Professional Documents
Culture Documents
Instrumented Test Section For The Evaluation of Geogrids in Asphalt Pavements
Instrumented Test Section For The Evaluation of Geogrids in Asphalt Pavements
A. Graziani *
Assistant Professor, Università Politecnica delle Marche, IT
A. Virgili
Professor, Università Politecnica delle Marche, IT
L. Belogi
PhD student, Università Politecnica delle Marche, IT
*
Dipartimento di Idraulica, Strade, Ambiente e Chimica. 60131 Ancona, Italy,
a.graziani@univpm.it
ABSTRACT
The evaluation of geogrid reinforcement for asphalt pavement rehabilitation is a
complex task where considerable research is needed. An instrumented flexible
pavement test section was constructed along an in-service road in Ancona
(Italy) to study the effectiveness of geogrid reinforcement in terms of stress-
strain response and pavement performance. The instrumented pavement is part
of a larger project that also involves a RILEM inter-laboratory test of geogrids
in asphalt pavements. A glass fiber grid and a carbon fiber grid were installed at
the interface between two asphalt layers. An unreinforced section with a
traditional tack-coat interface was constructed for reference. Moreover, areas
with artificial cracks and partial debonding were prepared in the lower asphalt
layer to simulate challenging situations frequently encountered in practical
rehabilitation projects. The three test section were instrumented with pressure
cells, asphalt strain gauges and temperature sensors. This paper describes the
site preparation and the test sections construction phases, with particular
emphasis to the instrumentation and the data acquisition set-up. FWD and full-
scale tests were performed on the newly constructed pavement. Results show
the effects of geogrid reinforcement on the pavement response both in terms of
surface deflection and stress-strain response. They will be the benchmark for
the planned long-term monitoring of the test sections.
1
1. INTRODUCTION
2. PROJECT DESCRIPTION
2.1 Background
The full-scale instrumented test section described in this paper is part of a larger
research project on “Advanced Interface Testing of Geogrids in Asphalt
Pavements”. The project originated inside the TG 4 “Pavement Performance
Prediction and Evaluation” of RILEM TC 206/ATB “Advanced Testing and
Characterization of Bituminous Materials” and comprises the construction of
two full-scale pavement test sections. The first section was used to prepare
double-layer reinforced asphalt samples using real scale paving equipment and
geogrid installation techniques. Specimens cut from this section will be studied
2
in an interlaboratory test organized by RILEM and focused on the comparison
of laboratory procedures and devices for the mechanical characterization of
geogrid reinforced interfaces in asphalt concrete pavements. The second
section, that will be described hereafter, was designed constructed and
instrumented to perform a real scale analysis of the same interface
configurations. The parameters (stress, strain and temperature) measured in this
section will also give feedback for the evaluation of the test results.
45.0 m
0.0 m
Wall
Reference Plan view
N
5.0 m
CF UN FP Wheel Path
Geogrid No Geogrid Geogrid
Wall
The existing asphalt surfacing was milled and reconstructed, while the
unbound granular base course and the subgrade were maintained (§4.1). The
cross section of the test pavement is depicted in Figure 2. The new surfacing is
composed by:
- a lower asphalt concrete layer (thickness 40 mm).;
- the interface (either reinforced or unreinforced);
- an upper asphalt concrete layer (thickness 50 mm)
The same asphalt concrete mixture was used for the two layers (§2.3).
To simulate challenging situations frequently encountered in overlaying
projects, areas with “artificial” cracks and critical bonding conditions were
prepared in the lower asphalt layer (Figure 3). The artificial cracks where
produced through full-depth saw cuts in the lower asphalt layer, while a thin
layer of fine sand was used to create de-bonding.
3
50 mm Upper AC Layer
Interface
40 mm Lower AC Layer
Subgrade
7.0 m
2.0 m
8.6 m
1.0 m
0.0 m
12.8 m
15.0 m
14.0 m
1.2 m
Reference
Wheel Path
area cracks
3.8 m
0.4 m
0.4 m
Figure 3 Debonding and artificial cracks on the lower asphalt layer surface.
4
100
Average gradation (100% crushed
limestone aggregates)
Specification limits for AC 12
75 Bitumen 5.4% by aggregate weight
Passing [%]
50
25
0
0.01 0.1 1 10 100
Sieve size [mm]
Figure 5 Glass fiber polymer geogrid (left); Carbon fiber geogrid (right);
3. INSTRUMENTATION
5
Plain view
1.0 m 0.6 m 0.6 m
0.6 m
Strain Gauge Wheel Path
Cross section
Upper AC layer
60 mm
Interface 140 mm
Lower AC layer
Unbounded base
Figure 6 Instrumented area plain view and cross section.
6
laptop computer. The HBM Catman Express software was used for data
acquisition. Each Spider8 unit is equipped with four digital amplifiers modules
(SR55) in 4.8 kHz carrier-frequency technology, suitable for passive
transducers, like the ASG, and the DC voltage output of the EPC. The
capability of one unit was extended with three DC modules (SR01) suitable for
resistance measurements up to 4.0 kOhm.
The data acquisition system was designed to carry out independent, full-
scale, field tests in each subsection. Therefore, the Spider8 units are connected
to the sensors installed in each subsection in a flexible and efficient manner. For
this task, a custom connection board was realized and installed at each
subsection, along with custom connection cables. The main system structure in
described in Figure 7:
- the EPC vertical pressure readings were carried out with a SR55
amplifier module, while its excitation was provided by a separate 12
VDC power supply circuit (Spider8 units provide only 1 V excitation
voltage);
- the four ASG were connected to the SR55 modules (4-wires full-bridge
circuits);
- the three thermistors (one from EPC, two from ASG) were connected to
the three SR01 modules; a 4.8 kOhm shunt resistance circuit was
necessary because the resistance of the thermistors at normal operating
temperatures (1–50 kOhm) falls outside the measuring range of the SR01
amplifier module (0-4 kOhm).
7
4. TEST SECTION CONSTRUCTION
8
Figure 8 shows the connection board and its roadside housing. At the end of
construction, a sensor survey revealed the following survival rate:
- pressure cells: 3 out of 3;
- ASG: 11 out of 12;
- traditional strain gauges: 16 out of 24.
Two types of full-scale tests have been scheduled on the instrumented test
section: Falling Weight Deflectometer and full scale truck tests.
FWD tests will be performed at selected points inside each subsection,
including the EPC and ASG positions. Figure 9 shows: (a) the superimposition
of the 3 EPC outputs obtained for 3 consecutive FWD drops in the same spot
and (b) the ASG response to a single FWD drop.
Full scale tests will be performed driving a loaded truck over the
instrumented area of each subsection. Figure 10 shows the time histories
recorded from the EPC and the longitudinal ASG during a pass of a 2 axle truck
on the unreinforced section. Stress and strains responses to each axle load is
visibly captured.
9
0.3 100
ASG L2
Pressure [MPa]
50
ASG T1
Strain [me]
0.2
0.1
ASG L1 -50
ASG T2
0 -100
0.12 0.17 0.22 0.1 0.15 0.2 0.25
Time [s] Time [s]
Figure 9 Sample stress and strain measurements from real scale test.
0.4 200
EPC
ASG L1
0.3 100
ASG L2
Pressure [MPa]
Strain [me]
0.2 0
0.1 -100
0 -200
-0.1 -300
2 2.2 2.4 2.6 2.8 3 3.2 3.4 3.6 3.8 4
Time [s]
Figure 10 Sample stress and strain measurements from real scale test.
CONCLUSIONS
A full-scale instrumented pavement test section was constructed along an in-
service road to study the effectiveness of geogrid reinforcement in asphalt
layers. A carbon fiber (CF) and a glass fiber reinforced polymer (FRP) geogrid
were installed inside an asphalt double-layer surfacing. In each subsection, one
pressure cell was installed near the top of the existing aggregate base, and four
asphalt strain gauges beneath the double-layer interface. Areas with artificial
cracks and de-bonding were also prepared. The data acquisition system was
realized to carry out independent, full-scale, field tests in each subsection. A
portable data acquisition unit can be easily connected to the installed sensors
using a custom connection board that was installed in each subsection. The
entire construction process took six working days and more than 90% of the
major sensors (EPC and ASG) survived this critical phase. The first full-scale
tests performed on the section with a FWD and driving a truck over the
10
instruments position confirm that vertical stresses inside the base course and
horizontal strains beneath the reinforced interface can be measured with
confidence.
REFERENCES:
11
[11] K. S. Henry, E. R. Cortez, L. S. Danyluk, G. Brentrup, N. Lamie and T. W.
Arnold, Construction and Instrumentation of Full-Scale Geogrid
Reinforced Pavement Test Sections, ERDC/CRREL TR-08-6, 2008.
[12] D.H. Timm, A.L. Priest, T.V. McEwen, Design and Instrumentation of the
Structural Pavement Experiment at the NCAT Test Track, NCAT Report
04-01, 2004.
[13] D. H. Timm, Design, Construction and Instrumentation of the 2006 Test
Track Structural Study, NCAT Report 09-01, 2009.
12