Professional Documents
Culture Documents
1.0d Mobilization of Equipment and tools (upon submission of list of Equipment at Site,
certified by Company)
$246,881.65
A2.1b - Water Injection Flowlines U/G piping 8"÷12" connection / distributor headers (NEW) 32.6 km WI
WI-PLI-001 PRICE/BREAKDOWN SCHEDULE buried FLOW
LINE OPT SoW
1.0 ENGINEERING
$ 7,742,359.82
DSI-5000008451 CALL OFF 03 CALL OFF 03
A1.1 - Water Injection Wellhead area hook up - WI-WEL-002 - 10" pipe
11 OPT. SoW WI 11 OPT. SoW WI
PRICE BREAKDOWN SCHEDULE -LUMP SUM PRICE (LS) WELL HEAD WELL HEAD
1.0 ENGINEERING
3.0a.07 Earthing/Grounding
3.0a.07.01 Earthing System. Installation and Connection of earth electrodes, earthing groundbeds, $12,993.17
system earthing, including bonding of all electrical equipment, skids and structure
3.0c.01 Laying LV Electrical cable from end of flowline to LER (in cable trench 3.0a.02)
3.0c.02 Laying FOC from end of flowstation to LER (in cable trench 3.0a.02)
3.0c.03 Laying LV cable from LER to WHCP (in cable trench 3.0a.03)
3.0c.04 Laying LV cable from LER to Field Instruments PT and TT, Ultrasonic Flowmeter and remote
Junction box (in cable trench 3.0a.03)
3.0c.05 Laying I/O cables from Field Instruments PT, TT, Ultrasonic flowmeter and remote Junction
box to LER (in cable trench 3.0a.03)
3.0c.06 Laying I/O cables from WHCP to LER (in cable trench 3.0a.03)
4.0c.02 Pre commissioning for Field Instruments (PT, TT, FM, FOC etc..)- Megger test and OTDR
4.0c.03 Electrical Pre commissioning for LER and its equipments (HVAC, F&G, LV Switchgears, UPS and
batteries)
4.0c.04 Electrical Pre commissioning for external equipment installed by Contractor or by Other and
fed by LER (WHCP)
4.0c.05 Cathodic Protection pre-commissioning $2,121.33
4.0d COMMISSIONING & START-UP
4.0d.01 Mechanical $26,516.67
4.0d.02 LER
23 Crossing
A2.2 - Main Crossings - WI-CRS-002 Open Cut Open Cut OPT
PRICE/BREAKDOWN SCHEDULE SoW
1.0 ENGINEERING
1.0 ENGINEERING
3.0a.07 Earthing/Grounding
3.0a.07.01 Earthing System. Installation and Connection of earth electrodes, earthing groundbeds, $ 11,127.07
system earthing, including bonding of all electrical equipment, skids and structure
3.0c.01 Laying LV Electrical cable from end of flowline to LER (in cable trench 3.0a.02)
3.0c.02 Laying FOC from end of flowstation to LER (in cable trench 3.0a.02)
3.0c.03 Laying LV cable from LER to WHCP (in cable trench 3.0a.03)
3.0c.04 Laying LV cable from LER to Field Instruments PT and TT, Ultrasonic Flowmeter and remote
Junction box (in cable trench 3.0a.03)
3.0c.05 Laying I/O cables from Field Instruments PT, TT, Ultrasonic flowmeter and remote Junction
box to LER (in cable trench 3.0a.03)
3.0c.06 Laying I/O cables from WHCP to LER (in cable trench 3.0a.03)
4.0c.02 Pre commissioning for Field Instruments (PT, TT, FM, FOC etc..)- Megger test and OTDR
4.0c.03 Electrical Pre commissioning for LER and its equipments (HVAC, F&G, LV Switchgears, UPS and
batteries)
4.0c.04 Electrical Pre commissioning for external equipment installed by Contractor or by Other and
fed by LER (WHCP)
4.0c.05 Cathodic Protection pre-commissioning $ 1,816.66
4.0d COMMISSIONING & START-UP
4.0d.01 Mechanical $ 22,708.30
4.0d.02 LER