Professional Documents
Culture Documents
SUB-CONTRACT No. :
SUB-CONTRACTOR : MAGNETRON CONSTRUCTION AND DEVELOPMENT CORPORATION
Grand Summary
Contract Amount
(PHP)
1 WP-06
1.1 OFFICE BUILDING 151,200,000.00
1.2 RESIDENTIAL BUILDING-1 193,536,000.00
1.3 RESIDENTIAL BUILDING-2 193,536,000.00
1.4 RESIDENTIAL BUILDING-3 193,536,000.00
Page 1 of 161
STA-ANA CAGAYAN MIXED DEVELOMENT PROJECT
SUB-CONTRACT No. :
SUB-CONTRACTOR : MAGNETRON CONSTRUCTION AND DEVELOPMENT CORPORATION
Grand Summary
Contract Amount
(PHP)
Name : Name :
Page 2 of 161
Workdone
(PHP)
174,042,201.53
38,800,555.84
48,035,344.90
45,699,481.48
41,506,819.31
174,042,201.53
Prepared By :_________________________
Page 3 of 161
Workdone
(PHP)
174,042,201.53
Page 4 of 161
STA-ANA CAGAYAN MIXED DEVELOMENT PROJECT
CONSTRUCTION AND COMPLETION OF ONE UNIT FOUR STOREY OFFICE BUILDING
OFFICE BUILDINGS
GENERAL REQUIREMENTS
1.1 Mobilization/Demobilization LOT 1.00 500,000.00
1.2 Temporary Facilities and Utilities
1.2.1 Temporary Barracks LOT 1.00 250,000.00
1.2.2 Temporary Warehouse LOT 1.00 200,000.00
1.2.3 Temporary Office LOT 1.00 150,000.00
1.3 Engineers & Staff incl. Safety Officer and Aide LOT 1.00 1,000,000.00
1.4 Quality Control & Testings
1.4.1 Material Testing LOT 1.00 350,000.00
1.4.2 Surveying & Inspection Services LOT 1.00 150,000.00
1.4.3 Concrete & Rebar Testing LOT 1 150,000.00
1.5 Temporary Utilities
1.5.1 Electricity LOT 1.00 1,500,000.00
1.5.2 Water LOT 1.00 500,000.00
1.5.3 Communication LOT 1.00 70,000.00
1.6 Construction Equipment
1.6.1 Crane LOT 1.00 1,500,000.00
1.6.2 Passenger & Material Hoist LOT 1.00
1.6.3 Support Equipment (Trucks/Payloaders/etc.) LOT 1.00 2,500,000.00
1.7 Security & Safety Measures LOT 1.00 300,000.00
1.7.1 Security Guards LOT 1.00 350,000.00
1.7.2 First Aids/Medicines LOT 1.00
1.7.3 Safety Signages LOT 1.00 25,000.00
1.7.4 Security Lightings LOT 1.00 150,000.00
1.7.5 Safety Canopy
1.7.6 *Safety Railings
1.7.8 *Safety Net
1.8 Housekeeping
Page 5 of 161
STA-ANA CAGAYAN MIXED DEVELOMENT PROJECT
CONSTRUCTION AND COMPLETION OF ONE UNIT FOUR STOREY OFFICE BUILDING
OFFICE BUILDINGS
1.8.1 *Housekeeping LOT 1.00 250,000.00
1.8.2 *Disposal of Debris and Waste LOT 1.00 650,000.00
1.9 Bonds & Insurances
1.9.1 Contractor All Risk Insurance (CARI) LOT 1.00 500,000.00
1.9.2 Surety Bond (20%) LOT 1.00 250,000.00
1.9.3 Performance Bond (25%) LOT 1.00 250,000.00
1.9.4 Guarantee Bond (10%) LOT 1.00 250,000.00
1.9.5 Group Personal Accident Insurance (GPAI) LOT 1.00 300,000.00
1.10 Permits
1.10.1 Building Permit (Gen Con Legwork Only, Fees by Owner) LOT 1.00 500,000.00
1.10.2 Occupancy Permit LOT 1.00 250,000.00
1.10.3 DOLE Permits LOT 1.00 50,000.00
1.10.4 ECC
1.11 Combined Services Drawing (CSD) LOT 1.00 2,000,000.00
1.12 As-Built Plans LOT 1.00 50,000.00
2 STRUCTURAL WORKS
2.1 CIVIL WORKS
2.1.1 EXCAVATION
2.1.2 Column Footing cu.m. 760.00 500.00 500.00
2.1.3 Footing Tie Beam cu.m. 3,859.90 500.00 500.00
2.1.4 BACKFILLING AND COMPACTION
2.1.4.1 Column Footing cu.m. 720.00 500.00 500.00
2.1.4.2 Footing Tie Beam cu.m. 3,780.00 500.00 500.00
2.1.5 GRAVEL BEDDING
2.1.5.1 Column Footing cu.m. 30.00 1,000.00 500.00 1,500.00
2.1.5.2 Footing Tie Beam cu.m. 17.55 1,000.00 1,000.00 2,000.00
2.1.5.3 Slab on Fill cu.m. 173.22 1,000.00 500.00 1,500.00
2.1.6 SOIL POISOINING
2.1.6.1 Slab-On-Fill sq.m. 6,048.00 120.00 50.00 170.00
Page 6 of 161
STA-ANA CAGAYAN MIXED DEVELOMENT PROJECT
CONSTRUCTION AND COMPLETION OF ONE UNIT FOUR STOREY OFFICE BUILDING
OFFICE BUILDINGS
2.1.7 MOISTURE AND VAPOR BARRIER
2.1.7.1 Slab-On-Fill sq.m. 6,048.00 80.00 50.00 130.00
2.1.7.2 Layout/board skating lot 1.00 150,000.00 150,000.00
2.1.7.3 Grading and Leveling lot 1.00 250,000.00 250,000.00
2.1.8 Damp proofing sq.m. 1,500.00 100.00 100.00
2.1.9 Dewatering lot 1.00 300,000.00 300,000.00
2.4 Formworks
2.4.1 Column Footing sq.m. 171.25 1,150.00 460.00 1,610.00
2.4.2 Footing Tie Beam sq.m. 469.32 1,150.00 460.00 1,610.00
2.4.3 Pedestal Column sq.m. 356.27 1,150.00 460.00 1,610.00
2.4.4 Stairs sq.m. 195.96 1,150.00 460.00 1,610.00
Page 7 of 161
STA-ANA CAGAYAN MIXED DEVELOMENT PROJECT
CONSTRUCTION AND COMPLETION OF ONE UNIT FOUR STOREY OFFICE BUILDING
OFFICE BUILDINGS
2.5.5 12mm Anchor Bolts pcs 600.00 850.00 340.00 1,190.00
2.5.6 25mm thk Ear Plate kgs 7,197.12 65.00 26.00 91.00
2.5.7 Gusset plates, bolts and consumables lot 1.00 5,000,000.00 169,262.00 5,169,262.00
3 ARCHITECTURAL WORKS
3.1 FLOOR FINISHES
3.1.1 600X600 Homogenous Tiles, Polished (FF-1) sq.m. 6,237.84 1325 250 1,575.00
3.1.2 300x300 Ceramic Floor Tiles for Toilets (FF-2) sq.m. 295.68 1100 250 1,350.00
3.1.3 300x300 Non-skid Tiles for stair landings (FF-3) sq.m. 185.60 1300 250 1,550.00
3.1.4 300x300 Non-skid Tiles for stairs (FF-4) sq.m. 256.48 1300 250 1,550.00
3.1.5 600X600 Homogenous Tiles, Non-skid (FF-5) sq.m. 56.80 1325 250 1,575.00
3.1.6 Floor Topping sq.m 6,000.00 200 200 400.00
Page 8 of 161
STA-ANA CAGAYAN MIXED DEVELOMENT PROJECT
CONSTRUCTION AND COMPLETION OF ONE UNIT FOUR STOREY OFFICE BUILDING
OFFICE BUILDINGS
3.3.1 Semi-Gloss Latex Painted for SRC Wall sq.m. 3,020.00 320.00 130.00 450.00
3.3.2 Column Cladding / Cover sq.m. 1,000.00 650.00 260.00 910.00
3.3.3 Semi-Gloss Latex Painted for Dry Wall sq.m. 108.86 350.00 150.00 500.00
3.3.4 200x300 Ceramic Tile Finish sq.m. 71.71 1,100.00 250.00 1,350.00
3.3.5 50x50mm Tubular Metal Painted Finish sq.m. 424.80 4,500.00 1,800.00 6,300.00
3.3.6 Equipments and stair railings m 250.00 3,500.00 500.00 4,000.00
Page 9 of 161
STA-ANA CAGAYAN MIXED DEVELOMENT PROJECT
CONSTRUCTION AND COMPLETION OF ONE UNIT FOUR STOREY OFFICE BUILDING
OFFICE BUILDINGS
3.6 CANOPY
3.6.1 125mm thk Metal Deck with concrete topping . sq.m. 56.50 800.00 320.00 1,120.00
3.6.2 Concreting cu.m. 3.11 5,550.00 1,550.00 7,100.00
3.6.3 Rebars kgs 467.82 43.00 17.20 60.20
3.7 WATERPROOFING
3.7.1 Toilets sq.m. 295.68 700.00 200.00 900.00
3.7.2 External Walls sq.m 3,000.00 800.00 200.00 1,000.00
3.7.3 Canopy sq.m. 56.50 700.00 200.00 900.00
4 ELECTRICAL WORKS
4.1 CIVIL WORKS
4.1.1 Excavation Work for Duct Bank lot 1 10000 20000 30,000.00
4.1.2 Concrete Pedestal lot 1 70000 25000 95,000.00
4.1.3 Concrete Encasement lm 18 5000 2000 7,000.00
Page 10 of 161
STA-ANA CAGAYAN MIXED DEVELOMENT PROJECT
CONSTRUCTION AND COMPLETION OF ONE UNIT FOUR STOREY OFFICE BUILDING
OFFICE BUILDINGS
4.2.7 Wire 125mm² THHN lm 1338 802 280 1,082.00
4.2.8 Wire 30mm² THHN lm 350 180 72 252.00
4.2.9 Wire 22mm² THHN lm 350 123 49 172.00
4.2.10 Wire 8.0mm² THHN lm 120 50 20 70.00
4.2.11 Fire Rated Cable 200mm² lm 250 1725 517 2,242.00
4.2.12 Fire Rated Cable 30mm² lm 65 322 96 418.00
4.2.13 Fiitings/Pullnbox lot 1 15000 6000 21,000.00
Page 11 of 161
STA-ANA CAGAYAN MIXED DEVELOMENT PROJECT
CONSTRUCTION AND COMPLETION OF ONE UNIT FOUR STOREY OFFICE BUILDING
OFFICE BUILDINGS
4.6.1 LVSG assy 1 820000 30000 850,000.00
Main: 2000AT,3P,400V,65 KAIC
Brch: 6- 100AT,3P,400V
Page 12 of 161
STA-ANA CAGAYAN MIXED DEVELOMENT PROJECT
CONSTRUCTION AND COMPLETION OF ONE UNIT FOUR STOREY OFFICE BUILDING
OFFICE BUILDINGS
Brch: 6- 20AT,1P,230V
4.6.9 Panel LP2 assy 1 28000 4000 32,000.00
Main: 30AT,3P,400V
Brch: 6- 20AT,1P,230V
4.6.10 Panel LP3 assy 1 28000 4000 32,000.00
Main: 30AT,3P,400V
Brch: 6- 20AT,1P,230V
4.6.11 Panel LP4 assy 1 28000 4000 32,000.00
Main: 30AT,3P,400V
Brch: 6- 20AT,1P,230V
4.6.12 METER CENTER assy 1 290000 10000 300,000.00
4.6.13 NEMA3R,700AT,3P,400V assy 1 65000 4000 69,000.00
4.6.14 NEMA3R,250AT,3P,400V assy 4 35000 4000 39,000.00
CCTV Camera
4.9 Conduit,wIres, fittings & supports
4.9.1 75mmø PVC Pipe pcs 4 550.00 220.00 770.00
4.9.2 Pullbox 200mmX400mmX400mm pcs 3 1,200.00 500.00 1,700.00
4.9.3 20mmø PVC Pipe pcs 480 80.00 32.00 112.00
4.9.4 20mmø PVC Adapter with locknut prs 120 15.00 5.00 20.00
4.9.5 Junction box ga.#16 pcs 40 50.00 20.00 70.00
4.9.6 Square box, ga.#16 pcs 5 85.00 34.00 119.00
Page 13 of 161
STA-ANA CAGAYAN MIXED DEVELOMENT PROJECT
CONSTRUCTION AND COMPLETION OF ONE UNIT FOUR STOREY OFFICE BUILDING
OFFICE BUILDINGS
4.9.7 15mmø FMC lm 45 24.00 9.00 33.00
4.9.8 15mmø FMC Connector pcs 45 20.00 8.00 28.00
4.9.9 UTP CAT5 boxes 5 5,800.00 2,300.00 8,100.00
Page 14 of 161
STA-ANA CAGAYAN MIXED DEVELOMENT PROJECT
CONSTRUCTION AND COMPLETION OF ONE UNIT FOUR STOREY OFFICE BUILDING
OFFICE BUILDINGS
Supply and installation of the following pipes:
Page 15 of 161
STA-ANA CAGAYAN MIXED DEVELOMENT PROJECT
CONSTRUCTION AND COMPLETION OF ONE UNIT FOUR STOREY OFFICE BUILDING
OFFICE BUILDINGS
5.1.22 Pressure Gauge pc/s 5.00 550.00 100.00 650.00
5.1.23 Hose bibb 15mm pc/s 1.00 880.00 100.00 980.00
5.1.24 Hangers, Support and Braces lot 1.00 258,712.00 103,484.80 362,196.80
5.1.25 Testing Works lot 1.00 50,000.00 50,000.00
Page 16 of 161
STA-ANA CAGAYAN MIXED DEVELOMENT PROJECT
CONSTRUCTION AND COMPLETION OF ONE UNIT FOUR STOREY OFFICE BUILDING
OFFICE BUILDINGS
Polyvinyl chloride (PVC) pipes, Series 1000, conforming to
ASTM D2729, including fittings, elbows, tees, reducers,
hangers & support, sleeves, painting and all other
necessary accessories to complete the system.
5.3.1 200 mm diameter (8") m 36.00 1,320.00 528.00 1,848.00
5.3.2 150 mm diameter (6") m 24.00 896.00 358.40 1,254.40
5.3.3 100 mm diameter (4") m 678.00 472.00 188.80 660.80
5.3.4 50 mm diameter (2") m 140.00 56.00 196.00
other pipe sizes (specify below)
5.3.5 PVC Fittings lot 1.00 289,500.00 115,800.00 405,300.00
Polyvinyl chloride (PVC) pipes, Blue, Class 150, including
fittings, elbows, tees, reducers, hangers & support,
sleeves, painting and all other necessary accessories to
complete the system.
5.3.6 25 mm diameter (3/4") m 0.00 85.00 34.00 119.00
other pipe sizes (specify below)
5.3.7 PVC Fittings lot 0.00 2,935.00 1,174.00 4,109.00
Supply and installation of Drains & Accessories
Floor Drain
5.3.8 50 mm diameter (2") pc/s 48.00 1,350.00 200.00 1,550.00
Shower Drain
5.3.9 50 mm diameter (2") pc/s 1,350.00 200.00 1,550.00
Floor cleanout
5.3.10 100 mm diameter (4") pc/s 3,630.00 200.00 3,830.00
Roof Drain/Deck Drain
5.3.11 100 mm diameter (4") pc/s 26.00 3,950.00 200.00 4,150.00
Trench Grating Cover
5.3.12 1000mm x 300mm pc/s 3,250.00 200.00 3,450.00
Catch Basin
5.3.13 500mm x 500mm pc/s 22.00 23,600.00 1,200.00 24,800.00
5.3.14 Hangers, Support and Braces lot 1.00 136,700.00 54,680.00 191,380.00
5.3.15 Testing Works lot 1.00 50,000.00 50,000.00
Page 17 of 161
STA-ANA CAGAYAN MIXED DEVELOMENT PROJECT
CONSTRUCTION AND COMPLETION OF ONE UNIT FOUR STOREY OFFICE BUILDING
OFFICE BUILDINGS
5.4 PLUMBING FIXTURES
Installation of plumbing fixtures including accessories,
supports and other miscellaneous items necessary to
complete the system.
Supply and Installation of the following: POZZI Brand
5.4.1 Water closet (tank type) complete with cistern, seat, set 36.00 16,000.00 750.00 16,750.00
cover, all necessary fittings and accessories
5.4.2 lavatories; complete with faucet, all set 16.00 12,000.00 750.00 12,750.00
necessary fittings and accessories
5.4.3 Shower sets; complete with mixing valves, shower set 15,000.00 750.00 15,750.00
head, faucet, all necessary fittings and accessories
Urinal set 20.00 16,020.00 980.00 17,000.00
5.4.4 Lavatory counter lot 4.00 75,000.00 25,000.00 100,000.00
Urinal partitions pc/s 12.00 10,000.00 2,000.00 12,000.00
Phenolic enclosures with door pc/s 32.00 22,000.00 2,500.00 24,500.00
5.5 EQUIPMENT
Supply and installation of the following equipment:
Elevated water tank, w/ 5,000 liters Capacity
as shown on details and plans:Stainless Steel
5.5.1 Bladder/ hydropneumatic Tank, 220 Gals. Capacity unit/s 2.00 673,500.00 45,110.00 718,610.00
5.5.2 Booster Pump 1.5HP unit/s 2.00 120,000.00 7,800.00 127,800.00
5.5.3 Transfer Pumps unit/s 2.00 75,000.00 12,000.00 87,000.00
5.5.4 Allowance for Electrical Work lot 1.00 45,890.00 15,550.00 61,440.00
5.5.5 Others Specify lot 1.00 86,954.00 14,338.80 101,292.80
Sub-Total Sanitary and Plumbing Works
Page 18 of 161
STA-ANA CAGAYAN MIXED DEVELOMENT PROJECT
CONSTRUCTION AND COMPLETION OF ONE UNIT FOUR STOREY OFFICE BUILDING
OFFICE BUILDINGS
Sub-Total Carried to Summary
Page 19 of 161
WP-06
% Total Amount
AMOUNT (PHP)
WORDONE (PHP)
1,500,000.00 0.00
500,000.00 20% 100,000.00
70,000.00 0.00
0.00
1,500,000.00 20% 300,000.00
0.00
2,500,000.00 80% 2,000,000.00
300,000.00 0.00
350,000.00 0.00
0.00
25,000.00 0.00
150,000.00 20% 30,000.00
Page 20 of 161
WP-06
250,000.00 10% 25,000.00
650,000.00 100% 650,000.00
2,000,000.00 0.00
50,000.00 0.00
14,945,000.00 5,825,000.00
1,028,160.00
Page 21 of 161
WP-06
786,240.00
150,000.00 100%
250,000.00 100%
150,000.00
300,000.00 100% 300,000.00
Page 22 of 161
WP-06
714,000.00 70% 499,800.00
654,937.92 70% 458,456.54
5,169,262.00 0% 0.00
189,371.00
1,320,000.00
247,500.00
229,600.00
72,000.00
64,177,914.44 32,975,557.29
9,824,598.00
399,168.00
287,680.00
397,544.00
89,460.00
2,400,000.00
1,661,400.00
2,400,000.00
3,264,800.00
6,342,000.00
1,300,000.00
1,208,000.00
Page 23 of 161
WP-06
1,359,000.00
910,000.00
54,430.00
96,808.50
2,676,240.00
1,000,000.00
3,809,016.00
55,370.00
31,075.00
313,600.00
176,000.00
48,000.00
9,000.00
112,000.00
1,960,000.00
54,000.00
126,000.00
96,000.00
56,000.00
294,000.00
112,000.00
112,000.00
56,000.00
Page 24 of 161
WP-06
63,280.00
22,063.25
28,162.76
266,112.00
3,000,000.00
50,850.00
1,760,000.00
1,375,000.00
440,000.00
550,000.00
50,646,657.51 0.00
30,000.00
95,000.00
126,000.00
127,400.00
418,600.00
68,250.00
10,752.00
4,384.00
2,654,592.00
Page 25 of 161
WP-06
1,447,716.00
88,200.00
60,200.00
8,400.00
560,500.00
27,170.00
21,000.00
42,560.00
6,680.00
1,485.00
1,260.00
6,160.00
3,150.00
1,190.00
367,500.00
88,800.00
5,640.00
28,560.00
4,320.00
3,840.00
1,680.00
57,200.00
224,400.00
Page 26 of 161
WP-06
850,000.00
750,000.00
864,000.00
115,000.00
115,000.00
115,000.00
115,000.00
32,000.00
Page 27 of 161
WP-06
32,000.00
32,000.00
32,000.00
300,000.00
69,000.00
156,000.00
200,000.00
6,000.00
27,000.00
49,500.00
73,409.10
60,000.00
82,000.00
3,080.00
5,100.00
53,760.00
2,400.00
2,800.00
595.00
Page 28 of 161
WP-06
1,485.00
1,260.00
40,500.00
138,600.00
6,800.00
9,240.00
18,200.00
5,670.00
2,856.00
2,673.00
2,268.00
56,000.00
320,000.00
324,000.00
90,000.00
54,012.00
14,000.00
14,000.00
11,836,797.10 0.00
Page 29 of 161
WP-06
0.00
62,697.60
0.00
63,000.00
30,004.80
201,096.00
277,760.00
59,136.00
28,672.00
418,754.00
14,180.00
0.00
26,100.00
26,320.00
17,408.00
8,704.00
11,430.00
31,250.00
53,380.00
31,700.00
0.00
Page 30 of 161
WP-06
3,250.00
980.00
362,196.80
50,000.00
131,544.00
53,298.00
88,704.00
68,409.60
611,900.80
265,580.00
122,388.00
50,000.00
Page 31 of 161
WP-06
66,528.00
30,105.60
448,022.40
0.00
405,300.00
0.00
0.00
74,400.00
0.00
0.00
107,900.00
0.00
545,600.00
191,380.00
50,000.00
Page 32 of 161
WP-06
603,000.00
204,000.00
0.00
340,000.00
400,000.00
144,000.00
784,000.00
1,437,220.00
255,600.00
174,000.00
61,440.00
101,292.80
9,593,632.40 0.00
Page 33 of 161
WP-06
151,200,000.00 38,800,555.84
Page 34 of 161
STA-ANA CAGAYAN MIXED DEVELOMENT PROJECT
CONSTRUCTION AND COMPLETION OF THREE UNITS FOUR STOREY RESIDENTIAL BUILDING
RESIDENTIAL BUILDINGS
GENERAL REQUIREMENTS
1.1 Mobilization/Demobilization LOT 3.00 500,000.00 500,000.00
1.2 Temporary Facilities and Utilities 0.00 0.00
1.2.1 Temporary Barracks LOT 3.00 250,000.00 250,000.00
1.2.2 Temporary Warehouse LOT 3.00 200,000.00 200,000.00
1.2.3 Temporary Office LOT 3.00 150,000.00 150,000.00
1.3 Engineers & Staff incl. Safety Officer and Aide LOT 3.00 1,000,000.00 1,000,000.00
1.4 Quality Control & Testings
1.4.1 Material Testing LOT 3.00 350,000.00 350,000.00
1.4.2 Surveying & Inspection Services LOT 3.00 150,000.00 150,000.00
1.4.3 Concrete & Rebar Testing LOT 3.00 150,000.00 150,000.00
1.5 Temporary Utilities
1.5.1 Electricity LOT 3.00 1,500,000.00 1,500,000.00
1.5.2 Water LOT 3.00 500,000.00 500,000.00
1.5.3 Communication LOT 3.00 70,000.00 70,000.00
1.6 Construction Equipment
1.6.1 Crane LOT 3.00 1,500,000.00 1,500,000.00
1.6.2 Passenger & Material Hoist LOT 3.00 0.00 0.00
1.6.3 Support Equipment (Trucks/Payloaders/etc.) LOT 3.00 2,500,000.00 2,500,000.00
1.7 Security & Safety Measures LOT 3.00 300,000.00 300,000.00
1.7.1 Security Guards LOT 3.00 350,000.00 350,000.00
1.7.2 First Aids/Medicines LOT 3.00 0.00
1.7.3 Safety Signages LOT 3.00 25,000.00 25,000.00
1.7.4 Security Lightings LOT 3.00 150,000.00 150,000.00
Page 35 of 161
STA-ANA CAGAYAN MIXED DEVELOMENT PROJECT
CONSTRUCTION AND COMPLETION OF THREE UNITS FOUR STOREY RESIDENTIAL BUILDING
RESIDENTIAL BUILDINGS
1.7.5 Safety Canopy LOT
1.7.6 *Safety Railings LOT
1.7.8 *Safety Net LOT
1.8 Housekeeping
1.8.1 *Housekeeping LOT 3.00 250,000.00 250,000.00
1.8.2 *Disposal of Debris and Waste LOT 3.00 650,000.00 650,000.00
1.9 Bonds & Insurances
1.9.1 Contractor All Risk Insurance (CARI) LOT 3.00 500,000.00 500,000.00
1.9.2 Surety Bond (20%) LOT 3.00 250,000.00 250,000.00
1.9.3 Performance Bond (25%) LOT 3.00 250,000.00 250,000.00
1.9.4 Guarantee Bond (10%) LOT 3.00 250,000.00 250,000.00
1.9.5 Group Personal Accident Insurance (GPAI) LOT 3.00 300,000.00 300,000.00
1.10 Permits
1.10.1 Building Permit (Gen Con Legwork Only, Fees by Owner) LOT 3.00 500,000.00 500,000.00
1.10.2 Occupancy Permit LOT 3.00 200,000.00 200,000.00
1.10.3 DOLE Permits LOT 3.00 50,000.00 50,000.00
1.10.4 Clearances & Certificates
1.11 Combined Services Drawing (CSD) LOT 3.00 2,000,000.00 2,000,000.00
1.12 As-Built Plans LOT 3.00 50,000.00 50,000.00
Others (Siteworks)
Sub-Total General Requirements
2 STRUCTURAL WORKS
2.1 CIVIL WORKS
2.1.1 EXCAVATION
2.1.2 Column Footing cu.m. 3,131.01 500.00 500.00
2.1.3 Footing Tie Beam cu.m. 11,621.81 500.00 500.00
2.1.4 BACKFILLING AND COMPACTION 0.00
Page 36 of 161
STA-ANA CAGAYAN MIXED DEVELOMENT PROJECT
CONSTRUCTION AND COMPLETION OF THREE UNITS FOUR STOREY RESIDENTIAL BUILDING
RESIDENTIAL BUILDINGS
2.1.4.1 Column Footing cu.m. 2,974.46 500.00 500.00
2.1.4.2 Footing Tie Beam cu.m. 11,040.72 500.00 500.00
2.1.5 GRAVEL BEDDING 0.00
2.1.5.1 Column Footing cu.m. 131.37 1,000.00 500.00 1,500.00
2.1.5.2 Footing Tie Beam cu.m. 57.63 1,000.00 500.00 1,500.00
2.1.5.3 Slab on Fill cu.m. 566.89 1,000.00 500.00 1,500.00
2.1.6 SOIL POISOINING 0.00
2.1.6.1 Slab-On-Fill sq.m. 18,144.00 120.00 50.00 170.00
2.1.7 MOISTURE AND VAPOR BARRIER 0.00
2.1.7.1 Slab-On-Fill sq.m. 18,144.00 80.00 50.00 130.00
2.1.7.2 Waterproofing 0.00 0.00
2.1.7.3 T&B sq.m. 1,492.92 350.00 50.00 400.00
2.1.8 Balcony sq.m. 1,312.74 80.00 50.00 130.00
2.1.9 Layout/board skating lot 3.00 150,000.00 150,000.00
2.1.10 Grading and Leveling lot 3.00 250,000.00 250,000.00
2.1.11 Damp proofing sq.m. 4,500.00 100.00 100.00
2.1.12 Dewatering lot 3.00 350,000.00 350,000.00
Page 37 of 161
STA-ANA CAGAYAN MIXED DEVELOMENT PROJECT
CONSTRUCTION AND COMPLETION OF THREE UNITS FOUR STOREY RESIDENTIAL BUILDING
RESIDENTIAL BUILDINGS
2.3.2 Footing Tie Beam kgs 143,183.82 43.00 17.20 60.20
2.3.3 Pedestal Column kgs 15,104.04 43.00 17.20 60.20
2.3.4 Floor Slab kgs 112,829.63 43.00 17.20 60.20
2.3.5 Stairs kgs 7,872.60 43.00 17.20 60.20
2.4 Formworks
2.4.1 Foundation sq.m. 544.10 700.00 280.00 980.00
2.4.2 Footing Tie Beam sq.m. 1,522.09 700.00 280.00 980.00
2.4.3 Pedestal Column sq.m. 1,153.15 700.00 280.00 980.00
2.4.4 Stairs sq.m. 587.88 700.00 280.00 980.00
Page 38 of 161
STA-ANA CAGAYAN MIXED DEVELOMENT PROJECT
CONSTRUCTION AND COMPLETION OF THREE UNITS FOUR STOREY RESIDENTIAL BUILDING
RESIDENTIAL BUILDINGS
3 ARCHITECTURAL WORKS
3.1 FLOOR FINISHES
3.1.1 600X600 Homogenous Tiles, Polished ( FF-1) sq.m. 3,287.52 1,325.00 250.00 1,575.00
3.1.2 2mmX940X180 Vinyl Tiles, Wood Grained Finish ( FF-2) sq.m. 9,182.16 1,200.00 250.00 1,450.00
3.1.3 300x300 Ceramic Floor Tiles for Toilets (FF-3) sq.m. 2,330.64 1,100.00 250.00 1,350.00
3.1.4 300x300 Non-skid Tiles for Balcony (FF-4) sq.m. 1,432.08 1,300.00 250.00 1,550.00
3.1.5 300x300 Non-skid Tiles for stair landings ( FF-5) sq.m. 92.40 1,300.00 250.00 1,550.00
3.1.6 300x300 Non-skid Tiles for stairs (FF-6) sq.m. 92.40 1,300.00 250.00 1,550.00
3.1.7 300x300 Non-skid Tiles for Front Porch (FF-7) sq.m. 286.92 1,300.00 250.00 1,550.00
3.1.8 Stone Finish for Exterior Walk Area (FF-80 sq.m. 311.10 950.00 250.00 1,200.00
3.1.9 Floor topping sq.m 18,000.00 200.00 200.00 400.00
Page 39 of 161
STA-ANA CAGAYAN MIXED DEVELOMENT PROJECT
CONSTRUCTION AND COMPLETION OF THREE UNITS FOUR STOREY RESIDENTIAL BUILDING
RESIDENTIAL BUILDINGS
Page 40 of 161
STA-ANA CAGAYAN MIXED DEVELOMENT PROJECT
CONSTRUCTION AND COMPLETION OF THREE UNITS FOUR STOREY RESIDENTIAL BUILDING
RESIDENTIAL BUILDINGS
3.5.2.6 Swing Type Panel Door Toilet 0.70 m X 2.10 m ( D-6 ) SET 468.00 11,000.00 4,400.00 15,400.00
3.5.2.7 Swing Type Panel Door Toilet 1.0 m X 2.10 m ( D-7 ) SET 234.00 11,000.00 4,400.00 15,400.00
3.5.2.8 Fire Rated metal Flush Door 1.8 m X 2.10 m ( D-8) SET 6.00 11,000.00 4,400.00 15,400.00
3.5.2.9 Swing Type Metal Door Door 0.90 m X 2.10 m ( D-9 ) SET 48.00 11,000.00 4,400.00 15,400.00
0.00
3.6 CANOPY 0.00
3.6.1 125mm thk Metal Deck with concrete topping . sq.m. 169.50 800.00 320.00 1,120.00
3.6.2 Concreting cu.m. 9.32 5,000.00 1,550.00 6,550.00
3.6.3 Rebars kgs 1,402.50 43.00 17.20 60.20
3.7 WATERPROOFING
3.7.1 Toilets sq.m. 3,762.72 700.00 200.00 900.00
3.7.2 External Walls sq.m 169.50 700.00 200.00 900.00
3.7.3 Canopy sq.m. 8,820.00 800.00 200.00 1,000.00
4 ELECTRICAL WORKS
4.1 PRELIMINARIES / GENERAL REQUIREMENTS
4.1.1 Testing and Commissioning lot 3.00 5,000.00 10,000.00 15,000.00
Page 41 of 161
STA-ANA CAGAYAN MIXED DEVELOMENT PROJECT
CONSTRUCTION AND COMPLETION OF THREE UNITS FOUR STOREY RESIDENTIAL BUILDING
RESIDENTIAL BUILDINGS
4.2.3 Concrete Encasement lm 105.00 5,000.00 2,000.00 7,000.00
Page 42 of 161
STA-ANA CAGAYAN MIXED DEVELOMENT PROJECT
CONSTRUCTION AND COMPLETION OF THREE UNITS FOUR STOREY RESIDENTIAL BUILDING
RESIDENTIAL BUILDINGS
4.4.1.9 Wire 5.5mm² THHN lm 120,000.00 38.00 14.00 52.00
Page 43 of 161
STA-ANA CAGAYAN MIXED DEVELOMENT PROJECT
CONSTRUCTION AND COMPLETION OF THREE UNITS FOUR STOREY RESIDENTIAL BUILDING
RESIDENTIAL BUILDINGS
1 - 800AT,3P,400V
4.7.3 MDPGA assy 3.00 85,000.00 5,000.00 90,000.00
Main: 600AT,3P,400V
Brch: 1- 400AT,3P,400V
1 - 300AT,3P,400V
1 - 100AT,3P,400V
Page 44 of 161
STA-ANA CAGAYAN MIXED DEVELOMENT PROJECT
CONSTRUCTION AND COMPLETION OF THREE UNITS FOUR STOREY RESIDENTIAL BUILDING
RESIDENTIAL BUILDINGS
1 - 125AT,3P,400V
Page 45 of 161
STA-ANA CAGAYAN MIXED DEVELOMENT PROJECT
CONSTRUCTION AND COMPLETION OF THREE UNITS FOUR STOREY RESIDENTIAL BUILDING
RESIDENTIAL BUILDINGS
3 - 30AT,1P,230V
Page 46 of 161
STA-ANA CAGAYAN MIXED DEVELOMENT PROJECT
CONSTRUCTION AND COMPLETION OF THREE UNITS FOUR STOREY RESIDENTIAL BUILDING
RESIDENTIAL BUILDINGS
8 - 30AT,1P,230V
Page 47 of 161
STA-ANA CAGAYAN MIXED DEVELOMENT PROJECT
CONSTRUCTION AND COMPLETION OF THREE UNITS FOUR STOREY RESIDENTIAL BUILDING
RESIDENTIAL BUILDINGS
Page 48 of 161
STA-ANA CAGAYAN MIXED DEVELOMENT PROJECT
CONSTRUCTION AND COMPLETION OF THREE UNITS FOUR STOREY RESIDENTIAL BUILDING
RESIDENTIAL BUILDINGS
4.8 Grounding System
4.8.1 Lightning Arrester assy 3.00 150,000.00 20,000.00 170,000.00
4.8.2 Ground Bus Terminal 6.25x50x400mm assy 3.00 5,000.00 1,000.00 6,000.00
4.8.3 Ground Rod 20mmØ x 3000mm pcs 9.00 2,500.00 500.00 3,000.00
4.8.4 Ground Well with Cover pcs 9.00 5,000.00 500.00 5,500.00
4.8.5 BCW, 100mm² lm 240.00 610.00 244.00 854.00
Miscellaneous LOT 3.00 50,000.00 20,000.00 70,000.00
Hanger and Support LOT 3.00 100,000.00 40,000.00 140,000.00
AUXILLIARY WORKS
CCTV Camera
4.9.1 Conduit,wIres, fittings & supports
4.9.1.1 75mmø PVC Pipe pcs 12.00 550.00 220.00 770.00
4.9.1.2 Pullbox 200mmX400mmX400mm pcs 9.00 1,200.00 500.00 1,700.00
4.9.1.3 20mmø PVC Pipe pcs 2,550.00 80.00 32.00 112.00
4.9.1.4 20mmø PVC Adapter with locknut prs 270.00 15.00 5.00 20.00
4.9.1.5 Junction box ga.#16 pcs 132.00 50.00 20.00 70.00
4.9.1.6 Square box, ga.#16 pcs 45.00 85.00 34.00 119.00
4.9.1.7 15mmø FMC lm 132.00 24.00 9.00 33.00
4.9.1.8 15mmø FMC Connector pcs 132.00 20.00 8.00 28.00
4.9.1.9 UTP CAT5 boxes 36.00 5,800.00 2,300.00 8,100.00
Page 49 of 161
STA-ANA CAGAYAN MIXED DEVELOMENT PROJECT
CONSTRUCTION AND COMPLETION OF THREE UNITS FOUR STOREY RESIDENTIAL BUILDING
RESIDENTIAL BUILDINGS
4.9.2.4 15mmø EMT Connector pcs 690.00 25.00 8.00 33.00
4.9.2.5 15mmø EMT Coupling pcs 2,400.00 20.00 8.00 28.00
4.9.2.6 Junction box ga.#16 pcs 243.00 50.00 20.00 70.00
4.9.2.7 Square box, ga.#16 pcs 72.00 85.00 34.00 119.00
4.9.2.8 15mmø FMC lm 243.00 24.00 9.00 33.00
4.9.2.9 15mmø FMC Connector pcs 243.00 20.00 8.00 28.00
4.9.2.10 TF Wire #18 rls 48.00 2,500.00 1,000.00 3,500.00
Page 50 of 161
STA-ANA CAGAYAN MIXED DEVELOMENT PROJECT
CONSTRUCTION AND COMPLETION OF THREE UNITS FOUR STOREY RESIDENTIAL BUILDING
RESIDENTIAL BUILDINGS
Galvanize Iron (G.I) pipe, seamless, sched. 40, grade A,
standard weight, conforming to ASTM A-120 or A53 including
fittings, elbows, tees and reducers,sleeves, insulation, hangers
and supports, leak testing and all other necessary accessories
and connections to complete the system.
5.1.1 75 mm diameter (4") m 45.00 1,771 708 2,479.40
5.1.2 65 mm diameter (3") m 1,149.00 1,144 458 1,601.60
5.1.3 50 mm diameter (2") m 768.00 915 366 1,281.00
Page 51 of 161
STA-ANA CAGAYAN MIXED DEVELOMENT PROJECT
CONSTRUCTION AND COMPLETION OF THREE UNITS FOUR STOREY RESIDENTIAL BUILDING
RESIDENTIAL BUILDINGS
5.1.21 Water Meter
5.1.22 75 mm diameter (3") pc/s 3.00 28,100.00 3,500.00 31,600.00
5.1.23 25 mm diameter (1") pc/s 234.00 6,810.00 2,724.00 9,534.00
5.1.24 Pressure Gauge pc/s 15.00 450.00 100.00 550.00
5.1.25 Hose bibb 15mm pc/s 3.00 780.00 100.00 880.00
5.1.26 Hangers, Support and Braces lot 3.00 258,712.00 103,484.80 362,196.80
5.1.28 Testing Works lot 3.00 50,000.00 50,000.00
Page 52 of 161
STA-ANA CAGAYAN MIXED DEVELOMENT PROJECT
CONSTRUCTION AND COMPLETION OF THREE UNITS FOUR STOREY RESIDENTIAL BUILDING
RESIDENTIAL BUILDINGS
Page 53 of 161
STA-ANA CAGAYAN MIXED DEVELOMENT PROJECT
CONSTRUCTION AND COMPLETION OF THREE UNITS FOUR STOREY RESIDENTIAL BUILDING
RESIDENTIAL BUILDINGS
5.3.12 Trench Grating Cover pc/s 78.00 3,150.00 200.00 3,350.00
1000mm x 300mm
5.3.13 Manhole Cover pc/s 6.00 23,500.00 1,200.00 24,700.00
5.3.14 500mm x 500mm lot 3.00 136,700.00 54,680.00 191,380.00
5.3.15 Hangers, Support and Braces lot 3.00 265,814.00 106,325.60 372,139.60
5.3.17 Testing Works lot 3.00 50,000.00 50,000.00
5.4.2 lavatories; complete with faucet, all pc/s 240.00 9,730.00 750.00 10,480.00
necessary fittings and accessories
5.4.3 Shower sets; complete with mixing valves, shower pc/s 468.00 14,500.00 750.00 15,250.00
head, faucet, all necessary fittings and accessories
5.5 EQUIPMENT
5.5.1 Supply and installation of the following equipment: unit/s 6.00 562,500.00 45,110.00 607,610.00
Elevated water tank, w/ 5,000 liters Capacity
5.5.2 as shown on details and plans:Stainless Steel unit/s 6.00 89,700.00 7,800.00 97,500.00
Page 54 of 161
STA-ANA CAGAYAN MIXED DEVELOMENT PROJECT
CONSTRUCTION AND COMPLETION OF THREE UNITS FOUR STOREY RESIDENTIAL BUILDING
RESIDENTIAL BUILDINGS
5.5.3 Bladder/ hydropneumatic Tank, 220 Gals. Capacity unit/s 6.00 12,870.00 12,000.00 24,870.00
5.5.4 Booster Pump 1.5HP lot 6.00 45,890.00 15,550.00 61,440.00
5.5.5 Transfer Pumps lot 3.00 37,595.00 14,338.80 51,933.80
Sub-Total Sanitary and Plumbing Works
Page 55 of 161
WP-07
% Total Amount
AMOUNT (PHP) WORDONE (PHP)
4,500,000.00 0.00
0.00
7,500,000.00 0.00
900,000.00 0.00
1,050,000.00 0.00
0.00
75,000.00 0.00
450,000.00 0.00
Page 56 of 161
WP-07
-
750,000.00 0.00
1,950,000.00 0.00
1,500,000.00 0.00
750,000.00 0.00
750,000.00 0.00
750,000.00 0.00
900,000.00 0.00
1,500,000.00 0.00
600,000.00 0.00
150,000.00 0.00
6,000,000.00 0.00
150,000.00 0.00
44,685,000.00 1,650,000.00
Page 57 of 161
WP-07
1,487,231.46 0.00
5,520,358.80 0.00
0.00
197,056.80 0.00
86,443.20 0.00
850,338.00 0.00
0.00
3,084,480.00 0.00
0.00
2,358,720.00 0.00
0.00
597,168.00 0.00
170,656.20 0.00
450,000.00 0.00
750,000.00 0.00
450,000.00 0.00
1,050,000.00 0.00
2,714,634.00 0.00
1,628,078.40 0.00
1,106,398.80 0.00
15,533,816.81 0.00
979,740.00 0.00
Page 58 of 161
WP-07
8,619,666.10 71% 6,119,962.93
909,263.45 71% 645,577.05
6,792,343.70 71% 4,822,564.03
473,930.52 71% 336,490.67
568,113.00 0.00
3,960,000.00 0.00
643,500.00 0.00
688,800.00 0.00
216,000.00 0.00
228,579,204.42 130,940,123.35
Page 59 of 161
WP-07
5,177,844.00 0.00
13,314,132.00 0.00
3,146,364.00 0.00
2,219,724.00 0.00
143,220.00 0.00
143,220.00 0.00
444,726.00 0.00
373,320.00 0.00
7,200,000.00 0.00
22,815,000.00 0.00
8,904,000.00 0.00
9,794,400.00 0.00
12,307,500.00 0.00
4,102,500.00 0.00
5,400,000.00 0.00
4,695,327.00 0.00
5,675,670.00 0.00
4,455,000.00 0.00
6,953,850.00 0.00
8,028,720.00 0.00
3,156,000.00 0.00
Page 60 of 161
WP-07
7,009,002.00 0.00
1,403,438.40 0.00
787,644.00 0.00
2,284,027.20 0.00
1,281,852.00 0.00
355,975.20 0.00
199,782.00 0.00
174,000.00 0.00
1,474,200.00 0.00
369,600.00 0.00
268,800.00 0.00
168,000.00 0.00
100,800.00 0.00
378,000.00 0.00
108,000.00 0.00
336,000.00 0.00
336,000.00 0.00
3,276,000.00 0.00
Page 61 of 161
WP-07
7,207,200.00 0.00
3,603,600.00 0.00
92,400.00 0.00
739,200.00 0.00
189,840.00 0.00
61,062.38 0.00
84,430.50 0.00
3,386,448.00 0.00
152,550.00 0.00
8,820,000.00 0.00
6,300,000.00 0.00
3,960,000.00 0.00
1,440,000.00 0.00
1,800,000.00 0.00
186,598,368.68 0.00
45,000.00 0.00
360,000.00 0.00
285,000.00 0.00
Page 62 of 161
WP-07
735,000.00 0.00
0.00
0.00
588,000.00 0.00
546,000.00 0.00
267,750.00 0.00
72,576.00 0.00
82,200.00 0.00
131,250.00 0.00
9,752,400.00 0.00
3,622,500.00 0.00
1,113,390.00 0.00
603,288.00 0.00
247,680.00 0.00
257,400.00 0.00
111,300.00 0.00
210,000.00 0.00
3,796,800.00 0.00
509,400.00 0.00
246,510.00 0.00
209,160.00 0.00
218,625.00 0.00
508,200.00 0.00
178,500.00 0.00
7,425,438.00 0.00
Page 63 of 161
WP-07
6,240,000.00 0.00
689,850.00 0.00
96,000.00 0.00
93,600.00 0.00
187,200.00 0.00
257,400.00 0.00
192,000.00 0.00
48,600.00 0.00
216,000.00 0.00
10,800.00 0.00
711,000.00 0.00
5,733,000.00 0.00
2,133,000.00 0.00
720,000.00 0.00
2,460,000.00 0.00
2,460,000.00 0.00
Page 64 of 161
WP-07
270,000.00 0.00
270,000.00 0.00
270,000.00 0.00
270,000.00 0.00
270,000.00 0.00
Page 65 of 161
WP-07
270,000.00 0.00
300,000.00 0.00
270,000.00 0.00
225,000.00 0.00
195,000.00 0.00
Page 66 of 161
WP-07
195,000.00 0.00
195,000.00 0.00
195,000.00 0.00
195,000.00 0.00
195,000.00 0.00
Page 67 of 161
WP-07
225,000.00 0.00
195,000.00 0.00
225,000.00 0.00
195,000.00 0.00
225,000.00 0.00
Page 68 of 161
WP-07
195,000.00 0.00
225,000.00 0.00
195,000.00 0.00
225,000.00 0.00
162,000.00 0.00
1,053,000.00 0.00
49,500.00 0.00
Page 69 of 161
WP-07
510,000.00 0.00
18,000.00 0.00
27,000.00 0.00
49,500.00 0.00
204,960.00 0.00
210,000.00 0.00
420,000.00 0.00
9,240.00 0.00
15,300.00 0.00
285,600.00 0.00
5,400.00 0.00
9,240.00 0.00
5,355.00 0.00
4,356.00 0.00
3,696.00 0.00
291,600.00 0.00
831,600.00 0.00
20,400.00 0.00
Page 70 of 161
WP-07
22,770.00 0.00
67,200.00 0.00
17,010.00 0.00
8,568.00 0.00
8,019.00 0.00
6,804.00 0.00
168,000.00 0.00
1,740,000.00 0.00
1,368,000.00 0.00
972,000.00 0.00
270,000.00 0.00
162,000.00 0.00
25,200.00 0.00
120,000.00 0.00
186,000.00 0.00
69,189,135.00 0.00
Page 71 of 161
WP-07
111,573.00 0.00
1,840,238.40 0.00
983,808.00 0.00
821,520.00 0.00
3,212,664.00 0.00
148,512.00 0.00
258,720.00 0.00
1,515,402.00 0.00
42,240.00 0.00
198,891.00 0.00
92,160.00 0.00
9,570.00 0.00
460,872.00 0.00
33,990.00 0.00
36,900.00 0.00
319,080.00 0.00
Page 72 of 161
WP-07
94,800.00 0.00
2,230,956.00 0.00
8,250.00 0.00
2,640.00 0.00
1,086,590.40 0.00
150,000.00 0.00
1,204,140.00 0.00
401,536.80 0.00
216,783.00 0.00
365,820.00 0.00
935,214.00 0.00
367,164.00 0.00
150,000.00 0.00
Page 73 of 161
WP-07
1,409,100.00 0.00
300,888.00 0.00
648,396.00 0.00
192,192.00 0.00
1,614,900.00 0.00
28,350.00 0.00
11,907.00 0.00
678,600.00 0.00
678,600.00 0.00
671,400.00 0.00
498,150.00 0.00
Page 74 of 161
WP-07
261,300.00 0.00
148,200.00 0.00
574,140.00 0.00
150,000.00 0.00
5,957,640.00 0.00
2,515,200.00 0.00
7,137,000.00 0.00
3,563,118.00 0.00
674,856.00 0.00
1,638,000.00 0.00
3,645,660.00 0.00
585,000.00 0.00
Page 75 of 161
WP-07
149,220.00 0.00
368,640.00 0.00
155,801.40 0.00
51,556,293.00 0.00
580,608,000.00 132,590,123.35
Page 76 of 161
STA-ANA CAGAYAN MIXED DEVELOMENT PROJECT
CONSTRUCTION AND COMPLETION OF THREE UNITS FOUR STOREY RESIDENTIAL BUILDING
RESIDENTIAL BUILDINGS-1
GENERAL REQUIREMENTS
1.1 Mobilization/Demobilization LOT 1.00
1.2 Temporary Facilities and Utilities
1.2.1 Temporary Barracks LOT 1.00
1.2.2 Temporary Warehouse LOT 1.00
1.2.3 Temporary Office LOT 1.00
1.3 Engineers & Staff incl. Safety Officer and Aide LOT 1.00
1.4 Quality Control & Testings
1.4.1 Material Testing LOT 1.00
1.4.2 Surveying & Inspection Services LOT 1.00
1.4.3 Concrete & Rebar Testing LOT 1.00
1.5 Temporary Utilities
1.5.1 Electricity LOT 1.00
1.5.2 Water LOT 1.00
1.5.3 Communication LOT 1.00
1.6 Construction Equipment
1.6.1 Crane LOT 1.00
1.6.2 Passenger & Material Hoist LOT 1.00
1.6.3 Support Equipment (Trucks/Payloaders/etc.) LOT 1.00
1.7 Security & Safety Measures LOT 1.00
1.7.1 Security Guards LOT 1.00
1.7.2 First Aids/Medicines LOT 1.00
1.7.3 Safety Signages LOT 1.00
1.7.4 Security Lightings LOT 1.00
1.7.5 Safety Canopy LOT
1.7.6 *Safety Railings LOT
1.7.8 *Safety Net LOT
1.8 Housekeeping
1.8.1 *Housekeeping LOT 1.00
1.8.2 *Disposal of Debris and Waste LOT 1.00
1.9 Bonds & Insurances
1.9.1 Contractor All Risk Insurance (CARI) LOT 1.00
1.9.2 Surety Bond (20%) LOT 1.00
1.9.3 Performance Bond (25%) LOT 1.00
1.9.4 Guarantee Bond (10%) LOT 1.00
1.9.5 Group Personal Accident Insurance (GPAI) LOT 1.00
1.10 Permits
1.10.1 Building Permit (Gen Con Legwork Only, Fees by Owner) LOT 1.00
1.10.2 Occupancy Permit LOT 1.00
1.10.3 DOLE Permits LOT 1.00
1.10.4 Clearances & Certificates
1.11 Combined Services Drawing (CSD) LOT 1.00
1.12 As-Built Plans LOT 1.00
Others (Siteworks)
Sub-Total General Requirements
2 STRUCTURAL WORKS
2.1 CIVIL WORKS
2.1.1 EXCAVATION
2.1.1.1 Column Footing cu.m. 1,043.67
2.1.1.2 Footing Tie Beam cu.m. 3,873.94
2.1.2 BACKFILLING AND COMPACTION
2.1.2.1 Column Footing cu.m. 991.49
2.1.2.2 Footing Tie Beam cu.m. 3,680.24
2.1.3 GRAVEL BEDDING
2.1.3.1 Column Footing cu.m. 43.79
2.1.3.2 Footing Tie Beam cu.m. 19.21
2.1.3.3 Slab on Fill cu.m. 188.96
2.1.3.4 SOIL POISOINING
2.1.3.5 Slab-On-Fill sq.m. 6,048.00
2.1.4 MOISTURE AND VAPOR BARRIER
2.1.4.1 Slab-On-Fill sq.m. 6,048.00
2.1.5 Waterproofing 0.00
2.1.6 T&B sq.m. 497.64
2.1.7 Balcony sq.m. 437.58
2.1.8 Layout/board skating lot 1.00
2.1.9 Grading and Leveling lot 1.00
2.1.10 Damp proofing sq.m. 1,500.00
2.1.11 Dewatering lot 1.00
2.4 Formworks
2.4.1 Foundation sq.m. 181.37
2.4.2 Footing Tie Beam sq.m. 507.36
2.4.3 Pedestal Column sq.m. 384.38
2.4.4 Stairs sq.m. 195.96
3 ARCHITECTURAL WORKS
3.1 FLOOR FINISHES
3.1.1 600X600 Homogenous Tiles, Polished ( FF-1) sq.m. 1,095.84
3.1.2 2mmX940X180 Vinyl Tiles, Wood Grained Finish ( FF-2) sq.m. 3,060.72
3.1.3 300x300 Ceramic Floor Tiles for Toilets (FF-3) sq.m. 776.88
3.1.4 300x300 Non-skid Tiles for Balcony (FF-4) sq.m. 477.36
3.1.5 300x300 Non-skid Tiles for stair landings ( FF-5) sq.m. 30.80
3.1.6 300x300 Non-skid Tiles for stairs (FF-6) sq.m. 30.80
3.1.7 300x300 Non-skid Tiles for Front Porch (FF-7) sq.m. 95.64
3.1.8 Stone Finish for Exterior Walk Area (FF-80 sq.m. 103.70
3.1.9 Floor topping sq.m 6,000.00
3.6 CANOPY
3.6.1 125mm thk Metal Deck with concrete topping . sq.m. 56.50
3.6.2 Concreting cu.m. 3.11
3.6.3 Rebars kgs 467.50
3.7 WATERPROOFING
3.7.1 Toilets sq.m. 1,254.24
3.7.2 External Walls sq.m 56.50
3.7.3 Canopy sq.m. 2,940.00
4 ELECTRICAL WORKS
4.1 PRELIMINARIES / GENERAL REQUIREMENTS
4.1.1 Testing and Commissioning lot 1.00
AUXILLIARY WORKS
CCTV Camera
4.9.1 Conduit,wIres, fittings & supports
4.9.1.1 75mmø PVC Pipe pcs 4.00
4.9.1.2 Pullbox 200mmX400mmX400mm pcs 3.00
4.9.1.3 20mmø PVC Pipe pcs 850.00
4.9.1.4 20mmø PVC Adapter with locknut prs 90.00
4.9.1.5 Junction box ga.#16 pcs 44.00
4.9.1.6 Square box, ga.#16 pcs 15.00
4.9.1.7 15mmø FMC lm 44.00
4.9.1.8 15mmø FMC Connector pcs 44.00
4.9.1.9 UTP CAT5 boxes 12.00
5.4.3 Shower sets; complete with mixing valves, shower pc/s 156.00
head, faucet, all necessary fittings and accessories
5.5 EQUIPMENT
5.5.1 Supply and installation of the following equipment: unit/s 2.00
Elevated water tank, w/ 5,000 liters Capacity
5.5.2 as shown on details and plans:Stainless Steel unit/s 2.00
5.5.3 Bladder/ hydropneumatic Tank, 220 Gals. Capacity unit/s 2.00
5.5.4 Booster Pump 1.5HP lot 2.00
5.5.5 Transfer Pumps lot 1.00
Sub-Total Sanitary and Plumbing Works
14,895,000.00
500.00 500.00 521,835.60 100%
500.00 500.00 1,936,968.00 100%
65 26 91.00 189,371.00
600 200 800.00 1,320,000.00
80 50 130.00 214,500.00
1000 400 1,400.00 229,600.00
400 200 600.00 72,000.00
76,193,068.15
193,536,000.00
WP-07
Total Amount
(PHP)
250,000.00
175,000.00
140,000.00
105,000.00
-
175,000.00
75,000.00
0.00
-
0.00
100,000.00
0.00
300,000.00
2,000,000.00
0.00
0.00
0.00
30,000.00
-
25,000.00
650,000.00
500,000.00
250,000.00
250,000.00
250,000.00
0.00
500,000.00
0.00
50,000.00
0.00
0.00
5,825,000.00
521,835.60
1,936,968.00
495,743.82
1,840,119.60
65,685.60
28,814.40
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
350,000.00
904,878.00
0.00
0.00
0.00
0.00
442,126.64
2,011,255.42
212,161.47
0.00
0.00
177,740.64
0.00
0.00
0.00
365,566.66
9,208,800.95
22,718,024.50
0.00
479,808.00
450,815.60
0.00
0.00
0.00
0.00
0.00
42,210,344.90
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
48,035,344.90
STA-ANA CAGAYAN MIXED DEVELOMENT PROJECT
CONSTRUCTION AND COMPLETION OF THREE UNITS FOUR STOREY RESIDENTIAL BUILDING
RESIDENTIAL BUILDINGS-2
GENERAL REQUIREMENTS
1.1 Mobilization/Demobilization LOT 1.00
1.2 Temporary Facilities and Utilities
1.2.1 Temporary Barracks LOT 1.00
1.2.2 Temporary Warehouse LOT 1.00
1.2.3 Temporary Office LOT 1.00
1.3 Engineers & Staff incl. Safety Officer and Aide LOT 1.00
1.4 Quality Control & Testings
1.4.1 Material Testing LOT 1.00
1.4.2 Surveying & Inspection Services LOT 1.00
1.4.3 Concrete & Rebar Testing LOT 1.00
1.5 Temporary Utilities
1.5.1 Electricity LOT 1.00
1.5.2 Water LOT 1.00
1.5.3 Communication LOT 1.00
1.6 Construction Equipment
1.6.1 Crane LOT 1.00
1.6.2 Passenger & Material Hoist LOT 1.00
1.6.3 Support Equipment (Trucks/Payloaders/etc.) LOT 1.00
1.7 Security & Safety Measures LOT 1.00
1.7.1 Security Guards LOT 1.00
1.7.2 First Aids/Medicines LOT 1.00
1.7.3 Safety Signages LOT 1.00
1.7.4 Security Lightings LOT 1.00
1.7.5 Safety Canopy LOT
1.7.6 *Safety Railings LOT
1.7.8 *Safety Net LOT
1.8 Housekeeping
1.8.1 *Housekeeping LOT 1.00
1.8.2 *Disposal of Debris and Waste LOT 1.00
1.9 Bonds & Insurances
1.9.1 Contractor All Risk Insurance (CARI) LOT 1.00
1.9.2 Surety Bond (20%) LOT 1.00
1.9.3 Performance Bond (25%) LOT 1.00
1.9.4 Guarantee Bond (10%) LOT 1.00
1.9.5 Group Personal Accident Insurance (GPAI) LOT 1.00
1.10 Permits
1.10.1 Building Permit (Gen Con Legwork Only, Fees by Owner) LOT 1.00
1.10.2 Occupancy Permit LOT 1.00
1.10.3 DOLE Permits LOT 1.00
1.10.4 Clearances & Certificates
1.11 Combined Services Drawing (CSD) LOT 1.00
1.12 As-Built Plans LOT 1.00
Others (Siteworks)
Sub-Total General Requirements
2 STRUCTURAL WORKS
2.1 CIVIL WORKS
2.1.1 EXCAVATION
2.1.2 Column Footing cu.m. 1,043.67
2.1.3 Footing Tie Beam cu.m. 3,873.94
2.1.4 BACKFILLING AND COMPACTION
2.1.4.1 Column Footing cu.m. 991.49
2.1.4.2 Footing Tie Beam cu.m. 3,680.24
2.1.5 GRAVEL BEDDING
2.1.5.1 Column Footing cu.m. 43.79
2.1.5.2 Footing Tie Beam cu.m. 19.21
2.1.5.3 Slab on Fill cu.m. 188.96
2.1.6 SOIL POISOINING
2.1.6.1 Slab-On-Fill sq.m. 6,048.00
2.1.7 MOISTURE AND VAPOR BARRIER
2.1.7.1 Slab-On-Fill sq.m. 6,048.00
2.1.7.2 Waterproofing 0.00
2.1.7.3 T&B sq.m. 497.64
2.1.8 Balcony sq.m. 437.58
2.1.9 Layout/board skating lot 1.00
2.1.10 Grading and Leveling lot 1.00
2.1.11 Damp proofing sq.m. 1,500.00
2.1.12 Dewatering lot 1.00
3 ARCHITECTURAL WORKS
3.1 FLOOR FINISHES
3.1.1 600X600 Homogenous Tiles, Polished ( FF-1) sq.m. 1,095.84
3.1.2 2mmX940X180 Vinyl Tiles, Wood Grained Finish ( FF-2) sq.m. 3,060.72
3.1.3 300x300 Ceramic Floor Tiles for Toilets (FF-3) sq.m. 776.88
3.1.4 300x300 Non-skid Tiles for Balcony (FF-4) sq.m. 477.36
3.1.5 300x300 Non-skid Tiles for stair landings ( FF-5) sq.m. 30.80
3.1.6 300x300 Non-skid Tiles for stairs (FF-6) sq.m. 30.80
3.1.7 300x300 Non-skid Tiles for Front Porch (FF-7) sq.m. 95.64
3.1.8 Stone Finish for Exterior Walk Area (FF-80 sq.m. 103.70
3.1.9 Floor topping sq.m 6,000.00
3.6 CANOPY
3.6.1 125mm thk Metal Deck with concrete topping . sq.m. 56.50
3.6.2 Concreting cu.m. 3.11
3.6.3 Rebars kgs 467.50
3.7 WATERPROOFING
3.7.1 Toilets sq.m. 1,254.24
3.7.2 External Walls sq.m 56.50
3.7.3 Canopy sq.m. 2,940.00
4 ELECTRICAL WORKS
4.1 PRELIMINARIES / GENERAL REQUIREMENTS
4.1.1 Testing and Commissioning lot 1.00
AUXILLIARY WORKS
CCTV Camera
4.9.1 Conduit,wIres, fittings & supports
4.9.1.1 75mmø PVC Pipe pcs 4.00
4.9.1.2 Pullbox 200mmX400mmX400mm pcs 3.00
4.9.1.3 20mmø PVC Pipe pcs 850.00
4.9.1.4 20mmø PVC Adapter with locknut prs 90.00
4.9.1.5 Junction box ga.#16 pcs 44.00
4.9.1.6 Square box, ga.#16 pcs 15.00
4.9.1.7 15mmø FMC lm 44.00
4.9.1.8 15mmø FMC Connector pcs 44.00
4.9.1.9 UTP CAT5 boxes 12.00
5.4.3 Shower sets; complete with mixing valves, shower pc/s 156.00
head, faucet, all necessary fittings and accessories
5.5 EQUIPMENT
5.5.1 Supply and installation of the following equipment: unit/s 2.00
Elevated water tank, w/ 5,000 liters Capacity
5.5.2 as shown on details and plans:Stainless Steel unit/s 2.00
5.5.3 Bladder/ hydropneumatic Tank, 220 Gals. Capacity unit/s 2.00
5.5.4 Booster Pump 1.5HP lot 2.00
5.5.5 Transfer Pumps lot 1.00
Sub-Total Sanitary and Plumbing Works
Sub-Total Carried to Summary
L BUILDING
WP-07
14,895,000.00 5,825,000.00
0.00
800.00 320.00 1,120.00 63,280.00 0.00
5,000.00 1,550.00 6,550.00 20,354.13 0.00
43.00 17.20 60.20 28,143.50 0.00
0.00
1,220.00 488.00 1,708.00 469,700.00 0.00
796.00 318.40 1,114.40 100,296.00 0.00
372.00 148.80 520.80 216,132.00 0.00
130.00 52.00 182.00 64,064.00 0.00
RESIDENTIAL BUILDINGS-3
GENERAL REQUIREMENTS
1.1 Mobilization/Demobilization LOT 1.00
1.2 Temporary Facilities and Utilities
1.2.1 Temporary Barracks LOT 1.00
1.2.2 Temporary Warehouse LOT 1.00
1.2.3 Temporary Office LOT 1.00
1.3 Engineers & Staff incl. Safety Officer and Aide LOT 1.00
1.4 Quality Control & Testings
1.4.1 Material Testing LOT 1.00
1.4.2 Surveying & Inspection Services LOT 1.00
1.4.3 Concrete & Rebar Testing LOT 1.00
1.5 Temporary Utilities
1.5.1 Electricity LOT 1.00
1.5.2 Water LOT 1.00
1.5.3 Communication LOT 1.00
1.6 Construction Equipment
1.6.1 Crane LOT 1.00
1.6.2 Passenger & Material Hoist LOT 1.00
1.6.3 Support Equipment (Trucks/Payloaders/etc.) LOT 1.00
1.7 Security & Safety Measures LOT 1.00
1.7.1 Security Guards LOT 1.00
1.7.2 First Aids/Medicines LOT 1.00
1.7.3 Safety Signages LOT 1.00
1.7.4 Security Lightings LOT 1.00
1.7.5 Safety Canopy LOT
1.7.6 *Safety Railings LOT
1.7.8 *Safety Net LOT
1.8 Housekeeping
1.8.1 *Housekeeping LOT 1.00
1.8.2 *Disposal of Debris and Waste LOT 1.00
1.9 Bonds & Insurances
1.9.1 Contractor All Risk Insurance (CARI) LOT 1.00
1.9.2 Surety Bond (20%) LOT 1.00
1.9.3 Performance Bond (25%) LOT 1.00
1.9.4 Guarantee Bond (10%) LOT 1.00
1.9.5 Group Personal Accident Insurance (GPAI) LOT 1.00
1.10 Permits
1.10.1 Building Permit (Gen Con Legwork Only, Fees by Owner) LOT 1.00
1.10.2 Occupancy Permit LOT 1.00
1.10.3 DOLE Permits LOT 1.00
1.10.4 Clearances & Certificates
1.11 Combined Services Drawing (CSD) LOT 1.00
1.12 As-Built Plans LOT 1.00
Others (Siteworks)
Sub-Total General Requirements
2 STRUCTURAL WORKS
2.1 CIVIL WORKS
2.1.1 EXCAVATION
2.1.1.1 Column Footing cu.m. 1,043.67
2.1.1.2 Footing Tie Beam cu.m. 3,873.94
2.1.2 BACKFILLING AND COMPACTION
2.1.2.1 Column Footing cu.m. 991.49
2.1.2.2 Footing Tie Beam cu.m. 3,680.24
2.1.3 GRAVEL BEDDING
2.1.3.1 Column Footing cu.m. 43.79
2.1.3.2 Footing Tie Beam cu.m. 19.21
2.1.3.3 Slab on Fill cu.m. 188.96
2.1.3.4 SOIL POISOINING
2.1.3.5 Slab-On-Fill sq.m. 6,048.00
2.1.4 MOISTURE AND VAPOR BARRIER
2.1.4.1 Slab-On-Fill sq.m. 6,048.00
2.1.5 Waterproofing
2.1.6 T&B sq.m. 497.64
2.1.7 Balcony sq.m. 437.58
2.1.8 Layout/board skating lot 1.00
2.1.9 Grading and Leveling lot 1.00
2.1.10 Damp proofing sq.m. 1,500.00
2.1.11 Dewatering lot 1.00
3 ARCHITECTURAL WORKS
3.1 FLOOR FINISHES
3.1.1 600X600 Homogenous Tiles, Polished ( FF-1) sq.m. 1,095.84
3.1.2 2mmX940X180 Vinyl Tiles, Wood Grained Finish ( FF-2) sq.m. 3,060.72
3.1.3 300x300 Ceramic Floor Tiles for Toilets (FF-3) sq.m. 776.88
3.1.4 300x300 Non-skid Tiles for Balcony (FF-4) sq.m. 477.36
3.1.5 300x300 Non-skid Tiles for stair landings ( FF-5) sq.m. 30.80
3.1.6 300x300 Non-skid Tiles for stairs (FF-6) sq.m. 30.80
3.1.7 300x300 Non-skid Tiles for Front Porch (FF-7) sq.m. 95.64
3.1.8 Stone Finish for Exterior Walk Area (FF-80 sq.m. 103.70
3.1.9 Floor topping sq.m 6,000.00
3.6 CANOPY
3.6.1 125mm thk Metal Deck with concrete topping . sq.m. 56.50
3.6.2 Concreting cu.m. 3.11
3.6.3 Rebars kgs 467.50
3.7 WATERPROOFING
3.7.1 Toilets sq.m. 1,254.24
3.7.2 External Walls sq.m 56.50
3.7.3 Canopy sq.m. 2,940.00
4 ELECTRICAL WORKS
4.1 PRELIMINARIES / GENERAL REQUIREMENTS
4.1.1 Testing and Commissioning lot 1.00
AUXILLIARY WORKS
CCTV Camera
4.9.1 Conduit,wIres, fittings & supports
4.9.1.1 75mmø PVC Pipe pcs 4.00
4.9.1.2 Pullbox 200mmX400mmX400mm pcs 3.00
4.9.1.3 20mmø PVC Pipe pcs 850.00
4.9.1.4 20mmø PVC Adapter with locknut prs 90.00
4.9.1.5 Junction box ga.#16 pcs 44.00
4.9.1.6 Square box, ga.#16 pcs 15.00
4.9.1.7 15mmø FMC lm 44.00
4.9.1.8 15mmø FMC Connector pcs 44.00
4.9.1.9 UTP CAT5 boxes 12.00
5.4.3 Shower sets; complete with mixing valves, shower pc/s 156.00
head, faucet, all necessary fittings and accessories
5.5 EQUIPMENT
5.5.1 Supply and installation of the following equipment: unit/s 2.00
Elevated water tank, w/ 5,000 liters Capacity
5.5.2 as shown on details and plans:Stainless Steel unit/s 2.00
5.5.3 Bladder/ hydropneumatic Tank, 220 Gals. Capacity unit/s 2.00
5.5.4 Booster Pump 1.5HP lot 2.00
5.5.5 Transfer Pumps lot 1.00
Sub-Total Sanitary and Plumbing Works
Sub-Total Carried to Summary
L BUILDING
WP-07
14,895,000.00 5,825,000.00
0.00
800.00 320.00 1,120.00 63,280.00 0.00
5,000.00 1,550.00 6,550.00 20,354.13 0.00
43.00 17.20 60.20 28,143.50 0.00
0.00
1,220.00 488.00 1,708.00 469,700.00 0.00
796.00 318.40 1,114.40 100,296.00 0.00
372.00 148.80 520.80 216,132.00 0.00
130.00 52.00 182.00 64,064.00 0.00