk, 25mm

ILUSTRASI PEMASANGAN ARMAFLEX


1 LAYER
UNTUK LINE RETURN = 25 MM ARMAFLEX THK. 25 UNTUK
MM LINE SUPPLY = 50 MM
LAYER 2
ARMAFLEX THK. 25 MM
d
d
PIPA BS WELDED
LAYER 1
ARMAFLEX THK. 25 MM
Ø> 2" Ø> 2"
PIPA BS WELDED

d
LAYER 3
d LAYER 2 ARMAFLEX THK. 25 MM
ARMAFLEX THK. 13
MM
LAYER 2
LAYER 1 Ø<= 2" ARMAFLEX THK. 13 MM
ARMAFLEX THK. 13
MM
LAYER 1
Ø<= 2" ARMAFLEX THK. 13 MM

Page 1 of 8
LUASAN INSULATION

L= ᶯ X ∆d X t

L = Luasan Armaflex
ᶯ= 3,14
∆d = Diameter ( pipa + Armaflex )
t = Panjang Pipa

Dari Rumus diatas maka diperoleh Luasan Armaflex sbb : tabel : 2


1 ly 2 ly
NO Ø> 2" SAT QTY PANJANG RETURN SUPPLY
(M) ( M² ) ( M² )

1 PIPA BS Ø6" LJR 32 192 60 139


2 PIPA BS Ø4" LJR 117 702 157 370
3 PIPA BS Ø3" LJR 87 522 96 232
4 PIPA BS Ø2-1/2" LJR 27 162 28 69

TOTAL 341 810

DEMENSI ARMAFLEX THK 25 MM = 1.22 X 4 4 M² ( Dibulatkan )

Kebutuhan Return = 341/4 = 86 ROLL


Kebutuhan Supply = 810/4 = 203 ROLL
sub Total 289 ROLL
tabel : 3
RETURN SUPPLY
PANJANG
NO Ø<= 2" SAT QTY ( M² ) ( M² )
(M) 2x13mm 2 layer (13mm) 1 layer (25mm)

1 PIPA BS Ø2" LJR 26 156 48 48 36


2 PIPA BS Ø1-1/2" LJR 64 384 94 94 77
3 PIPA BS Ø1-1/4" LJR 5 30 10 10 7
4 PIPA BS Ø1" LJR 88 528 100 100 92
5 PIPA BS Ø1/2" LJR 1 6 1,6 1,6 1,5

TOTAL 252 252 212

DEMENSI ARMAFLEX THK 13 MM = 1.22 X 8 8 M² ( Dibulatkan )


Kebutuhan ARMAFLEX 13mm = ( 252 + 252 ) M² /8 M² = 63 roll
Kebutuhan ARMAFLEX 25mm = 212/4 = 53 roll
sub Total 116 rool

KEBUTUHAN ARMAFLEX PIPA PHE = 289 + 116 = 405 roll

B. KEBUTUHAN ARMAFLEX UNTUK KERJA TAMBAH MATERIAL FITTING & ACCESORIS


dari tabel no 1 diatas diperoleh sbb :
Line return = 70 M
Line supply = 106 M
sub Total = 176 /4 = 44 roll

KEBUTUHAN ARMAFLEX FITTING & ACCESSORIES = 44 roll

B KEBUTUHAN JACKETING SS 204 THK. 0.5MM ( PIPA )


tabel : 4
PANJANG RETURN SUPPLY
NO DESKRIPSI SAT QTY KETERANGAN
(M) (M² ) ( M² )

1 PIPA BS Ø6" LJR 32 192 53 61


2 PIPA BS Ø4" LJR 117 702 140 167
3 PIPA BS Ø3" LJR 87 522 83 103
4 PIPA BS Ø2-1/2" LJR 27 162 23 29
5 PIPA BS Ø2" LJR 26 156 19 25
6 PIPA BS Ø1 -1/2" LJR 64 384 38 53
7 PIPA BS Ø1 -1/4" LJR 5 30 3 4
8 PIPA BS Ø1 " LJR 88 528 42 63
9 PIPA BS Ø1/2 " LJR 1 6 1 1

TOTAL 402 506

DEMENSI SS 204 THK. 0.5 MM = 1.2 x 2.4 = 2.88 M²


Kebutuhan SS 204 THK 0.5MM UNTUK PIPA = 908 M2 454 LBR

C. KEBUTUHAN SS 204 THK.0,5 MM UNTUK KERJA TAMBAH MATERIAL FITTING & ACCESORIS

Line return = 90 M²
Line supply = 100 M²
Sub Total = 190 M²

Kebutuhan SS 204 THK 0.5MM = 190/2.88 M² 66 Lbr


Page 2 of 8
TOTAL KEBUTUHAN JACKETING SS 204 THK 0.5 MM = 454 + 66 = 520 lbr

Page 3 of 8
KEBUTUHAN ARMAFLEX PAKET IV NEW SKM - UNIT 5

KEDATANGAN BQ FINAL BQ DEV


NO URAIAN SAT KETERANGAN
PAKET II PAKET IV TOTAL PAKET II PAKET IV TOTAL PAKET II PAKET IV TOTAL K.KURANG K.TAMBAH
a b c=a+b d e f=d+e g h i=g+h j=c-i g=i-c
A. PIPA
1 ARMAFLEX THK. 25 MM MAT'L BY GG ROLL 526 93 267 360 93 359 452 74 See Calculation sheet
2 ARMAFLEX THK. 13 MM MAT'L BY GG ROLL 8 64 64 56 See Calculation sheet

B. KERJA TAMBAH U/ FITTING, ACCESORIS


1 ARMAFLEX THK. 25 MM MAT'L BY GG ROLL 0 44 44 44 See Calculation sheet

TOTAL 74 100 ROLL


SELISIH ( KERJA TAMBAH ) 26 ROLL

KEBUTUHAN JACKETING SS 240 THK 0.5 MM PAKET IV NEW SKM - UNIT 5

NO URAIAN SAT BQ FINAL BQ KETERANGAN


K.KURANG K.TAMBAH
A. PIPA
1 SS 240 THK 0.5 MM Lbr 473 454 19 - See Calculation sheet

B. KERJA TAMBAH U/ FITTING, ACCESORIS


1 SS 240 THK 0.5 MM Lbr - 66 - 66 See Calculation sheet

SELISIH ( Kerja Tambah ) 47 Lbr

Disetujui Oleh: Dibuat Oleh :


PT. GUDANG GARAM, Tbk. PT.SWADAYA GRAHA
IV PEMBONGKARAN & PEMASANGAN POMPA COOLING TOWER

NO URAIAN SPEC QTY SAT

1 BONGKAR POMPA CT Berat += 200 kg 200 KG


2 PASANG POMPA Berat += 300 kg 300 KG

3 MODIFIKASI SUPPORT
a. Man Power
1. SPV. 1 Personil 52 JAM
2. FITTER 1 Personil 52 JAM
3. HELPER 3 Personil 153 JAM

4 EQUIPMENT & TOOL


Sewa Crane 45 Ton 4 JAM
Batu Gerinda + kawat Las 1 LOT

TOTAL
HARGA TOTAL KETERANGAN

10,000 2,000,000
10,000 3,000,000 MAT'L BY GG

18,750 975,000
12,750 663,000
9,375 1,434,375

750,000 3,000,000
500,000 500,000

11,572,375
IV PEMBONGKARAN LINE COMPRESSOR DAN BLOW GUN FILTER D1 FIRST FLOOR

NO URAIAN SPEC QTY SAT

A Man Power
1. SPV. 1 Personil 40 JAM
2. FITTER 1 Personil 40 JAM
3. HELPER 3 Personil 120 JAM

B EQUIPMENT & TOOL


Batu Gerinda 1 LOT

TOTAL
D1 FIRST FLOOR

HARGA TOTAL KETERANGAN

18,750 750,000
12,750 510,000
9,375 1,125,000

500,000 500,000

2,885,000