You are on page 1of 34

Presented by:-

Dr. Zack Lim


Principal of Academy of Concrete Technology
Managing Director of Zacklim Flat Floor Specialist Sdn Bhd
Extracted from website: Is this right?

Above website mistakes


1. This is not an expansion joints but contraction joints.
2. Placing around columns are isolation joints, not expansion joints.

Another rule of thumb: Joints to be 36 times the slab thickness


Eg. 100mm x 36 times = 3.6m spacing
1. To release stress (permit movement) in order to avoid cracks.
2. To control floor cracks to avoid random cracking.
3. Impossible to complete jointless slab (eg.10,000m2) within a day.

© Copyright - Academy of Concrete Technology 3


Results due to lack of design understanding on joints.

No isolation Edge is irregular Crack due to left-over Late saw cut or


insufficient depth
© COPYRIGHT | ACADEMY OF CONCRETE TECHNOLOGY 4
Joint defects due to poor workmanship.

Inferior side formwork Lack of vibration Poor joint finish Presentable joint
1. Construction joints
a) Slab on grade
b) Suspended slab

2. Contraction joint
a) Plain contraction joints
b) Dowelled contraction joints
c) Dowelled contraction joint with bottom mesh continuous

3. Movement joints
a) Expansion joints

4. Isolation joints
a) Slab on grade only

5. Cold joints

6. Curling at joint

7. Sealant
© Copyright - Academy of Concrete Technology

6
1. Construction joints for slab on grade

• Joints formed between slabs are called Construction Joints.


• Also assist to relieve stress.

© Copyright - Academy of Concrete Technology 7


Importance of detailing Dowel Bars Design
To ensure bars are
To facilitate movement, dowels Length of dowel?
debonded, coat bars with
must be straight, well-aligned. 400 – 450 mm
bituminous compound,
To prevent transition settlement. Spacing: 300 mm
one half of the dowels

© Copyright - Academy of Concrete Technology 8


1a) Construction joints for slab on grade
(With plate dowels)

Two way lateral movement

© COPYRIGHT | ACADEMY OF CONCRETE TECHNOLOGY 9


1b) Construction joints for slab on grade
(Without dowels – key joint)
2. Contraction Joint (saw-cut joint).
a. Contraction joint is to control the location of cracking by
creating a plane of weakness.
b. Also assist to relieve internal stress.

• As soon as the floor is hard enough and concrete


When to
does not ravel (chipped off) from the saw blade.
Cut?
• Normally 8 to 12 hrs after finishing.

• Saw-cuts width: 4mm to 6mm.


How Deep
• 30% for steel fibers.
to Cut?
• Usually 25% of the slab thickness.

What is • Rule of thumb: < 36 times the slab thickness


the Spacing? or wider subject to dosage of reinforcement.

© Copyright - Academy of Concrete Technology


Note: Only do saw-cuts to slab-on-grade only.
11
2a) Plain contraction joint

2b) Dowelled contraction joint


2c) Dowelled contraction joint with bottom mesh continuous
© COPYRIGHT | ACADEMY OF CONCRETE TECHNOLOGY 13
For narrow and long strip slab
How far apart should a contraction joint be?
Aspect ratio of width/length = 1:1.5
7.5 m

5m Contraction
joint

10 m 13 m

Potential
5m transverse
crack

© COPYRIGHT | ACADEMY OF CONCRETE TECHNOLOGY 14


Narrow strip slab, placing dowel basket at contraction joints
7.5 m

Contraction
5m joint

© Copyright - Academy of Concrete Technology 15


1c) Construction joints for suspended/elevated slab

Is saw cut required on suspended slab?

© COPYRIGHT | ACADEMY OF CONCRETE TECHNOLOGY 16


Is saw cutting recommended for suspended
slab to mitigate cracking?
1.Firstly, for suspended floors, prohibited to cut the rebars.
If you cut, will it induce the cracking?

2. Effective depth of saw cut: 25% of slab thickness – likely to cut the re-bars.

Three examples
concrete cover: 30mm
200mm
thick slab

concrete cover: 30mm

Reinforcement position is incorrect – cover exceeded the code

concrete cover:70- 100mm

Reinforcement
Case study
Saw cut proposed on suspended slab

© COPYRIGHT | ACADEMY OF CONCRETE TECHNOLOGY 18


Tie bars Vs Dowel bars

Tie bars are installed to prevent the construction joints (longitudinal) from opening up.

© COPYRIGHT | ACADEMY OF CONCRETE TECHNOLOGY 19


3a) Movement/Thermal expansion joint (Suspended & External slab)
DOWEL BAR
HALF LENGTH COATED
WITH BITUMEN ARMOUR JOINT
REBAR (THCK: 9mm x HIGH 25mm) ANCHOR STUD

250 mm

Armour joint with filler board


(external)
• Floor slabs expands during day and contract at night.
• For internal floors, concrete only shrinks, no flexible board required.
• How far apart should an expansion joint be designed?

© Copyright - Academy of Concrete Technology 20


Expansion/Movement Joint –Before and after

Upon completion – tight joint After 1 year – gap widened

© COPYRIGHT | ACADEMY OF CONCRETE TECHNOLOGY 21


Traditional movement joint
Armoured joints Armoured joints
– flat bar – sinus

22

© COPYRIGHT | ACADEMY OF CONCRETE TECHNOLOGY


Movement joints – Slab-on-piles

▪ Armored joints are needed to relieve the


stresses caused by drying shrinkage.
▪ Needed for warehouse in lieu of angle
iron.
▪ No compressible filler board required
(only for external).
▪ Placed at every 50m to 70m apart.

© COPYRIGHT | ACADEMY OF CONCRETE TECHNOLOGY 23


Cracks already appeared, shall I proceed with saw cutting?

Too shallow or too late


© Copyright - Academy of Concrete Technology 24
Is filler board needed for armoured joints for internal
suspended floor?

© COPYRIGHT | ACADEMY OF CONCRETE TECHNOLOGY 25


Is expansion joints needed for slab on ground?

© COPYRIGHT | ACADEMY OF CONCRETE TECHNOLOGY 26


Column Manhole Round Pipe

© Copyright - Academy of Concrete Technology 27


4) Isolation Joints – slab on grade
Allow vertical and horizontal movement between the
adjoining structure and the slab.
Isolate slab from columns, machine foundations, walls
and any protrusions.

Install compressible board around structure to relieve


stress.

Wrong to place bars below mesh Diagonal reinforced bars

© Copyright - Academy of Concrete Technology 28

Suspended slab
5) CURLING of floor slab

© Copyright - Academy of Concrete Technology 29


CURLING of floor slab

Curling at construction joint Curling at intersection joint Damaged at intersection joint

© COPYRIGHT | ACADEMY OF CONCRETE TECHNOLOGY 30


▪ Cold joint is a weak joint resulted by earlier batch of
concrete laid has hardened and later batch of fresh
concrete supplied cannot intermix.

Causes
Disruption of concrete supply due to:
• Batching plant breakdown.
• Truck delivery problem.
• Concrete pump breakdown.

© COPYRIGHT | ACADEMY OF CONCRETE TECHNOLOGY 31


Shrinkage at construction joint Apply sealant too early Apply sealant

• Delay applying as late as possible. • Type of sealant


• Hardness of sealant–Shore Hardness A
• Sealant must be apply during cool weather.

© COPYRIGHT | ACADEMY OF CONCRETE TECHNOLOGY 32


Q&A

© COPYRIGHT | ACADEMY OF CONCRETE TECHNOLOGY 33


What is the maximum size floor slab can be
casted with acceptable cracks?
Jointed floors
Jointed floor has saw cuts joints generally spaced at 6m.
All contraction joints will allow shrinkage.
Reinforcement: mesh or fibres.
Concrete: Normal
Eg. Slab on grade ( can also be jointless)

Jointless floor
Jointless floor have construction joints between floor panels.
All construction joints will allow drying shrinkage.
Reinforcement: Fibres, Hybrid-mesh with fibres.
Concrete: Shrinkage compensating concrete.
Eg. Slab on piles

You might also like