Cement Planning & Engineering Department

SQUEEZE CEMENTING PROCEDURE (AGHAR-020)

Cement Squeeze Procedure:

1- Clean up tanks and preparing chemicals for mixing fluid.


2- Fill up Mud Reserve tank with Fresh Water [Main: 60 bbl] for mixing fluids
3-Before finished running Drill Pipe and RTTS packer to …. (m) With Co. man approval, start
mixing cement additives and preparing mixing fluids according to below cement mixing
procedure

Squeeze Cement Solution mixing procedure:

 Add TA-47 to Fresh water and allow mixing for 5 minutes.


 Add PK-FL8 and allow mixing for 10 minutes.
 Add O-CFR8 and allow mixing for 10 minutes.
 Add O-R12 and allow mixing for 10 minutes.
 Add PK-Gas7 and allow mixing until the cement operation will finish.

4-After running drill pipe and RTTS packer , install circulating cement head (swage), start
circulation at least one drill pipe cap volume

5-Pre job safety meeting with involved personnel and arrange with mud engineer to measure
drilling fluid during cement job.

6-Setting RTTS packer to …. m, and mud circulation by circulating valve.


7-Test cements line W/ 3500 psi.

8-Close circulating valve and hold the pressure of 1500 psi in annuals (on the packer).

9-Perform injectivity test with drilling fluid by pump truck.

10-Maximum pressure is .… and maximum rate is …. .

11-Release string pressure and record volume of returned mud in the displace tank pump truck.

12-Release pressure on the packer and open circulating valve.

13-Circulate mud.
Cement Planning & Engineering Department

SQUEEZE CEMENTING PROCEDURE (AGHAR-020)

14-Pump 10 bbl Salt Saturated Water as Spacer Ahead

15-Mix and pump 60 bbl Main cement slurry.(118pcf). ….. above circulating valve (calculate
at rig). Close circulating valve and hold the pressure of 1500 psi in annuals (on the packer).

16- Pump …. bbl Salt Saturated Water as Spacer Behind

17-Continue displaced and inject cement with…. bbl drilling fluid with maximum rate and
pressure (displace cement to …. meters under RTTS packer). (Calculate at rig).

18-Close the cement line valve on top of the string and release cement line pressure and wait for
Cement to get Hard.

19-WOC

NOTE 1: PUMPS OF EFFICIENCY FACTOR SHOULD BE DETERMINED IN RIG SITE BEFORE CEMENTING
OPERATIONS BY COMPANY MAN.
NOTE 2: THE VOLUME OF DISPLACEMENT SHOULD BE CALCULATED IN RIG SITE BY COMPANY MAN AND TO ALL
THE EXECUTIVE GROUPS TO BE ANNOUNCED.

PREPARED BY: APPROVED BY:


M. HAYATDAVOUDI M. BEIRANVAND
NIDC CEMENT ENGINEER HEAD OF CEMENT ENGINEERING