Professional Documents
Culture Documents
MillOps 2018 HIT Application at Meadowbank Gold Mine
MillOps 2018 HIT Application at Meadowbank Gold Mine
• Introduction
• Results
2
Introduction
3
Process Plant Description
445 – 515 tph throughput depending on ore type, P80 75-110 microns
95 % Availability with 90.5 to 95.5 % recovery
4
What is the HIT?
5
Hardness Index Tester Highlights
6
HIT Evaluation at Meadowbank
• Can routine ore hardness testing, using SAG feed samples, assist in
forecasting the SAB grinding circuit performance?
• Submitted for HIT testing at CSD laboratory to provide estimates of both the
competency (Axb) and grindability (Bond BWi) hardness.
• Program extended until end of March 2018, with a further 107 days of
sampling
7
Meadowbank and Amaruq Projects
8
Data Analysis Approach
• AEM provided a summary of the triplicate HIT Axb and duplicate HIT
Bond Wi results in Excel (for each apron feeder sample collected)
• Daily operating information from Meadowbank
Ore Zone Crusher shut Mill Down time Availability (%)
Vault (%) down (hrs) (hrs)
Throughput Tonnage SAG Power Draw BM Power Draw
(TPH) (tpd) (kW) (kW)
SAG F80 (inch) SAG %-1inch SAG T80 Product P80
WipFrag WipFrag (if reliable) (cyc. OF)
9
Challenges
• HIT testing and feed sizing was conducted on material from a ~10kg
sample of SAG feed (mix of grab samples and composites).
• Inconsistent sample taking due to cross shift effect.
• Manual sampling of coarse material challenging, despite lower F80.
10
Initial Modelling Results
8.0
7.5
SAG S.E. (kWh/t)
7.0
6.5
6.0
Calc
5.5
Actual
BM P80 ‐ 7Oct to 30Nov17
135
5.0
10/02/2017 10/12/2017 10/22/2017 11/01/2017 11/11/2017 11/21/2017
130 12/01/2017 12/11/2017
125
BM P80 (microns)
120
115
110
105
Calc
100
Actual
11 95
10/02/2017 10/12/2017 10/22/2017 11/01/2017 11/11/2017 11/21/2017 12/01/2017 12/11/2017
Validation Results
8.5
(kWh/t)
115
8.0
110
7.5
SAG S.E.
105
7.0
100
6.5
95
90
6.0
85
5.5
calibration forecast
80
5.0
09/22/2017
09/22/2017 10/12/2017
10/12/2017 11/01/2017
11/01/2017 11/21/2017
11/21/2017 12/11/2017
12/11/2017 12/31/2017
12/31/2017 01/20/2018
01/20/2018 02/09/2018
02/09/2018 03/01/2018
03/01/2018 03/21/2018
03/21/2018 04/10/2018
04/10/2018
12
Conclusions
• Variation in Axb was more significant than Bond Wi, 27 to 45 for Axb and
12.9 to 15.4 kWh/t for Bond Wi. – values align with range of standard test
results from Meadowbank deposit.
• Other variables affecting the SAG and Ball Mill circuit performance are
feed size, specifically the %-1", and ore SG as expected.
• Data from the HIT test was used to justify throughput issues in Q1 2018
• Site has capacity to conduct BWi tests, but no information on Axb
• Meadowbank wants to re-work the models to predict the TPH for a given
target P80.
• More adapted to the needs: maximizing TPH for a set grind target
• Method to verify if the grinding circuit is performing optimally
13
Future Work
• Use the new model to verify the actual TPH versus the predicted value as a
measure of the circuit efficiency.
• Justification of performance when faced with different feed types
• Indicator that circuit performance is not optimal, requiring investigation
• Implement use of the HIT test to map the hardness variation in the future
Amaruq deposit and develop an ore blending strategy based on the results.
14
agnico-eagle.com
15 simsage.com.au