You are on page 1of 3

A Clearing & Grubbing 200 m²

B Footing excavation 30.24 m³


C Fabrication of Footing Reinf. 379.2 kgs
D Footing concrete pouring 5.04 m³
E Fabrication of Grade Beam Reinf. 277.68 kgs
F Installation of Formworks for Grade beam 60.32 m²
G grade beam concrete pouring 5.028 m³
H Disassembling of formworks of Grade beam 66.42 m²
I Fabrication of column Reinf. 805.8 kgs
J installation of formworks for column 88.2 m²
K column concrete pouring 5.67 m³
L Disassembling of formworks of column 88.2 m²
M Fabrication of slab rsb 2157.6 kgs
N concrete pouring on slab 15.2 m³
O Excavation for septic tank 12 m³
P Laying of chb wall (septic tank) 22.8 m²
Q plastering of chb (septic tank) 22.8 m²
R concrete pouring for septic tank top cover 0.75 m³
S Fabrication for Roof beam rsb 46.28 kgs
T Installation of formworks for roof beam 66.42 m²
U conrete pouring of roof beam 4.428 m³
V disassembling of formworks 66.42 m²
W laying chb walls 159.34 m²
X palstering of chb walls 159.34 m²
Y truss fabrication 250 bf
Z roof installation 250 bf
AA purlins & roofing installation 145.2 m²
AB installation of ceilings& framework 121.6 m²
AC installation of doors & windows 14.7 m²
AD installation of wooden partitions 13.14 m²
AE installation of floor tiles 121.6 m²
AF paint works 311.88 m²
from philcon
productivity rates productivity duration in days
rates
0.03 MH/m² (manual clearing) 0.8
0.5 mh/m³ (machine) 1.9
0.07 MH/kg 3.3
4 MH/m³ 2.5
0.1 MH/kg 3.5
0.66 MH/m² 5
4 MH/m³ 2.5
0.23 MH/m² 1.9
0.1 MH/kg 10.1
0.66 MH/m² 7.3
4 MH/m³ 2.8
0.23 MH/m² 2.5
0.1 MH/kg 27
4 MH/m³ 7.6
0.5 mh/m³ (machine) 0.8
10 m²/day 2.3
10 m²/day 2.3
4 MH/m³ 0.4
0.1 MH/kg 0.6
0.66 MH/m² 5.5 A Clearing &
4 MH/m³ 2.2 B Footing exc
0.23 MH/m² 1.9 C Fabrication
10 m²/day 15.9 D Footing con
10 m²/day 15.9 E Fabrication
0.35 MH/B.F. 10.9 F Installatio
0.8 MH/B.F. 25 G grade beam
0.27 MH/B.F. 4.9 H Disassembl
0.36 MH/B.F. 5.5 I Fabrication
2.37 MH/m² 4.4 J installatio
3.44 MH/m² 5.7 K column con
0.55 MH/m² 8.4 L Disassembl
0.24 MH/m² 9.4 M Fabrication
N concrete po
200 m² 0.03 MH/m² (man 0.8
30.24 m³ 0.5 mh/m³ (mac 1.9
379.2 kgs 0.07 MH/kg 3.3
5.04 m³ 4 MH/m³ 2.5
277.68 kgs 0.1 MH/kg 3.5
60.32 m² 0.66 MH/m² 5
5.028 m³ 4 MH/m³ 2.5
66.42 m² 0.23 MH/m² 1.9
805.8 kgs 0.1 MH/kg 10.1
88.2 m² 0.66 MH/m² 7.3
5.67 m³ 4 MH/m³ 2.8
88.2 m² 0.23 MH/m² 2.5
2157.6 kgs 0.1 MH/kg 27
15.2 m³ 4 MH/m³ 7.6

You might also like