Professional Documents
Culture Documents
JMS IWL TA4MS SUMMARY Rev00
JMS IWL TA4MS SUMMARY Rev00
AWL F1 F2 GW RI HW FW WEL PNT CBT MHRS MHRS MHRS MHRS MHRS MHRS MHRS MHRS MHRS
NO TASKID No TAPHASE TASK TASKNOTE OWNER CONTR DATA DUR (HRS) (AWL) (F1) (F2) (GW) MHRS (HW) (FW) (WEL) (PNT) (CBT) SCAFFOLDING (M3) INSULATION (M2)
(RI)
MHRS MHRS CRANE GEN SET WELDING SET HTW/HBT COMPRESSOR
PIPING
Open
RESOURCE (MAN) MANHOURS RESOURCE (EQPT)
AWL F1 F2 GW RI HW FW WEL PNT CBT MHRS MHRS MHRS MHRS MHRS MHRS MHRS MHRS MHRS
NO TASKID No TAPHASE TASK TASKNOTE OWNER CONTR DATA DUR (HRS) (AWL) (F1) (F2) (GW) MHRS (HW) (FW) (WEL) (PNT) (CBT) SCAFFOLDING (M3) INSULATION (M2)
(RI)
MHRS MHRS CRANE GEN SET WELDING SET HTW/HBT COMPRESSOR
31 2-Execution Deblinding as per EIS (above to 12" Nom Bore) HRSB 0 0 0 0 0 0 0 0 0 0 0 0
32 2-Execution Deblinding as per EIS (above to 4" Nom Bore) HRSB 2 1 0 0 0 0 0 0 0 0 0 0 0 0
33 2-Execution Deblinding as per EIS (up to 4" Nom Bore) HRSB 1 0.4 1 1 0.8 0 0.4 0 0.4 0 0 0 0 0 0 0.8
34 2-Execution Housekeeping HRSB 1 1 1 0 0 0 1 0 0 0 0 0 0 1
Open
RESOURCE (MAN) MANHOURS RESOURCE (EQPT)
AWL F1 F2 GW RI HW FW WEL PNT CBT MHRS MHRS MHRS MHRS MHRS MHRS MHRS MHRS MHRS
NO TASKID No TAPHASE TASK TASKNOTE OWNER CONTR DATA DUR (HRS) (AWL) (F1) (F2) (GW) MHRS (HW) (FW) (WEL) (PNT) (CBT) SCAFFOLDING (M3) INSULATION (M2)
(RI)
MHRS MHRS CRANE GEN SET WELDING SET HTW/HBT COMPRESSOR
2-Execution 2.0 Painting pipe HRSB 0 0 0 0 0 0 0 0 0 0 0 0
59 2-Execution Site preparation HRSB 1 1 1 2 0 1 0 1 0 0 0 0 0 0 2
60 2-Execution Remove & Install new U-bolt 12'' 2 1 1 1 2 0 1 0 1 0 0 0 0 0 0 2
61 2-Execution Surface preparation (Power tool) HRSB 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0
62 2-Execution Inspection surface preparation by AIMD HRSB 0 0 0 0 0 0 0 0 0 0 0 0
63 2-Execution Painting 1st coat HRSB 1 1 0 0 0 0 0 0 0 0 0 0 0 0
64 2-Execution Overcoating interval HRSB 0 0 0 0 0 0 0 0 0 0 0 0
65 2-Execution 1st coat inspection by AIMD HRSB 0 0 0 0 0 0 0 0 0 0 0 0
66 2-Execution Painting 2nd coat HRSB 1 1 0 0 0 0 0 0 0 0 0 0 0 0
67 2-Execution Overcoating interval HRSB 0 0 0 0 0 0 0 0 0 0 0 0
68 2-Execution 2nd coat inspection by AIMD HRSB 0 0 0 0 0 0 0 0 0 0 0 0
69 2-Execution Painting final coat HRSB 1 1 0 0 0 0 0 0 0 0 0 0 0 0
70 2-Execution Overcoating interval HRSB 0 0 0 0 0 0 0 0 0 0 0 0
71 2-Execution Final coat inspection by AIMD HRSB 0 0 0 0 0 0 0 0 0 0 0 0
PAINTING
8''-PG-225178-1101A-PG
1 IWL/BT2/2018/21 PAINTING
2"-SVH-225380-1101A-NI
1 1-Pre Execution a) Site Preparation HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2 1-Pre Execution Mobilization manpower, equipment, tools & consumable HRSB 0 0 0 0 0 0 0 0 0 0 0 0
3 1-Pre Execution Apply protection on others PPTSB assets equipment/cable/tag number and etc. HRSB 0 0 0 0 0 0 0 0 0 0 0 0
4 1-Pre Execution Shelter/Laydown erection 0 0 0 0 0 0 0 0 0 0 0 0
5 1-Pre Execution Scaffolding erection HRSB 0 0 0 0 0 0 0 0 0 0 0 0
6 1-Pre Execution Remove Insulation 0 0 0 0 0 0 0 0 0 0 0 0
HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution b) During Project Activity HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution 1.0 Painting pipe HRSB 0 0 0 0 0 0 0 0 0 0 0 0
7 2-Execution Site preparation INSP 1 1 1 2 0 1 0 1 0 0 0 0 0 0 2
8 2-Execution Surface preparation (Power tool) 84.32 168.64371 1 1 1 505.9311 0 168.64 0 168.64 0 0 168.64 0 0 0 505.9311
9 2-Execution Inspection surface preparation by AIMD 84.32 1 0 0 0 0 0 0 0 0 0 0 0 0
10 2-Execution Painting 1st coat INSP 84.32 126.48 1 1 252.9656 0 0 0 126.48 0 0 0 0 126.48 0 252.9656
11 2-Execution Overcoating interval HRSB 84.32 8 0 0 0 0 0 0 0 0 0 0 0 0
12 2-Execution 1st coat inspection by AIMD INSP 84.32 1 0 0 0 0 0 0 0 0 0 0 0 0
13 2-Execution Painting 2nd coat HRSB 84.32 84.32 1 1 168.6437 0 0 0 84.322 0 0 0 0 84.322 0 168.6437
14 2-Execution Overcoating interval INSP 84.32 4 0 0 0 0 0 0 0 0 0 0 0 0
15 2-Execution 2nd coat inspection by AIMD INSP 84.32 1 0 0 0 0 0 0 0 0 0 0 0 0
16 2-Execution Painting final coat HRSB 84.32 84.32 1 1 168.6437 0 0 0 84.322 0 0 0 0 84.322 0 168.6437
17 2-Execution Overcoating interval HRSB 84.32 4 0 0 0 0 0 0 0 0 0 0 0 0
18 2-Execution Final coat inspection by AIMD INSP 84.32 1 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution 2.0 Painting pipe support HRSB 0 0 0 0 0 0 0 0 0 0 0 0
19 2-Execution Lift up pipe & support pipe using wooden block (1st side ) INSP HRSB 1 1 0 0 0 0 0 0 0 0 0 0 0 0
20 2-Execution To reinstate pipe support to its original position / Insert round bar 3 1 0
0 0 0 0 0 0 0 0 0 0 0
21 2-Execution Surface preparation (Power tool) HRSB 1.80 3.6 1 1 1 10.8 0 3.6 0 3.6 0 0 3.6 0 0 0 10.8
22 2-Execution Inspection surface preparation by AIMD HRSB 1.80 1 0 0 0 0 0 0 0 0 0 0 0 0
23 2-Execution Painting 1st coat INSP 1.80 2.70 1 1 5.4 0 0 0 2.7 0 0 0 0 2.7 0 5.4
24 2-Execution Overcoating interval HRSB 1.80 8 0 0 0 0 0 0 0 0 0 0 0 0
25 2-Execution 1st coat inspection by AIMD 1.80 1 0 0 0 0 0 0 0 0 0 0 0 0
26 2-Execution Painting 2nd coat 1.80 1.80 1 1 3.6 0 0 0 1.8 0 0 0 0 1.8 0 3.6
27 2-Execution Overcoating interval 1.80 4 0 0 0 0 0 0 0 0 0 0 0 0
28 2-Execution 2nd coat inspection by AIMD 1.80 1.00 0 0 0 0 0 0 0 0 0 0 0 0
29 2-Execution Painting final coat 1.80 1.80 1 1 3.6 0 0 0 1.8 0 0 0 0 1.8 0 3.6
30 2-Execution Overcoating interval 1.80 4 0 0 0 0 0 0 0 0 0 0 0 0
31 2-Execution Final coat inspection by AIMD 1.80 1 0 0 0 0 0 0 0 0 0 0 0 0
32 2-Execution Lift up pipe & support pipe using wooden block (2nd side ) 0 1 1 0 0 0 0 0 0 0 0 0 0 0 0
33 2-Execution Surface preparation (Power tool) 0 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0
34 2-Execution Inspection surface preparation by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
35 2-Execution Painting 1st coat 0.00 1 1 0 0 0 0 0 0 0 0 0 0 0 0
36 2-Execution Overcoating interval 0 0 0 0 0 0 0 0 0 0 0 0
37 2-Execution 1st coat inspection by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
38 2-Execution Painting 2nd coat 0.00 1 1 0 0 0 0 0 0 0 0 0 0 0 0
39 2-Execution Overcoating interval 0 0 0 0 0 0 0 0 0 0 0 0
40 2-Execution 2nd coat inspection by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
41 2-Execution Painting final coat 0.00 1 1 0 0 0 0 0 0 0 0 0 0 0 0
42 2-Execution Overcoating interval 0 0 0 0 0 0 0 0 0 0 0 0
43 2-Execution Final coat inspection by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
Open
RESOURCE (MAN) MANHOURS RESOURCE (EQPT)
AWL F1 F2 GW RI HW FW WEL PNT CBT MHRS MHRS MHRS MHRS MHRS MHRS MHRS MHRS MHRS
NO TASKID No TAPHASE TASK TASKNOTE OWNER CONTR DATA DUR (HRS) (AWL) (F1) (F2) (GW) MHRS (HW) (FW) (WEL) (PNT) (CBT) SCAFFOLDING (M3) INSULATION (M2)
(RI)
MHRS MHRS CRANE GEN SET WELDING SET HTW/HBT COMPRESSOR
44 2-Execution Lift up pipe,remove wooden block & lift down pipe 1 1 0 0 0 0 0 0 0 0 0 0 0 0
45 2-Execution To apply silicone sealant 0 1 0 0 0 0 0 0 0 0 0 0 0 0
48 2-Execution Housekeeping 1 1 1 0 0 0 1 0 0 0 0 0 0 1
0 0 0 0 0 0 0 0 0 0 0 0
3-Post Execution C) Post execution 0 0 0 0 0 0 0 0 0 0 0 0
49 3-Post Execution Re instate Insulation 0 0 0 0 0 0 0 0 0 0 0 0
50 3-Post Execution Dismantle External Scaffolding 0 0 0 0 0 0 0 0 0 0 0 0
51 3-Post Execution Demobilization 0 0 0 0 0 0 0 0 0 0 0 0
515.6702 1122.584 0 173.24 0 475.67 0 0 172.24 0 301.43 0 1122.584
2 IWL/BT2/2018/22 8''-PL-225127-1101A-PG PAINTING
1 1-Pre Execution a) Site Preparation HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2 1-Pre Execution Mobilization manpower, equipment, tools & consumable HRSB 0 0 0 0 0 0 0 0 0 0 0 0
3 1-Pre Execution Apply protection on others PPTSB assets equipment/cable/tag number and etc. HRSB 0 0 0 0 0 0 0 0 0 0 0 0
4 1-Pre Execution Shelter/Laydown erection 0 0 0 0 0 0 0 0 0 0 0 0
5 1-Pre Execution Scaffolding erection HRSB 0 0 0 0 0 0 0 0 0 0 0 0
6 1-Pre Execution Remove Insulation 0 0 0 0 0 0 0 0 0 0 0 0
HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution b) During Project Activity HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution 1.0 Painting pipe HRSB 0 0 0 0 0 0 0 0 0 0 0 0
7 2-Execution Site preparation INSP 1 1 1 2 0 1 0 1 0 0 0 0 0 0 2
8 2-Execution Surface preparation (Power tool) 56.51 113.02544 1 1 1 339.0763 0 113 0 113 0 0 113 0 0 0 339.0763
9 2-Execution Inspection surface preparation by AIMD 56.51 1 0 0 0 0 0 0 0 0 0 0 0 0
10 2-Execution Painting 1st coat INSP 56.51 84.77 1 1 169.5382 0 0 0 84.769 0 0 0 0 84.769 0 169.5382
11 2-Execution Overcoating interval HRSB 56.51 8 0 0 0 0 0 0 0 0 0 0 0 0
12 2-Execution 1st coat inspection by AIMD INSP 56.51 1 0 0 0 0 0 0 0 0 0 0 0 0
13 2-Execution Painting 2nd coat HRSB 56.51 56.51 1 1 113.0254 0 0 0 56.513 0 0 0 0 56.513 0 113.0254
14 2-Execution Overcoating interval INSP 56.51 4 0 0 0 0 0 0 0 0 0 0 0 0
15 2-Execution 2nd coat inspection by AIMD INSP 56.51 1 0 0 0 0 0 0 0 0 0 0 0 0
16 2-Execution Painting final coat HRSB 56.51 56.51 1 1 113.0254 0 0 0 56.513 0 0 0 0 56.513 0 113.0254
17 2-Execution Overcoating interval HRSB 56.51 4 0 0 0 0 0 0 0 0 0 0 0 0
18 2-Execution Final coat inspection by AIMD INSP 56.51 1 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution 2.0 Painting pipe support HRSB 0 0 0 0 0 0 0 0 0 0 0 0
19 2-Execution Lift up pipe & support pipe using wooden block (1st side ) INSP HRSB 1 1 0 0 0 0 0 0 0 0 0 0 0 0
20 2-Execution To reinstate pipe support to its original position / Insert round bar 3 1 0
0 0 0 0 0 0 0 0 0 0 0
21 2-Execution Surface preparation (Power tool) HRSB 3.24 6.48 1 1 1 19.44 0 6.48 0 6.48 0 0 6.48 0 0 0 19.44
22 2-Execution Inspection surface preparation by AIMD HRSB 3.24 1 0 0 0 0 0 0 0 0 0 0 0 0
23 2-Execution Painting 1st coat INSP 3.24 4.86 1 1 9.72 0 0 0 4.86 0 0 0 0 4.86 0 9.72
24 2-Execution Overcoating interval HRSB 3.24 8 0 0 0 0 0 0 0 0 0 0 0 0
25 2-Execution 1st coat inspection by AIMD 3.24 1 0 0 0 0 0 0 0 0 0 0 0 0
26 2-Execution Painting 2nd coat 3.24 3.24 1 1 6.48 0 0 0 3.24 0 0 0 0 3.24 0 6.48
27 2-Execution Overcoating interval 3.24 4 0 0 0 0 0 0 0 0 0 0 0 0
28 2-Execution 2nd coat inspection by AIMD 3.24 1.00 0 0 0 0 0 0 0 0 0 0 0 0
29 2-Execution Painting final coat 3.24 3.24 1 1 6.48 0 0 0 3.24 0 0 0 0 3.24 0 6.48
30 2-Execution Overcoating interval 3.24 4 0 0 0 0 0 0 0 0 0 0 0 0
31 2-Execution Final coat inspection by AIMD 3.24 1 0 0 0 0 0 0 0 0 0 0 0 0
32 2-Execution Lift up pipe & support pipe using wooden block (2nd side ) 0 1 1 0 0 0 0 0 0 0 0 0 0 0 0
33 2-Execution Surface preparation (Power tool) 0 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0
34 2-Execution Inspection surface preparation by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
35 2-Execution Painting 1st coat 0.00 1 1 0 0 0 0 0 0 0 0 0 0 0 0
36 2-Execution Overcoating interval 0 0 0 0 0 0 0 0 0 0 0 0
37 2-Execution 1st coat inspection by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
38 2-Execution Painting 2nd coat 0.00 1 1 0 0 0 0 0 0 0 0 0 0 0 0
39 2-Execution Overcoating interval 0 0 0 0 0 0 0 0 0 0 0 0
40 2-Execution 2nd coat inspection by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
41 2-Execution Painting final coat 0.00 1 1 0 0 0 0 0 0 0 0 0 0 0 0
42 2-Execution Overcoating interval 0 0 0 0 0 0 0 0 0 0 0 0
43 2-Execution Final coat inspection by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
44 2-Execution Lift up pipe,remove wooden block & lift down pipe 1 1 0 0 0 0 0 0 0 0 0 0 0 0
45 2-Execution To apply silicone sealant 0 1 0 0 0 0 0 0 0 0 0 0 0 0
48 2-Execution Housekeeping 1 1 1 0 0 0 1 0 0 0 0 0 0 1
0 0 0 0 0 0 0 0 0 0 0 0
3-Post Execution C) Post execution 0 0 0 0 0 0 0 0 0 0 0 0
49 3-Post Execution Re instate Insulation 0 0 0 0 0 0 0 0 0 0 0 0
50 3-Post Execution Dismantle External Scaffolding 0 0 0 0 0 0 0 0 0 0 0 0
51 3-Post Execution Demobilization 0 0 0 0 0 0 0 0 0 0 0 0
370.63995 779.7853 0 120.51 0 330.64 0 0 119.51 0 209.13 0 779.7853
6''-PL-225136-3101A-NI
3 IWL/BT2/2018/10 PAINTING
4"-PL-225145-3101A-NI
1 1-Pre Execution a) Site Preparation HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2 1-Pre Execution Mobilization manpower, equipment, tools & consumable HRSB 0 0 0 0 0 0 0 0 0 0 0 0
3 1-Pre Execution Apply protection on others PPTSB assets equipment/cable/tag number and etc. HRSB 0 0 0 0 0 0 0 0 0 0 0 0
4 1-Pre Execution Shelter/Laydown erection 0 0 0 0 0 0 0 0 0 0 0 0
5 1-Pre Execution Scaffolding erection HRSB 0 0 0 0 0 0 0 0 0 0 0 0
6 1-Pre Execution Remove Insulation 0 0 0 0 0 0 0 0 0 0 0 0
HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution b) During Project Activity HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution 1.0 Painting pipe HRSB 0 0 0 0 0 0 0 0 0 0 0 0
7 2-Execution Site preparation INSP 1 1 1 2 0 1 0 1 0 0 0 0 0 0 2
8 2-Execution Surface preparation (Power tool) 93.27 186.54 1 1 1 559.62 0 186.54 0 186.54 0 0 186.54 0 0 0 559.62
9 2-Execution Inspection surface preparation by AIMD 93.27 1 0 0 0 0 0 0 0 0 0 0 0 0
10 2-Execution Painting 1st coat INSP 93.27 139.91 1 1 279.81 0 0 0 139.91 0 0 0 0 139.91 0 279.81
11 2-Execution Overcoating interval HRSB 93.27 8 0 0 0 0 0 0 0 0 0 0 0 0
12 2-Execution 1st coat inspection by AIMD INSP 93.27 1 0 0 0 0 0 0 0 0 0 0 0 0
13 2-Execution Painting 2nd coat HRSB 93.27 93.27 1 1 186.54 0 0 0 93.27 0 0 0 0 93.27 0 186.54
14 2-Execution Overcoating interval INSP 93.27 4 0 0 0 0 0 0 0 0 0 0 0 0
15 2-Execution 2nd coat inspection by AIMD INSP 93.27 1 0 0 0 0 0 0 0 0 0 0 0 0
16 2-Execution Painting final coat HRSB 93.27 93.27 1 1 186.54 0 0 0 93.27 0 0 0 0 93.27 0 186.54
17 2-Execution Overcoating interval HRSB 93.27 4 0 0 0 0 0 0 0 0 0 0 0 0
18 2-Execution Final coat inspection by AIMD INSP 93.27 1 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution 2.0 Painting pipe support HRSB 0 0 0 0 0 0 0 0 0 0 0 0
Lift up pipe & support pipe using wooden block (1st side )/ To
19 2-Execution 0 1 1 0
reinstate pipe support to its original position INSP HRSB 0 0 0 0 0 0 0 0 0 0 0
20 2-Execution Surface preparation (Power tool) HRSB 6.16 12.32 1 1 1 36.96 0 12.32 0 12.32 0 0 12.32 0 0 0 36.96
21 2-Execution Inspection surface preparation by AIMD HRSB 6.16 1 0 0 0 0 0 0 0 0 0 0 0 0
Open
RESOURCE (MAN) MANHOURS RESOURCE (EQPT)
AWL F1 F2 GW RI HW FW WEL PNT CBT MHRS MHRS MHRS MHRS MHRS MHRS MHRS MHRS MHRS
NO TASKID No TAPHASE TASK TASKNOTE OWNER CONTR DATA DUR (HRS) (AWL) (F1) (F2) (GW) MHRS (HW) (FW) (WEL) (PNT) (CBT) SCAFFOLDING (M3) INSULATION (M2)
(RI)
MHRS MHRS CRANE GEN SET WELDING SET HTW/HBT COMPRESSOR
22 2-Execution Painting 1st coat INSP 6.16 9.24 1 1 18.48 0 0 0 9.24 0 0 0 0 9.24 0 18.48
23 2-Execution Overcoating interval HRSB 6.16 8 0 0 0 0 0 0 0 0 0 0 0 0
24 2-Execution 1st coat inspection by AIMD 6.16 1 0 0 0 0 0 0 0 0 0 0 0 0
25 2-Execution Painting 2nd coat 6.16 6.16 1 1 12.32 0 0 0 6.16 0 0 0 0 6.16 0 12.32
26 2-Execution Overcoating interval 6.16 4 0 0 0 0 0 0 0 0 0 0 0 0
27 2-Execution 2nd coat inspection by AIMD 6.16 1.00 0 0 0 0 0 0 0 0 0 0 0 0
28 2-Execution Painting final coat 6.16 6.16 1 1 12.32 0 0 0 6.16 0 0 0 0 6.16 0 12.32
29 2-Execution Overcoating interval 6.16 4 0 0 0 0 0 0 0 0 0 0 0 0
30 2-Execution Final coat inspection by AIMD 6.16 1 0 0 0 0 0 0 0 0 0 0 0 0
31 2-Execution Lift up pipe & support pipe using wooden block (2nd side ) 6.16 2.0328 1 1 4.0656 0 2.0328 0 2.0328 0 0 0 0 0 0 4.0656
32 2-Execution Surface preparation (Power tool) 6.16 12.32 1 1 1 36.96 0 12.32 0 12.32 0 0 12.32 0 0 0 36.96
33 2-Execution Inspection surface preparation by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
34 2-Execution Painting 1st coat 0.00 1 1 0 0 0 0 0 0 0 0 0 0 0 0
35 2-Execution Overcoating interval 0 0 0 0 0 0 0 0 0 0 0 0
36 2-Execution 1st coat inspection by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
37 2-Execution Painting 2nd coat 0.00 1 1 0 0 0 0 0 0 0 0 0 0 0 0
38 2-Execution Overcoating interval 0 0 0 0 0 0 0 0 0 0 0 0
39 2-Execution 2nd coat inspection by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
40 2-Execution Painting final coat 0.00 1 1 0 0 0 0 0 0 0 0 0 0 0 0
41 2-Execution Overcoating interval 0 0 0 0 0 0 0 0 0 0 0 0
42 2-Execution Final coat inspection by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
43 2-Execution Lift up pipe,remove wooden block & lift down pipe 0 1 1 0 0 0 0 0 0 0 0 0 0 0 0
44 2-Execution To apply silicone sealant 0 1 0 0 0 0 0 0 0 0 0 0 0 0
45 2-Execution Remove & install handle valve - 1 unit 1 1 0 0 0 0 0 0 0 0 0 0 0 0
46 2-Execution Housekeeping 1 1 1 2 0 1 0 1 0 0 0 0 0 0 2
0 0 0 0 0 0 0 0 0 0 0 0
3-Post Execution C) Post execution 0 0 0 0 0 0 0 0 0 0 0 0
47 3-Post Execution Re instate Insulation 0 0 0 0 0 0 0 0 0 0 0 0
48 3-Post Execution Dismantle External Scaffolding 0 0 0 0 0 0 0 0 0 0 0 0
49 3-Post Execution Demobilization 0 0 0 0 0 0 0 0 0 0 0 0
603.2178 1337.616 0 215.21 0 563.22 0 0 211.18 0 348 0 1337.616
4 IWL/BT2/2018/19 6''-PL-22064-3101A-NI PAINTING
1 1-Pre Execution a) Site Preparation HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2 1-Pre Execution Mobilization manpower, equipment, tools & consumable HRSB 0 0 0 0 0 0 0 0 0 0 0 0
3 1-Pre Execution Apply protection on others PPTSB assets equipment/cable/tag number and etc. HRSB 0 0 0 0 0 0 0 0 0 0 0 0
4 1-Pre Execution Shelter/Laydown erection 0 0 0 0 0 0 0 0 0 0 0 0
5 1-Pre Execution Scaffolding erection HRSB 0 0 0 0 0 0 0 0 0 0 0 0
6 1-Pre Execution Remove Insulation 0 0 0 0 0 0 0 0 0 0 0 0
HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution b) During Project Activity HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution 1.0 Painting pipe HRSB 0 0 0 0 0 0 0 0 0 0 0 0
7 2-Execution Site preparation INSP 1 1 1 2 0 1 0 1 0 0 0 0 0 0 2
8 2-Execution Surface preparation (Power tool) 79.39 158.77799 1 1 1 476.334 0 158.78 0 158.78 0 0 158.78 0 0 0 476.334
9 2-Execution Inspection surface preparation by AIMD 79.39 1 0 0 0 0 0 0 0 0 0 0 0 0
10 2-Execution Painting 1st coat INSP 79.39 119.08 1 1 238.167 0 0 0 119.08 0 0 0 0 119.08 0 238.167
11 2-Execution Overcoating interval HRSB 79.39 8 0 0 0 0 0 0 0 0 0 0 0 0
12 2-Execution 1st coat inspection by AIMD INSP 79.39 1 0 0 0 0 0 0 0 0 0 0 0 0
13 2-Execution Painting 2nd coat HRSB 79.39 79.39 1 1 158.778 0 0 0 79.389 0 0 0 0 79.389 0 158.778
14 2-Execution Overcoating interval INSP 79.39 4 0 0 0 0 0 0 0 0 0 0 0 0
15 2-Execution 2nd coat inspection by AIMD INSP 79.39 1 0 0 0 0 0 0 0 0 0 0 0 0
16 2-Execution Painting final coat HRSB 79.39 79.39 1 1 158.778 0 0 0 79.389 0 0 0 0 79.389 0 158.778
17 2-Execution Overcoating interval HRSB 79.39 4 0 0 0 0 0 0 0 0 0 0 0 0
18 2-Execution Final coat inspection by AIMD INSP 79.39 1 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution 2.0 Painting pipe support HRSB 0 0 0 0 0 0 0 0 0 0 0 0
19 2-Execution Lift up pipe & support pipe using wooden block (1st side ) INSP HRSB 1 1 0 0 0 0 0 0 0 0 0 0 0 0
20 2-Execution To reinstate pipe support to its original position / Insert round bar 3 1 0
0 0 0 0 0 0 0 0 0 0 0
21 2-Execution Surface preparation (Power tool) HRSB 8.40 16.8 1 1 1 50.4 0 16.8 0 16.8 0 0 16.8 0 0 0 50.4
22 2-Execution Inspection surface preparation by AIMD HRSB 8.40 1 0 0 0 0 0 0 0 0 0 0 0 0
23 2-Execution Painting 1st coat INSP 8.40 12.60 1 1 25.2 0 0 0 12.6 0 0 0 0 12.6 0 25.2
24 2-Execution Overcoating interval HRSB 8.40 8 0 0 0 0 0 0 0 0 0 0 0 0
25 2-Execution 1st coat inspection by AIMD 8.40 1 0 0 0 0 0 0 0 0 0 0 0 0
26 2-Execution Painting 2nd coat 8.40 8.40 1 1 16.8 0 0 0 8.4 0 0 0 0 8.4 0 16.8
27 2-Execution Overcoating interval 8.40 4 0 0 0 0 0 0 0 0 0 0 0 0
28 2-Execution 2nd coat inspection by AIMD 8.40 1.00 0 0 0 0 0 0 0 0 0 0 0 0
29 2-Execution Painting final coat 8.40 8.40 1 1 16.8 0 0 0 8.4 0 0 0 0 8.4 0 16.8
30 2-Execution Overcoating interval 8.40 4 0 0 0 0 0 0 0 0 0 0 0 0
31 2-Execution Final coat inspection by AIMD 8.40 1 0 0 0 0 0 0 0 0 0 0 0 0
32 2-Execution Lift up pipe & support pipe using wooden block (2nd side ) 0 1 1 0 0 0 0 0 0 0 0 0 0 0 0
33 2-Execution Surface preparation (Power tool) 0 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0
34 2-Execution Inspection surface preparation by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
35 2-Execution Painting 1st coat 0.00 1 1 0 0 0 0 0 0 0 0 0 0 0 0
36 2-Execution Overcoating interval 0 0 0 0 0 0 0 0 0 0 0 0
37 2-Execution 1st coat inspection by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
38 2-Execution Painting 2nd coat 0.00 1 1 0 0 0 0 0 0 0 0 0 0 0 0
39 2-Execution Overcoating interval 0 0 0 0 0 0 0 0 0 0 0 0
40 2-Execution 2nd coat inspection by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
41 2-Execution Painting final coat 0.00 1 1 0 0 0 0 0 0 0 0 0 0 0 0
42 2-Execution Overcoating interval 0 0 0 0 0 0 0 0 0 0 0 0
43 2-Execution Final coat inspection by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
44 2-Execution Lift up pipe,remove wooden block & lift down pipe 1 1 0 0 0 0 0 0 0 0 0 0 0 0
45 2-Execution To apply silicone sealant 0 1 0 0 0 0 0 0 0 0 0 0 0 0
48 2-Execution Housekeeping 1 1 1 0 0 0 1 0 0 0 0 0 0 1
0 0 0 0 0 0 0 0 0 0 0 0
3-Post Execution C) Post execution 0 0 0 0 0 0 0 0 0 0 0 0
49 3-Post Execution Re instate Insulation 0 0 0 0 0 0 0 0 0 0 0 0
50 3-Post Execution Dismantle External Scaffolding 0 0 0 0 0 0 0 0 0 0 0 0
51 3-Post Execution Demobilization 0 0 0 0 0 0 0 0 0 0 0 0
524.83947 1144.257 0 176.58 0 484.84 0 0 175.58 0 307.26 0 1144.257
5 IWL/BT2/2018/5 24''-P2-225188-1101A-NI PAINTING
1 1-Pre Execution a) Site Preparation HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2 1-Pre Execution Mobilization manpower, equipment, tools & consumable HRSB 0 0 0 0 0 0 0 0 0 0 0 0
3 1-Pre Execution Apply protection on others PPTSB assets equipment/cable/tag number and etc. HRSB 0 0 0 0 0 0 0 0 0 0 0 0
4 1-Pre Execution Shelter/Laydown erection 0 0 0 0 0 0 0 0 0 0 0 0
5 1-Pre Execution Scaffolding erection HRSB 0 0 0 0 0 0 0 0 0 0 0 0
6 1-Pre Execution Remove Insulation HRSB 0 0 0 0 0 0 0 0 0 0 0 0
Open
RESOURCE (MAN) MANHOURS RESOURCE (EQPT)
AWL F1 F2 GW RI HW FW WEL PNT CBT MHRS MHRS MHRS MHRS MHRS MHRS MHRS MHRS MHRS
NO TASKID No TAPHASE TASK TASKNOTE OWNER CONTR DATA DUR (HRS) (AWL) (F1) (F2) (GW) MHRS (HW) (FW) (WEL) (PNT) (CBT) SCAFFOLDING (M3) INSULATION (M2)
(RI)
MHRS MHRS CRANE GEN SET WELDING SET HTW/HBT COMPRESSOR
HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution b) During Project Activity HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution 1.0 Painting pipe HRSB 0 0 0 0 0 0 0 0 0 0 0 0
7 2-Execution Site preparation INSP 1 1 1 2 0 1 0 1 0 0 0 0 0 0 2
8 2-Execution Surface preparation (Power tool) 225.79 451.58081 1 1 1 1354.742 0 451.58 0 451.58 0 0 451.58 0 0 0 1354.742
9 2-Execution Inspection surface preparation by AIMD 225.79 1 0 0 0 0 0 0 0 0 0 0 0 0
10 2-Execution Painting 1st coat INSP 225.79 338.69 1 1 677.3712 0 0 0 338.69 0 0 0 0 338.69 0 677.3712
11 2-Execution Overcoating interval HRSB 225.79 8 0 0 0 0 0 0 0 0 0 0 0 0
12 2-Execution 1st coat inspection by AIMD INSP 225.79 1 0 0 0 0 0 0 0 0 0 0 0 0
13 2-Execution Painting 2nd coat HRSB 225.79 225.79 1 1 451.5808 0 0 0 225.79 0 0 0 0 225.79 0 451.5808
14 2-Execution Overcoating interval INSP 225.79 4 0 0 0 0 0 0 0 0 0 0 0 0
15 2-Execution 2nd coat inspection by AIMD INSP 225.79 1 0 0 0 0 0 0 0 0 0 0 0 0
16 2-Execution Painting final coat HRSB 225.79 225.79 1 1 451.5808 0 0 0 225.79 0 0 0 0 225.79 0 451.5808
17 2-Execution Overcoating interval HRSB 225.79 4 0 0 0 0 0 0 0 0 0 0 0 0
18 2-Execution Final coat inspection by AIMD INSP 225.79 1 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution 2.0 Painting pipe support HRSB 0 0 0 0 0 0 0 0 0 0 0 0
19 2-Execution Lift up pipe & support pipe using wooden block (1st side ) INSP HRSB 1 1 0 0 0 0 0 0 0 0 0 0 0 0
20 2-Execution To reinstate pipe support to its original position / Insert round bar 3 1 0
0 0 0 0 0 0 0 0 0 0 0
21 2-Execution Surface preparation (Power tool) HRSB 7.58 15.16 1 1 1 45.48 0 15.16 0 15.16 0 0 15.16 0 0 0 45.48
22 2-Execution Inspection surface preparation by AIMD HRSB 7.58 1 0 0 0 0 0 0 0 0 0 0 0 0
23 2-Execution Painting 1st coat INSP 7.58 11.37 1 1 22.74 0 0 0 11.37 0 0 0 0 11.37 0 22.74
24 2-Execution Overcoating interval HRSB 7.58 8 0 0 0 0 0 0 0 0 0 0 0 0
25 2-Execution 1st coat inspection by AIMD 7.58 1 0 0 0 0 0 0 0 0 0 0 0 0
26 2-Execution Painting 2nd coat 7.58 7.58 1 1 15.16 0 0 0 7.58 0 0 0 0 7.58 0 15.16
27 2-Execution Overcoating interval 7.58 4 0 0 0 0 0 0 0 0 0 0 0 0
28 2-Execution 2nd coat inspection by AIMD 7.58 1.00 0 0 0 0 0 0 0 0 0 0 0 0
29 2-Execution Painting final coat 7.58 7.58 1 1 15.16 0 0 0 7.58 0 0 0 0 7.58 0 15.16
30 2-Execution Overcoating interval 7.58 4 0 0 0 0 0 0 0 0 0 0 0 0
31 2-Execution Final coat inspection by AIMD 7.58 1 0 0 0 0 0 0 0 0 0 0 0 0
32 2-Execution Lift up pipe & support pipe using wooden block (2nd side ) 0 1 1 0 0 0 0 0 0 0 0 0 0 0 0
33 2-Execution Surface preparation (Power tool) 0 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0
34 2-Execution Inspection surface preparation by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
35 2-Execution Painting 1st coat 0.00 1 1 0 0 0 0 0 0 0 0 0 0 0 0
36 2-Execution Overcoating interval 0 0 0 0 0 0 0 0 0 0 0 0
37 2-Execution 1st coat inspection by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
38 2-Execution Painting 2nd coat 0.00 1 1 0 0 0 0 0 0 0 0 0 0 0 0
39 2-Execution Overcoating interval 0 0 0 0 0 0 0 0 0 0 0 0
40 2-Execution 2nd coat inspection by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
41 2-Execution Painting final coat 0.00 1 1 0 0 0 0 0 0 0 0 0 0 0 0
42 2-Execution Overcoating interval 0 0 0 0 0 0 0 0 0 0 0 0
43 2-Execution Final coat inspection by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
44 2-Execution Lift up pipe,remove wooden block & lift down pipe 1 1 0 0 0 0 0 0 0 0 0 0 0 0
45 2-Execution To apply silicone sealant 0 1 0 0 0 0 0 0 0 0 0 0 0 0
48 2-Execution Housekeeping 1 1 1 0 0 0 1 0 0 0 0 0 0 1
0 0 0 0 0 0 0 0 0 0 0 0
3-Post Execution C) Post execution 0 0 0 0 0 0 0 0 0 0 0 0
49 3-Post Execution Re instate Insulation 0 0 0 0 0 0 0 0 0 0 0 0
50 3-Post Execution Dismantle External Scaffolding 0 0 0 0 0 0 0 0 0 0 0 0
51 3-Post Execution Demobilization 0 0 0 0 0 0 0 0 0 0 0 0
1325.5372 3036.815 0 467.74 0 1286 0 0 466.74 0 816.8 0 3036.815
6 IWL/BT2/2018/15 6''-PL-225064-1101A-NI PAINTING
1 1-Pre Execution a) Site Preparation HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2 1-Pre Execution Mobilization manpower, equipment, tools & consumable HRSB 0 0 0 0 0 0 0 0 0 0 0 0
3 1-Pre Execution Apply protection on others PPTSB assets equipment/cable/tag number and etc. HRSB 0 0 0 0 0 0 0 0 0 0 0 0
4 1-Pre Execution Shelter/Laydown erection 0 0 0 0 0 0 0 0 0 0 0 0
5 1-Pre Execution Scaffolding erection HRSB 0 0 0 0 0 0 0 0 0 0 0 0
6 1-Pre Execution Remove Insulation 0 0 0 0 0 0 0 0 0 0 0 0
HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution b) During Project Activity HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution 1.0 Painting pipe HRSB 0 0 0 0 0 0 0 0 0 0 0 0
7 2-Execution Site preparation INSP 44.38 1 1 1 2 0 1 0 1 0 0 0 0 0 0 2
8 2-Execution Surface preparation (Power tool) 44.38 88.766989 1 1 1 266.301 0 88.767 0 88.767 0 0 88.767 0 0 0 266.301
9 2-Execution Inspection surface preparation by AIMD 44.38 1 0 0 0 0 0 0 0 0 0 0 0 0
10 2-Execution Painting 1st coat INSP 44.38 66.58 1 1 133.1505 0 0 0 66.575 0 0 0 0 66.575 0 133.1505
11 2-Execution Overcoating interval HRSB 44.38 8 0 0 0 0 0 0 0 0 0 0 0 0
12 2-Execution 1st coat inspection by AIMD INSP 44.38 1 0 0 0 0 0 0 0 0 0 0 0 0
13 2-Execution Painting 2nd coat HRSB 44.38 44.38 1 1 88.76699 0 0 0 44.383 0 0 0 0 44.383 0 88.76699
14 2-Execution Overcoating interval INSP 44.38 4 0 0 0 0 0 0 0 0 0 0 0 0
15 2-Execution 2nd coat inspection by AIMD INSP 44.38 1 0 0 0 0 0 0 0 0 0 0 0 0
16 2-Execution Painting final coat HRSB 44.38 44.38 1 1 88.76699 0 0 0 44.383 0 0 0 0 44.383 0 88.76699
17 2-Execution Overcoating interval HRSB 44.38 4 0 0 0 0 0 0 0 0 0 0 0 0
18 2-Execution Final coat inspection by AIMD INSP 44.38 1 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution 2.0 Painting pipe support HRSB 0 0 0 0 0 0 0 0 0 0 0 0
Lift up pipe & support pipe using wooden block (1st side )/ To
19 2-Execution 0 1 1 0
reinstate pipe support to its original position INSP HRSB 0 0 0 0 0 0 0 0 0 0 0
20 2-Execution Surface preparation (Power tool) HRSB 1.55 3.091251 1 1 1 9.273753 0 3.0913 0 3.0913 0 0 3.0913 0 0 0 9.273753
21 2-Execution Inspection surface preparation by AIMD HRSB 1.55 1 0 0 0 0 0 0 0 0 0 0 0 0
22 2-Execution Painting 1st coat INSP 1.55 2.32 1 1 4.636876 0 0 0 2.3184 0 0 0 0 2.3184 0 4.636876
23 2-Execution Overcoating interval HRSB 1.55 8 0 0 0 0 0 0 0 0 0 0 0 0
24 2-Execution 1st coat inspection by AIMD 1.55 1 0 0 0 0 0 0 0 0 0 0 0 0
25 2-Execution Painting 2nd coat 1.55 1.55 1 1 3.091251 0 0 0 1.5456 0 0 0 0 1.5456 0 3.091251
26 2-Execution Overcoating interval 1.55 4 0 0 0 0 0 0 0 0 0 0 0 0
27 2-Execution 2nd coat inspection by AIMD 1.55 1.00 0 0 0 0 0 0 0 0 0 0 0 0
28 2-Execution Painting final coat 1.55 1.55 1 1 3.091251 0 0 0 1.5456 0 0 0 0 1.5456 0 3.091251
29 2-Execution Overcoating interval 1.55 4 0 0 0 0 0 0 0 0 0 0 0 0
30 2-Execution Final coat inspection by AIMD 1.55 1 0 0 0 0 0 0 0 0 0 0 0 0
31 2-Execution Lift up pipe & support pipe using wooden block (2nd side ) 0 1 1 0 0 0 0 0 0 0 0 0 0 0 0
32 2-Execution Surface preparation (Power tool) 0 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0
33 2-Execution Inspection surface preparation by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
34 2-Execution Painting 1st coat 0.00 1 1 0 0 0 0 0 0 0 0 0 0 0 0
35 2-Execution Overcoating interval 0 0 0 0 0 0 0 0 0 0 0 0
36 2-Execution 1st coat inspection by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
37 2-Execution Painting 2nd coat 0.00 1 1 0 0 0 0 0 0 0 0 0 0 0 0
38 2-Execution Overcoating interval 0 0 0 0 0 0 0 0 0 0 0 0
Open
RESOURCE (MAN) MANHOURS RESOURCE (EQPT)
AWL F1 F2 GW RI HW FW WEL PNT CBT MHRS MHRS MHRS MHRS MHRS MHRS MHRS MHRS MHRS
NO TASKID No TAPHASE TASK TASKNOTE OWNER CONTR DATA DUR (HRS) (AWL) (F1) (F2) (GW) MHRS (HW) (FW) (WEL) (PNT) (CBT) SCAFFOLDING (M3) INSULATION (M2)
(RI)
MHRS MHRS CRANE GEN SET WELDING SET HTW/HBT COMPRESSOR
39 2-Execution 2nd coat inspection by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
40 2-Execution Painting final coat 0.00 1 1 0 0 0 0 0 0 0 0 0 0 0 0
41 2-Execution Overcoating interval 0 0 0 0 0 0 0 0 0 0 0 0
42 2-Execution Final coat inspection by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
43 2-Execution Lift up pipe,remove wooden block & lift down pipe 0 1 1 0 0 0 0 0 0 0 0 0 0 0 0
44 2-Execution To apply silicone sealant 0 1 0 0 0 0 0 0 0 0 0 0 0 0
45 2-Execution Remove & install handle valve - 1 unit 1 1 0 0 0 0 0 0 0 0 0 0 0 0
46 2-Execution Housekeeping 1 1 1 0 0 0 1 0 0 0 0 0 0 1
0 0 0 0 0 0 0 0 0 0 0 0
3-Post Execution C) Post execution 0 0 0 0 0 0 0 0 0 0 0 0
47 3-Post Execution Re instate Insulation 0 0 0 0 0 0 0 0 0 0 0 0
48 3-Post Execution Dismantle External Scaffolding 0 0 0 0 0 0 0 0 0 0 0 0
49 3-Post Execution Demobilization 0 0 0 0 0 0 0 0 0 0 0 0
294.61016 600.0786 0 92.858 0 254.61 0 0 91.858 0 160.75 0 600.0786
7 IWL/BT2/2018/23 3''-PG-225177-1101A-PG PAINTING
1 1-Pre Execution a) Site Preparation HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2 1-Pre Execution Mobilization manpower, equipment, tools & consumable HRSB 0 0 0 0 0 0 0 0 0 0 0 0
3 1-Pre Execution Apply protection on others PPTSB assets equipment/cable/tag number and etc. HRSB 0 0 0 0 0 0 0 0 0 0 0 0
4 1-Pre Execution Shelter/Laydown erection 0 0 0 0 0 0 0 0 0 0 0 0
5 1-Pre Execution Scaffolding erection HRSB 0 0 0 0 0 0 0 0 0 0 0 0
6 1-Pre Execution Remove Insulation 0 0 0 0 0 0 0 0 0 0 0 0
HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution b) During Project Activity HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution 1.0 Painting pipe HRSB 0 0 0 0 0 0 0 0 0 0 0 0
7 2-Execution Site preparation INSP 1 1 1 2 0 1 0 1 0 0 0 0 0 0 2
8 2-Execution Surface preparation (Power tool) 11.14 22.276073 1 1 1 66.82822 0 22.276 0 22.276 0 0 22.276 0 0 0 66.82822
9 2-Execution Inspection surface preparation by AIMD 11.14 1 0 0 0 0 0 0 0 0 0 0 0 0
10 2-Execution Painting 1st coat INSP 11.14 16.71 1 1 33.41411 0 0 0 16.707 0 0 0 0 16.707 0 33.41411
11 2-Execution Overcoating interval HRSB 11.14 8 0 0 0 0 0 0 0 0 0 0 0 0
12 2-Execution 1st coat inspection by AIMD INSP 11.14 1 0 0 0 0 0 0 0 0 0 0 0 0
13 2-Execution Painting 2nd coat HRSB 11.14 11.14 1 1 22.27607 0 0 0 11.138 0 0 0 0 11.138 0 22.27607
14 2-Execution Overcoating interval INSP 11.14 4 0 0 0 0 0 0 0 0 0 0 0 0
15 2-Execution 2nd coat inspection by AIMD INSP 11.14 1 0 0 0 0 0 0 0 0 0 0 0 0
16 2-Execution Painting final coat HRSB 11.14 11.14 1 1 22.27607 0 0 0 11.138 0 0 0 0 11.138 0 22.27607
17 2-Execution Overcoating interval HRSB 11.14 4 0 0 0 0 0 0 0 0 0 0 0 0
18 2-Execution Final coat inspection by AIMD INSP 11.14 1 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution 2.0 Painting pipe support HRSB 0 0 0 0 0 0 0 0 0 0 0 0
19 2-Execution Lift up pipe & support pipe using wooden block (1st side ) INSP HRSB 1 1 0 0 0 0 0 0 0 0 0 0 0 0
20 2-Execution To reinstate pipe support to its original position / Insert round bar 3 1 0
0 0 0 0 0 0 0 0 0 0 0
21 2-Execution Surface preparation (Power tool) HRSB 0.50 1 1 1 1 3 0 1 0 1 0 0 1 0 0 0 3
22 2-Execution Inspection surface preparation by AIMD HRSB 0.50 1 0 0 0 0 0 0 0 0 0 0 0 0
23 2-Execution Painting 1st coat INSP 0.50 0.75 1 1 1.5 0 0 0 0.75 0 0 0 0 0.75 0 1.5
24 2-Execution Overcoating interval HRSB 0.50 8 0 0 0 0 0 0 0 0 0 0 0 0
25 2-Execution 1st coat inspection by AIMD 0.50 1 0 0 0 0 0 0 0 0 0 0 0 0
26 2-Execution Painting 2nd coat 0.50 0.50 1 1 1 0 0 0 0.5 0 0 0 0 0.5 0 1
27 2-Execution Overcoating interval 0.50 4 0 0 0 0 0 0 0 0 0 0 0 0
28 2-Execution 2nd coat inspection by AIMD 0.50 1.00 0 0 0 0 0 0 0 0 0 0 0 0
29 2-Execution Painting final coat 0.50 0.50 1 1 1 0 0 0 0.5 0 0 0 0 0.5 0 1
30 2-Execution Overcoating interval 0.50 4 0 0 0 0 0 0 0 0 0 0 0 0
31 2-Execution Final coat inspection by AIMD 0.50 1 0 0 0 0 0 0 0 0 0 0 0 0
32 2-Execution Lift up pipe & support pipe using wooden block (2nd side ) 0 1 1 0 0 0 0 0 0 0 0 0 0 0 0
33 2-Execution Surface preparation (Power tool) 0 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0
34 2-Execution Inspection surface preparation by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
35 2-Execution Painting 1st coat 0.00 1 1 0 0 0 0 0 0 0 0 0 0 0 0
36 2-Execution Overcoating interval 0 0 0 0 0 0 0 0 0 0 0 0
37 2-Execution 1st coat inspection by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
38 2-Execution Painting 2nd coat 0.00 1 1 0 0 0 0 0 0 0 0 0 0 0 0
39 2-Execution Overcoating interval 0 0 0 0 0 0 0 0 0 0 0 0
40 2-Execution 2nd coat inspection by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
41 2-Execution Painting final coat 0.00 1 1 0 0 0 0 0 0 0 0 0 0 0 0
42 2-Execution Overcoating interval 0 0 0 0 0 0 0 0 0 0 0 0
43 2-Execution Final coat inspection by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
44 2-Execution Lift up pipe,remove wooden block & lift down pipe 1 1 0 0 0 0 0 0 0 0 0 0 0 0
45 2-Execution To apply silicone sealant 0 1 0 0 0 0 0 0 0 0 0 0 0 0
48 2-Execution Housekeeping 1 1 1 0 0 0 1 0 0 0 0 0 0 1
0 0 0 0 0 0 0 0 0 0 0 0
3-Post Execution C) Post execution 0 0 0 0 0 0 0 0 0 0 0 0
49 3-Post Execution Re instate Insulation 0 0 0 0 0 0 0 0 0 0 0 0
50 3-Post Execution Dismantle External Scaffolding 0 0 0 0 0 0 0 0 0 0 0 0
51 3-Post Execution Demobilization 0 0 0 0 0 0 0 0 0 0 0 0
106.0092 154.2945 0 24.276 0 66.009 0 0 23.276 0 40.733 0 154.2945
8 IWL/BT2/2018/9 8''-MC-225274-3126A-PG PAINTING
1 1-Pre Execution a) Site Preparation HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2 1-Pre Execution Mobilization manpower, equipment, tools & consumable HRSB 0 0 0 0 0 0 0 0 0 0 0 0
3 1-Pre Execution Apply protection on others PPTSB assets equipment/cable/tag number and etc. HRSB 0 0 0 0 0 0 0 0 0 0 0 0
4 1-Pre Execution Shelter/Laydown erection 0 0 0 0 0 0 0 0 0 0 0 0
5 1-Pre Execution Scaffolding erection HRSB 0 0 0 0 0 0 0 0 0 0 0 0
6 1-Pre Execution Remove Insulation 0 0 0 0 0 0 0 0 0 0 0 0
HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution b) During Project Activity HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution 1.0 Painting pipe HRSB 0 0 0 0 0 0 0 0 0 0 0 0
7 2-Execution Site preparation INSP 1 1 1 2 0 1 0 1 0 0 0 0 0 0 2
8 2-Execution Surface preparation (Power tool) 27.54 55.072976 1 1 1 165.2189 0 55.073 0 55.073 0 0 55.073 0 0 0 165.2189
9 2-Execution Inspection surface preparation by AIMD 27.54 1 0 0 0 0 0 0 0 0 0 0 0 0
10 2-Execution Painting 1st coat INSP 27.54 41.30 1 1 82.60946 0 0 0 41.305 0 0 0 0 41.305 0 82.60946
11 2-Execution Overcoating interval HRSB 27.54 8 0 0 0 0 0 0 0 0 0 0 0 0
12 2-Execution 1st coat inspection by AIMD INSP 27.54 1 0 0 0 0 0 0 0 0 0 0 0 0
13 2-Execution Painting 2nd coat HRSB 27.54 27.54 1 1 55.07298 0 0 0 27.536 0 0 0 0 27.536 0 55.07298
14 2-Execution Overcoating interval INSP 27.54 4 0 0 0 0 0 0 0 0 0 0 0 0
15 2-Execution 2nd coat inspection by AIMD INSP 27.54 1 0 0 0 0 0 0 0 0 0 0 0 0
16 2-Execution Painting final coat HRSB 27.54 27.54 1 1 55.07298 0 0 0 27.536 0 0 0 0 27.536 0 55.07298
17 2-Execution Overcoating interval HRSB 27.54 4 0 0 0 0 0 0 0 0 0 0 0 0
18 2-Execution Final coat inspection by AIMD INSP 27.54 1 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution HRSB 0 0 0 0 0 0 0 0 0 0 0 0
Open
RESOURCE (MAN) MANHOURS RESOURCE (EQPT)
AWL F1 F2 GW RI HW FW WEL PNT CBT MHRS MHRS MHRS MHRS MHRS MHRS MHRS MHRS MHRS
NO TASKID No TAPHASE TASK TASKNOTE OWNER CONTR DATA DUR (HRS) (AWL) (F1) (F2) (GW) MHRS (HW) (FW) (WEL) (PNT) (CBT) SCAFFOLDING (M3) INSULATION (M2)
(RI)
MHRS MHRS CRANE GEN SET WELDING SET HTW/HBT COMPRESSOR
2-Execution 2.0 Painting pipe support HRSB 0 0 0 0 0 0 0 0 0 0 0 0
19 2-Execution Lift up pipe & support pipe using wooden block (1st side ) INSP HRSB 1 1 0 0 0 0 0 0 0 0 0 0 0 0
20 2-Execution To reinstate pipe support to its original position / Insert round bar 3 1 0
0 0 0 0 0 0 0 0 0 0 0
21 2-Execution Surface preparation (Power tool) HRSB 3.60 7.2 1 1 1 21.6 0 7.2 0 7.2 0 0 7.2 0 0 0 21.6
22 2-Execution Inspection surface preparation by AIMD HRSB 3.60 1 0 0 0 0 0 0 0 0 0 0 0 0
23 2-Execution Painting 1st coat INSP 3.60 5.40 1 1 10.8 0 0 0 5.4 0 0 0 0 5.4 0 10.8
24 2-Execution Overcoating interval HRSB 3.60 8 0 0 0 0 0 0 0 0 0 0 0 0
25 2-Execution 1st coat inspection by AIMD 3.60 1 0 0 0 0 0 0 0 0 0 0 0 0
26 2-Execution Painting 2nd coat 3.60 3.60 1 1 7.2 0 0 0 3.6 0 0 0 0 3.6 0 7.2
27 2-Execution Overcoating interval 3.60 4 0 0 0 0 0 0 0 0 0 0 0 0
28 2-Execution 2nd coat inspection by AIMD 3.60 1.00 0 0 0 0 0 0 0 0 0 0 0 0
29 2-Execution Painting final coat 3.60 3.60 1 1 7.2 0 0 0 3.6 0 0 0 0 3.6 0 7.2
30 2-Execution Overcoating interval 3.60 4 0 0 0 0 0 0 0 0 0 0 0 0
31 2-Execution Final coat inspection by AIMD 3.60 1 0 0 0 0 0 0 0 0 0 0 0 0
32 2-Execution Lift up pipe & support pipe using wooden block (2nd side ) 0 0 1 1 0 0 0 0 0 0 0 0 0 0 0 0
33 2-Execution Surface preparation (Power tool) 0 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0
34 2-Execution Inspection surface preparation by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
35 2-Execution Painting 1st coat 0.00 1 1 0 0 0 0 0 0 0 0 0 0 0 0
36 2-Execution Overcoating interval 0 0 0 0 0 0 0 0 0 0 0 0
37 2-Execution 1st coat inspection by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
38 2-Execution Painting 2nd coat 0.00 1 1 0 0 0 0 0 0 0 0 0 0 0 0
39 2-Execution Overcoating interval 0 0 0 0 0 0 0 0 0 0 0 0
40 2-Execution 2nd coat inspection by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
41 2-Execution Painting final coat 0.00 1 1 0 0 0 0 0 0 0 0 0 0 0 0
42 2-Execution Overcoating interval 0 0 0 0 0 0 0 0 0 0 0 0
43 2-Execution Final coat inspection by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
44 2-Execution Lift up pipe,remove wooden block & lift down pipe 1 1 0 0 0 0 0 0 0 0 0 0 0 0
45 2-Execution To apply silicone sealant 0 1 0 0 0 0 0 0 0 0 0 0 0 0
48 2-Execution Housekeeping 1 1 1 0 0 0 1 0 0 0 0 0 0 1
0 0 0 0 0 0 0 0 0 0 0 0
3-Post Execution C) Post execution 0 0 0 0 0 0 0 0 0 0 0 0
49 3-Post Execution Re instate Insulation 0 0 0 0 0 0 0 0 0 0 0 0
50 3-Post Execution Dismantle External Scaffolding 0 0 0 0 0 0 0 0 0 0 0 0
51 3-Post Execution Demobilization 0 0 0 0 0 0 0 0 0 0 0 0
213.25068 407.7743 0 63.273 0 173.25 0 0 62.273 0 109 0 407.7743
9 IWL/BT2/2018/17 2''-SA-283096-1112B-PG PAINTING
1 1-Pre Execution a) Site Preparation HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2 1-Pre Execution Mobilization manpower, equipment, tools & consumable HRSB 0 0 0 0 0 0 0 0 0 0 0 0
3 1-Pre Execution Apply protection on others PPTSB assets equipment/cable/tag number and etc. HRSB 0 0 0 0 0 0 0 0 0 0 0 0
4 1-Pre Execution Shelter/Laydown erection 0 0 0 0 0 0 0 0 0 0 0 0
5 1-Pre Execution Scaffolding erection HRSB 0 0 0 0 0 0 0 0 0 0 0 0
6 1-Pre Execution Remove Insulation 0 0 0 0 0 0 0 0 0 0 0 0
HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution b) During Project Activity HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution 1.0 Painting pipe HRSB 0 0 0 0 0 0 0 0 0 0 0 0
7 2-Execution Site preparation INSP 1 1 1 2 0 1 0 1 0 0 0 0 0 0 2
8 2-Execution Surface preparation (Power tool) 21.63 43.268521 1 1 1 129.8056 0 43.269 0 43.269 0 0 43.269 0 0 0 129.8056
9 2-Execution Inspection surface preparation by AIMD 21.63 1 0 0 0 0 0 0 0 0 0 0 0 0
10 2-Execution Painting 1st coat INSP 21.63 32.45 1 1 64.90278 0 0 0 32.451 0 0 0 0 32.451 0 64.90278
11 2-Execution Overcoating interval HRSB 21.63 8 0 0 0 0 0 0 0 0 0 0 0 0
12 2-Execution 1st coat inspection by AIMD INSP 21.63 1 0 0 0 0 0 0 0 0 0 0 0 0
13 2-Execution Painting 2nd coat HRSB 21.63 21.63 1 1 43.26852 0 0 0 21.634 0 0 0 0 21.634 0 43.26852
14 2-Execution Overcoating interval INSP 21.63 4 0 0 0 0 0 0 0 0 0 0 0 0
15 2-Execution 2nd coat inspection by AIMD INSP 21.63 1 0 0 0 0 0 0 0 0 0 0 0 0
16 2-Execution Painting final coat HRSB 21.63 21.63 1 1 43.26852 0 0 0 21.634 0 0 0 0 21.634 0 43.26852
17 2-Execution Overcoating interval HRSB 21.63 4 0 0 0 0 0 0 0 0 0 0 0 0
18 2-Execution Final coat inspection by AIMD INSP 21.63 1 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution 2.0 Painting pipe support HRSB 0 0 0 0 0 0 0 0 0 0 0 0
Lift up pipe & support pipe using wooden block (1st side )/ To
19 2-Execution reinstate pipe support to its original position 0 1 1 0
INSP HRSB 0 0 0 0 0 0 0 0 0 0 0
20 2-Execution Surface preparation (Power tool) HRSB 2.85 5.704984 1 1 1 17.11495 0 5.705 0 5.705 0 0 5.705 0 0 0 17.11495
21 2-Execution Inspection surface preparation by AIMD HRSB 2.85 1 0 0 0 0 0 0 0 0 0 0 0 0
22 2-Execution Painting 1st coat INSP 2.85 4.28 1 1 8.557476 0 0 0 4.2787 0 0 0 0 4.2787 0 8.557476
23 2-Execution Overcoating interval HRSB 2.85 8 0 0 0 0 0 0 0 0 0 0 0 0
24 2-Execution 1st coat inspection by AIMD 2.85 1 0 0 0 0 0 0 0 0 0 0 0 0
25 2-Execution Painting 2nd coat 2.85 2.85 1 1 5.704984 0 0 0 2.8525 0 0 0 0 2.8525 0 5.704984
26 2-Execution Overcoating interval 2.85 4 0 0 0 0 0 0 0 0 0 0 0 0
27 2-Execution 2nd coat inspection by AIMD 2.85 1.00 0 0 0 0 0 0 0 0 0 0 0 0
28 2-Execution Painting final coat 2.85 2.85 1 1 5.704984 0 0 0 2.8525 0 0 0 0 2.8525 0 5.704984
29 2-Execution Overcoating interval 2.85 4 0 0 0 0 0 0 0 0 0 0 0 0
30 2-Execution Final coat inspection by AIMD 2.85 1 0 0 0 0 0 0 0 0 0 0 0 0
31 2-Execution Lift up pipe & support pipe using wooden block (2nd side ) 0 1 1 0 0 0 0 0 0 0 0 0 0 0 0
32 2-Execution Surface preparation (Power tool) 0 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0
33 2-Execution Inspection surface preparation by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
34 2-Execution Painting 1st coat 0.00 1 1 0 0 0 0 0 0 0 0 0 0 0 0
35 2-Execution Overcoating interval 0 0 0 0 0 0 0 0 0 0 0 0
36 2-Execution 1st coat inspection by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
37 2-Execution Painting 2nd coat 0.00 1 1 0 0 0 0 0 0 0 0 0 0 0 0
38 2-Execution Overcoating interval 0 0 0 0 0 0 0 0 0 0 0 0
39 2-Execution 2nd coat inspection by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
40 2-Execution Painting final coat 0.00 1 1 0 0 0 0 0 0 0 0 0 0 0 0
41 2-Execution Overcoating interval 0 0 0 0 0 0 0 0 0 0 0 0
42 2-Execution Final coat inspection by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
43 2-Execution Lift up pipe,remove wooden block & lift down pipe 0 1 1 0 0 0 0 0 0 0 0 0 0 0 0
44 2-Execution To apply silicone sealant 0 1 0 0 0 0 0 0 0 0 0 0 0 0
45 2-Execution Remove & install handle valve - 1 unit 1 1 0 0 0 0 0 0 0 0 0 0 0 0
46 2-Execution Housekeeping 1 1 1 2 0 1 0 1 0 0 0 0 0 0 2
0 0 0 0 0 0 0 0 0 0 0 0
3-Post Execution C) Post execution 0 0 0 0 0 0 0 0 0 0 0 0
47 3-Post Execution Re instate Insulation 0 0 0 0 0 0 0 0 0 0 0 0
48 3-Post Execution Dismantle External Scaffolding 0 0 0 0 0 0 0 0 0 0 0 0
49 3-Post Execution Demobilization 0 0 0 0 0 0 0 0 0 0 0 0
176.67714 322.3278 0 50.974 0 136.68 0 0 48.974 0 85.704 0 322.3278
10 IWL/BT2/2018/20 3''-PL-225123-1101A-NI PAINTING
1 1-Pre Execution a) Site Preparation HRSB 0 0 0 0 0 0 0 0 0 0 0 0
Open
RESOURCE (MAN) MANHOURS RESOURCE (EQPT)
AWL F1 F2 GW RI HW FW WEL PNT CBT MHRS MHRS MHRS MHRS MHRS MHRS MHRS MHRS MHRS
NO TASKID No TAPHASE TASK TASKNOTE OWNER CONTR DATA DUR (HRS) (AWL) (F1) (F2) (GW) MHRS (HW) (FW) (WEL) (PNT) (CBT) SCAFFOLDING (M3) INSULATION (M2)
(RI)
MHRS MHRS CRANE GEN SET WELDING SET HTW/HBT COMPRESSOR
2 1-Pre Execution Mobilization manpower, equipment, tools & consumable HRSB 0 0 0 0 0 0 0 0 0 0 0 0
3 1-Pre Execution Apply protection on others PPTSB assets equipment/cable/tag number and etc. HRSB 0 0 0 0 0 0 0 0 0 0 0 0
4 1-Pre Execution Shelter/Laydown erection 0 0 0 0 0 0 0 0 0 0 0 0
5 1-Pre Execution Scaffolding erection HRSB 0 0 0 0 0 0 0 0 0 0 0 0
6 1-Pre Execution Remove Insulation 0 0 0 0 0 0 0 0 0 0 0 0
HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution b) During Project Activity HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution 1.0 Painting pipe HRSB 0 0 0 0 0 0 0 0 0 0 0 0
7 2-Execution Site preparation INSP 1 1 1 2 0 1 0 1 0 0 0 0 0 0 2
8 2-Execution Surface preparation (Power tool) 45.11 90.221587 1 1 1 270.6648 0 90.222 0 90.222 0 0 90.222 0 0 0 270.6648
9 2-Execution Inspection surface preparation by AIMD 45.11 1 0 0 0 0 0 0 0 0 0 0 0 0
10 2-Execution Painting 1st coat INSP 45.11 67.67 1 1 135.3324 0 0 0 67.666 0 0 0 0 67.666 0 135.3324
11 2-Execution Overcoating interval HRSB 45.11 8 0 0 0 0 0 0 0 0 0 0 0 0
12 2-Execution 1st coat inspection by AIMD INSP 45.11 1 0 0 0 0 0 0 0 0 0 0 0 0
13 2-Execution Painting 2nd coat HRSB 45.11 45.11 1 1 90.22159 0 0 0 45.111 0 0 0 0 45.111 0 90.22159
14 2-Execution Overcoating interval INSP 45.11 4 0 0 0 0 0 0 0 0 0 0 0 0
15 2-Execution 2nd coat inspection by AIMD INSP 45.11 1 0 0 0 0 0 0 0 0 0 0 0 0
16 2-Execution Painting final coat HRSB 45.11 45.11 1 1 90.22159 0 0 0 45.111 0 0 0 0 45.111 0 90.22159
17 2-Execution Overcoating interval HRSB 45.11 4 0 0 0 0 0 0 0 0 0 0 0 0
18 2-Execution Final coat inspection by AIMD INSP 45.11 1 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution 2.0 Painting pipe support HRSB 0 0 0 0 0 0 0 0 0 0 0 0
19 2-Execution Lift up pipe & support pipe using wooden block (1st side ) INSP HRSB 1 1 0 0 0 0 0 0 0 0 0 0 0 0
20 2-Execution To reinstate pipe support to its original position / Insert round bar 3 1 0
0 0 0 0 0 0 0 0 0 0 0
21 2-Execution Surface preparation (Power tool) HRSB 8.75 17.5 1 1 1 52.5 0 17.5 0 17.5 0 0 17.5 0 0 0 52.5
22 2-Execution Inspection surface preparation by AIMD HRSB 8.75 1 0 0 0 0 0 0 0 0 0 0 0 0
23 2-Execution Painting 1st coat INSP 8.75 13.13 1 1 26.25 0 0 0 13.125 0 0 0 0 13.125 0 26.25
24 2-Execution Overcoating interval HRSB 8.75 8 0 0 0 0 0 0 0 0 0 0 0 0
25 2-Execution 1st coat inspection by AIMD 8.75 1 0 0 0 0 0 0 0 0 0 0 0 0
26 2-Execution Painting 2nd coat 8.75 8.75 1 1 17.5 0 0 0 8.75 0 0 0 0 8.75 0 17.5
27 2-Execution Overcoating interval 8.75 4 0 0 0 0 0 0 0 0 0 0 0 0
28 2-Execution 2nd coat inspection by AIMD 8.75 1.00 0 0 0 0 0 0 0 0 0 0 0 0
29 2-Execution Painting final coat 8.75 8.75 1 1 17.5 0 0 0 8.75 0 0 0 0 8.75 0 17.5
30 2-Execution Overcoating interval 8.75 4 0 0 0 0 0 0 0 0 0 0 0 0
31 2-Execution Final coat inspection by AIMD 8.75 1 0 0 0 0 0 0 0 0 0 0 0 0
32 2-Execution Lift up pipe & support pipe using wooden block (2nd side ) 0 1 1 0 0 0 0 0 0 0 0 0 0 0 0
33 2-Execution Surface preparation (Power tool) 0 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0
34 2-Execution Inspection surface preparation by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
35 2-Execution Painting 1st coat 0.00 1 1 0 0 0 0 0 0 0 0 0 0 0 0
36 2-Execution Overcoating interval 0 0 0 0 0 0 0 0 0 0 0 0
37 2-Execution 1st coat inspection by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
38 2-Execution Painting 2nd coat 0.00 1 1 0 0 0 0 0 0 0 0 0 0 0 0
39 2-Execution Overcoating interval 0 0 0 0 0 0 0 0 0 0 0 0
40 2-Execution 2nd coat inspection by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
41 2-Execution Painting final coat 0.00 1 1 0 0 0 0 0 0 0 0 0 0 0 0
42 2-Execution Overcoating interval 0 0 0 0 0 0 0 0 0 0 0 0
43 2-Execution Final coat inspection by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
44 2-Execution Lift up pipe,remove wooden block & lift down pipe 1 1 0 0 0 0 0 0 0 0 0 0 0 0
45 2-Execution To apply silicone sealant 0 1 0 0 0 0 0 0 0 0 0 0 0 0
48 2-Execution Housekeeping 1 1 1 0 0 0 1 0 0 0 0 0 0 1
0 0 0 0 0 0 0 0 0 0 0 0
3-Post Execution C) Post execution 0 0 0 0 0 0 0 0 0 0 0 0
49 3-Post Execution Re instate Insulation 0 0 0 0 0 0 0 0 0 0 0 0
50 3-Post Execution Dismantle External Scaffolding 0 0 0 0 0 0 0 0 0 0 0 0
51 3-Post Execution Demobilization 0 0 0 0 0 0 0 0 0 0 0 0
338.23437 703.1903 0 108.72 0 298.23 0 0 107.72 0 188.51 0 703.1903
11 IWL/BT2/2018/18 2''-PL-225067-3101A-ST PAINTING
1 1-Pre Execution a) Site Preparation HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2 1-Pre Execution Mobilization manpower, equipment, tools & consumable HRSB 0 0 0 0 0 0 0 0 0 0 0 0
3 1-Pre Execution Apply protection on others PPTSB assets equipment/cable/tag number and etc. HRSB 0 0 0 0 0 0 0 0 0 0 0 0
4 1-Pre Execution Shelter/Laydown erection 0 0 0 0 0 0 0 0 0 0 0 0
5 1-Pre Execution Scaffolding erection HRSB 0 0 0 0 0 0 0 0 0 0 0 0
6 1-Pre Execution Remove Insulation 0 0 0 0 0 0 0 0 0 0 0 0
HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution b) During Project Activity HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution 1.0 Painting pipe HRSB 0 0 0 0 0 0 0 0 0 0 0 0
7 2-Execution Site preparation INSP 1 1 1 2 0 1 0 1 0 0 0 0 0 0 2
8 2-Execution Surface preparation (Power tool) 14.14 28.277293 1 1 1 84.83188 0 28.277 0 28.277 0 0 28.277 0 0 0 84.83188
9 2-Execution Inspection surface preparation by AIMD 14.14 1 0 0 0 0 0 0 0 0 0 0 0 0
10 2-Execution Painting 1st coat INSP 14.14 21.21 1 1 42.41594 0 0 0 21.208 0 0 0 0 21.208 0 42.41594
11 2-Execution Overcoating interval HRSB 14.14 8 0 0 0 0 0 0 0 0 0 0 0 0
12 2-Execution 1st coat inspection by AIMD INSP 14.14 1 0 0 0 0 0 0 0 0 0 0 0 0
13 2-Execution Painting 2nd coat HRSB 14.14 14.14 1 1 28.27729 0 0 0 14.139 0 0 0 0 14.139 0 28.27729
14 2-Execution Overcoating interval INSP 14.14 4 0 0 0 0 0 0 0 0 0 0 0 0
15 2-Execution 2nd coat inspection by AIMD INSP 14.14 1 0 0 0 0 0 0 0 0 0 0 0 0
16 2-Execution Painting final coat HRSB 14.14 14.14 1 1 28.27729 0 0 0 14.139 0 0 0 0 14.139 0 28.27729
17 2-Execution Overcoating interval HRSB 14.14 4 0 0 0 0 0 0 0 0 0 0 0 0
18 2-Execution Final coat inspection by AIMD INSP 14.14 1 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution 2.0 Painting pipe support HRSB 0 0 0 0 0 0 0 0 0 0 0 0
19 2-Execution Lift up pipe & support pipe using wooden block (1st side ) INSP HRSB 1 1 0 0 0 0 0 0 0 0 0 0 0 0
20 2-Execution To reinstate pipe support to its original position / Insert round bar 3 1 0
0 0 0 0 0 0 0 0 0 0 0
21 2-Execution Surface preparation (Power tool) HRSB 2.47 4.942097 1 1 1 14.82629 0 4.9421 0 4.9421 0 0 4.9421 0 0 0 14.82629
22 2-Execution Inspection surface preparation by AIMD HRSB 2.47 1 0 0 0 0 0 0 0 0 0 0 0 0
23 2-Execution Painting 1st coat INSP 2.47 3.71 1 1 7.413145 0 0 0 3.7066 0 0 0 0 3.7066 0 7.413145
24 2-Execution Overcoating interval HRSB 2.47 8 0 0 0 0 0 0 0 0 0 0 0 0
25 2-Execution 1st coat inspection by AIMD 2.47 1 0 0 0 0 0 0 0 0 0 0 0 0
26 2-Execution Painting 2nd coat 2.47 2.47 1 1 4.942097 0 0 0 2.471 0 0 0 0 2.471 0 4.942097
27 2-Execution Overcoating interval 2.47 4 0 0 0 0 0 0 0 0 0 0 0 0
28 2-Execution 2nd coat inspection by AIMD 2.47 1.00 0 0 0 0 0 0 0 0 0 0 0 0
29 2-Execution Painting final coat 2.47 2.47 1 1 4.942097 0 0 0 2.471 0 0 0 0 2.471 0 4.942097
30 2-Execution Overcoating interval 2.47 4 0 0 0 0 0 0 0 0 0 0 0 0
31 2-Execution Final coat inspection by AIMD 2.47 1 0 0 0 0 0 0 0 0 0 0 0 0
32 2-Execution Lift up pipe & support pipe using wooden block (2nd side ) 0 1 1 0 0 0 0 0 0 0 0 0 0 0 0
33 2-Execution Surface preparation (Power tool) 0 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0
Open
RESOURCE (MAN) MANHOURS RESOURCE (EQPT)
AWL F1 F2 GW RI HW FW WEL PNT CBT MHRS MHRS MHRS MHRS MHRS MHRS MHRS MHRS MHRS
NO TASKID No TAPHASE TASK TASKNOTE OWNER CONTR DATA DUR (HRS) (AWL) (F1) (F2) (GW) MHRS (HW) (FW) (WEL) (PNT) (CBT) SCAFFOLDING (M3) INSULATION (M2)
(RI)
MHRS MHRS CRANE GEN SET WELDING SET HTW/HBT COMPRESSOR
34 2-Execution Inspection surface preparation by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
35 2-Execution Painting 1st coat 0.00 1 1 0 0 0 0 0 0 0 0 0 0 0 0
36 2-Execution Overcoating interval 0 0 0 0 0 0 0 0 0 0 0 0
37 2-Execution 1st coat inspection by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
38 2-Execution Painting 2nd coat 0.00 1 1 0 0 0 0 0 0 0 0 0 0 0 0
39 2-Execution Overcoating interval 0 0 0 0 0 0 0 0 0 0 0 0
40 2-Execution 2nd coat inspection by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
41 2-Execution Painting final coat 0.00 1 1 0 0 0 0 0 0 0 0 0 0 0 0
42 2-Execution Overcoating interval 0 0 0 0 0 0 0 0 0 0 0 0
43 2-Execution Final coat inspection by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
44 2-Execution Lift up pipe,remove wooden block & lift down pipe 1 1 0 0 0 0 0 0 0 0 0 0 0 0
45 2-Execution To apply silicone sealant 0 1 0 0 0 0 0 0 0 0 0 0 0 0
48 2-Execution Housekeeping 1 1 1 0 0 0 1 0 0 0 0 0 0 1
0 0 0 0 0 0 0 0 0 0 0 0
3-Post Execution C) Post execution 0 0 0 0 0 0 0 0 0 0 0 0
49 3-Post Execution Re instate Insulation 0 0 0 0 0 0 0 0 0 0 0 0
50 3-Post Execution Dismantle External Scaffolding 0 0 0 0 0 0 0 0 0 0 0 0
51 3-Post Execution Demobilization 0 0 0 0 0 0 0 0 0 0 0 0
133.35332 218.926 0 34.219 0 93.353 0 0 33.219 0 58.134 0 218.926
12 IWL/BT2/2018/1 6''-PL-225110-1101A-IH PAINTING
1 1-Pre Execution a) Site Preparation HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2 1-Pre Execution Mobilization manpower, equipment, tools & consumable HRSB 0 0 0 0 0 0 0 0 0 0 0 0
3 1-Pre Execution Apply protection on others PPTSB assets equipment/cable/tag number and etc. HRSB 0 0 0 0 0 0 0 0 0 0 0 0
4 1-Pre Execution Shelter/Laydown erection 0 0 0 0 0 0 0 0 0 0 0 0
5 1-Pre Execution Scaffolding erection HRSB 0 0 0 0 0 0 0 0 0 0 0 0
6 1-Pre Execution Remove Insulation HRSB 14.29m2 0 0 0 0 0 0 0 0 0 0 0 0
HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution b) During Project Activity HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution 1.0 Painting pipe HRSB 0 0 0 0 0 0 0 0 0 0 0 0
7 2-Execution Site preparation INSP 1 1 1 2 0 1 0 1 0 0 0 0 0 0 2
8 2-Execution Surface preparation (Power tool) 9.10 18.21 1 1 1 54.61613 0 18.205 0 18.205 0 0 18.205 0 0 0 54.61613
9 2-Execution Inspection surface preparation by AIMD 9.10 1 0 0 0 0 0 0 0 0 0 0 0 0
10 2-Execution Painting 1st coat INSP 9.10 13.65 1 1 27.30806 0 0 0 13.654 0 0 0 0 13.654 0 27.30806
11 2-Execution Overcoating interval HRSB 9.10 8 0 0 0 0 0 0 0 0 0 0 0 0
12 2-Execution 1st coat inspection by AIMD INSP 9.10 1 0 0 0 0 0 0 0 0 0 0 0 0
13 2-Execution Painting 2nd coat HRSB 9.10 9.10 1 1 18.20538 0 0 0 9.1027 0 0 0 0 9.1027 0 18.20538
14 2-Execution Overcoating interval INSP 9.10 4 0 0 0 0 0 0 0 0 0 0 0 0
15 2-Execution 2nd coat inspection by AIMD INSP 9.10 1 0 0 0 0 0 0 0 0 0 0 0 0
16 2-Execution Painting final coat HRSB 9.10 9.10 1 1 18.20538 0 0 0 9.1027 0 0 0 0 9.1027 0 18.20538
17 2-Execution Overcoating interval HRSB 9.10 4 0 0 0 0 0 0 0 0 0 0 0 0
18 2-Execution Final coat inspection by AIMD INSP 9.10 1 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution 2.0 Painting pipe support HRSB 0 0 0 0 0 0 0 0 0 0 0 0
19 2-Execution Lift up pipe & support pipe using wooden block (1st side ) INSP HRSB 1 1 0 0 0 0 0 0 0 0 0 0 0 0
20 2-Execution To reinstate pipe support to its original position / Insert round bar 3 1 0
0 0 0 0 0 0 0 0 0 0 0
21 2-Execution Surface preparation (Power tool) HRSB 0.72 1.44 1 1 1 4.32 0 1.44 0 1.44 0 0 1.44 0 0 0 4.32
22 2-Execution Inspection surface preparation by AIMD HRSB 0.72 1 0 0 0 0 0 0 0 0 0 0 0 0
23 2-Execution Painting 1st coat INSP 0.72 1.08 1 1 2.16 0 0 0 1.08 0 0 0 0 1.08 0 2.16
24 2-Execution Overcoating interval HRSB 0.72 8 0 0 0 0 0 0 0 0 0 0 0 0
25 2-Execution 1st coat inspection by AIMD 0.72 1 0 0 0 0 0 0 0 0 0 0 0 0
26 2-Execution Painting 2nd coat 0.72 0.72 1 1 1.44 0 0 0 0.72 0 0 0 0 0.72 0 1.44
27 2-Execution Overcoating interval 0.72 4 0 0 0 0 0 0 0 0 0 0 0 0
28 2-Execution 2nd coat inspection by AIMD 0.72 1 0 0 0 0 0 0 0 0 0 0 0 0
29 2-Execution Painting final coat 0.72 0.72 1 1 1.44 0 0 0 0.72 0 0 0 0 0.72 0 1.44
30 2-Execution Overcoating interval 0.72 4 0 0 0 0 0 0 0 0 0 0 0 0
31 2-Execution Final coat inspection by AIMD 0.72 1 0 0 0 0 0 0 0 0 0 0 0 0
32 2-Execution Lift up pipe & support pipe using wooden block (2nd side ) 1 1 0 0 0 0 0 0 0 0 0 0 0 0
33 2-Execution Surface preparation (Power tool) 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0
34 2-Execution Inspection surface preparation by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
35 2-Execution Painting 1st coat 1 1 0 0 0 0 0 0 0 0 0 0 0 0
36 2-Execution Overcoating interval 0 0 0 0 0 0 0 0 0 0 0 0
37 2-Execution 1st coat inspection by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
38 2-Execution Painting 2nd coat 1 1 0 0 0 0 0 0 0 0 0 0 0 0
39 2-Execution Overcoating interval 0 0 0 0 0 0 0 0 0 0 0 0
40 2-Execution 2nd coat inspection by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
41 2-Execution Painting final coat 1 1 0 0 0 0 0 0 0 0 0 0 0 0
42 2-Execution Overcoating interval 0 0 0 0 0 0 0 0 0 0 0 0
43 2-Execution Final coat inspection by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
44 2-Execution Lift up pipe,remove wooden block & lift down pipe 1 1 0 0 0 0 0 0 0 0 0 0 0 0
45 2-Execution To apply silicone sealant 1 0 0 0 0 0 0 0 0 0 0 0 0
48 2-Execution Housekeeping 1 1 1 0 0 0 1 0 0 0 0 0 0 1
0 0 0 0 0 0 0 0 0 0 0 0
3-Post Execution C) Post execution 0 0 0 0 0 0 0 0 0 0 0 0
49 3-Post Execution Re instate Insulation 14.29m2 0 0 0 0 0 0 0 0 0 0 0 0
50 3-Post Execution Dismantle External Scaffolding 0 0 0 0 0 0 0 0 0 0 0 0
51 3-Post Execution Demobilization 0 0 0 0 0 0 0 0 0 0 0 0
96.024785 130.6949 0 20.645 0 56.025 0 0 19.645 0 34.379 0 130.6949
13 IWL/BT2/2018/4 6''-PL-225125-1101A-PG PAINTING
1 1-Pre Execution a) Site Preparation HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2 1-Pre Execution Mobilization manpower, equipment, tools & consumable HRSB 0 0 0 0 0 0 0 0 0 0 0 0
3 1-Pre Execution Apply protection on others PPTSB assets equipment/cable/tag number and etc. HRSB 0 0 0 0 0 0 0 0 0 0 0 0
4 1-Pre Execution Shelter/Laydown erection 0 0 0 0 0 0 0 0 0 0 0 0
5 1-Pre Execution Scaffolding erection HRSB 0 0 0 0 0 0 0 0 0 0 0 0
6 1-Pre Execution Remove Insulation 0 0 0 0 0 0 0 0 0 0 0 0
HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution b) During Project Activity HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution 1.0 Painting pipe HRSB 0 0 0 0 0 0 0 0 0 0 0 0
7 2-Execution Site preparation INSP 1 1 1 2 0 1 0 1 0 0 0 0 0 0 2
8 2-Execution Surface preparation (Power tool) 16.33 32.653314 1 1 1 97.95994 0 32.653 0 32.653 0 0 32.653 0 0 0 97.95994
9 2-Execution Inspection surface preparation by AIMD 16.33 1 0 0 0 0 0 0 0 0 0 0 0 0
10 2-Execution Painting 1st coat INSP 16.33 24.49 1 1 48.97997 0 0 0 24.49 0 0 0 0 24.49 0 48.97997
11 2-Execution Overcoating interval HRSB 16.33 8 0 0 0 0 0 0 0 0 0 0 0 0
12 2-Execution 1st coat inspection by AIMD INSP 16.33 1 0 0 0 0 0 0 0 0 0 0 0 0
13 2-Execution Painting 2nd coat HRSB 16.33 16.33 1 1 32.65331 0 0 0 16.327 0 0 0 0 16.327 0 32.65331
14 2-Execution Overcoating interval INSP 16.33 4 0 0 0 0 0 0 0 0 0 0 0 0
Open
RESOURCE (MAN) MANHOURS RESOURCE (EQPT)
AWL F1 F2 GW RI HW FW WEL PNT CBT MHRS MHRS MHRS MHRS MHRS MHRS MHRS MHRS MHRS
NO TASKID No TAPHASE TASK TASKNOTE OWNER CONTR DATA DUR (HRS) (AWL) (F1) (F2) (GW) MHRS (HW) (FW) (WEL) (PNT) (CBT) SCAFFOLDING (M3) INSULATION (M2)
(RI)
MHRS MHRS CRANE GEN SET WELDING SET HTW/HBT COMPRESSOR
15 2-Execution 2nd coat inspection by AIMD INSP 16.33 1 0 0 0 0 0 0 0 0 0 0 0 0
16 2-Execution Painting final coat HRSB 16.33 16.33 1 1 32.65331 0 0 0 16.327 0 0 0 0 16.327 0 32.65331
17 2-Execution Overcoating interval HRSB 16.33 4 0 0 0 0 0 0 0 0 0 0 0 0
18 2-Execution Final coat inspection by AIMD INSP 16.33 1 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution 2.0 Painting pipe support HRSB 0 0 0 0 0 0 0 0 0 0 0 0
19 2-Execution Lift up pipe & support pipe using wooden block (1st side ) INSP HRSB 1 1 0 0 0 0 0 0 0 0 0 0 0 0
20 2-Execution To reinstate pipe support to its original position / Insert round bar 3 1 0
0 0 0 0 0 0 0 0 0 0 0
21 2-Execution Surface preparation (Power tool) HRSB 2.76 5.52 1 1 1 16.56 0 5.52 0 5.52 0 0 5.52 0 0 0 16.56
22 2-Execution Inspection surface preparation by AIMD HRSB 2.76 1 0 0 0 0 0 0 0 0 0 0 0 0
23 2-Execution Painting 1st coat INSP 2.76 4.14 1 1 8.28 0 0 0 4.14 0 0 0 0 4.14 0 8.28
24 2-Execution Overcoating interval HRSB 2.76 8 0 0 0 0 0 0 0 0 0 0 0 0
25 2-Execution 1st coat inspection by AIMD 2.76 1 0 0 0 0 0 0 0 0 0 0 0 0
26 2-Execution Painting 2nd coat 2.76 2.76 1 1 5.52 0 0 0 2.76 0 0 0 0 2.76 0 5.52
27 2-Execution Overcoating interval 2.76 4 0 0 0 0 0 0 0 0 0 0 0 0
28 2-Execution 2nd coat inspection by AIMD 2.76 1.00 0 0 0 0 0 0 0 0 0 0 0 0
29 2-Execution Painting final coat 2.76 2.76 1 1 5.52 0 0 0 2.76 0 0 0 0 2.76 0 5.52
30 2-Execution Overcoating interval 2.76 4 0 0 0 0 0 0 0 0 0 0 0 0
31 2-Execution Final coat inspection by AIMD 2.76 1 0 0 0 0 0 0 0 0 0 0 0 0
32 2-Execution Lift up pipe & support pipe using wooden block (2nd side ) 0 0 1 1 0 0 0 0 0 0 0 0 0 0 0 0
33 2-Execution Surface preparation (Power tool) 0 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0
34 2-Execution Inspection surface preparation by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
35 2-Execution Painting 1st coat 0.00 1 1 0 0 0 0 0 0 0 0 0 0 0 0
36 2-Execution Overcoating interval 0 0 0 0 0 0 0 0 0 0 0 0
37 2-Execution 1st coat inspection by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
38 2-Execution Painting 2nd coat 0.00 1 1 0 0 0 0 0 0 0 0 0 0 0 0
39 2-Execution Overcoating interval 0 0 0 0 0 0 0 0 0 0 0 0
40 2-Execution 2nd coat inspection by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
41 2-Execution Painting final coat 0.00 1 1 0 0 0 0 0 0 0 0 0 0 0 0
42 2-Execution Overcoating interval 0 0 0 0 0 0 0 0 0 0 0 0
43 2-Execution Final coat inspection by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
44 2-Execution Lift up pipe,remove wooden block & lift down pipe 1 1 0 0 0 0 0 0 0 0 0 0 0 0
45 2-Execution To apply silicone sealant 0 1 0 0 0 0 0 0 0 0 0 0 0 0
48 2-Execution Housekeeping 1 1 1 0 0 0 1 0 0 0 0 0 0 1
0 0 0 0 0 0 0 0 0 0 0 0
3-Post Execution C) Post execution 0 0 0 0 0 0 0 0 0 0 0 0
49 3-Post Execution Re instate Insulation 0 0 0 0 0 0 0 0 0 0 0 0
50 3-Post Execution Dismantle External Scaffolding 0 0 0 0 0 0 0 0 0 0 0 0
51 3-Post Execution Demobilization 0 0 0 0 0 0 0 0 0 0 0 0
146.97661 251.1265 0 39.173 0 107 0 0 38.173 0 66.803 0 251.1265
14 IWL/BT2/2018/136 4''-MC-225274-3126A-PG PAINTING
1 1-Pre Execution a) Site Preparation HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2 1-Pre Execution Mobilization manpower, equipment, tools & consumable HRSB 0 0 0 0 0 0 0 0 0 0 0 0
3 1-Pre Execution Apply protection on others PPTSB assets equipment/cable/tag number and etc. HRSB 0 0 0 0 0 0 0 0 0 0 0 0
4 1-Pre Execution Shelter/Laydown erection 0 0 0 0 0 0 0 0 0 0 0 0
5 1-Pre Execution Scaffolding erection HRSB 0 0 0 0 0 0 0 0 0 0 0 0
6 1-Pre Execution Remove Insulation (PP CAGE) HRSB 24.17m2 0 0 0 0 0 0 0 0 0 0 0 0
HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution b) During Project Activity HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution 1.0 Painting pipe HRSB 0 0 0 0 0 0 0 0 0 0 0 0
7 2-Execution Site preparation INSP 1 1 1 2 0 1 0 1 0 0 0 0 0 0 2
8 2-Execution Surface preparation (Power tool) 39.75 79.499209 1 1 1 238.4976 0 79.499 0 79.499 0 0 79.499 0 0 0 238.4976
9 2-Execution Inspection surface preparation by AIMD 39.75 1 0 0 0 0 0 0 0 0 0 0 0 0
10 2-Execution Painting 1st coat INSP 39.75 59.62 1 1 119.2488 0 0 0 59.624 0 0 0 0 59.624 0 119.2488
11 2-Execution Overcoating interval HRSB 39.75 8 0 0 0 0 0 0 0 0 0 0 0 0
12 2-Execution 1st coat inspection by AIMD INSP 39.75 1 0 0 0 0 0 0 0 0 0 0 0 0
13 2-Execution Painting 2nd coat HRSB 39.75 39.75 1 1 79.49921 0 0 0 39.75 0 0 0 0 39.75 0 79.49921
14 2-Execution Overcoating interval INSP 39.75 4 0 0 0 0 0 0 0 0 0 0 0 0
15 2-Execution 2nd coat inspection by AIMD INSP 39.75 1 0 0 0 0 0 0 0 0 0 0 0 0
16 2-Execution Painting final coat HRSB 39.75 39.75 1 1 79.49921 0 0 0 39.75 0 0 0 0 39.75 0 79.49921
17 2-Execution Overcoating interval HRSB 39.75 4 0 0 0 0 0 0 0 0 0 0 0 0
18 2-Execution Final coat inspection by AIMD INSP 39.75 1 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution 2.0 Painting pipe support HRSB 0 0 0 0 0 0 0 0 0 0 0 0
19 2-Execution Lift up pipe & support pipe using wooden block (1st side ) INSP HRSB 1 1 0 0 0 0 0 0 0 0 0 0 0 0
20 2-Execution To reinstate pipe support to its original position / Insert round bar 3 1 0
0 0 0 0 0 0 0 0 0 0 0
21 2-Execution Surface preparation (Power tool) HRSB 2.27 4.5432 1 1 1 13.6296 0 4.5432 0 4.5432 0 0 4.5432 0 0 0 13.6296
22 2-Execution Inspection surface preparation by AIMD HRSB 2.27 1 0 0 0 0 0 0 0 0 0 0 0 0
23 2-Execution Painting 1st coat INSP 2.27 3.41 1 1 6.8148 0 0 0 3.4074 0 0 0 0 3.4074 0 6.8148
24 2-Execution Overcoating interval HRSB 2.27 8 0 0 0 0 0 0 0 0 0 0 0 0
25 2-Execution 1st coat inspection by AIMD 2.27 1 0 0 0 0 0 0 0 0 0 0 0 0
26 2-Execution Painting 2nd coat 2.27 2.27 1 1 4.5432 0 0 0 2.2716 0 0 0 0 2.2716 0 4.5432
27 2-Execution Overcoating interval 2.27 4 0 0 0 0 0 0 0 0 0 0 0 0
28 2-Execution 2nd coat inspection by AIMD 2.27 1.00 0 0 0 0 0 0 0 0 0 0 0 0
29 2-Execution Painting final coat 2.27 2.27 1 1 4.5432 0 0 0 2.2716 0 0 0 0 2.2716 0 4.5432
30 2-Execution Overcoating interval 2.27 4 0 0 0 0 0 0 0 0 0 0 0 0
31 2-Execution Final coat inspection by AIMD 2.27 1 0 0 0 0 0 0 0 0 0 0 0 0
32 2-Execution Lift up pipe & support pipe using wooden block (2nd side ) 0 1 1 0 0 0 0 0 0 0 0 0 0 0 0
33 2-Execution Surface preparation (Power tool) 0 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0
34 2-Execution Inspection surface preparation by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
35 2-Execution Painting 1st coat 0.00 1 1 0 0 0 0 0 0 0 0 0 0 0 0
36 2-Execution Overcoating interval 0 0 0 0 0 0 0 0 0 0 0 0
37 2-Execution 1st coat inspection by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
38 2-Execution Painting 2nd coat 0.00 1 1 0 0 0 0 0 0 0 0 0 0 0 0
39 2-Execution Overcoating interval 0 0 0 0 0 0 0 0 0 0 0 0
40 2-Execution 2nd coat inspection by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
41 2-Execution Painting final coat 0.00 1 1 0 0 0 0 0 0 0 0 0 0 0 0
42 2-Execution Overcoating interval 0 0 0 0 0 0 0 0 0 0 0 0
43 2-Execution Final coat inspection by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
44 2-Execution Lift up pipe,remove wooden block & lift down pipe 1 1 0 0 0 0 0 0 0 0 0 0 0 0
45 2-Execution To apply silicone sealant 0 1 0 0 0 0 0 0 0 0 0 0 0 0
48 2-Execution Housekeeping 1 1 1 0 0 0 1 0 0 0 0 0 0 1
0 0 0 0 0 0 0 0 0 0 0 0
3-Post Execution C) Post execution 0 0 0 0 0 0 0 0 0 0 0 0
49 3-Post Execution Re instate Insulation (PP CAGE) 24.17m2 0 0 0 0 0 0 0 0 0 0 0 0
50 3-Post Execution Dismantle External Scaffolding 0 0 0 0 0 0 0 0 0 0 0 0
Open
RESOURCE (MAN) MANHOURS RESOURCE (EQPT)
AWL F1 F2 GW RI HW FW WEL PNT CBT MHRS MHRS MHRS MHRS MHRS MHRS MHRS MHRS MHRS
NO TASKID No TAPHASE TASK TASKNOTE OWNER CONTR DATA DUR (HRS) (AWL) (F1) (F2) (GW) MHRS (HW) (FW) (WEL) (PNT) (CBT) SCAFFOLDING (M3) INSULATION (M2)
(RI)
MHRS MHRS CRANE GEN SET WELDING SET HTW/HBT COMPRESSOR
51 3-Post Execution Demobilization 0 0 0 0 0 0 0 0 0 0 0 0
273.11663 549.2757 0 85.042 0 233.12 0 0 84.042 0 147.07 0 549.2757
14''-CS-244018-1120A-NI
14"-CR-244022-1120A-NI,
12''-CS-2254271-1120A-NI
12"-CR-225265-1120A-NI,
15 IWL/BT2/2018/12 PAINTING
10''-CS-225269-1120A-NI
10"-CR-225263-1120A-NI,
2''-CS-225486-1120A-NI
2"-CR-225487-1120A-NI
Open
RESOURCE (MAN) MANHOURS RESOURCE (EQPT)
AWL F1 F2 GW RI HW FW WEL PNT CBT MHRS MHRS MHRS MHRS MHRS MHRS MHRS MHRS MHRS
NO TASKID No TAPHASE TASK TASKNOTE OWNER CONTR DATA DUR (HRS) (AWL) (F1) (F2) (GW) MHRS (HW) (FW) (WEL) (PNT) (CBT) SCAFFOLDING (M3) INSULATION (M2)
(RI)
MHRS MHRS CRANE GEN SET WELDING SET HTW/HBT COMPRESSOR
1 1-Pre Execution a) Site Preparation HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2 1-Pre Execution Mobilization manpower, equipment, tools & consumable HRSB 0 0 0 0 0 0 0 0 0 0 0 0
3 1-Pre Execution Apply protection on others PPTSB assets equipment/cable/tag number and etc. HRSB 0 0 0 0 0 0 0 0 0 0 0 0
4 1-Pre Execution Shelter/Laydown erection 0 0 0 0 0 0 0 0 0 0 0 0
5 1-Pre Execution Scaffolding erection HRSB 0 0 0 0 0 0 0 0 0 0 0 0
6 1-Pre Execution Remove Insulation 0 0 0 0 0 0 0 0 0 0 0 0
HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution b) During Project Activity HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution 1.0 Painting pipe HRSB 0 0 0 0 0 0 0 0 0 0 0 0
7 2-Execution Site preparation INSP 1 1 1 2 0 1 0 1 0 0 0 0 0 0 2
8 2-Execution Surface preparation (Power tool) 7.89 15.78 1 1 1 47.34 0 15.78 0 15.78 0 0 15.78 0 0 0 47.34
9 2-Execution Inspection surface preparation by AIMD 7.89 1 0 0 0 0 0 0 0 0 0 0 0 0
10 2-Execution Painting 1st coat INSP 7.89 11.84 1 1 23.67 0 0 0 11.835 0 0 0 0 11.835 0 23.67
11 2-Execution Overcoating interval HRSB 7.89 8 0 0 0 0 0 0 0 0 0 0 0 0
12 2-Execution 1st coat inspection by AIMD INSP 7.89 1 0 0 0 0 0 0 0 0 0 0 0 0
13 2-Execution Painting 2nd coat HRSB 7.89 7.89 1 1 15.78 0 0 0 7.89 0 0 0 0 7.89 0 15.78
14 2-Execution Overcoating interval INSP 7.89 4 0 0 0 0 0 0 0 0 0 0 0 0
15 2-Execution 2nd coat inspection by AIMD INSP 7.89 1 0 0 0 0 0 0 0 0 0 0 0 0
16 2-Execution Painting final coat HRSB 7.89 7.89 1 1 15.78 0 0 0 7.89 0 0 0 0 7.89 0 15.78
17 2-Execution Overcoating interval HRSB 7.89 4 0 0 0 0 0 0 0 0 0 0 0 0
18 2-Execution Final coat inspection by AIMD INSP 7.89 1 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution 2.0 Painting pipe support HRSB 0 0 0 0 0 0 0 0 0 0 0 0
19 2-Execution Lift up pipe & support pipe using wooden block (1st side ) INSP HRSB 72 23.76 1 1 47.52 0 23.76 0 23.76 0 0 0 0 0 0 47.52
20 2-Execution To reinstate pipe support to its original position 1 2 3 1 8 0 6 0 2 0 0 0 0 0 0 8
21 2-Execution Surface preparation (Power tool) HRSB 16.37 32.74 1 1 1 98.22 0 32.74 0 32.74 0 0 32.74 0 0 0 98.22
22 2-Execution Inspection surface preparation by AIMD HRSB 16.37 1 0 0 0 0 0 0 0 0 0 0 0 0
23 2-Execution Painting 1st coat INSP 16.37 24.56 1 1 49.11 0 0 0 24.555 0 0 0 0 24.555 0 49.11
24 2-Execution Overcoating interval HRSB 16.37 8 0 0 0 0 0 0 0 0 0 0 0 0
25 2-Execution 1st coat inspection by AIMD 16.37 1 0 0 0 0 0 0 0 0 0 0 0 0
26 2-Execution Painting 2nd coat 16.37 16.37 1 1 32.74 0 0 0 16.37 0 0 0 0 16.37 0 32.74
27 2-Execution Overcoating interval 16.37 4 0 0 0 0 0 0 0 0 0 0 0 0
28 2-Execution 2nd coat inspection by AIMD 16.37 1.00 0 0 0 0 0 0 0 0 0 0 0 0
29 2-Execution Painting final coat 16.37 16.37 1 1 32.74 0 0 0 16.37 0 0 0 0 16.37 0 32.74
30 2-Execution Overcoating interval 16.37 4 0 0 0 0 0 0 0 0 0 0 0 0
31 2-Execution Final coat inspection by AIMD 16.37 1 0 0 0 0 0 0 0 0 0 0 0 0
32 2-Execution Lift up pipe & support pipe using wooden block (2nd side ) 72 23.76 1 1 47.52 0 23.76 0 23.76 0 0 0 0 0 0 47.52
33 2-Execution Surface preparation (Power tool) 0 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0
34 2-Execution Inspection surface preparation by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
35 2-Execution Painting 1st coat 0.00 1 1 0 0 0 0 0 0 0 0 0 0 0 0
36 2-Execution Overcoating interval 0 0 0 0 0 0 0 0 0 0 0 0
37 2-Execution 1st coat inspection by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
38 2-Execution Painting 2nd coat 0.00 1 1 0 0 0 0 0 0 0 0 0 0 0 0
39 2-Execution Overcoating interval 0 0 0 0 0 0 0 0 0 0 0 0
40 2-Execution 2nd coat inspection by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
41 2-Execution Painting final coat 0.00 1 1 0 0 0 0 0 0 0 0 0 0 0 0
42 2-Execution Overcoating interval 0 0 0 0 0 0 0 0 0 0 0 0
43 2-Execution Final coat inspection by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
44 2-Execution Lift up pipe,remove wooden block & lift down pipe 72 23.76 1 1 47.52 0 23.76 0 23.76 0 0 0 0 0 0 47.52
45 2-Execution To apply silicone sealant 0 1 0 0 0 0 0 0 0 0 0 0 0 0
46 2-Execution To install sleeve cover 4 1 1 8 0 4 0 4 0 0 0 0 0 0 8
47 2-Execution Too remove steel wire 0.5 1 0.5 0 0 0 0.5 0 0 0 0 0 0 0.5
48 2-Execution Housekeeping 1 1 1 0 0 0 1 0 0 0 0 0 0 1
0 0 0 0 0 0 0 0 0 0 0 0
3-Post Execution C) Post execution 0 0 0 0 0 0 0 0 0 0 0 0
49 3-Post Execution Re instate Insulation 0 0 0 0 0 0 0 0 0 0 0 0
50 3-Post Execution Dismantle External Scaffolding 0 0 0 0 0 0 0 0 0 0 0 0
51 3-Post Execution Demobilization 0 0 0 0 0 0 0 0 0 0 0 0
253.21 477.44 0 130.8 0 213.21 0 0 48.52 0 84.91 0 477.44
34 IWR/BT3/2019/146 6''-PL-294052-1101A-NI PAINTING
1 1-Pre Execution a) Site Preparation HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2 1-Pre Execution Mobilization manpower, equipment, tools & consumable HRSB 0 0 0 0 0 0 0 0 0 0 0 0
3 1-Pre Execution Apply protection on others PPTSB assets equipment/cable/tag number and etc. HRSB 0 0 0 0 0 0 0 0 0 0 0 0
4 1-Pre Execution Shelter/Laydown erection 0 0 0 0 0 0 0 0 0 0 0 0
5 1-Pre Execution Scaffolding erection HRSB 0 0 0 0 0 0 0 0 0 0 0 0
6 1-Pre Execution Remove Insulation 0 0 0 0 0 0 0 0 0 0 0 0
HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution b) During Project Activity HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution 1.0 Painting pipe HRSB 0 0 0 0 0 0 0 0 0 0 0 0
7 2-Execution Site preparation INSP 1 1 1 2 0 1 0 1 0 0 0 0 0 0 2
8 2-Execution Surface preparation (Power tool) 87.48 174.95273 1 1 1 524.8582 0 175 0 175 0 0 175 0 0 0 524.8582
9 2-Execution Inspection surface preparation by AIMD 87.48 1 0 0 0 0 0 0 0 0 0 0 0 0
10 2-Execution Painting 1st coat INSP 87.48 131.21 1 1 262.4291 0 0 0 131.21 0 0 0 0 131.21 0 262.4291
11 2-Execution Overcoating interval HRSB 87.48 8 0 0 0 0 0 0 0 0 0 0 0 0
12 2-Execution 1st coat inspection by AIMD INSP 87.48 1 0 0 0 0 0 0 0 0 0 0 0 0
13 2-Execution Painting 2nd coat HRSB 87.48 87.48 1 1 174.9527 0 0 0 87.476 0 0 0 0 87.476 0 174.9527
14 2-Execution Overcoating interval INSP 87.48 4 0 0 0 0 0 0 0 0 0 0 0 0
15 2-Execution 2nd coat inspection by AIMD INSP 87.48 1 0 0 0 0 0 0 0 0 0 0 0 0
16 2-Execution Painting final coat HRSB 87.48 87.48 1 1 174.9527 0 0 0 87.476 0 0 0 0 87.476 0 174.9527
17 2-Execution Overcoating interval HRSB 87.48 4 0 0 0 0 0 0 0 0 0 0 0 0
18 2-Execution Final coat inspection by AIMD INSP 87.48 1 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution 2.0 Painting pipe support HRSB 0 0 0 0 0 0 0 0 0 0 0 0
19 2-Execution Lift up pipe & support pipe using wooden block (1st side ) INSP HRSB 39 12.87 1 1 25.74 0 12.87 0 12.87 0 0 0 0 0 0 25.74
20 2-Execution To reinstate pipe support to its original position 0 0 3 1 0 0 0 0 0 0 0 0 0 0 0 0
21 2-Execution Surface preparation (Power tool) HRSB 6.52 13.0408 1 1 1 39.1224 0 13.041 0 13.041 0 0 13.041 0 0 0 39.1224
22 2-Execution Inspection surface preparation by AIMD HRSB 6.52 1 0 0 0 0 0 0 0 0 0 0 0 0
23 2-Execution Painting 1st coat INSP 6.52 9.78 1 1 19.5612 0 0 0 9.7806 0 0 0 0 9.7806 0 19.5612
24 2-Execution Overcoating interval HRSB 6.52 8 0 0 0 0 0 0 0 0 0 0 0 0
25 2-Execution 1st coat inspection by AIMD 6.52 1 0 0 0 0 0 0 0 0 0 0 0 0
26 2-Execution Painting 2nd coat 6.52 6.52 1 1 13.0408 0 0 0 6.5204 0 0 0 0 6.5204 0 13.0408
27 2-Execution Overcoating interval 6.52 4 0 0 0 0 0 0 0 0 0 0 0 0
28 2-Execution 2nd coat inspection by AIMD 6.52 1.00 0 0 0 0 0 0 0 0 0 0 0 0
29 2-Execution Painting final coat 6.52 6.52 1 1 13.0408 0 0 0 6.5204 0 0 0 0 6.5204 0 13.0408
30 2-Execution Overcoating interval 6.52 4 0 0 0 0 0 0 0 0 0 0 0 0
31 2-Execution Final coat inspection by AIMD 6.52 1 0 0 0 0 0 0 0 0 0 0 0 0
32 2-Execution Lift up pipe & support pipe using wooden block (2nd side ) 39 12.87 1 1 25.74 0 12.87 0 12.87 0 0 0 0 0 0 25.74
Open
RESOURCE (MAN) MANHOURS RESOURCE (EQPT)
AWL F1 F2 GW RI HW FW WEL PNT CBT MHRS MHRS MHRS MHRS MHRS MHRS MHRS MHRS MHRS
NO TASKID No TAPHASE TASK TASKNOTE OWNER CONTR DATA DUR (HRS) (AWL) (F1) (F2) (GW) MHRS (HW) (FW) (WEL) (PNT) (CBT) SCAFFOLDING (M3) INSULATION (M2)
(RI)
MHRS MHRS CRANE GEN SET WELDING SET HTW/HBT COMPRESSOR
33 2-Execution Surface preparation (Power tool) 0 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0
34 2-Execution Inspection surface preparation by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
35 2-Execution Painting 1st coat 0.00 1 1 0 0 0 0 0 0 0 0 0 0 0 0
36 2-Execution Overcoating interval 0 0 0 0 0 0 0 0 0 0 0 0
37 2-Execution 1st coat inspection by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
38 2-Execution Painting 2nd coat 0.00 1 1 0 0 0 0 0 0 0 0 0 0 0 0
39 2-Execution Overcoating interval 0 0 0 0 0 0 0 0 0 0 0 0
40 2-Execution 2nd coat inspection by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
41 2-Execution Painting final coat 0.00 1 1 0 0 0 0 0 0 0 0 0 0 0 0
42 2-Execution Overcoating interval 0 0 0 0 0 0 0 0 0 0 0 0
43 2-Execution Final coat inspection by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
44 2-Execution Lift up pipe,remove wooden block & lift down pipe 39 12.87 1 1 25.74 0 12.87 0 12.87 0 0 0 0 0 0 25.74
45 2-Execution To apply silicone sealant 0 1 0 0 0 0 0 0 0 0 0 0 0 0
46 2-Execution To remove and install spring hanger 4 1 1 8 0 4 0 4 0 0 0 0 0 0 8
47 2-Execution Too remove steel wire 1 0 0 0 0 0 0 0 0 0 0 0 0
48 2-Execution Housekeeping 1 1 1 0 0 0 1 0 0 0 0 0 0 1
0 0 0 0 0 0 0 0 0 0 0 0
3-Post Execution C) Post execution 0 0 0 0 0 0 0 0 0 0 0 0
49 3-Post Execution Re instate Insulation 0 0 0 0 0 0 0 0 0 0 0 0
50 3-Post Execution Dismantle External Scaffolding 0 0 0 0 0 0 0 0 0 0 0 0
51 3-Post Execution Demobilization 0 0 0 0 0 0 0 0 0 0 0 0
601.59219 1310.178 0 231.6 0 561.59 0 0 188 0 329 0 1310.178
35 IWR/BT3/2019/051 3''-PL-294008-1101A-NI PAINTING
1 1-Pre Execution a) Site Preparation HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2 1-Pre Execution Mobilization manpower, equipment, tools & consumable HRSB 0 0 0 0 0 0 0 0 0 0 0 0
3 1-Pre Execution Apply protection on others PPTSB assets equipment/cable/tag number and etc. HRSB 0 0 0 0 0 0 0 0 0 0 0 0
4 1-Pre Execution Shelter/Laydown erection 0 0 0 0 0 0 0 0 0 0 0 0
5 1-Pre Execution Scaffolding erection HRSB 0 0 0 0 0 0 0 0 0 0 0 0
6 1-Pre Execution Remove Insulation 0 0 0 0 0 0 0 0 0 0 0 0
HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution b) During Project Activity HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution 1.0 Painting pipe HRSB 0 0 0 0 0 0 0 0 0 0 0 0
7 2-Execution Site preparation INSP 1 1 1 2 0 1 0 1 0 0 0 0 0 0 2
8 2-Execution Surface preparation (Power tool) 29.94 59.872 1 1 1 179.616 0 59.872 0 59.872 0 0 59.872 0 0 0 179.616
9 2-Execution Inspection surface preparation by AIMD 29.94 1 0 0 0 0 0 0 0 0 0 0 0 0
10 2-Execution Painting 1st coat INSP 29.94 44.90 1 1 89.808 0 0 0 44.904 0 0 0 0 44.904 0 89.808
11 2-Execution Overcoating interval HRSB 29.94 8 0 0 0 0 0 0 0 0 0 0 0 0
12 2-Execution 1st coat inspection by AIMD INSP 29.94 1 0 0 0 0 0 0 0 0 0 0 0 0
13 2-Execution Painting 2nd coat HRSB 29.94 29.94 1 1 59.872 0 0 0 29.936 0 0 0 0 29.936 0 59.872
14 2-Execution Overcoating interval INSP 29.94 4 0 0 0 0 0 0 0 0 0 0 0 0
15 2-Execution 2nd coat inspection by AIMD INSP 29.94 1 0 0 0 0 0 0 0 0 0 0 0 0
16 2-Execution Painting final coat HRSB 29.94 29.94 1 1 59.872 0 0 0 29.936 0 0 0 0 29.936 0 59.872
17 2-Execution Overcoating interval HRSB 29.94 4 0 0 0 0 0 0 0 0 0 0 0 0
18 2-Execution Final coat inspection by AIMD INSP 29.94 1 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution 2.0 Painting pipe support HRSB 0 0 0 0 0 0 0 0 0 0 0 0
19 2-Execution Lift up pipe & support pipe using wooden block (1st side ) INSP HRSB 16 5.28 1 1 10.56 0 5.28 0 5.28 0 0 0 0 0 0 10.56
20 2-Execution To reinstate pipe support to its original position 3 1 0 0 0 0 0 0 0 0 0 0 0 0
21 2-Execution Surface preparation (Power tool) HRSB 2.1 4.2 1 1 1 12.6 0 4.2 0 4.2 0 0 4.2 0 0 0 12.6
22 2-Execution Inspection surface preparation by AIMD HRSB 2.1 1 0 0 0 0 0 0 0 0 0 0 0 0
23 2-Execution Painting 1st coat INSP 2.1 3.15 1 1 6.3 0 0 0 3.15 0 0 0 0 3.15 0 6.3
24 2-Execution Overcoating interval HRSB 2.1 8 0 0 0 0 0 0 0 0 0 0 0 0
25 2-Execution 1st coat inspection by AIMD 2.1 1 0 0 0 0 0 0 0 0 0 0 0 0
26 2-Execution Painting 2nd coat 2.1 2.10 1 1 4.2 0 0 0 2.1 0 0 0 0 2.1 0 4.2
27 2-Execution Overcoating interval 2.1 4 0 0 0 0 0 0 0 0 0 0 0 0
28 2-Execution 2nd coat inspection by AIMD 2.1 1.00 0 0 0 0 0 0 0 0 0 0 0 0
29 2-Execution Painting final coat 2.1 2.10 1 1 4.2 0 0 0 2.1 0 0 0 0 2.1 0 4.2
30 2-Execution Overcoating interval 2.1 4 0 0 0 0 0 0 0 0 0 0 0 0
31 2-Execution Final coat inspection by AIMD 2.1 1 0 0 0 0 0 0 0 0 0 0 0 0
32 2-Execution Lift up pipe & support pipe using wooden block (2nd side ) 16 5.28 1 1 10.56 0 5.28 0 5.28 0 0 0 0 0 0 10.56
33 2-Execution Surface preparation (Power tool) 0 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0
34 2-Execution Inspection surface preparation by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
35 2-Execution Painting 1st coat 0.00 1 1 0 0 0 0 0 0 0 0 0 0 0 0
36 2-Execution Overcoating interval 0 0 0 0 0 0 0 0 0 0 0 0
37 2-Execution 1st coat inspection by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
38 2-Execution Painting 2nd coat 0.00 1 1 0 0 0 0 0 0 0 0 0 0 0 0
39 2-Execution Overcoating interval 0 0 0 0 0 0 0 0 0 0 0 0
40 2-Execution 2nd coat inspection by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
41 2-Execution Painting final coat 0.00 1 1 0 0 0 0 0 0 0 0 0 0 0 0
42 2-Execution Overcoating interval 0 0 0 0 0 0 0 0 0 0 0 0
43 2-Execution Final coat inspection by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
44 2-Execution Lift up pipe,remove wooden block & lift down pipe 16 5.28 1 1 10.56 0 5.28 0 5.28 0 0 0 0 0 0 10.56
45 2-Execution To apply silicone sealant 0 1 0 0 0 0 0 0 0 0 0 0 0 0
46 2-Execution Remove & install spring support - 1 unit 1 2 1 1 4 0 2 0 2 0 0 0 0 0 0 4
47 2-Execution To service gate valve - 1 unit 1 2 1 1 4 0 2 0 2 0 0 0 0 0 0 4
48 2-Execution Housekeeping 1 1 1 0 0 0 1 0 0 0 0 0 0 1
0 0 0 0 0 0 0 0 0 0 0 0
3-Post Execution C) Post execution 0 0 0 0 0 0 0 0 0 0 0 0
48 3-Post Execution Re instate Insulation 0 0 0 0 0 0 0 0 0 0 0 0
49 3-Post Execution Dismantle External Scaffolding 0 0 0 0 0 0 0 0 0 0 0 0
50 3-Post Execution Demobilization 0 0 0 0 0 0 0 0 0 0 0 0
238.038 459.148 0 84.912 0 198 0 0 64.072 0 112.13 0 459.148
36 IWR/BT3/2019/027 12''-PL-291021-1101A-NI PAINTING
1 1-Pre Execution a) Site Preparation HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2 1-Pre Execution Mobilization manpower, equipment, tools & consumable HRSB 0 0 0 0 0 0 0 0 0 0 0 0
3 1-Pre Execution Apply protection on others PPTSB assets equipment/cable/tag number and etc. HRSB 0 0 0 0 0 0 0 0 0 0 0 0
4 1-Pre Execution Shelter/Laydown erection 0 0 0 0 0 0 0 0 0 0 0 0
5 1-Pre Execution Scaffolding erection HRSB 0 0 0 0 0 0 0 0 0 0 0 0
6 1-Pre Execution Remove Insulation 0 0 0 0 0 0 0 0 0 0 0 0
HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution b) During Project Activity HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution 1.0 Painting pipe HRSB 0 0 0 0 0 0 0 0 0 0 0 0
7 2-Execution Site preparation INSP 1 1 1 2 0 1 0 1 0 0 0 0 0 0 2
8 2-Execution Surface preparation (Power tool) 40.59 81.18 1 1 1 243.54 0 81.18 0 81.18 0 0 81.18 0 0 0 243.54
9 2-Execution Inspection surface preparation by AIMD 40.59 1 0 0 0 0 0 0 0 0 0 0 0 0
10 2-Execution Painting 1st coat INSP 40.59 60.89 1 1 121.77 0 0 0 60.885 0 0 0 0 60.885 0 121.77
Open
RESOURCE (MAN) MANHOURS RESOURCE (EQPT)
AWL F1 F2 GW RI HW FW WEL PNT CBT MHRS MHRS MHRS MHRS MHRS MHRS MHRS MHRS MHRS
NO TASKID No TAPHASE TASK TASKNOTE OWNER CONTR DATA DUR (HRS) (AWL) (F1) (F2) (GW) MHRS (HW) (FW) (WEL) (PNT) (CBT) SCAFFOLDING (M3) INSULATION (M2)
(RI)
MHRS MHRS CRANE GEN SET WELDING SET HTW/HBT COMPRESSOR
11 2-Execution Overcoating interval HRSB 40.59 8 0 0 0 0 0 0 0 0 0 0 0 0
12 2-Execution 1st coat inspection by AIMD INSP 40.59 1 0 0 0 0 0 0 0 0 0 0 0 0
13 2-Execution Painting 2nd coat HRSB 40.59 40.59 1 1 81.18 0 0 0 40.59 0 0 0 0 40.59 0 81.18
14 2-Execution Overcoating interval INSP 40.59 4 0 0 0 0 0 0 0 0 0 0 0 0
15 2-Execution 2nd coat inspection by AIMD INSP 40.59 1 0 0 0 0 0 0 0 0 0 0 0 0
16 2-Execution Painting final coat HRSB 40.59 40.59 1 1 81.18 0 0 0 40.59 0 0 0 0 40.59 0 81.18
17 2-Execution Overcoating interval HRSB 40.59 4 0 0 0 0 0 0 0 0 0 0 0 0
18 2-Execution Final coat inspection by AIMD INSP 40.59 1 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution 2.0 Painting pipe support HRSB 0 0 0 0 0 0 0 0 0 0 0 0
Lift up pipe & support pipe using wooden block (1st side )/ To
19 2-Execution reinstate pipe support to its original position 0 1 1 0
INSP HRSB 0 0 0 0 0 0 0 0 0 0 0
20 2-Execution Surface preparation (Power tool) HRSB 6.12 12.24 1 1 1 36.72 0 12.24 0 12.24 0 0 12.24 0 0 0 36.72
21 2-Execution Inspection surface preparation by AIMD HRSB 6.12 1 0 0 0 0 0 0 0 0 0 0 0 0
22 2-Execution Painting 1st coat INSP 6.12 9.18 1 1 18.36 0 0 0 9.18 0 0 0 0 9.18 0 18.36
23 2-Execution Overcoating interval HRSB 6.12 8 0 0 0 0 0 0 0 0 0 0 0 0
24 2-Execution 1st coat inspection by AIMD 6.12 1 0 0 0 0 0 0 0 0 0 0 0 0
25 2-Execution Painting 2nd coat 6.12 6.12 1 1 12.24 0 0 0 6.12 0 0 0 0 6.12 0 12.24
26 2-Execution Overcoating interval 6.12 4 0 0 0 0 0 0 0 0 0 0 0 0
27 2-Execution 2nd coat inspection by AIMD 6.12 1.00 0 0 0 0 0 0 0 0 0 0 0 0
28 2-Execution Painting final coat 6.12 6.12 1 1 12.24 0 0 0 6.12 0 0 0 0 6.12 0 12.24
29 2-Execution Overcoating interval 6.12 4 0 0 0 0 0 0 0 0 0 0 0 0
30 2-Execution Final coat inspection by AIMD 6.12 1 0 0 0 0 0 0 0 0 0 0 0 0
31 2-Execution Lift up pipe & support pipe using wooden block (2nd side ) 0 1 1 0 0 0 0 0 0 0 0 0 0 0 0
32 2-Execution Surface preparation (Power tool) 0 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0
33 2-Execution Inspection surface preparation by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
34 2-Execution Painting 1st coat 0.00 1 1 0 0 0 0 0 0 0 0 0 0 0 0
35 2-Execution Overcoating interval 0 0 0 0 0 0 0 0 0 0 0 0
36 2-Execution 1st coat inspection by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
37 2-Execution Painting 2nd coat 0.00 1 1 0 0 0 0 0 0 0 0 0 0 0 0
38 2-Execution Overcoating interval 0 0 0 0 0 0 0 0 0 0 0 0
39 2-Execution 2nd coat inspection by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
40 2-Execution Painting final coat 0.00 1 1 0 0 0 0 0 0 0 0 0 0 0 0
41 2-Execution Overcoating interval 0 0 0 0 0 0 0 0 0 0 0 0
42 2-Execution Final coat inspection by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
43 2-Execution Lift up pipe,remove wooden block & lift down pipe 0 1 1 0 0 0 0 0 0 0 0 0 0 0 0
44 2-Execution To apply silicone sealant 0 1 0 0 0 0 0 0 0 0 0 0 0 0
45 2-Execution Replace new U-bolt -1/2'' 1 unit 0.16 1 0.16 0 0.16 0 0 0 0 0 0 0 0 0.16
46 2-Execution Housekeeping 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
3-Post Execution C) Post execution 0 0 0 0 0 0 0 0 0 0 0 0
47 3-Post Execution Re instate Insulation 0 0 0 0 0 0 0 0 0 0 0 0
48 3-Post Execution Dismantle External Scaffolding 0 0 0 0 0 0 0 0 0 0 0 0
49 3-Post Execution Demobilization 0 0 0 0 0 0 0 0 0 0 0 0
298.065 609.39 0 94.58 0 257.91 0 0 93.42 0 163.49 0 609.39
37 IWR/BT3/2019/012 12''-PL-291013-1101A-NI PAINTING
1 1-Pre Execution a) Site Preparation HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2 1-Pre Execution Mobilization manpower, equipment, tools & consumable HRSB 0 0 0 0 0 0 0 0 0 0 0 0
3 1-Pre Execution Apply protection on others PPTSB assets equipment/cable/tag number and etc. HRSB 0 0 0 0 0 0 0 0 0 0 0 0
4 1-Pre Execution Shelter/Laydown erection 0 0 0 0 0 0 0 0 0 0 0 0
5 1-Pre Execution Scaffolding erection HRSB 0 0 0 0 0 0 0 0 0 0 0 0
6 1-Pre Execution Remove Insulation 0 0 0 0 0 0 0 0 0 0 0 0
HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution b) During Project Activity HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution 1.0 Painting pipe HRSB 0 0 0 0 0 0 0 0 0 0 0 0
7 2-Execution Site preparation INSP 1 1 1 2 0 1 0 1 0 0 0 0 0 0 2
8 2-Execution Surface preparation (Power tool) 12.67 25.34 1 1 1 76.02 0 25.34 0 25.34 0 0 25.34 0 0 0 76.02
9 2-Execution Inspection surface preparation by AIMD 12.67 1 0 0 0 0 0 0 0 0 0 0 0 0
10 2-Execution Painting 1st coat INSP 12.67 19.01 1 1 38.01 0 0 0 19.005 0 0 0 0 19.005 0 38.01
11 2-Execution Overcoating interval HRSB 12.67 8 0 0 0 0 0 0 0 0 0 0 0 0
12 2-Execution 1st coat inspection by AIMD INSP 12.67 1 0 0 0 0 0 0 0 0 0 0 0 0
13 2-Execution Painting 2nd coat HRSB 12.67 12.67 1 1 25.34 0 0 0 12.67 0 0 0 0 12.67 0 25.34
14 2-Execution Overcoating interval INSP 12.67 4 0 0 0 0 0 0 0 0 0 0 0 0
15 2-Execution 2nd coat inspection by AIMD INSP 12.67 1 0 0 0 0 0 0 0 0 0 0 0 0
16 2-Execution Painting final coat HRSB 12.67 12.67 1 1 25.34 0 0 0 12.67 0 0 0 0 12.67 0 25.34
17 2-Execution Overcoating interval HRSB 12.67 4 0 0 0 0 0 0 0 0 0 0 0 0
18 2-Execution Final coat inspection by AIMD INSP 12.67 1 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution 2.0 Painting pipe support HRSB 0 0 0 0 0 0 0 0 0 0 0 0
19 2-Execution Lift up pipe & support pipe using wooden block (1st side ) INSP HRSB 0 1 1 0 0 0 0 0 0 0 0 0 0 0 0
20 2-Execution Surface preparation (Power tool) HRSB 2.01 4.02 1 1 1 12.06 0 4.02 0 4.02 0 0 4.02 0 0 0 12.06
21 2-Execution Inspection surface preparation by AIMD HRSB 2.01 1 0 0 0 0 0 0 0 0 0 0 0 0
22 2-Execution Painting 1st coat INSP 2.01 3.02 1 1 6.03 0 0 0 3.015 0 0 0 0 3.015 0 6.03
23 2-Execution Overcoating interval HRSB 2.01 8 0 0 0 0 0 0 0 0 0 0 0 0
24 2-Execution 1st coat inspection by AIMD 2.01 1 0 0 0 0 0 0 0 0 0 0 0 0
25 2-Execution Painting 2nd coat 2.01 2.01 1 1 4.02 0 0 0 2.01 0 0 0 0 2.01 0 4.02
26 2-Execution Overcoating interval 2.01 4 0 0 0 0 0 0 0 0 0 0 0 0
27 2-Execution 2nd coat inspection by AIMD 2.01 1.00 0 0 0 0 0 0 0 0 0 0 0 0
28 2-Execution Painting final coat 2.01 2.01 1 1 4.02 0 0 0 2.01 0 0 0 0 2.01 0 4.02
29 2-Execution Overcoating interval 2.01 4 0 0 0 0 0 0 0 0 0 0 0 0
30 2-Execution Final coat inspection by AIMD 2.01 1 0 0 0 0 0 0 0 0 0 0 0 0
31 2-Execution Lift up pipe & support pipe using wooden block (2nd side ) 0 1 1 0 0 0 0 0 0 0 0 0 0 0 0
32 2-Execution Surface preparation (Power tool) 0 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0
33 2-Execution Inspection surface preparation by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
34 2-Execution Painting 1st coat 0.00 1 1 0 0 0 0 0 0 0 0 0 0 0 0
35 2-Execution Overcoating interval 0 0 0 0 0 0 0 0 0 0 0 0
36 2-Execution 1st coat inspection by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
37 2-Execution Painting 2nd coat 0.00 1 1 0 0 0 0 0 0 0 0 0 0 0 0
38 2-Execution Overcoating interval 0 0 0 0 0 0 0 0 0 0 0 0
39 2-Execution 2nd coat inspection by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
40 2-Execution Painting final coat 0.00 1 1 0 0 0 0 0 0 0 0 0 0 0 0
41 2-Execution Overcoating interval 0 0 0 0 0 0 0 0 0 0 0 0
42 2-Execution Final coat inspection by AIMD 0 0 0 0 0 0 0 0 0 0 0 0
43 2-Execution Lift up pipe,remove wooden block & lift down pipe 0 1 1 0 0 0 0 0 0 0 0 0 0 0 0
44 2-Execution Housekeeping 1 1 1 0 0 0 1 0 0 0 0 0 0 1
0 0 0 0 0 0 0 0 0 0 0 0
3-Post Execution C) Post execution 0 0 0 0 0 0 0 0 0 0 0 0
44 3-Post Execution Re instate Insulation 0 0 0 0 0 0 0 0 0 0 0 0
Open
RESOURCE (MAN) MANHOURS RESOURCE (EQPT)
AWL F1 F2 GW RI HW FW WEL PNT CBT MHRS MHRS MHRS MHRS MHRS MHRS MHRS MHRS MHRS
NO TASKID No TAPHASE TASK TASKNOTE OWNER CONTR DATA DUR (HRS) (AWL) (F1) (F2) (GW) MHRS (HW) (FW) (WEL) (PNT) (CBT) SCAFFOLDING (M3) INSULATION (M2)
(RI)
MHRS MHRS CRANE GEN SET WELDING SET HTW/HBT COMPRESSOR
45 3-Post Execution Dismantle External Scaffolding 0 0 0 0 0 0 0 0 0 0 0 0
46 3-Post Execution Demobilization 0 0 0 0 0 0 0 0 0 0 0 0
122.74 193.84 0 30.36 0 82.74 0 0 29.36 0 51.38 0 193.84
38 IWL/BT3/FY2018/723 1"-SOP-292047-1105D-NI BOLTS AND NUTS REPLACEMENT
1 1-Pre Execution a) Site Preparation HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2 1-Pre Execution Mobilization manpower, equipment, tools & consumable HRSB 0 0 0 0 0 0 0 0 0 0 0 0
3 1-Pre Execution Apply protection on others PPTSB assets equipment/cable/tag number and etc. HRSB 0 0 0 0 0 0 0 0 0 0 0 0
4 1-Pre Execution Shelter/Laydown erection HRSB 0 0 0 0 0 0 0 0 0 0 0 0
5 1-Pre Execution Scaffolding erection HRSB 0 0 0 0 0 0 0 0 0 0 0 0
6 1-Pre Execution Remove Insulation HRSB 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
2-Execution b) During Project Activity HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution 1.0 Replace bolt and nuts HRSB 0 0 0 0 0 0 0 0 0 0 0 0
7 2-Execution Site preparation 1 1 1 2 0 1 0 1 0 0 0 0 0 0 2
8 2-Execution Blinding as per EIS (above to 12" Nom Bore) If any HRSB 0 0 0 0 0 0 0 0 0 0 0 0
9 2-Execution Blinding as per EIS (above to 4" Nom Bore) If any HRSB 2 1 0 0 0 0 0 0 0 0 0 0 0 0
10 2-Execution Blinding as per EIS (up to 4" Nom Bore) If any HRSB 1 1 0 0 0 0 0 0 0 0 0 0 0 0
11 2-Execution Inspection by PPTSB reps INSP PPTSB 1.00 0.5 1 0.5 0 0 0 0 0.5 0 0 0 0 0 0.5
12 2-Execution
Unbolt bolt and nuts 32mm x 24pcs A193G R.B7/A194GR.2H HRSB 2.00 0.33 1 1 0.666667 0 0.3333 0 0.3333 0 0 0 0 0 0 0.666667
13 2-Execution Apply molykote on bolts and nuts (32MM) X 24 PCS 1 0 0 0 0 0 0 0 0 0 0 0 0
14 2-Execution Tightening new bolts and nuts HRSB 2.00 0.33 1 1 0.666667 0 0.3333 0 0.3333 0 0 0 0 0 0 0.666667
15 2-Execution Inspection by PPTSB reps INSP PPTSB 1.00 0.5 1 0.5 0 0 0 0 0.5 0 0 0 0 0 0.5
16 2-Execution Deblinding as per EIS (above to 12" Nom Bore) If any HRSB 0 0 0 0 0 0 0 0 0 0 0 0
17 2-Execution Deblinding as per EIS (above to 4" Nom Bore) If any HRSB 2 1 0 0 0 0 0 0 0 0 0 0 0 0
18 2-Execution Deblinding as per EIS (up to 4" Nom Bore) If any HRSB 1 1 0 0 0 0 0 0 0 0 0 0 0 0
19 2-Execution Housekeeping HRSB 1 1 1 0 0 0 1 0 0 0 0 0 0 1
0 0 0 0 0 0 0 0 0 0 0 0
3-Post Execution C) Post execution HRSB 0 0 0 0 0 0 0 0 0 0 0 0
20 3-Post Execution Re instate Insulation 0 0 0 0 0 0 0 0 0 0 0 0
21 3-Post Execution Dismantle External Scaffolding 0 0 0 0 0 0 0 0 0 0 0 0
22 3-Post Execution Demobilization 0 0 0 0 0 0 0 0 0 0 0 0
3.6666667 5.333333 0 1.6667 0 2.6667 1 0 0 0 0 0 5.333333
39 IWL/BT3/FY2018/587 3"-SOP-292215-1105D-NI BOLTS AND NUTS REPLACEMENT
1 1-Pre Execution a) Site Preparation HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2 1-Pre Execution Mobilization manpower, equipment, tools & consumable HRSB 0 0 0 0 0 0 0 0 0 0 0 0
3 1-Pre Execution Apply protection on others PPTSB assets equipment/cable/tag number and etc. HRSB 0 0 0 0 0 0 0 0 0 0 0 0
4 1-Pre Execution Shelter/Laydown erection HRSB 0 0 0 0 0 0 0 0 0 0 0 0
5 1-Pre Execution Scaffolding erection HRSB 0 0 0 0 0 0 0 0 0 0 0 0
6 1-Pre Execution Remove Insulation HRSB 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
2-Execution b) During Project Activity HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution 1.0 Replace bolt and nuts HRSB 0 0 0 0 0 0 0 0 0 0 0 0
7 2-Execution Site preparation 1 1 1 2 0 1 0 1 0 0 0 0 0 0 2
8 2-Execution Blinding as per EIS (above to 12" Nom Bore) If any HRSB 0 0 0 0 0 0 0 0 0 0 0 0
9 2-Execution Blinding as per EIS (above to 4" Nom Bore) If any HRSB 2 1 0 0 0 0 0 0 0 0 0 0 0 0
10 2-Execution Blinding as per EIS (up to 4" Nom Bore) If any HRSB 1 1 0 0 0 0 0 0 0 0 0 0 0 0
11 2-Execution Inspection by PPTSB reps INSP PPTSB 1.00 0.5 1 0.5 0 0 0 0 0.5 0 0 0 0 0 0.5
12 2-Execution
Unbolt bolt and nuts 32mm x 48pcs A193G R.B7/A194GR.2H HRSB 2.00 0.67 1 1 1.333333 0 0.6667 0 0.6667 0 0 0 0 0 0 1.333333
13 2-Execution Apply molykote on bolts and nuts S.BOLT/HEX.NUT. #150 1 0 0 0 0 0 0 0 0 0 0 0 0
14 2-Execution Tightening new bolts and nuts HRSB 2.00 0.33 1 1 0.666667 0 0.3333 0 0.3333 0 0 0 0 0 0 0.666667
15 2-Execution Inspection by PPTSB reps INSP PPTSB 1.00 0.5 1 0.5 0 0 0 0 0.5 0 0 0 0 0 0.5
16 2-Execution Deblinding as per EIS (above to 12" Nom Bore) If any HRSB 0 0 0 0 0 0 0 0 0 0 0 0
17 2-Execution Deblinding as per EIS (above to 4" Nom Bore) If any HRSB 2 1 0 0 0 0 0 0 0 0 0 0 0 0
18 2-Execution Deblinding as per EIS (up to 4" Nom Bore) If any HRSB 1 1 0 0 0 0 0 0 0 0 0 0 0 0
19 2-Execution Housekeeping HRSB 1 1 1 0 0 0 1 0 0 0 0 0 0 1
0 0 0 0 0 0 0 0 0 0 0 0
3-Post Execution C) Post execution HRSB 0 0 0 0 0 0 0 0 0 0 0 0
20 3-Post Execution Re instate Insulation 0 0 0 0 0 0 0 0 0 0 0 0
21 3-Post Execution Dismantle External Scaffolding 0 0 0 0 0 0 0 0 0 0 0 0
22 3-Post Execution Demobilization 0 0 0 0 0 0 0 0 0 0 0 0
4 6 0 2 0 3 1 0 0 0 0 0 6
40 IWR/BT3/FY2018/690 1"-PL-291043-1101A-NI PAINTING
1 1-Pre Execution a) Site Preparation HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2 1-Pre Execution Mobilization manpower, equipment, tools & consumable HRSB 0 0 0 0 0 0 0 0 0 0 0 0
3 1-Pre Execution Apply protection on others PPTSB assets equipment/cable/tag number and etc. HRSB 0 0 0 0 0 0 0 0 0 0 0 0
4 1-Pre Execution Shelter/Laydown erection 0 0 0 0 0 0 0 0 0 0 0 0
5 1-Pre Execution Scaffolding erection HRSB 0 0 0 0 0 0 0 0 0 0 0 0
6 1-Pre Execution Remove Insulation HRSB 0 0 0 0 0 0 0 0 0 0 0 0
HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution b) During Project Activity HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2-Execution 1.0 Painting pipe HRSB 0 0 0 0 0 0 0 0 0 0 0 0
7 2-Execution Site preparation 1 1 1 2 0 1 0 1 0 0 0 0 0 0 2
8 2-Execution Surface preparation (Power tool) 0.70 1.3963102 1 1 1 4.18893 0 1.3963 0 1.3963 0 0 1.3963 0 0 0 4.18893
9 2-Execution Inspection surface preparation by AIMD INSP 0.70 1 0 0 0 0 0 0 0 0 0 0 0 0
10 2-Execution Painting 1st coat 0.70 1.05 1 1 2.094465 0 0 0 1.0472 0 0 0 0 1.0472 0 2.094465
11 2-Execution Overcoating interval HRSB 0.70 8 0 0 0 0 0 0 0 0 0 0 0 0
12 2-Execution 1st coat inspection by AIMD INSP 0.70 1 0 0 0 0 0 0 0 0 0 0 0 0
13 2-Execution Painting 2nd coat HRSB 0.70 0.70 1 1 1.39631 0 0 0 0.6982 0 0 0 0 0.6982 0 1.39631
14 2-Execution Overcoating interval 0.70 4 0 0 0 0 0 0 0 0 0 0 0 0
15 2-Execution 2nd coat inspection by AIMD INSP 0.70 1 0 0 0 0 0 0 0 0 0 0 0 0
16 2-Execution Painting final coat HRSB 0.70 0.70 1 1 1.39631 0 0 0 0.6982 0 0 0 0 0.6982 0 1.39631
17 2-Execution Overcoating interval HRSB 0.70 4 0 0 0 0 0 0 0 0 0 0 0 0
18 2-Execution Final coat inspection by AIMD INSP 0.70 1 0 0 0 0 0 0 0 0 0 0 0 0
STRUCTURE
Open
REMAKS
Open
REMAKS
Open
REMAKS
Open
REMAKS
Open
REMAKS
Open
REMAKS
Open
REMAKS
Open
REMAKS
Open
REMAKS
Open
REMAKS
Open
REMAKS
Open
REMAKS
Open
REMAKS
Open
REMAKS
Open
REMAKS
Open
REMAKS
Open
REMAKS
Open
REMAKS
Open
REMAKS
Open
REMAKS
Open
REMAKS
Open
REMAKS
Open
REMAKS
Open
REMAKS
Open
REMAKS
Open
REMAKS
Open
REMAKS
Open
REMAKS
Open
REMAKS
Open
REMAKS
Open
REMAKS
Open
REMAKS
Open
REMAKS
Open
REMAKS
Open
EIS (above to 12" Nom Bore) DURATION HRS
BLIND NO SIZE RATING BLINDING DE.BLIND FIL HLP
0.00 0.00 2 1
0.00 0.00 2 1
TOTAL 0.0 0.0
DURATION HRS
qty
piping
cutting/
weld type SIZE sch fit up weld
bevel
SW 3/4 80 0.4 0.20 0.6 1
SW 3/4 80 0.4 0.20 0.6 1
duration
QTY xtvt vol.m2 TOTAL SS FW
(hrs)
DURATION
Site pre 0.68 1 1
Surface prep 0.68 2 1.36323525 1 1
SP Insp. 0.68 1 0.681617625
1st coat 0.68 1.5 1.0224264375 1
curing 0.68 8 5.452941
1st coat Insp 0.68 1 0.681617625
2nd coat 0.68 1 0.681617625 1
curing 0.68 4 2.7264705
2nd coat Insp 0.68 1 0.681617625
Final coat 0.68 1 0.681617625 1
curing 0.68 4 2.7264705
Final coat Insp 0.68 1 0.681617625
TOTAL 0.00 0.00
CLEANING FORMULA
ID H π D
SHELL 4.88 28.4 3.142 4.88
SHELL 3 20.315 4.142 3
ELLIP TOP 3 1 1.084 3
ELLIP BOTTOM 4.88 1 1.084 4.88
D
ELLIP SHELL bottom 4.942 1 1.084
1.084 0
CLEANING LGHT ID π TOTAL QTY PLATE
PERIMETER
CLEANING FORMULA
ID H π D
TRAY 4.942 3.142 4.942
TRAY 3 3.142 3
D
1.084 0
1.084 0
NDT
NO TYPE QTY DURATION TOTAL DUR
1 BORO 0.083 0.0
2 IRIS 0.367 0.0
3 RFET 0.083 0.0
TOTAL (HR) 0.53 0.0
INT.SCAFFOLDING DURATION
L W H M3 ERECT DISMANTLE
5 5 4 100 25 25 bottom
5 5 2.5 63 16 16 tray 35#
0 0 0
TOTAL 163 41 41
RIG
0.00
TOTAL 0.0
HRS FOR
WELD
ONLY
RIG
RIG
1
1
TOUCH UP
1 Site pre
1 Surface prep
1 SP Insp.
1 1st coat
curing
1 1st coat Insp
1 2nd coat
curing
1 2nd coat Insp
1 Final coat
curing
1 Final coat Insp
RIG
ORMULA DURATION
AREA M2
H WIRE BRUSH COTTON RAG POWER BRUSH
28.4 435.46 217.73 145.15 72.58
20.32 252.43 126.22 84.14 42.07
1 3.25 1.63 1.08 0.54
1 5.29 2.64 1.76 0.88
D
0.00 0.00 0.00 0.00
0 0.00 0.00 0.00 0.00
TOTAL 696.43 348.22 232.14 73.46
DURATION
TOTAL
WELMENT TOTAL
QTY PLATE WELDMENT POWER BRUSH
TOP ELLIP VESSEL
& LENGTH
BOTTOM
ELLIP
15.53 23.67 582.29 97.0
12.43 16.93 340.39 56.7
9.43 0.83 61.27 10.2
15.53 0.83 100.93 16.8
0.00 0.00 0.00 0.0
TOTAL 271.22 45.2 25% TOTAL WELDMENT
ORMULA DURATION
AREA M2
H WIRE BRUSH COTTON RAG POWER BRUSH
0 124.22 62.11 41.41 20.70
0 61.27 30.63 20.42 10.21
D
0 0.00 0.00 0.00 0.00
0 0.00 0.00 0.00 0.00
TOTAL 185.49 92.75 61.83 30.92
0.00 1 1
0.0
DURATION HRS
Total
duration
vol.m2 duration
(hrs)
(hrs)
1 1
0.06 2 0.12
0.06 1 0.06
0.06 1.5 0.09
0.06 8 0.48
0.06 1 0.06
0.06 1 0.06
0.06 4 0.24
0.06 1 0.06
0.06 1 0.06
0.06 4 0.24
0.06 1 0.06
TOTAL 0.33
flushing
TOTAL WELDMENT
4 4 1
2 2 1
PCOGD SDN BHD TURNAROUND 2019
NO WORK ID LINE NO JOINT SIZE SCH WELD TYPE FW/SW F/U V/I DPI RT RT 1 HT PAINTING REMARKS
IWR/BT2/2016/Dec/148 3/4"-AP-224318-1108B-NI
1 3/4"-AP-224318-1108B-NI 1 0.75 80 SW FW 3/4 @ 0.75
3/4"-AP-224318-1108B-NI 2 0.75 80 SW FW 3/4 @ 0.75
3/4"-AP-224318-1108B-NI 3 0.75 80 BW SW 3/4 @ 0.75
3/4"-AP-224318-1108B-NI 4 0.75 80 BW SW 3/4 @ 0.75
3/4"-AP-224318-1108B-NI 5 0.75 80 SW SW 3/4 @ 0.75
3/4"-AP-224318-1108B-NI 6 0.75 80 SW SW 3/4 @ 0.75
Fit-up Joint Dia inch Fit-up Joint Dia inch DPI Done RT Done Ht Done PAINTING
Welded Weld Done
0 0 0 0 0 0 0 0
WORK REQUERST
TOTAL TOTAL DIA
SHOP FIELD SHOP FIELD JOINT INCH (Overall)
(Overall)
SW BW SW BW TH TH
JOINT 2 2 2 0 0 0 6
DIA INCH 1.50 1.5 1.5 0 0 0 4.50
TOTAL JT 4 TOTAL JT 2
TOTAL Ø
TOTAL Ø INCH 3 INCH 1.5 RT (total) RT (SHOP) RT (FIELD)
JOINT SW TOTAL JOINT SHOP/FIELD 6 2 2 0
AND BW DIA INCH JOINT SHOP/FIELD 4.5
#DIV/0!
MTO
Sch/
Item Qty Unit Size Description Rate (RM)
Rating
1 PIPE
2 6.5 m 3/4'' sch80 API5LGr.B SMLS PE SCH80
3
4
5 ELBOW 90
6 1 ea 3/4'' sch80 A234 GR.WPB SMLS BW
7
8
9 COUPLING
10 2 ea 3/4'' A234 WPB SW
11
12
13
14
15
16
17
18
19
20
21
Total (RM)