JMS Total Summary
JMS Total Summary
AWL F1 F2 GW RI HW FW WEL PNT CBT MHRS MHRS MHRS MHRS MHRS MHRS MHRS MHRS MHRS
NO TASKID No TAPHASE TASK TASKNOTE OWNER CONTR DATA DUR (HRS) (AWL) (F1) (F2) (GW) MHRS (HW) (FW) (WEL) (PNT) (CBT) SCAFFOLDING (M3) INSULATION (M2)
(RI)
MHRS MHRS CRANE GEN SET WELDING SET HTW/HBT COMPRESSOR
Open
RESOURCE (MAN) MANHOURS RESOURCE (EQPT)
AWL F1 F2 GW RI HW FW WEL PNT CBT MHRS MHRS MHRS MHRS MHRS MHRS MHRS MHRS MHRS
NO TASKID No TAPHASE TASK TASKNOTE OWNER CONTR DATA DUR (HRS) (AWL) (F1) (F2) (GW) MHRS (HW) (FW) (WEL) (PNT) (CBT) SCAFFOLDING (M3) INSULATION (M2)
(RI)
MHRS MHRS CRANE GEN SET WELDING SET HTW/HBT COMPRESSOR
1 IWR/BT2/2016/Dec/148 3/4"-AP-224318-1108B-NI PIPE REPLACEMENT & PAINTING
1 1-Pre Execution Material delivery INSP HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2 1-Pre Execution Material inspection by AIMD Inspector INSP HRSB 0 0 0 0 0 0 0 0 0 0 0 0
3 1-Pre Execution Spool fabrication, NDT Inspection by AIMD at workshop SHOPWELD 6 (2BW, 2SW) HRSB 0 0 0 0 0 0 0 0 0 0 0 0
4 1-Pre Execution Perform HT and Withness by AIMD Inspector INSP 0 0 0 0 0 0 0 0 0 0 0 0
5 1-Pre Execution Perform blasting and painting on new spool 0.68m2 HRSB 0 0 0 0 0 0 0 0 0 0 0 0
6 1-Pre Execution Painting inspection by AIMD HRSB 0 0 0 0 0 0 0 0 0 0 0 0
7 1-Pre Execution Erect external scaffolding HRSB 0 0 0 0 0 0 0 0 0 0 0 0
8 1-Pre Execution Remove insulation HRSB 0 0 0 0 0 0 0 0 0 0 0 0
14''-CS-244018-1120A-NI
14"-CR-244022-1120A-NI,
12''-CS-2254271-1120A-NI
12"-CR-225265-1120A-NI,
27 IWL/BT2/2018/12 PAINTING
10''-CS-225269-1120A-NI
10"-CR-225263-1120A-NI,
2''-CS-225486-1120A-NI
2"-CR-225487-1120A-NI
Open
RESOURCE (MAN) MANHOURS RESOURCE (EQPT)
AWL F1 F2 GW RI HW FW WEL PNT CBT MHRS MHRS MHRS MHRS MHRS MHRS MHRS MHRS MHRS
NO TASKID No TAPHASE TASK TASKNOTE OWNER CONTR DATA DUR (HRS) (AWL) (F1) (F2) (GW) MHRS (HW) (FW) (WEL) (PNT) (CBT) SCAFFOLDING (M3) INSULATION (M2)
(RI)
MHRS MHRS CRANE GEN SET WELDING SET HTW/HBT COMPRESSOR
29 2-Execution 2nd coat inspection by AIMD 0.06 1.00 0 0 0 0 0 0 0 0 0 0 0 0
30 2-Execution Painting final coat 0.06 0.06 1 1 0.12 0 0 0 0.06 0 0 0 0 0.06 0 0.12
31 2-Execution Overcoating interval 0.06 4 0 0 0 0 0 0 0 0 0 0 0 0
32 2-Execution Final coat inspection by AIMD 0.06 1 0 0 0 0 0 0 0 0 0 0 0 0
33 2-Execution Lift up pipe & support pipe using wooden block (2nd side ) 0 1 1 0 0 0 0 0 0 0 0 0 0 0 0
34 2-Execution Surface preparation (Power tool) 0 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0
35 2-Execution Inspection surface preparation by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
36 2-Execution Painting 1st coat 0.00 1 1 0 0 0 0 0 0 0 0 0 0 0 0
37 2-Execution Overcoating interval 0 0 0 0 0 0 0 0 0 0 0 0
38 2-Execution 1st coat inspection by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
39 2-Execution Painting 2nd coat 0.00 1 1 0 0 0 0 0 0 0 0 0 0 0 0
40 2-Execution Overcoating interval 0 0 0 0 0 0 0 0 0 0 0 0
41 2-Execution 2nd coat inspection by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
42 2-Execution Painting final coat 0.00 1 1 0 0 0 0 0 0 0 0 0 0 0 0
43 2-Execution Overcoating interval 0 0 0 0 0 0 0 0 0 0 0 0
44 2-Execution Final coat inspection by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
45 2-Execution Lift up pipe,remove wooden block & lift down pipe 1 1 0 0 0 0 0 0 0 0 0 0 0 0
46 2-Execution To apply silicone sealant 0 1 0 0 0 0 0 0 0 0 0 0 0 0
47 2-Execution Housekeeping 1 1 1 0 0 0 1 0 0 0 0 0 0 1
0 0 0 0 0 0 0 0 0 0 0 0
3-Post Execution C) Post execution 0 0 0 0 0 0 0 0 0 0 0 0
48 3-Post Execution Re instate Insulation 0 0 0 0 0 0 0 0 0 0 0 0
49 3-Post Execution Dismantle External Scaffolding 0 0 0 0 0 0 0 0 0 0 0 0
50 3-Post Execution Demobilization 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
47.169853 14.85602 0 3.5163 0 7.1699 0 0 1.5163 0 2.6535 0 14.85602
53 IWR/BT3/FY2018/707 1"-PL-291045-1101A-NI PAINTING
1 1-Pre Execution a) Site Preparation HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2 1-Pre Execution Mobilization manpower, equipment, tools & consumable HRSB 0 0 0 0 0 0 0 0 0 0 0 0
3 1-Pre Execution Apply protection on others PPTSB assets equipment/cable/tag number and etc. HRSB 0 0 0 0 0 0 0 0 0 0 0 0
4 1-Pre Execution Shelter/Laydown erection 0 0 0 0 0 0 0 0 0 0 0 0
5 1-Pre Execution Scaffolding erection HRSB 0 0 0 0 0 0 0 0 0 0 0 0
6 1-Pre Execution Remove Insulation HRSB 0 0 0 0 0 0 0 0 0 0 0 0
HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution b) During Project Activity HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution 1.0 Painting pipe HRSB 0 0 0 0 0 0 0 0 0 0 0 0
7 2-Execution Site preparation INSP 1 1 1 2 0 1 0 1 0 0 0 0 0 0 2
8 2-Execution Surface preparation (Power tool) 0.63 1.2651317 1 1 1 3.795395 0 1.2651 0 1.2651 0 0 1.2651 0 0 0 3.795395
9 2-Execution Inspection surface preparation by AIMD 0.63 1 0 0 0 0 0 0 0 0 0 0 0 0
10 2-Execution Painting 1st coat INSP 0.63 0.95 1 1 1.897697 0 0 0 0.9488 0 0 0 0 0.9488 0 1.897697
11 2-Execution Overcoating interval HRSB 0.63 8 0 0 0 0 0 0 0 0 0 0 0 0
12 2-Execution 1st coat inspection by AIMD INSP 0.63 1 0 0 0 0 0 0 0 0 0 0 0 0
13 2-Execution Painting 2nd coat HRSB 0.63 0.63 1 1 1.265132 0 0 0 0.6326 0 0 0 0 0.6326 0 1.265132
14 2-Execution Overcoating interval INSP 0.63 4 0 0 0 0 0 0 0 0 0 0 0 0
15 2-Execution 2nd coat inspection by AIMD INSP 0.63 1 0 0 0 0 0 0 0 0 0 0 0 0
16 2-Execution Painting final coat HRSB 0.63 0.63 1 1 1.265132 0 0 0 0.6326 0 0 0 0 0.6326 0 1.265132
17 2-Execution Overcoating interval HRSB 0.63 4 0 0 0 0 0 0 0 0 0 0 0 0
18 2-Execution Final coat inspection by AIMD INSP 0.63 1 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
2-Execution 2.0 Painting pipe support 0 0 0 0 0 0 0 0 0 0 0 0
19 2-Execution Site preparation INSP 1 1 1 2 0 1 0 1 0 0 0 0 0 0 2
20 2-Execution Lift up pipe & support pipe using wooden block (1st side ) INSP HRSB 1 1 0 0 0 0 0 0 0 0 0 0 0 0
21 2-Execution To reinstate pipe support to its original position / Insert round bar 3 1 0
0 0 0 0 0 0 0 0 0 0 0
22 2-Execution Surface preparation (Power tool) HRSB 0.06 0.12 1 1 1 0.36 0 0.12 0 0.12 0 0 0.12 0 0 0 0.36
23 2-Execution Inspection surface preparation by AIMD HRSB 0.06 1 0 0 0 0 0 0 0 0 0 0 0 0
24 2-Execution Painting 1st coat INSP 0.06 0.09 1 1 0.18 0 0 0 0.09 0 0 0 0 0.09 0 0.18
25 2-Execution Overcoating interval HRSB 0.06 8 0 0 0 0 0 0 0 0 0 0 0 0
26 2-Execution 1st coat inspection by AIMD 0.06 1 0 0 0 0 0 0 0 0 0 0 0 0
27 2-Execution Painting 2nd coat 0.06 0.06 1 1 0.12 0 0 0 0.06 0 0 0 0 0.06 0 0.12
28 2-Execution Overcoating interval 0.06 4 0 0 0 0 0 0 0 0 0 0 0 0
29 2-Execution 2nd coat inspection by AIMD 0.06 1.00 0 0 0 0 0 0 0 0 0 0 0 0
30 2-Execution Painting final coat 0.06 0.06 1 1 0.12 0 0 0 0.06 0 0 0 0 0.06 0 0.12
31 2-Execution Overcoating interval 0.06 4 0 0 0 0 0 0 0 0 0 0 0 0
32 2-Execution Final coat inspection by AIMD 0.06 1 0 0 0 0 0 0 0 0 0 0 0 0
33 2-Execution Lift up pipe & support pipe using wooden block (2nd side ) 0 1 1 0 0 0 0 0 0 0 0 0 0 0 0
34 2-Execution Surface preparation (Power tool) 0 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0
35 2-Execution Inspection surface preparation by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
36 2-Execution Painting 1st coat 0.00 1 1 0 0 0 0 0 0 0 0 0 0 0 0
37 2-Execution Overcoating interval 0 0 0 0 0 0 0 0 0 0 0 0
38 2-Execution 1st coat inspection by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
39 2-Execution Painting 2nd coat 0.00 1 1 0 0 0 0 0 0 0 0 0 0 0 0
40 2-Execution Overcoating interval 0 0 0 0 0 0 0 0 0 0 0 0
41 2-Execution 2nd coat inspection by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
42 2-Execution Painting final coat 0.00 1 1 0 0 0 0 0 0 0 0 0 0 0 0
43 2-Execution Overcoating interval 0 0 0 0 0 0 0 0 0 0 0 0
44 2-Execution Final coat inspection by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
45 2-Execution Lift up pipe,remove wooden block & lift down pipe 1 1 0 0 0 0 0 0 0 0 0 0 0 0
46 2-Execution To apply silicone sealant 0 1 0 0 0 0 0 0 0 0 0 0 0 0
47 2-Execution Housekeeping 1 1 1 0 0 0 1 0 0 0 0 0 0 1
0 0 0 0 0 0 0 0 0 0 0 0
3-Post Execution C) Post execution 0 0 0 0 0 0 0 0 0 0 0 0
48 3-Post Execution Re instate Insulation 0 0 0 0 0 0 0 0 0 0 0 0
49 3-Post Execution Dismantle External Scaffolding 0 0 0 0 0 0 0 0 0 0 0 0
50 3-Post Execution Demobilization 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
46.809112 14.00336 0 3.3851 0 6.8091 0 0 1.3851 0 2.424 0 14.00336
Open
REMAKS
Open
REMAKS
Open
REMAKS
Open
REMAKS
Open
REMAKS
Open
REMAKS
Open
REMAKS
Open
REMAKS
Open
REMAKS
Open
REMAKS
Open
REMAKS
Open
REMAKS
Open
REMAKS
Open
REMAKS
Open
REMAKS
Open
REMAKS
Open
REMAKS
Open
REMAKS
Open
REMAKS
Open
REMAKS
Open
REMAKS
Open
REMAKS
Open
REMAKS
Open
REMAKS
Open
REMAKS
Open
REMAKS
Open
REMAKS
Open
REMAKS
Open
REMAKS
Open
REMAKS
Open
REMAKS
Open
REMAKS
Open
REMAKS
Open
REMAKS
Open
REMAKS
Open
EIS (above to 12" Nom Bore) DURATION HRS
BLIND NO SIZE RATING BLINDING DE.BLIND FIL HLP
0.00 0.00 2 1
0.00 0.00 2 1
TOTAL 0.0 0.0
DURATION HRS
qty
piping
cutting/
weld type SIZE sch fit up weld
bevel
SW 3/4 80 0.4 0.20 0.6 1
SW 3/4 80 0.4 0.20 0.6 1
duration
QTY xtvt vol.m2 TOTAL SS FW
(hrs)
DURATION
Site pre 0.68 1 1
Surface prep 0.68 2 1.36323525 1 1
SP Insp. 0.68 1 0.681617625
1st coat 0.68 1.5 1.0224264375 1
curing 0.68 8 5.452941
1st coat Insp 0.68 1 0.681617625
2nd coat 0.68 1 0.681617625 1
curing 0.68 4 2.7264705
2nd coat Insp 0.68 1 0.681617625
Final coat 0.68 1 0.681617625 1
curing 0.68 4 2.7264705
Final coat Insp 0.68 1 0.681617625
TOTAL 0.00 0.00
CLEANING FORMULA
ID H π D
SHELL 4.88 28.4 3.142 4.88
SHELL 3 20.315 4.142 3
ELLIP TOP 3 1 1.084 3
ELLIP BOTTOM 4.88 1 1.084 4.88
D
ELLIP SHELL bottom 4.942 1 1.084
1.084 0
CLEANING LGHT ID π TOTAL QTY PLATE
PERIMETER
CLEANING FORMULA
ID H π D
TRAY 4.942 3.142 4.942
TRAY 3 3.142 3
D
1.084 0
1.084 0
NDT
NO TYPE QTY DURATION TOTAL DUR
1 BORO 0.083 0.0
2 IRIS 0.367 0.0
3 RFET 0.083 0.0
TOTAL (HR) 0.53 0.0
INT.SCAFFOLDING DURATION
L W H M3 ERECT DISMANTLE
5 5 4 100 25 25 bottom
5 5 2.5 63 16 16 tray 35#
0 0 0
TOTAL 163 41 41
RIG
0.00
TOTAL 0.0
HRS FOR
WELD
ONLY
RIG
RIG
1
1
TOUCH UP
1 Site pre
1 Surface prep
1 SP Insp.
1 1st coat
curing
1 1st coat Insp
1 2nd coat
curing
1 2nd coat Insp
1 Final coat
curing
1 Final coat Insp
RIG
ORMULA DURATION
AREA M2
H WIRE BRUSH COTTON RAG POWER BRUSH
28.4 435.46 217.73 145.15 72.58
20.32 252.43 126.22 84.14 42.07
1 3.25 1.63 1.08 0.54
1 5.29 2.64 1.76 0.88
D
0.00 0.00 0.00 0.00
0 0.00 0.00 0.00 0.00
TOTAL 696.43 348.22 232.14 73.46
DURATION
TOTAL
WELMENT TOTAL
QTY PLATE WELDMENT POWER BRUSH
TOP ELLIP VESSEL
& LENGTH
BOTTOM
ELLIP
15.53 23.67 582.29 97.0
12.43 16.93 340.39 56.7
9.43 0.83 61.27 10.2
15.53 0.83 100.93 16.8
0.00 0.00 0.00 0.0
TOTAL 271.22 45.2 25% TOTAL WELDMENT
ORMULA DURATION
AREA M2
H WIRE BRUSH COTTON RAG POWER BRUSH
0 124.22 62.11 41.41 20.70
0 61.27 30.63 20.42 10.21
D
0 0.00 0.00 0.00 0.00
0 0.00 0.00 0.00 0.00
TOTAL 185.49 92.75 61.83 30.92
0.00 1 1
0.0
DURATION HRS
Total
duration
vol.m2 duration
(hrs)
(hrs)
1 1
0.06 2 0.12
0.06 1 0.06
0.06 1.5 0.09
0.06 8 0.48
0.06 1 0.06
0.06 1 0.06
0.06 4 0.24
0.06 1 0.06
0.06 1 0.06
0.06 4 0.24
0.06 1 0.06
TOTAL 0.33
flushing
TOTAL WELDMENT
4 4 1
2 2 1
PCOGD SDN BHD TURNAROUND 2019
NO WORK ID LINE NO JOINT SIZE SCH WELD TYPE FW/SW F/U V/I DPI RT RT 1 HT PAINTING REMARKS
IWR/BT2/2016/Dec/148 3/4"-AP-224318-1108B-NI
1 3/4"-AP-224318-1108B-NI 1 0.75 80 SW FW 3/4 @ 0.75
3/4"-AP-224318-1108B-NI 2 0.75 80 SW FW 3/4 @ 0.75
3/4"-AP-224318-1108B-NI 3 0.75 80 BW SW 3/4 @ 0.75
3/4"-AP-224318-1108B-NI 4 0.75 80 BW SW 3/4 @ 0.75
3/4"-AP-224318-1108B-NI 5 0.75 80 SW SW 3/4 @ 0.75
3/4"-AP-224318-1108B-NI 6 0.75 80 SW SW 3/4 @ 0.75
Fit-up Joint Dia inch Fit-up Joint Dia inch DPI Done RT Done Ht Done PAINTING
Welded Weld Done
0 0 0 0 0 0 0 0
WORK REQUERST
TOTAL TOTAL DIA
SHOP FIELD SHOP FIELD JOINT INCH (Overall)
(Overall)
SW BW SW BW TH TH
JOINT 2 2 2 0 0 0 6
DIA INCH 1.50 1.5 1.5 0 0 0 4.50
TOTAL JT 4 TOTAL JT 2
TOTAL Ø
TOTAL Ø INCH 3 INCH 1.5 RT (total) RT (SHOP) RT (FIELD)
JOINT SW TOTAL JOINT SHOP/FIELD 6 2 2 0
AND BW DIA INCH JOINT SHOP/FIELD 4.5
#DIV/0!
MTO
Sch/
Item Qty Unit Size Description Rate (RM)
Rating
1 PIPE
2 6.5 m 3/4'' sch80 API5LGr.B SMLS PE SCH80
3
4
5 ELBOW 90
6 1 ea 3/4'' sch80 A234 GR.WPB SMLS BW
7
8
9 COUPLING
10 2 ea 3/4'' A234 WPB SW
11
12
13
14
15
16
17
18
19
20
21
Total (RM)