You are on page 1of 1

Proiect : PROPOSED ANTIPOLO RESORT PROJECT ( 834 SQM LOT)

Owner :
Subject : COST PROPOSAL (Phase 2)

UNIT COST
ITEM DESCRIPTION UNIT QUANTITY
UNIT AMOUNT
1.0 GENERAL REQUIREMENTS
1.1 Preliminaries
1.11 Mobilization and Demobilization lot 1.00 15,000.00 15,000.00
1.12 TemFacil/Utilities/Barracks/Storages area/6 mo staff huouse rental lot 1.00 -
1.13 Power consumption and others (For welding, equipments and lighting) lot 1.00 By Owner
1.14 Pocurement and transport/delivery of materials lot 1.00 8,000.00 8,000.00
1.2 As Built Plan lot 1.00 -
1.3 Plans and Permit lot 1.00 -
1.4 Bonds and Insurances lot 1.00 -
1.5 Haulling and disposal lot 1.00 12,000.00 12,000.00
SUB-TOTAL: 1.0 35,000.00
2.0 GENERAL SITE WORKS
2.1 Clearing works lot 1.00 10,000.00 10,000.00
2.11 Haulling out of debris Included Included
2.2 Hauling of soil cu.m 12.00 300.00 3,600.00
2.3 Maintenance lot 1.00 25,000.00 25,000.00
SUB-TOTAL: 2.0 38,600.00
3.0 SOFTSCAPE & HARDSCAPE
3.1 Complete Supply and Labor of Landscape Works
3.11 Cutting of Existing Plants, trees & shrubs lot 1.00 12,500.00
3.12 Softscape (Trees, Plants & Shrubs) lot 1.00 450,000.00
Sub-total: 3.12
SUB-TOTAL: 3.0 462,500.00
GRAND TOTAL 536,100.00

Page 1

You might also like