We are pleased to submit our quotation for supply of materials and labor the following scope of works:
I PRELIMINARY WORKS
Mobilization & Demobilization 1 l.s. 12,000.00
Water and Electricity Consumption (Owner's Expense) months C/O OWNER
Permits and Licenses (Owner's Expense) 1 l.s. -
Preparation of As-built drawings 1 l.s.
Insurance/Bond (Owner's Expense) 1 lot -
Tool Box 1 lot 3,500.00
Sub Total I 15,500.00
II SITE WORKS
Board up 1 l.s. -
Protection works - Bluesack 1 l.s. C/O OWNER
Scaffoldings 1 l.s. -
Stripping of Existing Walls, Ceiling and Floor Finish (If Any) sq.m. 10,000.00
Sub Total II 10,000.00
IV FINISHING WORKS
Painting Works
Ceiling 1 lot 34,800.00
Wall Painting (Selling Area) 1 lot 60,000.00
Sub Total IV 94,800.00
VI ELECTRICAL WORKS
Electrical rough-ins & lightning fixtures 1 lot PHP 65,880.00
Sub Total VI 65,880.00