A5.1 - MOBILIZATION / DEMOBILIZATION


Mobilization FIRM 
PRICE BREAKDOWN SCHEDULE -LUMP SUM PRICE (LS)
SoW

ITEM L0 ITEM L1 ITEM L2 ITEM L3 Description Full SoW


1.0 MOBILIZATION

Registration of Contract Entity(s) and Contract in Iraq
1.0a
$59,850.10
Mobilization of camp and lodging facilities, (ready for use and certified by Company)
1.0b
$134,662.72
Mobilization of Warehouses, Laydown area preparation, and Workshops, (ready for 
1.0c
use and certified by Company)
$246,881.65
Mobilization of Equipment and tools (upon submission of list of Equipment at Site, 
1.0d
certified by Company)
$246,881.65

1.0e First batch of Free Issue Material  received in Storage
$59,850.10
2.0
DEMOBILIZATION

Demobilization of Temporary Facilities, Equipment and personnel (Area cleaning and 
2.1a
restoring as per original status)

TOTAL  PRICE $748,126.22