Professional Documents
Culture Documents
AC – TRACTION MANUAL
Volume - 2
May 2015
AC Traction Manual
for
Delhi Metro Rail Corporation Limited
(Volume 2)
Chapter
Subject Page No.
Number
00 Abbreviations
01 Power Supply for Traction 1
02 Substations and Switching Stations 9
03 Overhead Equipment 122
04 SCADA systems 260
05 Operation of TPC 277
06 Power Block and Permit to work 286
07 Breakdowns 311
Preparation for Commissioning of Electric
08 326
Traction
09 Commissioning of Electric Traction 371
DELHI METRO RAIL CORPORATION LIMITED
ABBREVIATIONS
AC Alternating Current
ACA Anti Creep Anchor
ACC Anti Creep Centre
AFC Automatic Fare Collection
AFP Active Fire Protection
AIS Air Insulated Substation
AMS Auxiliary Main Station
ANSI American National Standards Institute
AQL Acceptable Quality Level
ASS Auxiliary Sub Station
AT Auxiliary Transformer
ATCB Auxiliary Transformer Circuit Breaker
ATD Automatic Tensioning Device
ATO Automatic Train Operation
ATP Automatic Train Protection
BC Bus Coupler
BCU Bay Control Unit
BDV Breakdown Voltage
BEC Buried Earth Conductor
BFB Broad Flange Beam
BFR Bogie Flat Rail Carrying Wagon
BG Broad Gauge
BIS Bureau of Indian Standards
BIT Bridging Interrupter
BLS Blue Light Station
BM Main Line Interrupter
BS Siding/Yard Interrupter
BRPL BSES Rajdhani Power Limited
BT Booster Transformer/ Bracket Tube
BWA Balance Weight Assembly
BYPL BSES Yamuna Power Limited
C&M Control & Monitoring
CAD Computer Aided Design
CB Circuit Breaker
CBCT Core Balance Current Transformer
CBTC Communication Based Train Control
CCITT The International Telegraph and Telephone Consultative
Committee
CCV Catenary Continuous Vulcanization
CEA Central Electricity Authority
CFL Compact Fluorescent Lamp
CHAPTER - 1
POWER SUPPLY FOR TRACTION
The entire power supply system with backup arrangements from alternative source
for operation is to be monitored and controlled locally as well as from the Operation
Control Centre (OCC) by Traction Power Controller (TPC). The Power Supply
architecture is designed to ensure that any failure of any electrical equipment does
not lead to any disturbance in Metro train services.
Delhi Metro Rail Corporation receives power supply generally from grid substations
of DTL (Delhi Transco Ltd.), Uttar Pradesh and Haryana on independent feeder
through DISCOMS (TPDDL, BYPL, BRPL, NDMC, UPPCL, DHBVN etc.).
Inside RSS, there are two substations namely the Traction Sub Station (TSS) and
the Auxiliary Main Substation (AMS). While the output of TSS is 25 kV single phase
AC, which is used to feed the OHE; the output of AMS is 33 kV three phase AC fed
to the ASS. Each Station has an ASS, in which this 33 kV three phase is further
stepped down to 415 V three phase for the local supply to the station. The Rolling
stock depot also has its own ASS. Duplicate 33 kV cables run along the corridor for
carrying 33 kV three phase power supply to the various ASS.
Fig. 201-01: Schematic Diagram of the Traction Substation and Feeding Post
For running commuter services, reliability and quality of power supply assumes
utmost importance. It is important that regular effective liaison is maintained between
the officials of DMRC and Supply Authorities.
Some of the definitions connected with Tariff as defined by the Delhi Electricity
Regulatory Commission (DERC)/Haryana Electricity Regulatory commission
(HERC)/Uttar Pradesh Electricity Regulatory Commission (UPERC) are given below.
iii. UPERC Maximum Demand: Maximum demand means the average amount
of kW or kVA, as the case may be, delivered at the point of supply of the
consumer and recorded during a fifteen (15) minutes period of maximum use
in the billing period.
iv. DERC Billing Demand: Billing demand means the contract demand or the
maximum demand indicated by the meter during the billing cycle, whichever
is more.
v. HERC Billing Demand: Billing demand means 65% of the contract demand
or the maximum demand indicated by the meter during the billing cycle,
whichever is more.
vi. UPERC Billing Demand: Billing demand means 75% of the contract demand
or the maximum demand indicated by the meter during the billing cycle,
whichever is more.
viii. Energy Charges: Shall mean the charges for energy actually taken by the
consumer in KVAH in any billing cycle. Demand charges are in addition to the
Energy charges.
ix. In “Time of day metering” tariff is different for different times of day i.e.
different for peak time, off peak time.
i. In any Mass Rapid Transit System - Electric Traction energy cost forms a
substantial portion of the total operating and maintenance cost. Therefore,
implications of the various parameters should be studied carefully to keep the
energy cost at the minimum possible level.
ii. Contract demand for each sub-station should be stipulated in relation to the
expected actual Maximum Demand so that charges for exceeding the
contract demands are avoided.
iii. In the tariff charged for electric traction, following parameters should be given
careful consideration with a view to curb the energy bill to the minimum:
iv. Notice period for altering Contract Demand should be kept as low as possible
in the agreement. Power Purchase Adjustment (PPA) is variable charge
imposed on fixed charges as well as unit charges based on variation in power
purchase rate from generation companies.
For metering and billing, DERC supply code performance standard regulations 2007,
HERC Electricity Supply Code 2014 and UPERC Electricity Supply Code 2005 are to
be followed. Temporary increase in maximum demand should be ignored for billing
purposes for DISCOMS. It should also be checked whether it is because of failure of
supply from DISCOM at some other feeding point. If it is so, then this should be
brought to the notice of DISCOMs. Regulatory commission already agrees for not
charging higher maximum demand by DISCOMs for failure on their account.
ii. Detailed instructions should be issued and the concerned Electrical officer
must counter check the items to be checked prior to passing the bills from the
Supply Authorities. An illustrative list is given below:
a. Arithmetical accuracy
b. Meter readings shown on the bill may be verified with jointly signed
readings and are generally tallying with each other.
c. The tariff applied is in terms of the agreement.
d. The method of calculation of the maximum demand for billing purpose is
in accordance with the agreement and that temporary increase in
maximum demand on account of emergency feeding has not been taken
into account.
e. In case of disruption of supply the Minimum guaranteed units are to be
adjusted by the Supply authorities.
f. In case of Meter being defective the readings are to be taken based on
last 6 months average or for the similar period of previous year as
decided by the Competent Authority.
g. The time allowed for payment is in accordance with the agreement.
h. There is no duplication in billing.
i. The payee, as provided for in the agreement is clearly indicated. The full
particulars of the payee should be advised to the Accounts branch to
enable that Branch to make payment accordingly.
j. Each new bill should be analysed and compared with earlier bill and the
reasons for any significant departures investigated.
The Officer In-Charge must countersign the bill as checked and verified and clear it
for payment. In case of any dispute/discrepancy, the payment shall be made “under
protest”.
The rolling stock of Delhi Metro Rail Corporation operates mostly at unity power
factor. However if the power factor remains poor on auxiliary load account, Delhi
Metro Rail Corporation shall consider providing power factor Improvement device in
the substations.
Detailed operating instructions mutually agreed between the Supply Authorities and
DMRC should be made out for each grid sub-station as well as traction sub-station
owned by the DMRC and should be issued to Traction Power Controller as well as
operators at Grid Substations. These instructions should contain the following
detailed procedures:
CHAPTER - 2
SUBSTATIONS AND SWITCHING STATIONS
202-00 Introduction
I ORGANISATION
202-01 Organizational Set up
202-02 Duties of official in Power Supply Installation (PSI)
202-00 Introduction
For any Metro Rail Transit System (MRTS) availability of un-interrupted power
supply is an essential requirement. Delhi Metro Rail Corporation (DMRC)
receives EHV power supply at 220/132/66 kV from different supplying
authorities/DISCOMS (DTL/DISCOMS) at Receiving Substations (RSS)
consisting of Traction Substations (TSS) and Auxiliary Main Substations
(AMS).
The RSS feeds power to the traction overhead equipment, at 27.5 kV, 50 Hz,
single phase AC, through Traction Substations (TSS). The RSS also feeds
auxiliary power at stations and en-route, through an Auxiliary Main Substation
(AMS), duplicate 33 kV cable network (in ring formation) and Auxiliary
Substations (ASS) at each underground and elevated station. The power
received at ASS is distributed to the auxiliary loads of the stations through LV
distribution system.
Section I Organisation
A broad set up of the organisation and duties of PSI (Power
Supply Installations) staffs are covered.
I ORGANISATION
In DMRC, the set up of senior subordinates working under Asst. Manager (AM) or
Manager /Traction, is based on following two patterns: -
i. Territorial basis
ii. Functional basis
In the territorial set up, one subordinate is responsible for all the activities of
maintenance and operation for a predetermined section. The functional set up
envisages separate subordinate to be in charge of each activity/combined activity
viz. Sub-station, OHE, PSI depot, etc.
In DMRC normally, the duties of officials at senior level (such as at SSE/SE level)
have been assigned on Territorial basis. The duties of the subordinates below
this level (such as ASE/JE/HM/SM) have been assigned on functional basis. The
subordinates who have been assigned duties on functional basis work as the
functional in charge of the specific activity.
ii. Carry out preventive and corrective maintenance of installations under his
charge in accordance with the prescribed schedules to keep them fully
serviceable at all times and in a state of good repair. He shall also ensure
proper record keeping of preventive and corrective maintenance of
installations and submit monthly report to SSE/SE indicating the
completion and next due dates, Equipment wise;
iii. Plan in advance the requirement of power blocks for PSI maintenance
based on the work to be done and submitting the requirements to SSE/SE
regarding power blocks/track access for PSI maintenance staff, in co-
ordination with OHE maintenance and other departments concerned as
far as possible, so as to take maximum advantage of power blocks/track
access and ensure effective utilisation of power blocks and completion of
the work within allotted time;
iv. Inspect all installations under his charge at least once a month and or as
per the prescribed schedule. The inspection should be with particular
attention to safety and operational aspects and he should submit the
prescribed inspection and periodical reports to SSE/SE;
v. Scrutinize daily reports on corrective and preventive maintenance
activities, failures and other defects noticed on PSI, as well as reports
from CTPC/TPC, inspection report of officers, daily foot patrol of cable
routes, pertaining to installations under his responsibilities and arranging
prompt rectification of defects pointed out and report compliances to
SSE/SE;
vi. Supervise maintenance gang under his control to ensure proper
maintenance complying with the prescribed schedules. He shall convey
the progress of each activity of preventive and corrective maintenance to
CTPC/TPC as well as updating the same in the progress register at his
department;
vii. Keep other staff under his control in constant readiness to deal promptly
with any breakdowns, failures of equipment, so as to attend any
emergencies/breakdown wherever and whenever required in a minimum
possible time;
viii. Guide, train and supervise staff under his control and ensure that they
shall operate and maintain the equipment properly and in particular do
actually observe all prescribed rules and regulations, Joint Procedure
orders issued from time to time, follow safety precautions, laid down
policies, ensure Personal Protective Equipment (PPE) while working on
the systems for himself and for working staff as well;
ix. Ensure that special tools and instruments provided for maintenance,
operation and testing of all installations are in good condition, are timely
calibrated and stored at proper identified place. In addition he shall also
ensure that the program of testing and maintenance of protective relays is
adhered to and ensure that other safety equipment including bonding and
earthing are functioning effectively;
x. Monitor availability of sufficient quantity of spares and other stores
required for maintenance and operation of the installations under his
charge and initiate timely action to recoup stocks. He shall also ensure
proper planning for procurement of Stock/Non-stock items, placement of
202-03 Introduction
Since reliability of electric traction of Delhi Metro Rail Corporation depends upon
continuous availability of power supply, sub-stations and switching stations have
to be kept in proper working condition at all the time. To ensure this, 25 kV feeder
lines and traction transformers with associated switchgears and control & relay
panels are duplicated so that if one unit fails, the standby unit can be brought into
service to continue power supply.
All switching operations are also centralized and controlled through SCADA by a
single authority, namely Traction Power Controller.
220/132/66 kV
to 33 k V
Transformers
LBCB2
LBCB1
LBCCB
Fig. 202-01:AMS
AMS simplified
Simplified DiagramDiagram
Local distribution
In each AMS, there are two numbers 3-Ø, indoor type cast resin dry type
33/0.415 kV transformers which feed the power supply to different auxiliary loads
of RSS itself like battery chargers, lighting, air conditioning and loads of other
substation equipments like circuit breakers, transformer cooling systems.
Typical schematic diagram is given below:
LVACB2
LVACB1
LVACCB
ACOCB ACOCB
As per energy conservation measure generally the load is fed from one
transformer and other is kept in de-energised/standby mode. Provision is typically
made for automatic changeover also.
Auxiliary substations (ASS) are located in each station which step down 33 kV to
415 V to supply distribution loads of the stations.
33 kV supply is fed to the ASS at the stations in ring formation. In rail corridor
both the 33 kV cables emanating from the AMS transformers are terminated in a
single ASS since typically a single ASS is provided in the rail corridor. In the UG
stations there are typically two/three ASS each of which is fed from separate 33
kV cable emanating from AMS transformer.
Traction Transformer
Two identical oil filled outdoor type Traction transformers of suitable capacity are
installed in RSS. The typical salient features are as under:
Characteristics
i. Two phase primary 220/132/66 KV and single phase secondary 25 kV
ii. On load tap changer on primary windings
iii. Cooling by natural oil circulation and banks of radiators mounted on
tank
iv. The Vector group shall be typically I.i0
Rated power
i. The transformer is guaranteed so as to perform satisfactorily at rated
power capacity. The maximum temperature at nominal rating shall
never exceed:
ii. 50°C above ambient temperature for mineral oil
iii. 55°C above ambient temperature for the copper winding and the iron
core.
Overload Capacity
Traction transformers usually have the following overload capacity. After
constant operating at continuous full load, the transformer shall have a
guaranteed minimum overload capacity of:
i. 50% for a duration of 15 minutes
ii. 100% for a duration of 5 minutes
Rated voltages
The primary winding voltage shall be 220/132/66 kV RMS at a power
frequency of 50 Hz on the main tapping. Operating voltage may increase to +
10% and drop to -15%.
The primary winding is fitted with on-load tap changer with 15 steps.
The secondary voltage shall be 27.5 kV at a power frequency of 50 Hz, one
terminal is connected to the earth and the other feeds the traction power.
Short-circuit on HV side
The transformer is designed and constructed so as to withstand without
damage, or impairment in its performances, any external short-circuit.
The HV winding and HV Bushings of the transformer shall be designed for
carrying the full symmetrical short circuit current typically for 3 sec.
Short-circuit on LV side
The maximum short circuit current at the output of feeding has to be
limited at 14 kA to comply with the breaking capacity of on board circuit
breakers of rolling stock.
The oil of the on-load tap changer unit is separated from the main transformer
tank and independent Buchholz relay is connected on the oil pipe between
the on-load tap changer and the expansion vessel.
Auxiliary Transformer
Two identical oil filled outdoor type Auxiliary transformers of suitable capacity are
installed in RSS. The typical salient features are as under:
Characteristics
i. Primary - 3 phase, 220/132/66 kV and Secondary - 3 phase 33 kV
ii. On load tap changer on primary windings,
iii. Cooling by natural or forced air and radiators mounted on transformer,
iv. The Vector group shall be typically Yn 0.
Rated power
The transformer is guaranteed so as to perform satisfactorily over rated
power, measured across the secondary winding.
Overload Capacity
The transformers shall be able to withstand an overload of 25% for duration of
2 hours, following continuous running at maximum continuous rated load
without exceeding the limits of temperature rise stipulated below:
i. 65 °C above ambient temperature for oil
Rated voltages
The primary winding voltage shall be 220/132/66 kV RMS at a power
frequency of 50 Hz on the main tapping. Operating voltage may increase to +
10% and drop to -15%.
The primary winding is fitted with on-load tap changer with 16 steps.
The secondary nominal voltage shall be 3 phase 33 kV at a power frequency
of 50 Hz.
Short-circuit on HV side
The transformer is designed and constructed so as to withstand without
damage, or impairment in its performances, any external short-circuit.
The HV winding and HV Bushings of the transformer shall be designed for
carrying the full symmetrical short circuit current typically for 3 sec.
Short-circuit on LV side
The maximum short circuit current at the output of feeder station has to be
limited at 1 kA.
The oil of the on-load tap changer unit is separated from the main transformer
tank and independent Buchholz relay is connected on the oil pipe between
the on-load tap changer and the expansion vessel.
In order to maintain the performance and to prolong the life of the transformers, EHV
grade oil is used. The following first two specifications are for the new inhibited
insulating oil and the third is for oil adopted in service.
The tests are wide ranging and should be done once a year. However, some of the
tests like Breakdown voltage (BDV) test, acidity tests, crackle test for moisture, may
be carried out in Sub-Stations once in six months when samples are drawn for
condition monitoring. Procedures for these tests are indicated in IS-1866.
The object of oil purification is to remove all contaminants such as water, carbon
deposits, dirt, sludge, dissolved moisture and gases. The most important quality
to be preserved is the dielectric strength, which is affected by the presence of
moisture.
In order to remove moisture in oil, the oil is heated in vacuum. Heating in vacuum
reduces the boiling point of water (dissolved in the transformer oil) thereby
dissolved water evaporates reducing any chances of decomposition of oil
molecules.
Insulation Resistance during drying out
Three readings of temperature and insulation resistance should be recorded
every two hours, from commencement until the full operation is completed.
It will be observed that there are four distinct stages:
i. Initially the insulation resistance drops down to a low value because of
rise in temperature of the oil up to about 55-600 C.
ii. Insulation resistance will continue to remain at a low level despite
temperature being maintained until most of the moisture from the
windings and oil has been driven out.
iii. The insulation resistance will thereafter rise gradually and level off,
indicating that all moisture has been driven out and the drying out
operation has been completed. At this point oil circulation should be
discontinued.
iv. As the oil cools off, the insulation resistance will rise well above the
levelling off point at the end of stage-C as given in the following figure.
This is because the insulation resistance value doubles on a fall in
temperature of about 100 C to 150 C.
Traction Transformers
Typically following protections are provided for Traction Transformers:
i. Instantaneous over current protection
ii. Delayed over current protection
iii. Differential Protection
iv. Tank earth fault
v. Buchholz protection
vi. Winding temperature rise protection
vii. Oil temperature rise protection
Buchholz Relay
The Buchholz relay assembly is provided on transformers to detect evolution of
gas caused due to internal faults. After first commissioning, the upper assembly
of the relay may sometimes be found to operate causing the relay to trip. Analysis
of the composition of gas collected will indicate the nature of fault. If the analysis
revealed that it is mere air bubbles, the transformer can be considered sound.
For details of tests manufacturers write up may be referred to. It is recommended
typically to get the dielectric strength of the oil tested, measure the insulation
resistance and carry out ratio test.
There have been cases of disconnection between MS buried rail and copper
cable due to overheating and corrosion effect. To overcome this problem copper
strip in place of MS rail is being used in phase-III as shown in Figure 202-06
below.
202-16 Introduction
i. Compact design
ii. Low weight
iii. High Reliability
iv. Low Maintenance
v. Safety to O&M personnel against touch contact.
vi. Quick erection at site due to extensive pre-fabrication and factory testing.
202-17 Application
i. High voltage installations: The higher the voltage, the more favourable
gas insulated technology becomes. The footprint of 25-220 kV
conventional Substation i.e. Air Insulated Substation (AIS) is high. The
size increases with voltage levels. GIS technology allows a significant size
reduction.
ii. Urban installations: GIS installation is expensive as compared to the air-
insulated installations of the same rating. The additional capital cost is
justified based on the reduced cost of real estate in metropolitan cities.
iii. Indoor Installations: It is generally not practical to build an air-insulated
substation inside a building, but GIS can easily be installed inside the
buildings.
202-19 66 kV GIS
Typical Structure
Maintenance Instructions
Typical Maintenance instructions of 66 KV GIS as per manufacturer are given
below:
Dis-
Circuit connector Make-Proof
Action SF6 Gas
Breaker earthing Earthing Switch
switch
Visual Once in a
Once in a year Once in a year
Inspection year
Inspection of
Monthly -
gas leakage
Every 8-12
Every 8-12 years
Major years after
after 2000
Inspection 5000 switching
switching cycles
cycles
Depending on the
Depending on
result of the
the result of the
Depending above inspection.
Depending above
on the result After 2000
on the inspection.
Preventive of the above operations. After
result of the Every 15 to 20
Maintenance inspection. closing on short
above years. After
After 2000 circuit current.
inspection cumulated
operations After completion
short circuit
of 100 close/open
current
cycles.
202-20 25 kV GIS
Typical Structure
Maintenance Instructions
Typical Maintenance instruction of 25 kV GIS are as given below: (For details
Maintenance manual to be referred):
202-21 33 kV GIS
33 kV GIS Switch gears are used in Auxiliary network in the ASS of Airport Line,
ASSs of Underground Stations of Phase-III. The electrical characteristics of 33
kV GIS are similar to the Air Insulated switchgears.
Typical Structure
202-22 Introduction
In DMRC about 1550 kms of HV cable network have been laid to meet power
supply requirement of 191 route km of Phase I & II. The cables of 220/132/66 kV
have been laid from grid substations to DMRC Receiving Substations and 33 kV
cables have been laid in loops for feeding supply to Auxiliary Substation of each
station. 25 kV cables supply power from TSS to feeding post.
Generally the manufacturer‟s catalogue indicates the rating factors for 25 kV and
above class of cables under different environment and working condition. In case
of single point bonding or cross bonded system, no de-rating of cables is
required. Various factors which affect rating of cables in all other cases are given
as under: -
i. The single core cables require de-rating, if it is laid in flat and trefoil
formation with the screen bonded at both ends.
ii. Rating of cable depends upon depth of laying, thermal resistivity of soil,
ground temperature, spacing between cables, numbers of cables laid in
the group.
iii. Rating of cable also depends upon its installation in underground pipes,
ambient temperature in case it is laid in the air.
iv. Over Load upto 105 °C: The cable may be overloaded during the
service, allowing conductor temperature to reach up to 105 °C. Both
occurrence and duration of these overloads should be kept to a minimum.
v. Emergency Load 130 °C: - In emergency, the conductor temperature is
allowed to rise up to 130 °C. However, the duration of the emergency load
should be restricted to not more than 50 Hours at a time and 500 Hours
per year in order not to shorten the cable life substantially.
vi. Short-Circuit Current: - The permissible short-circuit current of a cable is
determined by the maximum permissible conductor temperature of 250 °C
and by the duration of the short-circuit current. At high peak currents the
dynamic forces between the conductors must be taken into account.
The cable protection consists of differential pilot wire protection, over current,
earth fault and distance protection. Distance protection scheme is preferred over
differential pilot wire protection as it has been found to be more useful.
It is extremely important that cables are laid properly at the time of installation.
Any damage to the cables at the time of installation will lead to moisture ingress,
flow of circulating current and insulation failure due to overheating of the cable.
The reason for jacket insulation failure could also be due to switching surges and
development of high voltage during short circuit fault in the absence of proper
earthing/cross bonding/transposition of cable.
Any joint on cables of 25 kV and above should be done in dust and moisture free
environment. Ingress of moisture, especially in rainy season can become source
for failure of the joints. Care should also be taken in handling the joints during
laying as well as at the time of attending the failure of cables as it can become
source for another failure.
Along the cable length, aluminium tag with engraved alphabets at every 50 m or
less shall be provided. Required information for example on the cable tag is given
as under:
ND RSS - GTPS
66 kV Incomer - 1
R1 Phase
„
iii. Drums should not be pulled without supporting arrangement to avoid
damage to flange of the cables.
vii. Stabling of cable drums should be with the help of proper wedge blocks
only.
Clearances
The desired minimum clearance between different cables and gas/water pipe
lines shall be as per IS: 1255 and as per manufacturer‟s recommendations.
Depth
The desired minimum depth of laying from ground surface to the top of cable is
as follows:
The above information is based upon IS: 1255 and as per manufacturer‟s
recommendations.
Introduction
In high voltage power transmission, three single core cables are used in place of
three core cables. In the single core power transmission, the cables are usually
covered with a metallic sheath to protect the core from possible mechanical
damage and create an earthed shield.
In single core cables, unlike three core cables, whenever current is passed in
three phase AC system, it starts behaving like a single phase step down
transformer. The conductor acts as a primary winding and metallic sheath of
cables acts as secondary winding. Magnetic flux generated by the current flowing
through the conductor induces an EMF in the cable metallic sheath circuit. The
magnitude of EMF induced in the cable sheath is directly proportional to the
magnitude of the current through conductor and the magnitude of mutual
inductance between sheaths of the cables which depends upon the spacing
between cables, cable diameter and length of the circuit. Spacing between
different cores of cable depends upon how the cable has been laid in trenches
i.e. in trefoil formation or flat formation. As the inter-spacing between single core
cables in flat formation is always more as compared to trefoil formation, hence
voltage induced is also higher.
The voltage induced between the sheaths of each cable is opposite in magnitude
which causes circulating current to flow in the sheath when both ends of metallic
sheaths are bonded to the ground. Sheath circulating current cause power loss
and heating due to which cables are required to be de-rated. In order to utilize full
capacity of the cable, special sheath bonding methods are employed.
Trefoil Formation:
Fig.:202-16
To minimize the electromechanical forces between the cables under short-circuit
conditions, and to avoid eddy-current heating in nearby steelwork due to
magnetic fields set up by load currents, the three single-core cables comprising
the three phases of a 3-phase circuit are always run clamped in „Trefoil‟
formation.
Flat Formation:
Fig.: 202-17
are laid out (i.e. flat or trefoil). Generally standing voltage is not of concern
except if the runs are long and/or conductor current is high.
The floating end should be insulated from the ground. A Sheath Voltage
Limiter (SVL) shall be installed at the floating end so as to ensure that
sheath does not see very high voltages at the time of transient faults. For
longer feeder lengths, multiple single point bonding can be carried out
with a ground continuity conductor (GCC).
It is also possible to earth both the ends and provide SVLs at the midpoint
as shown in the figures below. However in both cases parallel ground
continuity conductors (GCC) are required.
i. Link Box: Link Boxes are used with cable joints and terminations to
provide easy access to shield breaks for test purposes and to limit voltage
build-up on the sheath. The link box is part of bonding system, which is
essential of improving current carrying capacity and human protection.
ii. Sheath Voltage Limiters (SVL) (Surge Arrestors): SVL is protective
device to limit induce voltages appearing on the bonded cable system due
to transient event. It is necessary to fit SVL‟s between the metallic screen
and ground inside the link box. Nominal voltage of SVL should be
selected such that it must be greater than developed induced voltage
during fault/ short circuit and at the same time SVL to be able to absorb
energy during transient event i.e. lightening and switching surges. SVL
design does not allow fault current to pass through it during short circuit
condition.
ii. Indraprastha Gas Limited: M/s IGL has allowed laying of DMRC‟s 220
kV cable across/along their gas pipe line after maintaining horizontal &
vertical gap of 2 m (or more). At crossing locations, 10 inch thick concrete
slab was provided between gas pipeline and EHV cable. Two or more
slabs should be properly jointed. 220 kV EHV cable will be charged only
after satisfactory installation of gas pipe line after grounding system.
iii. Indian Oil Corporation Limited: M/s IOCL has allowed laying of
DMRC‟s 66 kV cable across their pipe line after maintaining vertical
clearance of 6 m or 8 m from ground level to the top of HDPE ducts,
whichever is more. Actual depth of IOCL pipe lines has to ascertain at site
with the help of line locator equipment provided by IOCL‟s or by manual
digging as deemed fit by IOCL representative at site. The cables through
HDPE duct are laid by Horizontal Directional Drilling (HDD) method only.
i. Proper route marker is provided at the time of laying of the cable and needs
to be maintained as indicated below. DMRC contact number on route markers
facilitate external agency to contact whenever digging is required by them in
the vicinity of cable routes.
Fig. 202-23: Route marker front side Route marker rear side
ii. Regular foot patrolling of all cable routes, periodicity of which will be decided
by O&M based on field experience should be carried out to avoid cable
damage by external agency. DMRC staff should be deputed at digging site in
the vicinity of cable, during execution of any work by the external agency.
iii. Close coordination needs to be maintained with external agencies like PWD,
DDA, MCD, DJB, etc so as to prevent any damage to the cable during
execution of any work by external agencies. DMRC must maintain directory of
all the external agencies so that they can be easily contacted.
Tests on new installations are carried out after completion of work as per relevant
IEC standards. These tests are given below:
Type of Faults
Most common type of faults, which may occur in single core XLPE cable system
are:
For locating ground faults and short circuit faults, loop tests based on circuit of
Wheatstone bridge can be employed.
If fault is not detected in the IR testing method, High Volt AC or DC tests (Hi-pot
tests) may be carried out to ascertain fault in the cable. Following precautions are
to be taken before carrying out this test:
i. There should not be any PT in the circuit. If it is there, the same should be
isolated first.
ii. DC High voltage test (Hi-pot) beyond 10 kV is normally not recommended
for old XLPE cables and should be used only in unavoidable cases.
Loop Tests:
These tests are performed to identify the location of an earth faults or short circuit
faults in underground cables provided that a sound cable runs along the faulty
cable. In such cases the fault resistance does not affect the result obtained
except if the resistance of the fault is very high. Loop tests work on the principle
of Wheat Stone Bridge. Murray loop is most commonly used and is a modified
version of Wheat Stone Bridge for locating short circuit/earth fault in cables.
The temperature in high voltage cables is measured with special optical fibres
functioning as linear sensors, an optoelectronic device, known as Distributed
Temperature Sensing system (DTS). The resolution of temperature is less than
one meter. The advantage of temperature monitoring is detection of unexpected
hot spots in the cables and benefits of possible load management of the cables. It
is generally said that temperature monitoring for cable system makes sense
when the cable is expected to operate at the maximum load or when the
surrounding area of the laying place is populated or occupied in some way. In
such cases, the higher costs can be justified as the system can help to prevent
overheating and therefore, failure of the entire cable system.
In DMRC, Zinc Oxide with porcelain housing type LAs are normally provided at
following locations:
i. In 220/132/66 kV incomers.
ii. Upstream of transformer.
iii. 25 kV OHE feeders.
iv. At ramp transition between Rigid OCS and Flexible OHE.
v. In airport line LAs are also provided throughout OHE portion including
ramp and depot.
Zinc Oxide arrester consists of ZnO poly crystalline elements. The elements are
housed in a hollow full length of porcelain insulator and hermetically sealed. The
number and size of ZnO elements vary depending upon the system voltage and
energy class requirements. The elements exhibit high non-linear voltage current
characteristics. During normal voltages lightning arresters does not conduct and
acts as an insulator drawing a very little leakage current. When a surge wave
travelling along the overhead line comes to the arrester, the surges are absorbed
by Zinc oxide elements regain its impedance (i.e. pre-breakdown condition) and
ready for subsequent surge suppression.
Surge arresters are identified by the following minimum information which shall
appear on the rating plate (nameplate):
Monthly Schedule
Quarterly Schedule
Yearly Schedule
As per the international norms, various techniques are available for the health
monitoring of LAs in service. Some of the techniques are mentioned below:
The leakage current through a Metal Oxide resistor is mainly capacitive, with only
a small non-linear resistive component.
Effect of Aging
Electrical aging will result only in increase of the resistive component of the total
leakage current, and in consequence of the power losses, but not of the
capacitive component. The peak value of the total current is virtually not affected.
Following two methods are adopted for assessment of health of the LA:
202-39 Introduction
202-40 Transformers
Condition Monitoring
In oil filled equipment like transformers, normal deterioration or ageing of
insulation is caused by thermo-chemical reaction with participation of heat,
moisture and oxygen. This results in formation of soluble and insoluble products,
which accumulate and deteriorate the properties of oil and cellulosic insulation.
Whereas the oil can be reconditioned to restore functional properties, no such
treatment is possible for the cellulosic insulation, which suffers from reduction of
mechanical and dielectric strength. The condition of the insulation, therefore,
needs to be checked by suitable methods.
The thermal and electrical stresses caused during short circuits, overloads and
over voltages in the system result into appreciable amount of gas formation and
deterioration of dielectric properties and lowering of flash point of oil from 145 oC
to somewhere between 50 oC to 80 oC in extreme cases. In the case of incipient
faults, the gases being soluble are absorbed in the oil. The Buchholz relay cannot
respond during early stages of trouble and by the time these devices operate the
damage is already done. Dissolved gas analysis (DGA) provides an important
means in the art of condition monitoring of power transformers and other oil filled
equipment. Of the various methods of gas analysis Gas Chromatography (GS) is
one of the most sensitive, efficient and rapid method, eminently suited for
detection of incipient faults and for monitoring of growing faults, which are not
always revealed by established routine tests etc. In order to timely detect the
deterioration of insulation, oil sample shall be drawn annually and subjected to
gas chromatography Annexure 2-03.
Overhaul of Transformers
Taking into consideration the resources available with it, DMRC will carry out the
POH and repairs of the transformer through outside agencies departmentally.
Minor defects like leakage of oil from bushing, radiator gaskets etc. can be
attended at site.
Interlocking
All interlocks and automatic systems within the actuation system have been
designed so that the circuit breaker executes operations only when it is in a
position enabling to do so completely and reliably. That means, for example,
when an apparatus is in remote control, the local control does not operate.
SF 6 Circuit Breakers:
i. Gas System: The SF6 gas in a pure state is inert, exhibits exceptional
thermal stability and has excellent arc quenching properties as well as
exceptional high insulating properties. There is very little decomposition of
the gas after long periods of arcing. Such decomposition has virtually no
effect upon dielectric strength and interrupting capability. The solid arc
product formed by arcing is metallic fluoride, which appears in the form of
a fine grey powder that has high dielectric strength under dry conditions
as existing in the breaker. A good quality absorbent is used in the
apparatus to remove decomposed gaseous by-product. During the
maintenance gas pressure and temperature is recorded. Top up the gas if
pressure is less than the prescribed value. Check setting of gas pressure
switches.
ii. Interrupting Unit: Clean the surface of the porcelain and other parts.
Contacts should be inspected and replaced if necessary. Renew the
absorbent taking care that exposure of the absorbent to the atmosphere is
minimal. The breaker should be evacuated as soon as possible.
iii. Operating Mechanism: Check stroke from closed position to completely
opened position and over stroke from completely opened position to
stopped position. Check prescribed clearances. Re-lubricate the moving
parts. Check that pressure gauge is working correctly. Check pneumatic
system for tightness.
iv. The housing should be checked for water penetration and rust. Ensure
that fasteners are not loosened. Check connections of control circuit wires
for tightness.
Auxiliary power supply for the breakers and associated accessories is provided
through control cubicle (located near the main switching apparatuses) which
houses control & monitoring equipment and their AC/DC supply devices.
AC Power Supply
415/230 V, 50 Hz auxiliary power is supplied from the closest AC auxiliary
distribution board via cable and is distributed to the following services:
i. Emergency lighting,
ii. Plugs,
iii. Heating devices if installed inside electrical control boxes,
iv. Telecommunication fittings if any,
v. Rectifier power supply,
DC Power Supply
All control (motors, relays) and monitoring equipment are fed from 110 V DC from
set of rectifier. Batteries are also provided for ensuring continuity of supply, in
case of any failure of AC source. DC supply is distributed from DC battery
charger set to equipment via distribution board.
Smoking or the use of open flames or tools, which may generate sparks, is
strictly forbidden in the battery room. The battery room should be well ventilated
and dust free. It should be kept isolated from other electrical equipment.
Appropriate fuse protection for short circuit in the wiring between the battery and
distribution switchboard should be provided.
Some common troubles encountered in the batteries and their probable causes
are mentioned below:
i. Low Cell Voltage: If a cell shows very low voltage or very low water
consumption compared to other cells in the battery the cell is probably
subject to very high self discharge due to more or less internal developed
short circuit. This should be corrected by adding distilled water.
iii. Interruption: If the battery tends to show a high internal resistance, the
probable reason is dirty contact at connectors or insufficiently tightened
connectors.
Pilot Cells
One of the cells in each row of the battery set should be selected and kept as the
pilot cell. Readings should be taken on these cells with sufficient frequency to
indicate its state of discharge and charge and serve as a guide to the condition of
the other cells. The pilot cell, once selected, should not be changed unless the
cell has to undergo special treatment or repairs in which case a note should be
made immediately on record sheets. The height of the electrolyte in the pilot cell
should invariably be kept at a fixed point.
Cell Voltage
The voltage of new cells at the end of a full charge will be about 1.2 V when it is
receiving charge at the 15-hour rate. If the battery is floating and discharged only
during emergency condition then batteries are designed to accept constant
voltage charging since this is most preferred charging method. The charging
voltage is set depending upon the nature of battery load. Batteries with cyclic
loads require faster charging at higher voltage while batteries, which are on float
with infrequent discharges, require lower voltage.
It should be noted that the voltage of a cell gives an approximate indication of its
state of charge (or discharge) only when it is being discharged, and not when the
cell is open circuit.
Any drop varies with the amount of current flowing and in order to get voltages
that can be compared from month to month, the voltages should be taken with
the same current flowing in the cell. The cell testing voltmeters in use should be
periodically checked and recalibrated, if necessary.
Inter-Cell Connectors
The inter-cell connectors of the battery should be examined to ensure that they
are clean and tight, making perfect contact with cell lugs and that no corrosion is
taking place. Light Vaseline or grease should be applied to prevent corrosion.
The bench tests and final calibration should be carried out after measurement of
coil resistance and other data. Transport of the relays to and from the Depots
also requires utmost care including packing and handling. When laboratory tests
are fully satisfactory, the relays should be sealed and date of overhaul painted on
the outer cover of the relay.
vi. Apart from these detailed inspections, other field visits of inspecting officials
should be focused on random check of some items out of the check-list, in
addition to action taken on previously noticed shortcomings.
vii. The inspection schedule should be such as to cover all the installations in
their jurisdiction within the stipulated periods and stagger the inspections
among themselves to avoid over inspections of the some installations time
and again and neglect of other installations. A checklist in brief for various
inspections is given in the Annexure 2-02.
viii. The items of attention listed hereunder at any particular periodicity are over
and above those mentioned in the previous schedule. This should be kept in
view while carrying out maintenance work.
ix. The periodicity of the items of attention listed in the following paragraphs may
be modified to suit local requirements with the approval of HOD/Electrical.
x. As regards new equipment, if schedules have not been drawn up, tentative
schedules may be evolved, based on the Original Equipment Manufacturer‟s
guidelines and or any other benchmark, keeping in view the local conditions.
xi. Maintenance Schedule as per manufacturers recommendations Annexure-2-
05.
202-48 General
Check oil level monthly in sign gauge glass on daily basis and examine all joints
valves plugs etc for oil leakage in equipment; rectify leaky parts if found and
restore the oil level.
202-51 Insulators
202-54 Isolators
202-62 Cast Resin Dry Type Transformers (at RSS and ASS)
Cast Resin Dry Type Transformers (at RSS and ASS) (Refer Annexure
2-07.11)
Quarterly As per Annexure 2.07.11
Maintenance
i. Cleaning of Bushing with dry cloth and check any
lash and crack on bushing.
ii. Check the fuse of CT on secondary side.
iii. Check the oil level indicator of oil type CT and SF6
gas pressure of SF6 gas type CT.
iv. Check the tightness of all nut and bolt.
v. Check the gasket for wear and tear.
Half Yearly vi. Check of Temperature monitoring unit.
Maintenance vii. Check the transformer temperature.
viii. Cleaning of transformer enclosure for dust
removal with electric blower for
ix. Control of coil supports.
x. Tightening of Delta-Star Connections.
xi. Checking of earth connections.
xii. Sensor cleaning and checking of its connection.
Before onset of monsoon season, it should be ensured that for every equipment
no scheduled maintenance work is overdue. In the scheduled inspection just
preceding the monsoon, special attention should be paid to the vulnerable points
likely to permit ingress of moisture resulting in reduction in dielectric strength of
the equipment and rusting of parts.
i. Inspect the fence all-round the sub-station and bonding between metal
fencing panels and to earth. Put a drop of oil in the hinges of all doors.
Repaint any of the structural parts as necessary.
ii. Open all the trench cover and clean them completely. Clean all culverts
and remove cobwebs; check possibility of lizards or other inspect gaining
entry into enclosed control equipment, and make them insect-proof.
Annexure 2-01
S. Manager/AM
Nature of Inspection SSE/SE/ASE
No. (Traction)
1 Cab Inspection 2 4
2 OHE Inspection Car 1 4
3 OHE Depot 1 4
4 Station/ASS 4 4
5 RSS/AMS/TSS 1 2
6 SSP/SS 1 2
7 SP 1 1
8 Current Collection Half Yearly Half Yearly
Annexure 2-02
Check List for Inspections
1.1 RSS
Check
i. Attendance register
ii. Cleanliness of RSS & Upkeep of stores
iii. Stock position in Stores
iv. Compliance of audit & account inspection notes.
v. Test & Trial report
vi. Availability of equipment specifications
vii. Planning and Progress of Section works.
viii. Be on look out for any modifications made/being made in the power supply
arrangement.
ix. Note down meter readings and scrutinize and record important data regarding
power supply parameters including daily MD, variation in voltage, frequency and
power factor.
1.6 Isolator
Check
i. Locking arrangements.
ii. For correct alignment of blade tip in the fixed contact jaws.
iii. For correct matching & alignment of arcing horns,
1.10 Earthing
Check
i. Soundness of earth connection to each electrical equipment and structure.
ii. Last recorded earth resistance readings.
iii. Buried rail connection.
1.12 General
Check
i. Availability of fire buckets, Respiration chart, First Aid Box, Tools & Plants.
ii. Working of TPC Phones and emergency sockets.
iii. Inspection register and remarks made therein
iv. History sheets of various equipments.
1.13.1 Switchyard.
Check
i. For vegetation and spreading of Pebbles.
ii. Painting of fencing and equipments
iii. Condition of cables trenches & trench cabins.
1.13.2 Interrupters
Check
i. Control box gaskets for water and dust tightness.
ii. Operation by local & remote control.
iii. Operating mechanism for smooth operation.
iv. Oil level & leakage.
v. Interlocking of interrupters and under voltage relay operation at SP.
1.13.3 PT
Check
i. Cleanliness of PT
1.13.4 Isolator
Check
i. Locking arrangements
ii. For correct alignment of blade tips, in the fixed contact jaws & alignment of arcing
horns.
1.13.6 Earthing
Check
i. Soundness of earth connection to each electrical equipment & structures.
ii. Last recorded earth resistance readings.
1.13.7 General
Check
i. Availability of fire buckets, respiration chart, First Aid Box, Tools & Plants.
ii. Inspection register and remarks made therein
iii. History sheets of various equipments.
Annexure 2-03
1 Introduction
1.1 Dissolved Gas Analysis (DGA) is a powerful diagnostic technique for monitoring
the internal condition of transformer as it is capable of detecting faults in the
incipient stage, before they develop into major faults and results in the outage of
the transformer. The conventional Buchholz Relay is universally used in
transformers to protect against severe damages. However, its limitation is that
enough gas must be generated first to saturate the oil fully and then to come out
or there should be a gas surge to operate this relay. Moreover, Buchholz Relay is
never meant to be a diagnostic device for preventive maintenance of
transformers.
1.2 The DGA technique is very sensitive as it detect gas in parts per million (ppm) of
the oil by use of the Gas Chromatograph, it is possible to check whether a
transformer under service is being subjected to a normal aging and heating or
whether there are incipient defects such as Hot Spots, Arcing, Overheating or
Partial discharges. Such incipient faults otherwise remain undetected until they
develop into a major failure.
2 Formation of Gases in Oil Filled Transformers
2.1 It is well known that insulating oil in high voltage equipments can break down
under the influence of the thermal and electrical stresses to produce hydro-
carbon gases, hydrogen and carbon oxides. Gases may be formed in
transformers and other high voltage oil filled equipment due to aging and to a
greater extent as a result of faults. The accumulation of gases in transformer oil
may be sudden due to a severe arcing fault or more gradual as in the case of
slow deterioration of insulation. The principle mechanism of gas formation in a
transformer tank can be classified as under:
i. Oxidation,
ii. Vaporisation,
iii. Insulation decomposition,
iv. Oil breakdown and
v. Electrolytic action
2.2 Oxidation
Carbon dioxide is the gas predominantly liberated during the process of
oxidation. The process begins when small quantities of oil combine chemically
with the dissolved oxygen in the oil resulting in formation of traces of organic
acids. These acids react with the metal of the transformer, forming metal based
soaps which dissolve in the oil and act as a catalyst to accelerate the process of
oxidation.
2.3 Vaporisation
The vaporisation of oil occurs at about 280 ⁰C while that for water occurs at about
100 ⁰C. The false alarm of a Buchholz relay may be attributed to the fact that the
condensation of water vapour takes place when the excess moisture in the tank
is vaporised by a heat source. False alarm can also occur, when hydro-carbons,
the constituents of the insulating oil, vaporise.
3.1 Overheating
Overheating metallic parts heat up the surrounding regions such as paper
insulating tapes and oil. This leads to thermal deterioration of these materials.
Thermal degradation of paper produces carbon dioxide, carbon monoxide and
water. The ratio of carbon dioxide to carbon monoxide is typically five, but if the
ratio falls below three, there is indication of severe overheating of the paper. Oil
degradation produces a number of hydrocarbon gases such as methane, ethane,
ethylene, and acetylene. Methane and ethane are decomposition products that
appear above 120 ⁰C ethylene appear above 150 ⁰C while acetylene is a high
temperature product, appearing at several hundred degrees centigrade. Some
hydrogen is also produced along with the hydrocarbons gases. The proportion of
the various hydrocarbons varies with temperature. This is the basis of the well-
known Ratio code introduced several years ago by Dorenberg and R.R. Rogers.
3.3 Arcing
The third type of fault condition is arcing. Arcing can occur between leads,
between lead and coil and between other highly stressed regions weakened by
fault conditions. The high temperature caused by arcing results in the production
of acetylene and hydrogen.
Pattern of generation of gases in transformer is summarized below:
Fault/Pattern Key Gas
Conductor Overheating CO/CO2 (Carbon Oxides)
Oil overheating C2 H2 (Ethylene)
Particle discharge H2 (Hydrogen)
Arcing C2H2 (Acetylene)
4 Solubility of Gases
The solubility of gases in oil varies with temperature and pressure. While
solubility of H2, N2,CO, O2 in oil increases with temperature and that of CO2, C2,
H2, C2 H4 and C2 H6 decreases with temperature, solubility of CH4 remains
essentially constant.
All the gases become more soluble in oil with increase in pressure. Solubility of
gas is one of the factors contributing to the complexities in formulating
permissible levels of gases on the basis of service life of a transformer. Table-I
show solubility of different gases 25 ⁰C and at 1 atm. The homogeneity or the
gases in the oil is dependent on the rate of gas generation, access of the fault
area to flowing oil, rate of oil mixing and presence of gas blanket.
6.2 The results of the DGA for each transformer should be built into a data and based
on the trend of the gas levels over a period of time as well as the faults, if any,
that the transformer had suffered, an analysis may be done to establish the exact
nature of the incipient fault that may be developing in the transformer.
Table- I
Solubility of Different Gases in Transformer Oil at 25 ⁰C, 1 atm
Table - II
Range of Gas Levels (All Concentrations are in ppm)
Table - III
Gas Levels for Different Fault Condition (All Concentrations are in ppm)
Carbon
Fault Gases Hydrogen Methane Ethane Ethylene Acetylene
dioxide
H2 CH4 C2H6 C2H4 C2H2 CO2
3000-
Arcing 500-1000 20-130 10-30 10-30 40-100
4000
3000-
Partial 500-1000 20-130 10-30 10-30 10-15
4000
3000-
Hot Spot 20-150 10-30 10-30 150-200 10-15
4000
Gradual 3000-
20-150 10-30 150-200 10-30 10-30
Overheating 4000
Table - IV
Roger’s Method of Diagnosis by Hydro-Carbon Gas Ratios
% of
Methane Ethane Ethylene Acetylene
Diagnosis Transformers
Hydrogen Methane Ethane Ethylene
Sampled
If Methane/Hydrogen
0 0 0 0 less than 0.1 – partial 2.0
discharge
Normal Deterioration 34.2
Slight overheating
1 0 0 0 11.8
below 150 OC
Slight overheating
1 1 0 0 9.0
150 -200 OC
Slight overheating
0 1 0 0 7.8
200 -300 OC
Normal conductor
0 0 1 0 11.1
overheating
Circulating currents
1 0 1 0 and/or overheating 9.0
joints
Flashover without
0 0 0 1 2.1
power follow through
Tap changer selector
0 1 0 1 1.1
breaking current
Arc with power follow
0 0 1 1 through or persistent 9.7
arcing
CH4 - Methane
C2H6 - Ethane
C2H4 - Ethylene
C2H2 - Acetylene
H2 - Hydrogen
Annexure 2-04
Kg-f/cm2 gm / litre
At 0 : 6.25
At 1 : 12.3
At 5 : 38.2
At 10 : 75.6
At 15 : 119.0
Annexure 2-05
1 Battery Bank
2 Battery Charger
6 25 kV Single and Double Pole Motorized Isolator at Main line and Depot
9 Booster Transformer
Annexure - 2.06
Formats for Reading and Observation of Different Parameters at Receiving Substations (RSS)
Power Transformer
Date AT – 1 AT – 2 TT – 1 TT – 2
Oil and winding temperature is to be taken hourly
Wind.
TIME/ Oil Temp. Wind. Temp. Oil Temp. Wind. Temp. Oil Temp. Wind. Temp. Oil Temp.
Temp.
Param
Curr Curr Curr Curr Curr Curr Curr
eter Current Max. Max. Max. Max. Max. Max. Max. Max.
ent ent ent ent ent ent ent
66 kV & 25 kV Minimum Voltage Current and Frequently With Corresponding Time Form SCADA Before
Resetting at
220/132/66 kV I/C 1 & 2 separately 25 kV I/C 1 & 2 separately
VOLTAGE CURRENT VOLTAGE CURRENT
R Y B R Y B Y Y
Mini. Max. Mini. Max. Mini. Max. Mini. Max. Mini. Max. Mini. Max. Mini. Max. Mini. Max.
Power Transformer Oil Level (%) in Conservator and Bushings is to be Taken Once in a Day (Evening Shift at 1600 Hrs)
TT & AT separately
I/C – 1 I/C – 2 AT – 1 TT – 1 AT – 2 TT – 2 UP DN
R Y B R Y B R Y B R Y B R Y B R Y B 1 2 1 2
SF6 Gas Pressure & Counter Reading of Circuit Breaker of RSS & TSS is to be Taken Once in a Day (Evening Shift at 1600
hrs)
Gas Count. Gas Count. Gas Count. Gas Count. Gas Count. Gas Count. Gas Count. Gas Count.
AT – 1 AT – 2 TT – 1 TT – 2
R Y B R Y B R Y B Y B R Y B R Y B R Y B Y B
Check Fire Alarm Control Panel (FACP) for lamp test and existing/silenced alarm
(OK/Not OK)
Check the display of weight on WMS system by switching ON/OFF (OK/Not OK)
BB – 1 BB – 2 BB – 3 BB – 1 BB – 2 BB – 3 BB – 1 BB – 2 BB – 3
Morning
Evening
Night
Shift
Name Signature
Morning
Evening
Night
Annexure - 2-07.1
Maintenance of Insulators
Insulators
i. In industrial area insulators are subjected to smoke or industrial dust pollution
which is to be cleaned frequently to avoid flashing of insulators.
ii. Period of cleaning depends upon the intensity of pollution.
iii. More pollution area needs more frequently to be cleaned.
Section Insulator
Should be attended once in three months and at vulnerable location once in a month,
following checks to be carried out:
i. Clean insulators and replace badly chipped or even slightly cracked insulators.
ii. Checks runners for flash-marks.
iii. Check level of the assembly and adjust as required.
iv. Check for excessive contact wire wear near anchor clamps.
v. Tighten properly droppers and stiffeners.
vi. Check that pantograph passes underneath the SI smoothly.
Annexure - 2-07.2
Power Transformer
Annexure - 2-07.3
25 kV VCB and 25 kV SF6 Circuit Breaker
Annexure-2-07.4
Annexure - 2-07.5
Annexure - 2-07.6
Ni-Cd Battery Bank and Battery Chargers
Annexure - 2-07.7
PT and Cast Resin CT
Annexure - 2-07.8
Booster Transformer
For maintenance of Transformer oil, reference to be made to the Indian Standard Code
of practice 1866, which gives recommendations in detail for maintenance of insulating
oil. A few short notes on the subject are given below:
i. The oil level should be checked at frequent intervals and any excessive leakage
of oil should be investigated. There may be a slight loss of oil due to evaporation.
However it is not a serious concern if the tank is topped up at regular intervals.
ii. All leakages should be repaired as soon as it is possible so as to avoid the
trouble caused due to low levels of the insulating oil.
iii. Oil for topping-up should comply with IS-335 and should preferably be from the
same source as that of original oil, because oil refined from different crudes may
not be completely miscible and may separate into layers.
Furthermore, there may be a tendency to form acid or sludge in a mixed oil (oils
from separate sources of supply are mixed) rather than in an oil from a single
source of supply. Under no circumstances used oil to be mixed.
iv. Sample of oil should be taken at regular intervals and tested.
v. It may be mentioned that the di-electric strength does not give the true indication
of the deteriorated condition of the oil. Even a oil which is highly deteriorated may
give a high value of di-electric strength, if it is dry.
Normal method of oil purification only maintains the di-electric strength, but does
not give any indication about the deteriorated condition of the oil. It is therefore,
not advisable to depend solely on the dielectric strength of the oil by periodic
tests. If the dielectric strength is below 30 kV, the oil should be reconditioned by
passing through a centrifugal separator.
vi. It may be noted that the re-conditioning of the oil by centrifugal separation does
not remove acidity from the oil, it will remove sludge, dust, dirt etc. and will tend
to restore the process of deterioration.
The transformer tank and other external parts should be inspected periodically for any
rust or leakage. The rusted portion, if any, should be cleaned thoroughly and repainted in
proper paint shade. The transformer should be completely painted at regular intervals. If
any leakage is found, it should be investigated. If it is due to defective welding, the same
should be rectified immediately, but not by welding. The tank leakage may be attended
by a metal harder. Leaking joints can be rectified by tightening the bolts to a correct
pressure or by replacing the gaskets.
8.3 Bushings
The bushing should be inspected for any cracks or chipping of porcelain at regular
intervals and be kept free from dust and dirt. In locations where there are special and
abnormal conditions, such as storm, salt deposit, cement dust, acid fumes etc. Bushings
should be cleaned at frequent intervals.
Cable termination joints for both incoming and outgoing terminals should be examined at
regular intervals. Cable support brackets are also to be attended at regular intervals.
8.5 Conservator
A conservator is so arranged that the lower part acts as a sump in which any impurities
entering the conservator are collected. A plug is connected at the lowest point of the
conservator for draining and sampling. The inside of the conservator should be cleaned
once in a period of three years. A removable end plate is generally provided for this
purpose.
Oil level indicator should be kept clean. Generally the oil level is visible through a
transparent material. In case of leakage, immediate replacement is essential.
The breather shall be examined to ascertain the requirement of the change of silica gel.
The frequency of inspection depends upon the local climate/operating condition. More
frequent inspections are recommended when the transformers are subjected to
fluctuating loads. So long as the silica gel is in active stage, its colour is blue, but as it
becomes saturated with moisture, its colour gradually turns to pale pink. The gel is then
replaced or reactivated. The saturated gel can be reactivated by heating it upto 80oC for
4 to 6 hours, when it regains blue colour it may be used again.
The diaphragm which is fitted at the extreme end of the vent pipe should be inspected at
frequent intervals and replaced, if found damaged. If the diaphragm breaks because of
fault in the transformer, an inspection must be carried out to determine the nature and
cause of fault.
8.9 Gaskets
Gaskets sometimes shrink during service. It is, therefore, necessary to check the
tightness of bolts of the gasketed joints. The bolts should be tightened evenly round the
joints to avoid an uneven pressure. Leaking gaskets should be replaced as soon as
circumstances permit.
8.10 Earthing
External earthing for the main tank should be checked at regular intervals.
8.11 Spares
It is a fair practice to have a stock of essential spares like bushings, gaskets, explosion
vent diaphragm, breather and oil for topping up etc.
The frequency of the inspection should be determined by the size of equipment, local
climate and atmospheric conditions which will also influence the inspection schedule.
Annexure - 2-07.9
Lightening Arrestor
Annexure - 2-07.10
Oil and SF6 Type CT
Annexure - 2-07.11
33/0.415 kV Dry Type Aux. Transformer
Annexure - 2.07.12
33 kV VCB
DMRC
Check-Sheet for the Maintenance of 33 kV Circuit Breaker
S. No. Task Half Yearly Yearly
1 Date
2 Location
3 Equipment No.
Obtain Power Block and open the cover of
4 control box. Clean accumulated dust by
vacuum cleaner. Also clean the sight glass.
Check for moisture entry inside the box,
Examine the door gasket and bellows of
5
transmission rod for any damage, replace if
required.
Check availability of the handle, fixed
6 inside the door panel, for manual spring
charging.
Check the operation manually as well as
electrically in local and remote mode,
7 keeping the front door open, observe
whether the mechanism functions smoothly
without any rubbing and obstruction.
Check the working of counter and record
8
the counter reading.
Check working of semaphore indicator for
9
open/close mechanism.
Verify from SCADA status, the change of
10 position of local remote switch &
open/close status.
11 Check the working of heater.
Check electrical interlocking between CB
and associated isolators both locally and
12
remotely. Isolators should not operate
when CB is in closed condition.
Check all electrical connections of the
13
control panel for tightness
Check the bushing insulator for any
chipping and flash mark and clean with the
14
cotton cloth, anti track paint should be
applied on the chipping/flash marks.
Check & record SF6 gas pressure from the
gas density monitor. If low indication is
15
there, check for any gas leakage by SF6
detector. Top up gas, if required (Normal
CHAPTER - 3
OVERHEAD EQUIPMENT
203-00 Introduction
I ORGANISATION
203-01 Duties of Traction Officers
203-02 Duties of Senior Section Engineer (OHE)/Section
Engineer/OHE
203-03 Duties of ASE/JE (OHE)
203-04 Duties of Head Maintainer (HM)/Senior Maintainer
(SM)/Maintainer (OHE)
OVERHEAD EQUIPMENT
203-00 Introduction
Overhead Equipment stands for Flexible OHE used in Elevated sections and
Rigid OCS used in Underground sections stands for Overhead Catenary system/
Overhead Conductor system/ Overhead Contact system. All these three
terminologies are used interchangeably. Generally when the word OHE/OCS is
used, it can be interchangeably used both for Flexible and Rigid systems.
Section-IV: Safety Rules for Flexible OHE and Rigid OCS: The essential
safety rules applicable to both Flexible OHE and Rigid OCS are dealt in this
section.
I ORGANISATION
HOD (Electrical/O&M)
He is the overall in-charge of operation and maintenance of Traction system
besides being responsible for other assignments as well. HOD (Electrical) / O&M
has to ensure smooth functioning of all traction installations, including OHE, RSS,
SCADA, Tower Wagons, Catenary Maintenance Vehicles etc. He has to plan for
traction staff and ensure timely planning and replacements of assets. He has to
coordinate with HODs of Project wings of DMRC for ensuring timely completion
of project deadlines ensuring proper quality and standards. In case of
Breakdowns, he has to coordinate for ensuring timely and quick restoration of the
Metro services.
All other traction Officers, supervisors and staff shall report to him for ensuring
the above.
There may be one or more than one Dy. HOD (Traction) / O&M, depending upon
the requirements and work load.
grievances & appraising senior officers from time to time about the latest
conditions of the system.
v. In case of breakdowns, he shall immediately arrange men & material
including liasioning with OCC and rush to breakdown site by any possible
means available at the earliest.
vi. Any other works assigned to him.
ASE/JE (OHE) will be normally under SSE/SE (OHE) and will be responsible for
the following:
Duties of these officials are mentioned below. For HM/SM some duties which are
additional are given specifically:
i. HM/SM who are given EPIC (Engineering Possession In-charge) and
power block training are authorised to take PTW/Power block from
respective control centres.
ii. All Maintainers should have requisite competency to enable them working
independently.
iii. Every Maintainer should be conversant with the safety rules pertaining to
his work and be capable of independently attending to minor repairs and
adjustment work on OHE. This includes both Flexible OHE and Rigid
OCS. For this purpose he is always required to carry his tool box,
communication equipment, other equipments as required for cleaning,
measuring, lighting, safety equipments (such as discharge Rods), ladder
etc with him.
iv. A Maintainer should look for the common types of defects in OHE when
they are deputed for patrolling duty and report defects noticed during such
patrolling to the supervisors.
v. Every Maintainer should develop the ability to carry out temporary repairs
in the event of breakdowns so as to restore traffic as quickly as possible
and to deal with repairs necessary for all types of breakdowns of OHE.
vi. Make general check of all earth connections.
vii. Maintainers shall carry out the cleaning, oiling, bolting, servicing, minor
adjustments and repairs, daily checks and other works as part of
corrective and preventive maintenance.
viii. Carry out any other duty assigned to him by senior official/Officers.
This section has been divided into three parts; Description for Flexible OHE, Description
of Rigid OCS and Description of Catenary Track Motor Car.
203-05 Introduction
i. The tension in the catenary wire as well as in the contact wire has been
kept as 1200 kgf and 1000 kgf for contact wire of 150 mm2 and 107 mm2
size respectively.
ii. Automatic tensioning devices (ATD) of pulley types, Gas ATD type and
Spring type have been mostly utilised in DMRC. One significant feature in
the Rail Corridor line is that passenger stations are located close to each
other i.e. at a spacing of almost 1 to 1½ km. This puts a severe restriction
on space availability to locate insulated overlaps on the OHE to ensure a
good sectioning arrangement. It, therefore, becomes necessary to use
Section Insulators on the Main Line to provide necessary Sectioning.
Therefore, Section Insulators of superior light weight design have been
adopted in DMRC. These require less maintenance and less attention and
also ensure a high degree of performance along with spark-free passage
of pantograph (even at speeds as high as 200 kmph) under them.
iii. The DMRC Rail Corridor passes through a comparatively highly polluted
area. The pollution, combined with early morning fog during winter
months, is likely to cause flash-over problem on the insulators. Moreover,
the conventional porcelain insulators are also likely to need more frequent
attention by way of cleaning, application of silicone grease as pre-winter
precaution etc. With a view to minimise maintenance and increase
reliability, Synthetic Insulators are also used in DMRC.
iv. Jumpers and Droppers had been giving problems in the OHE of the
Indian Railways. The Parallel Groove clamps used in Jumper connection
had been problem-spots due to high temperature rise. Similarly droppers
with pre-fabricated loops had been subject to breakages, causing line
failures. With a view to minimise, if not eliminate failures on this account,
crimped jumpers and droppers are being used in DMRC Rail Corridor.
Flexible copper jumpers with crimped terminals, with modified fixing
arrangements are used in DMRC, which eliminate failures to a large
extent. Similarly, droppers of 12 mm2 Tin Bronze Flexible cables with
crimped terminals with eye, on either end, are used on the DMRC lines.
v. Bent steady arms are used in DMRC to ensure better current collection.
vi. Modified cantilever fittings using "Axle and Cardan type” connections have
been used. This type of connection provides better mechanical
performances of the Swivelling cantilever and ensures better
maintainability and a higher degree of reliability.
Types of Mast
Typical layout indicating the current flow is given in the rough sketch below:
107 mm2
150 mm2 150 mm2
Parameters Round
Flat Bottom Round Bottom
Bottom
Hard Drawn Hard Drawn Hard Drawn
Material
Copper Copper Copper
Cross Section
107 mm2 150 mm2 150 mm2
Area
Normal
1000 kg 1200 kg 1200 kg
tension
Condemnation
8.25 mm 9.25 mm 13.5 mm (30%)
Dia.
In spite of the care taken in design and erection, OHE masts may get out of
plumb in the Depots/Grades due to sinking of foundation/soil. Immediate action is
required whenever such a condition is noticed.
Masts, which appear to be out of plumb, should be checked with a plumb bob.
Since the normal height of the contact wire is 5.00 m above rail level, the extent
of deflection of the masts at this height can be conveniently calculated by
measuring the deflection at a height of 1.66 m above rail level and multiplying the
value by 3. If the mast is out of plumb, by more than 2 cm up to 4 cm, it should be
kept under watch after making sure that there is enough earthworks all round. To
identify such masts, to be kept under observation, a yellow band of width 4 cm
should be painted at a height of 1.66 m from rail level.
Masts, which are out of plumb for more than 4 cm, can be set right by releasing
the OHE and pulling the mast by a „Tirfor‟ to facilitate this, the foundation must
first be exposed on the side to which the mast is to be pulled by the Tirfor, and
the rear under side of the foundation should be packed and rammed with pieces
of stone until the foundation is fully supported. If necessary, the newly packed
foundation may be strengthened by pouring in cement concrete.
Any other method considered appropriate as per site conditions may be adopted.
In “at grade” section, any change in alignment due to slewing of tracks will affect
the setting distance and consequently the stagger of the contact wire. At
locations where the setting distance is critical i.e. close to the minimum
permissible value, slewing of track may result in infringement of the moving
dimensions (SOD) with consequent danger of accidents. Change in rail level due
to variation in ballast cushion or packing up or packing down of the track will also
result in change in contact wire height. Though provision exists in the cantilever
assembly for adjustments of the stagger and height, such adjustments are not to
be made unless absolutely necessary. It is best to maintain the position of OHE
and tracks as benchmarked in the SEDs.
Before any alteration to alignment or level of electrified track is done, due notice
shall be given to officer In-charge of the overhead equipment so that the
overhead equipment may be adjusted to conform to the new conditions.
It follows, therefore, that any alterations of the alignment of the track shall only be
made with the prior information and concurrence of the Traction department so
that he may arrange to correct the SEDs to the extent required. The authority
under which the revision has been made needs to be recorded.
To facilitate periodical checking, rail level and setting distance should be written
with paint at the base of each OHE mast face soon after commissioning,
preferably in black letters with yellow background. A horizontal line would indicate
the rail level. The setting distance should be in meters marked in correct to the
second decimal place. Repainting of these markings will ordinarily be required
once in two years.
During yearly maintenance of OHE, rail level and setting distance should be
checked and compared with the original figures. Any variation above 30 mm in
setting distance and 20 mm in rail level if noticed shall immediately be advised to
the SSE/SE/P-Way for correction. No change in setting distance and rail level
should be allowed if such change results in infringement of moving dimensions
(SOD).
It is essential to have a joint annual check of rail level and setting distance by the
ASE/JE (OHE) and ASE/JE (P-Way) in graded section.
Hard spots are points on the OHE where contact wire wear is likely to be higher
than at normal locations, due to less flexibility in the OHE. Smoke pollution
aggravates wear at hard spots. The usual spots where the contact wire is likely to
show more wear are:
iii. Splices.
iv. Turn outs.
v. Insulated Overlap (IOL) having rigid droppers.
vi. At approaches to tunnels and over line structures.
vii. Pull offs.
Hard spots are prominent where Rigid Droppers are in use. At such hard spots, it
is important to keep a watch on wear of contact wire by measuring and keeping a
record of contact wire thickness periodically. It is essential to concentrate on
these spots during annual measurement of contact wire wear.
It is important to measure and record the wear of contact wire at the known hard
spots and at a few selected locations where heavy wear may be expected, so as
to keep a watch on the rate of wear. Observations have indicated the wear of
contact wire at train starting point of the station is high where the train picks up
speed.
In addition to the known hard spots, the wire thickness may be measured at one
or two points between each pair of stations where speed is maximum. These
measurements should be taken at the time of yearly maintenance and recorded
in a register. When the average wire thickness approaches the condemning
thickness, the number of points where measurement is taken may be increased
and one location in each tension length may be covered in addition to the known
hard spots.
Splice is a small part which is used to join two ropes or wires. In case of catenary
system a splice is mostly used to join broken wire during repair and maintenance
activity.
The splice in OHE especially on contact wire of Metro railway is not desirable;
except the case if it becomes necessary when a small length requires
replacement as a result of restoration after breakdown. Contact wire splice
should not be reused.
Sparking occurs when there is loss of contact (or improper contact) between the
pantograph and the contact wire. The common causes attributable to the OHE
are:
i. Incorrect tension in regulated OHE due to maladjustment or sluggish
operation of regulating equipment;
ii. Inadequate tension of contact wire in the case of unregulated OHE;
iii. Kinks in contact wire.
iv. SI locations
The speed being low in yards and depots, the adverse effect of incorrect
tensioning will be less pronounced and re-tensioning at longer intervals of 3-4
years will be adequate.
The periodic current collection tests would reveal points where sparking takes
place. Apart from investigating and rectifying the cause of such sparking, it is also
important that the roughened surface of the contact wire be attended to, failing
which, there will be further deterioration, with successive passage of pantographs
resulting in reduced life of contact wire.
DMRC has adopted two different tensions for its OHE of main Line. Where
contact wire of 107 mm2 is used, tension of 1000 kgf in the catenary wire and
1000 kgf in the contact wire is adopted. Where contact wire of 150 mm2 is used,
the conductor tensions of 1200 kgf is considered in each of the two conductors,
i.e., 1200 kgf in the catenary wire and 1200 kgf in the contact wire. Airport Line is
an exception where size of contact wire is 107 mm2 but tension adopted is of
1200 kgf each both for contact wire and catenary wire.
In the regulated equipment, the tensions are maintained at the above pre-
determined values, irrespective of the changes in the ambient temperature, by
use of an Automatic Tensioning Device.
The use of a higher conductor tension in the catenary and contact wire ensures a
better current collection Performance. The mechanical interaction between the
contact wire and the pantograph plays an important role in the phenomenon of
current collection. The pantograph exerts an upward pressure on the contact wire
which tends to hog the contact wire. At the same time, the contact wire tends to
sag by its own unsupported weight and/or the pre-sag provided. The sag of the
contact wire will depend upon the tension in the contact wire. The net result of
this panto-contact wire interaction will play a vital role in flow of current from
contact wire to the panto. The increased tension in the contact wire helps to
contribute to better current collection at the design speeds.
Insulators
As discussed below, mainly following three types of insulators (based on
material composition) are available:
i. Porcelain Insulators of higher creepage length.
ii. Hybrid Insulators (with porcelain core and polymer sheds).
iii. Composite Insulators (with fibreglass core and polymer sheds).
Brief description of these insulators are as under:
and results in air gap. Any water ingress between FRP tube & EVA
insulation sleeve, results in tracking. For these reasons, it has
been later on decided to discontinue use of such type of insulators
and instead use silicon rubber insulators.
ii. EPDM (Ethylene Propylene Di-ene Monomer) rubber TYPE:
This is another type of insulators but not used in DMRC.
iii. SIR (Silicone Rubber type):- Silicone Rubber (SIR) has an
inherent UV resistance and hence longer life. Also SIR is directly
moulded on FRP tube and crimping is done on the ends.
Maintenance of SI
Maintenance and adjustment of SI is to be done as per schedule and special
maintenance instructions issued.
Fig 203-07
ii. In general, following three sizes of jumpers are used in the OHE:
a. 26 mm2 jumper of annealed copper. This is used as “In-span jumper”
(namely „H‟ jumper) and “Anti-theft jumper” (namely „F‟ jumper).
b. 164 mm2 jumper of annealed copper. This is used as “Feeding Jumper”.
This jumper wire is also used in fabricating “Continuity jumper” namely
„G‟ jumper.
c. 75 mm2 jumper of annealed copper. This jumper wire is used for
fabricating Continuity Jumper.
Neutral sections in OHE are provided for separation of Power supply coming from
two different RSS. This is provided at Sectioning & Paralleling post. There are
some basic requirements which should be fulfilled before deciding location of
Neutral Section:
i. To be located on tangent track.
ii. To be located on level track.
iii. To be away from stop signals.
Fig. 203-12
The OHE in Delhi Metro Rail Corporation has been designed for following
Meteorological conditions
Temperature
Minimum Temperature (ambient) 0ºC
Mean Temperature 35º C
Maximum Temperature 50º C
Humidity
Maximum relative humidity 100%
Minimum relative humidity 10%
Pollution
Pollution plays an important role in design of OHE, the atmospheric pollution
causes a large number of insulators flash over in certain areas. The flash over
mainly occurs in the early morning in winter before sunrise and in the pre
monsoon period, especially when monsoons are delayed. The pollutants provide
a creepage path resulting into flashover of insulators and consequent tripping of
the 25 kV and EHV circuit breakers. Pollution in and around Delhi is because of
chemical and Industrial emissions.
The OHE clearances should be checked with over line structures during the
annual maintenance and should be compared to the values given in “as erected”
drawings. Corrective action shall be taken as required.
The Catenary wire and contact wire are each given a tension of 1200 kgf each
(when Contact wire is of size 150 mm2) or 1000 kgf each (when the Contact Wire
is of size 107 mm2). However, for depots where tramway OHE is provided,
tension of 1200 kgf is maintained irrespective for contact wire of size 150 mm2
and 107 mm2. This tension has to be maintained irrespective of the variations in
the atmospheric temperatures.
This is achieved by providing Automatic Tensioning Devices (ATD), on either end
of each tension length. When the tension length is 700 m or less, ATD could be
provided at one end and the other end of the tension length could be fixed
without an ATD i.e. FTA (Fixed Termination Anchor). This will be termed as half-
tension-length and is provided depending upon the exigencies in the layout of
OHE. Normally the tension length is varying between 1000 m and 1100 m and
ATDs are provided at either end of the tension length.
Types of ATDs
The movable pulley of the ATD has a range of travel of 0.85 meters in the
horizontal direction. This is provided with anti falling arrangement for OHE
conductors suitable for this travel. This means, the counterweights can have a
maximum vertical travel of 5x0.85=4.25 m. While the counterweights will be free
to move over the above 4.25 m in sections at-grade, the free vertical travel of
counterweights in sections on viaduct is limited by the parapet height. The
maximum permissible travel of the counterweight, on viaduct, is calculated as
follows:
Height of anchor above Rail level 5900 mm
Height of parapet above Rail level 1050 mm
Height of anchor above parapet 5900-1050=4850 mm
Length of eye-rod 1340 mm
Allowance to be provided 360 mm
Maximum permissible travel of 4850-(1340+360)=3150 mm
counterweight
Hence, the half tension length of OHE, where the BWA termination is on the
Viaduct, should not exceed 570 m.
X-Y charts
With the increase or decrease in the conductor temperature, the conductor
expands or contracts respectively, and as a result the movable pulley moves
towards or away from the fixed pulley (i.e., towards or away from the anchor
mast), causing the counter-weights to travel downwards or upwards. The extent
of movement of counterweight depends upon the expansion or contraction of
OHE conductors. It is very important to ensure that under the extreme conditions,
the counterweight assembly maintains a predetermined minimum mechanical
clearance, from the bottom muff or the top anchor point, as the case may be. This
can be ensured by maintaining pre-determined clearance of bottom of
counterweight assembly from the muff (designated Y) and pre-determined
distance between the axes of fixed pulley and movable pulley (designated - X).
(5x+100)
* 700m max tension length on grades.
Maximum anchor height in both cases is 5.30m above rail
level.
4100 1200
3970 1174
3415 1063
3250
3100 1000
L=
57
0*
* L=
2860 952
6 00
L=
2310 842
70
0*
L=
2100 800 5 00
L=
4 00
Y X
(mm) (mm)
Temperature in degree centigrade
1100 600
100 400
0 5 10 15 20 25 30 35 40 45 50 55 60 65
Fig. 203-14
Given the maximum permissible value of travel of counterweight from the bottom
most position to top-most position (3150 mm), the values of X and Y can be
calculated for various tension lengths i.e., the distances between the fixed point
of the OHE (FTA or ACC) and the location (BWA) where the ATD is provided.
This tension length should not be more than 570 m, when BWA is located on the
viaduct. For purpose of illustration, the X-Y values calculated for tension lengths
L (400 m, 500 m, 570 m, 600 m, 700 m) and for temperature range from 0 ºC to
65 ºC, are shown in Figure 203-14
ii. Draw the contact wire. The counter weights should not rest on the ground.
iii. After 72 hours, adjust dimensions X and Y considering ambient
temperature and length to be tensioned (see adjusting chart).
Chart for Ram Extension .and „X‟ Value for Gas ATD
This chart is given for maximum tension length. For smaller lengths, the Ram
extension and X-values are to be calculated as per calculations procedure (excel
sheet) given by OEM.
Fig. 203-15
Fig. 203-16
the line remains practically constant along all the spring travel
(Force=Torque/Radius). This ATD has least number of moving parts
making its maintenance requirement very less. The photograph of this
type of ATD is given in Figure 203-17.
i. The tension length is provided with ATD on either end. With this arrangement,
the catenary system could move in the direction of traffic, due to the
interaction between the pantograph and the contact wire, unless the catenary
system is 'fixed' at some point. To arrest this movement, the catenary is fixed
at the midpoint of the tension length. This arrangement is called 'Anti-creep
arrangement' or 'Fixed point arrangement'.
ii. The cantilever at the Anti-creep central location is provided with a "Double
suspension clamp" wherein, apart from the normal catenary wire, one more
catenary wire is provided and this second catenary wire, called the “Anti-
creep” wire, is anchored on the masts. This location is called as the Anti
creep Centre, ACC.
203-19 Introduction
Rigid OCS
The Rigid OCS which carries the power supply from traction substation to the
pantographs of the Train Units has been designed to deliver a high level of
performance, both mechanically and electrically. It is designed for use in tunnels,
under and on bridges, as well as in maintenance depots. Due to its rigid-profile
design, the overhead conductor rail is especially suitable for restricted space
installation, e.g. in tunnel areas.
i. In the Rigid OCS, the contact wire is clamped into the conductor rail
profile and the conductor rail is supported by steel structures (drop tubes)
at specific intervals.
ii. The tension lengths in the Rigid OCS are designed considering the
thermal expansion of conductor rail and contact wire.
iii. In the Metro line with high intensity of train running (and pantograph
passing), the Rigid OCS have been designed in such a way, which
requires less maintenance and less attention and ensure a high degree of
performance and a spark-free passage of pantograph have been adopted
for the Underground sections of DMRC lines. The mechanical design of
Rigid OCS Support insulators are designed to take the mechanical
stresses to support the design train headway of 90 seconds. The
supporting insulator fixture shall permit free sliding of rigid conductor to
allow expansion on account of temperature changes.
iv. The flexible copper jumpers are used for the electrical connections
between the conductor rail sections by a set of two feeder clamps. One of
these feeder clamps is sufficient to transmit the entire current of the
overhead conductor rail. For reasons of redundancy, it is recommendable
to use two clamps per connection point.
v. A cable which supplies power to the Rigid OCS (or Flexible OHE Wire) is
known as a feeder. Generally 25 kV 240 mm2 copper cable is used for
power feeding. The power cables are terminated on the conductor rail
with the help of feeder clamps. The feeding is done through two numbers
of 25 kV flexible copper cables. Both the cables are then terminated on a
copper bus bar mounted on an insulator, Copper jumpers typically of
4x150 mm2 size will then connect the busbar to the CR through the feeder
clamp. The 25 kV cables cannot be terminated directly on to the
conductor rail as they are not very flexible; hence they cannot
accommodate movement of Conductor Rail due to thermal expansions
and contractions of the conductor rail. There is a danger of possible
breakage of the joint if they are terminated directly on the conductor rail.
Feeder
25 kV Insulator Clamps
vi. The transition from a Rigid OCS to a Flexible OHE system takes place
through the transition element. At the junction point of flexible OHE and
the Rigid OCS system, there will be a sudden change in the stiffness of
the contact wire. The Flexible OHE contact wire is tensioned but not rigid;
whereas the contact wire of Rigid OCS is not tensioned but clamped in
rigid CR. The movement of pantograph will not be smooth during the
transition from Flexible OHE to Rigid OCS or vice versa due to this
sudden change in the contact wire stiffness. Thus, there shall be a
gradual equalization of the difference in stiffness between the Flexible
OHE contact wire and the Rigid OCS contact wire to assist a smooth
transition of pantograph. The transition element is typically 6.00 m long.
Transition Bar is nothing but a piece of Conductor Rail with cut outs to
provide more flexibility and thus helps in absorbing the shocks. Additional
bolted joints are provided in order to ensure the clamping force of the
conductor rail profile despite the notches.
The Contact Wire from Flexible OHE enters straight into the transition bar.
The catenary wire is terminated at the tunnel mouth face through an
insulator. The transition element is provided with drilled holes to allow the
fixation of the electrical connections for transmitting the current flow from
the catenary wire.
vii. Typical drawing of the Rigid OCS arrangements showing the Conductor
Rail Position is shown below. Return Conductor and OPC wires are run
along the top of the number plate supports.
viii. In the underground sections of DMRC, the contact wire is Round bottom
and the stagger on Rigid OCS is achieved by staggering conductor rail
(which holds contact wire also).
150 mm2 Round Bottom Contact Wire has been used in underground
sections of Line-2, Line-3, Line-6, Line-7 and Line-8
Specifications of contact wire used in DMRC are as per table below:
Diameter 14.5 mm
Co-efficient of linear
17 X 10-6 per ºC
expansion (α)
The Conductor rails are supported by steel structures. According to the span,
these steel structures/Drop tubes are placed typically at 10/11 m for 90 kmph
speed depending on the design.
Fig. 203-26
The Rigid OCS Drop Tube is fixed to the tunnel ceiling with the help of anchor
bolts. These bolts are basically used to fix the rectangular drop tube to the tunnel
ceiling; and then the rest of the components are assembled on the drop tube.
The mechanical anchor bolt is hot dip galvanized type mechanical anchor as
shown in the photograph below:
The design is well proven and can be used wherever drilling depth will allow 115
mm as manufacturer recommends drilling depth of 115 mm. However the anchor
has to be installed till the red mark. The length of the bolt will permit some margin
to adjust the height and maintain the perpendicularly of the drop tube.
Cross section Drawings show offset i.e. distance from centre of drop tube to track
centre and the height of the contact wire from rail level at each location. These
are with reference to alignment and level of the track at the time of erection of
Rigid OCS.
It follows, therefore, that any alterations of the alignment of the track shall only be
made with the prior information and concurrence of the Traction department so
that arrangement be made to correct the cross section drawings to the extent
required.
No change in offset distance and rail level should be allowed if such change
results in infringement of moving dimensions (SOD).
Generally the rails will be delivered and installed in lengths of 11 m according and
11 m support distance will be used as standard span. These 11m rails are made
continuous by Splices/Rail Joints.
The conductor Rail Joint consists of inner and/or outer plates. The plates with
their large contact surfaces ensure the current transmission between the rail and
the joint and are also used for accurate mechanical fixing and fastening of the rail
height.
Fig. 203-28
203-24 Insulator
Porcelain type insulators have been used in the Rigid OCS installed in Vishwa
Vidyalaya to Central Secretariat of (Line-2) and Mandi House to Rajiv Chowk
(Line-3) of Phase-I. Whereas composite silicon insulators have been used in
Udyog Bhawan to Saket and Vishwa Vidyalaya to GTB Nagar (Line-2), Central
Secretariat to Jangpura (Line-6), Dwarka Sector-21 (Line-3) of Phase-II. All the
underground corridors of Line-7 and Line-8 and Line-6 extension of Phase-III are
also using composite silicon insulators due to the advantage of being light weight
and easier cleaning during maintenance. The electrical and mechanical
properties of support insulator shall be in accordance with the recommendations
of IEC 61109.
The minimum creepage distance of the insulator shall be 1100 mm, wet
frequency withstand voltage shall be 250 kV in accordance with the
recommendations of IEC 60913.
The jumper wires for the Rigid OCS shall be of stranded annealed copper with
adequate current carrying capacity. The jumpers are to be connected at air gaps
and at feeding points. The jumper wire shall be flexible to allow creeping of rigid
conductor. The jumper loops remain at least 75mm above the contact plane.
Neutral sections in Rigid OCS are provided for Power supply separation from
different RSS. The Neutral sections in the Rigid OCS are SI type or overlap type.
There are some basic requirements which should be fulfilled before deciding
location of Neutral Section:
i. To be located on tangent track.
ii. To be located on level track.
iii. To be away from stop signals.
iv. S&T track circuit boundaries may be considered as stop signals. Driver is
not required to stop under NS.
In the Rigid OCS, a mid-point is located in the middle of a tension length that
allows an unlimited expansion of the rail in both directions, thereby permitting a
large tension length. A support similar to the standard support will be used for the
fix point arrangement. The difference is that the rail will be firmly clamped to the
support.
To avoid this risk, in the area of tunnel mouths and local moisture points, the CR
is provided with a protective plastic cover. The Conductor Rails at the Platform
are also provided with the plastic cover. This cover is manufactured in suitable
lengths with a nominal dead weight of approx. 0.86kg/m, which has no great
effect on the sag of the CR as it is rather rigid itself.
Of course, the cover can be cut into shorter sections and can be installed easily
without any additional fixing parts. As the cover encloses the whole CR profile, it
cannot be used in the area of supports and all parts which extend out of the
profile.
In depot, generally tramway type OHE is used, there has been no constraint of
minimum clearances. However when work is required to be carried out on the
roof of the train in inspection bay lines (IBL), the Flexible OHE causes hindrance
and hence extra care has to be taken during the maintenance on the train roof.
In Abroad, in some depots Retractable Rigid OCS has been adopted which can
easily be retracted from the roof temporarily and may be repositioned back easily
after the completion of maintenance work. This is planned to be adopted in new
depots as the need be in Phase-III.
Fig. 203-36: Typical Cross section of Retractable Rigid OCS in Depot – OCS in
service
Fig. 203-37: Typical Cross section of Retractable Rigid OCS in Depot – OCS in
Retracted Condition
IEC 60913
Item (Live to Structure clearances) Normal distance in
mm
Static Dynamic
Basic insulation 70 70
Distortion of Electrical Field 30 30
Surge/ Over Voltages 100 0
Safety Margins- Other allowances 70 70
Total 270* 170*
Clearances* (mm)
Static Dynamic
Item
Absolute
Normal Normal
Minimum **
Live part of contact lines and to 270 170 150
bodies of structures (horizontal
/vertical)
Live part to vehicle 290 190 150
(horizontal/vertical)
DMRC has adopted close mode ventilation system, and the normal ventilation
through the piston effect of the train, therefore the tunnel environment is
controlled and pollution free, therefore static clearance of 270 mm & 290 mm was
adopted between „Live part to structure‟ and „Live part to vehicle‟ respectively.
EN-50122 -1997 prescribes the clearance for touching in a straight line from
standing surface against direct contact with live parts of an overhead contact wire
system as well as any live parts on the outside of a vehicle (e.g. current collector,
roof conductor, resistor), accessible to person (without use of any object) as 3.5
meters in public area and 2.75 meters in restricted areas.
All insulators, which are connected to a live part, shall be regarded as a live part
when considering clearance dimensions in EN 50122.
Fig. 203-38
Fig. 203-39
i. Straight Line Clearance from upper portion of horn of Panto (in raised
conditions) to the nearest platform area = 3495
ii. Straight Line Clearance from lowest portion of the horn of Panto (in raised
conditions) to the nearest platform area = 3512
iii. Straight Line Clearance from Contact Wire to the nearest portion of the
Platform coping= 3663
iv. Straight Line Clearance from Contact Wire (with 200 mm stagger) to the
nearest portion of the Platform coping= 3572
Detailed analysis shown above indicated that the Contact wire height of 4318 mm
provides safety clearance of 2750 mm or more in a restricted area but clearance
of 3500 mm in public areas (platform) is available only if the half width of the
pantograph is limited to 800 mm or alternatively, obstruction panels are provided.
Thus with 25 kV AC rigid catenary system inside the tunnel, the minimum contact
wire height of 4318 mm for underground corridor was found feasible and the
pantograph pan width was reduced from existing 2070 mm to 1600 mm.
Based on the above discussions, DMRC has adopted the following minimum
electrical clearances inside the tunnel for 25 kV traction:
Comparison for RIGID OCS in Phase-1, Phase-2, Airport Line and Phase-III
Sl.
Detail Phase-I Phase-II Airport Line Phase-III
No.
Furrer &
1 Design Railtech Furrer & Frey Railtech Frey and
Siemens
2 Design Speed 95 kmph 95 kmph 135 kmph 95 kmph
The conductor rail The conductor rail Mid
is fixed to the arm Mid Anchor plate is fixed to the arm Anchor
Anti creep
3 by means of one with Anti creep by means of one plate with
arrangement
clamp at the side wire used. clamp at the side Anticreep
of the arm. of the arm. wire used.
Silicon Silicon
Porcelain Silicon composite
Insulators composite composite
insulators insulators
insulators insulators
5 Typical Span 10 m 11 m 7.5 m 11 m
length
Electrical Electrical
Section Insulator separation Section Insulator separation
Section manufactured by achieved manufactured by achieved
6
Insulator M/s. through M/s. through
Railtech , France insulated Railtech, France insulated
overlaps overlaps
Gliding
Cantilever Hinged type of Gliding type Hinged type of
7 type
support type support support support
support
150 mm2
8 Jumpers 130 mm2 Cu 2
150 mm Cu 2
130 mm Cu Cu, 95
mm2 Cu
Typical Interval
between Normally under Maximum
9 480-500 m max 258 m max
expansion 250 m 500 m
joints
240 mm2
240 mm2 single single
240 mm2 single 240 mm2 single
10 Feeder cables core copper core
core copper cable core copper cable
cable copper
cable
150 mm2
240 mm2 bare
Tunnel earth Copper
11 stranded copper 150 mm2 Copper 93.3 mm2 ACSR
Wire(TEW) 240 mm2
conductor
Aluminium
70 mm2
Copper
Overhead
70 mm2, flexible mm2
12 Protection 70 mm2 Copper 93.3 mm2 ACSR
copper conductor Aluminium
Cable(OPC)
150 mm2
Aluminium
Return
240 mm2 240 mm2 240 mm2
13 Conductor 93.3 mm2 ACSR
Aluminium Aluminium Aluminium
(RC)
Typical
11 m to
14 Conductor rail 10 m 11.9 m 10 m
11.9 m
length
thermal expansion, the clamping force is so high that there is equal thermal
expansion and contraction in both.
i. The smaller wheels of the contact wire insertion device run on the rib sat
the lower part of the CR profile.
ii. With the bigger spreader wheels, the profile is locally opened.
iii. With the central roller, which is adjustable in height, the contact wire is
lifted so that the grooves of the contact wire are clamped in the CR profile
once the insertion device has passed.
The contact wire insertion device is pulled with the help of a rail vehicle and the
speed of insertion is around 5km/hr.
The contact wire insertion device needs almost no maintenance. It is
recommended to lubricate the axis of the spreader wheels with a little ordinary
machine oil from time to time and to store it in a dry place.
Greasing Pump
The contact wire is greased as an additional precaution to prevent corrosion
damage resulting from direct contact between copper and aluminium.
The grease has a protective effect but allows current flow between aluminium
and copper because it contains a high percentage of zinc. A special grease pump
is necessary due to the high viscosity of the grease. This grease pump is
electrically operated.
Short sections of contact wire can also be greased by hand. Although the grease
is not dangerous, it is recommended to use gloves if greasing by hand.
The arrangement of the greasing equipment is shown below and consists mainly
of a grease sleeve with stripper and a grease cylinder with pump.
iii. Smoothen the end of the contact wire with a file to ensure that there are
no sharp edges which could damage the plastic rings inside the grease
sleeve and the stripper.
iv. Contact wire is inserted through grease sleeve, stripper and contact
insertion device into the CR.
v. A bucket is installed under the stripper to collect excess grease. The
grease can be re-used again.
vi. The pump is put in operation.
vii. The sleeve is slowly moved back and forth until the grease appears.
viii. As soon as the grease begins to appear behind the sleeve, the greasing
of the contact wire can begin.
ix. The pumping has to be ceased if the contact wire insertion has to be
stopped. Otherwise, the grease will continue to come out of the sleeve.
Sparking occurs when there is loss of contact (or improper contact) between the
pantograph and the contact wire. The common causes attributable to the Rigid
OCS are:
i. Improper adjustment of Conductor Rail
The periodic current collection tests would reveal points where sparking takes
place. Apart from investigating and rectifying the cause of such sparking, it is also
important that the roughened surface of the contact wire be attended to, failing
which, there will be further deterioration, with successive passage of pantographs
resulting in reduced life of contact wire.
The Contact Wire is held by Conductor rails by clamping the grooves of the
Contact Wire. Aluminium rails have substantial current carrying capacity in itself
and thus larger wear of contact wire can be allowed based on the heating effect
of the current on the conductor rail and possibility of grooving on the rolling stock
pantograph due to the edges of the conductor rail.
The thickness of new contact wire is 14.50 mm. In general, it will be necessary to
replace contact wire when it has worn to a thickness of 9.8 mm which is almost
30% wear as shown below:
Fig. 203-43
Based on the inputs from other manufacturers, DMRC is also considering
allowing higher wear of 36% to 43% at which 1.5 mm clearance will be available
between edge of Aluminium conductor rail and contact wire plane section to
avoid grooves on the Panto graph as shown below:
It is important to measure and record the wear of contact wire at the known hard
spots and at a few selected locations where heavy wear may be expected, so as
to keep a watch on the rate of wear. Observations have indicated the wear of
contact wire at train starting point of the station is high where the train picks up
speed.
In addition to the known hard spots, the wire thickness may be measured at one
or two points between each pair of stations where speed is maximum. These
measurements should be taken at the time of yearly maintenance and recorded
in a register. When the average wire thickness approaches the condemning
thickness, the number of points where measurement is taken may be increased
and one location in each tension length may be covered in addition to the known
hard spots.
Catenary Track Motor Car, Tower Wagon, Catenary Maintenance Vehicle, Rigid
OCS Motor Vehicle are used interchangeably at various locations in DMRC's
ACTM. This vehicle is rail mounted, self propelled vehicle which is used for
maintenance of Flexible OHE and Rigid OCS.
The Cars should carry necessary tools for maintenance of Flexible OHE/Rigid
OCS for attending the breakdowns, such as tackles, straining screws, clamps,
ropes, minimum of two ladders as well as an adequate stock of insulators,
lengths of contact and Catenary wires and other Flexible OHE/ Rigid OCS
fittings. An approved list of tools and equipment to be carried in each car has
been issued. SSE/SE (OHE) shall ensure that tools and equipment as per the
approved list are always available in the car.
In addition, a road vehicle with all tools and tackles should always be kept in
readiness at the depot to reach the site of accident/ breakdown wherever faster
road access is available. Following important maintenance guidelines need to be
ensured:
i. Mechanical inspection of the bogies and running gear of each car shall be
done by Rolling Stock (RS) department quarterly.
ii. The SSE/SE (OHE) in charge of the car will advise RS department the
date on which it is required to be inspected and running repairs to be
carried out. He will also arrange for stencilling the date of examination on
the car. The POH of the car shall be done as per recommendations of
OEM.
The day-to-day maintenance of the diesel engines and driving gear of the car will
be the responsibility of the SSE/SE (OHE) concerned. The OHE inspection car
drivers/shift supervisor should carry out the daily maintenance
General
The movement of Catenary Maintenance Vehicle is governed by GR and
Procedure Orders issued.
i. Authorization: No Catenary Maintenance Vehicle can be operated by
any person unless he is specifically authorised to do so after he has been
trained and examined for his knowledge of the rules prescribed. The
Driving
i. Catenary Maintenance Vehicle shall be driven only by an authorized
person, and no person shall be so authorized unless he has knowledge of
the section (Road and Signals) on which the car is to be operated and is
conversant with the operation and maintenance of car. He should also be
in possession of competency certificate for the purpose.
ii. The Catenary Maintenance Vehicle shall be driven at a speed not
exceeding 10 km/h when checking contact wire level and stagger.
iii. If the Catenary Maintenance Vehicle is driven for other than recording
operations, the speed should not exceed the permissible speed limit
subject to the speed restrictions imposed in the section and safety
circulars in-vogue.
iv. In addition to regular CMV operators, the SSE/SE should also try to train
few other staffs for exigency purposes.
Pantograph Operation
i. The pantograph mounted on the roof of the Catenary Maintenance
Vehicle is electrically connected to the under frame by means of a cable
connection. This cable connection should be checked before starting any
operation for checking and adjustment of Flexible OHE/Rigid OCS.
ii. The pantograph should normally be kept in the fully lowered position and
clamped securely by means of the special clamp provided for the
purpose. No string, cord, etc. shall be used for the purpose.
iii. Before any person goes up to the roof of the Catenary Maintenance
Vehicle for commencing inspection and adjustment, the concerned
section of the Flexible OHE shall be made dead and earthed on either
sides. Additional earths shall be provided where necessary. An authorized
person not lower in rank than Maintainer shall then go up on the roof and
remove the clamps to release the pantograph.
iv. Under no circumstances should Catenary Maintenance Vehicle be worked
with the pantograph raised without an earth on either side of it on the
section of the Flexible OHE in which it is to be worked.
v. In order to ensure that the pantograph does not enter a section where the
Flexible OHE is live, the Catenary Maintenance Vehicle shall be protected
on both the sides with red banner flags and other signal flags, as required.
vi. Before start of work the Operator of Catenary Maintenance Vehicle shall
be fully informed regarding the section, of which, power block is taken.
vii. At the end of the Inspection and checking, the pantograph, shall be
lowered and clamped by an authorized person not lower in rank than a
Maintainer working on the roof after earthing the Flexible OHE of the track
on which the CMV operating. The earths on the Flexible OHE near the
CMV shall then be removed after all persons working on the platform/ Jib
& Cradle have come down.
i. In order to achieve high reliability and aim of Zero Defect Flexible OHE, and
to ensure effective checks on the maintenance work, a minimum schedule of
inspections to be carried out each month by the Officers and Senior
Subordinate in-charge of operation and maintenance of Flexible OHE and
associated system, is indicated at Annexure 3-01A.
ii. The schedule of inspections is the minimum quota for each official and should
be independent of other tasks. These will not be of routine nature but shall be
carried out in depth to identify:
a. Deficiencies and shortcomings.
b. Lack of skill amongst staff.
c. Inadequacies in maintenance facilities
d. Constraints experienced
e. Conditions of environment leading to poor quality of work.
iii. The inspecting officials should programme their inspections in such a manner
as to cover the widest areas in their jurisdiction over the year and so stagger
the inspections so as to avoid repeated inspections of the same section, in a
very short time while neglecting other areas. A brief for various inspections is
indicated at Annexure 3-02A.
203-38 General
iv. The periodicity of schedules laid down below applies to the majority of
installations. The periodicity may however, be modified by Dy. HOD
(Traction/O&M) or HOD (Electrical/O&M), where local conditions so warrant.
v. As regards new equipments, if schedules, have not been drawn up, tentative
schedules may be evolved based on the Original Equipment Manufacturer‟s
guidelines, keeping in the view the local conditions also and with the approval
of Dy. HOD (Traction/O&M).
Foot patrolling can only be done during non-traffic hours. The patrolman will take
permission to enter in the section from the Station Controller with clear indication
whether he will proceed to the next station or will come back after finishing his
work. No train movement will be permitted unless the patrolman has arrived at his
predefined destination.
n. Number plates
o. Any other abnormal/unusual situation
v. Major defects noticed by the Maintainers, which endanger safety, shall be
reported forthwith to TPC through the mobile/Tetra communication. Full
details should be given to enable the TPC to decide on the course of
action to be taken and if required to regulate train movements in the
affected section.
vi. The Maintainers should himself attend to and rectify such minor defects,
which can be rectified by him on the spot without special assistance. To
facilitate this, he shall carry with him a few essential tools. A report shall
be prepared regarding defects in prescribed format (Annexure 3.03A)
and entered by him in a Register maintained for the purpose in the depot.
The supervisor in charge of the depot will carefully scrutinize the Report/
Register and take prompt action to rectify defects reported, making
suitable entries in the Register.
A video camera with night vision and recording facility can be fixed on the roof of
the train for current collection test, so that it can capture the complete view of
pantograph interaction with Flexible OHE. A display screen connected to camera,
able to show real time view, may be installed in the inspection vehicle to observe
the sparking. Above arrangement for current collection is done by Rolling Stock
(RS wing). During current collection test (in nonrevenue hours), one staff is
deputed in driving cab to announce the approaching location by using PA system
of the train. The location where the sparking is observed and the severity of the
sparking should be immediately noted down by the Flexible OHE supervisor
jointly with RS staff. A report of such locations is prepared of complete section in
prescribed format. Flexible OHE at the sparking location should be checked up
as soon as possible to find out and eliminate the cause of sparking. Compliance
report for attending the sparking location recorded during current collection test
shall be submitted by Flexible OHE In-charge SSE/SE (OHE) at the earliest.
The current collection tests as above should be carried out by SSE/SE (OHE)
once in 6 months over his entire section.
While the majority of items require attention only during Annual Maintenance and
Periodical Overhaul, items listed below will require more frequent attention as
indicated against each:
Insulators
Generally insulators need cleaning along with the maintenance schedule. At
locations subject to smoke pollution or pollution due to industrial dust/chemicals,
the frequency of cleaning will have to be fixed based on the extent of such
pollution. Where pollution is heavy, cleaning may have to be done more
frequently. Polluted zones of complete section are to be identified by officer In-
charge and cleaning of insulators is to be done before monsoon and winter
season.
Section Insulators
Section insulators on the main lines such as at neutral sections and yards/depot
should be attended to as under once in three months or as per maintenance
scheduled issued.-
i. Clean Core insulators with soapy water, rinse thoroughly with potable
water. Use dry and fluff less cloth. Replace Section Insulator, if badly
chipped or even slightly cracked.
ii. Check runners for flash-marks. Carbon deposition on runners is to be
cleaned by carbon cleaner.
iii. Check level of the assembly and adjust as required. Longitudinal and
transverse parallelism with regards to running plane should be checked
and corrected if necessary.
iv. Diameter of contact wire at both ends of SI is to be measured and
recorded. Check for excessive contact wire wear near anchor clamps.
v. All nuts, bolts, check nuts and split pins of runners and droppers are to be
checked and tightened properly if required.
vi. Smooth gliding of pantograph underneath SI is to be checked and any
hitting or problem in smooth transition is to be adjusted by adjustable
droppers.
Bi-metallic clamps
The condition of junctions shall be checked by Thermal imaging camera. The hot
spot hence noticed shall be immediately attended in next available power block.
Bi metallic strip wherever provided shall be replaced with a new one. Yearly
checking of condition of bimetallic strip provided in Switchgears of Switching post
shall be carried out. All the worn out strips shall be replaced.
Earth Connections
Apart from general inspection of bond and earthing connections during foot-
patrolling, all such connections should be specially checked for continuity and
soundness of connections through Impedance bond/ITL with BEC and OPC once
in a year. Particulars of all earthing connections should be entered in a Register
station-wise for each section and the dates of Yearly inspection entered therein.
Feeders
Foot-patrolling of 25 kV feeders should be carried out every month. During this
check, the Maintainers shall also check that safety guards provided under the
feeders are properly earthed, if the clearances are adequate and caution notice
boards are in position.
Bird nests
Vigil should be exercised especially during the nesting season and the nests
removed as soon as possible and as per instructions issued in O&M.
Pre-monsoon checks
Some of the items to be attended to are:
i. All pulley type ATD‟s shall be checked for their free movement & X-Y
values adjusted if required.
ii. All tree branches in the section shall be trimmed to avoid any untoward
incident.
iii. Earth continuity and earth resistance shall be checked for all equipments
installed in section and recorded, rectification action shall be taken as
required.
iv. Special check shall be carried out to ensure working of isolators.
v. Where there is dripping of water on Flexible OHE/Rigid OCS from
overline structure the same should immediately be informed to Civil
Engineering department.
vi. Mast is to be checked for any leaning at grade section.
vii. PVC sleeve on BEC wire under track circuited rail to be checked for its
healthiness to avoid signal failures due to short circuiting.
Any special instruction, issued time to time, shall be complied.
ix. Clean all insulators and carefully check for cracks and broken sheds. If
more than 2 sheds are broken or there is any crack on the core, the
insulator should be replaced.
x. Check and adjust heights and staggers on the basis of setting distance
and rail level marked. Close co- ordination with SE/P-Way is required for
keeping the P- Way as per SEDs.
xi. Check presence and condition of caution notice boards, number plates,
coasting boards, etc. Replace the boards as required. Ensure that they
are all well secured.
xii. Ensure that the drain holes in the tubes are free and not clogged.
xiii. As the bracket is articulated, check the position with reference to the axis
of the mast. The position will vary with temperature and distance from
anti-creep. The register arm and steady arm should as far as possible be
in the same plane as the bracket.
Droppers
i. Droppers should be vertical and tight. Replace if found loose with
appropriate dropper.
ii. Check droppers for any damage or rubbing at multi cantilever location.
Correct if required.
Turn outs
The point at which one track separates/meets another track is called Turnout.
From Flexible OHE point of view, turnouts are provided for smooth transition of
pantograph during movement of train from main line to branch line or vice-versa.
i. With OHE Inspection Car running on main line, check if pantograph glides
smoothly under the main line OHE without any contact to OHE of loop
line. While moving on main line to branch line (Turnout) or vice versa,
smooth transition of pantograph from main line to turnout wire at
appropriate take-off must occur. Take-off/Take-on of main line wire should
be close to 55 cm marking on the pantograph.
ii. Check stagger of both the OHEs at turn outs. It shall not normally exceed
300 mm.
iii. Check that the main line OHE of overlap type turn out is about 30-50 mm
below that of the turnout OHE.
iv. Check up rail level and setting distance of the obligatory mast.
v. Check up for hard spots near rigid droppers, if any.
Isolators:
i. Check number plates for cleanliness and security.
Overlap (IOL/UIOL)
Where two OHE wire lengths are overlapped with each other with adequate
horizontal separation (500 mm for IOL (insulated overlap) & 200 mm for UIOL
(un-insulated overlap)) and suitable stagger is known as overlap. The overlap is
so arranged that both OHE‟s are available to the pantograph for minimum 2
meter at the same level on either direction of central mast. Thereafter the OHE‟s
are raised gradually by 500 mm and held at intermediate mast by RRA Clamp
(Raised Register Arm ).
i. Check height and stagger of OHE In the overlap section.
ii. Check whether the normal minimum clearance of 500 mm is available
between the two OHEs in an insulated overlap and 200 mm in an un-
insulated overlap.
iii. Check whether the lifting of out-of run OHE is correct.
iv. Check that parallel running of contact wires in the overlap for a minimum 2
m in the panto sweep region.
v. Check jumpers for any damage or signs of heating at jumper fittings / PG
clamps. Check the tightness of RRA clamp and jumper fittings.
Neutral Sections
Neutral Sections form an important check point during various OHE inspections
and maintenance schedules.
vi. Check the condition of adjuster, earthing jumper, splices, lock nut
pins etc.
vii. Check the hogging. If found improper then adjust it.
ATD
In Depots/Yards:
i. Check all bonds and replace defective or missing bonds. Paint all
bonds.
ii. Inspect earths (Earth Pits) and record earth resistance. Earths (Earth
Pits) having resistance of over 10 ohm should be attended to.
In main line
i. Check all connections and condition of BEC, plinth jumpers.
ii. All ITL/ Impedance bonds connections with RC, OPC, BEC and rails
are to be checked for their healthiness. Check for any sign of heating.
Attend, if required.
Feeder Lines
i. Check earthing of towers.
ii. Measure and record earthing resistance of towers.
iii. Clean insulators and replace those, which are cracked or chipped.
In case of Metro Rail, non-traffic hours are available for the purpose of combined
maintenance. Therefore, it is all the more necessary that annual maintenance
schedules can best be organized by adopting the system of Integrated Blocks.
Simultaneous work could be carried out by track, signal, and OHE/PSI staff
during night hours. Roster for the maintenance staff should be designed
accordingly.
of erection and again at the end of 12 months. Thereafter the tension should be
checked up once in 2 years and re-tensioning done as required.
The bottom line of carrying out any scheduled maintenance is that once it is
carried out that equipment should not fail till the next schedule falls due. The aim
of POH is to recondition and restore the installation in the condition it was when it
was first commissioned, whereas preventive maintenance has to take care of the
wear and tear during normal service and forestalling possible failures by regular
inspection and prompt attention.
The work involved during POH is somewhat greater in scope than the pre-
commissioning tests, since after years of service many parts would have suffered
wear and tear, of which necessary adjustments will have to be made or repairs
done to make good the wear, or the irreparable items replaced.
Periodicity of POH
Periodicity of POH is being kept as 4.5 years presently. For planning of POH, the
entire line should be divided into smaller sections. Pollution levels at different
sections shall be other criteria for reducing periodicity of POH.
As far as possible, gangs for the work should be earmarked so that a uniform
standard is achieved. All POH work should be done under the direct supervision
of a supervisor not lower in rank than a SE.
In addition to the items detailed under annual maintenance, the following items
should be attended to during POH:
The PG Clamps of contact wire, catenary wire & G-jumper shall be replaced with
new PG Clamp during POH.
Note: In all the cases ensure that proper PG Clamp is used as per size of cable.
The released PG Clamp may be treated as scrap & should not be used further.
Overline Structures
Check the height and gradient of the contact wire and tally the same with 'as
erected'.
Turn outs: Check the position of the contact wire with respect to the track for
compliance with SED.
General
i. During POH, fittings, which do not provide prescribed margin of
adjustment and proper fitting should be replaced.
ii. All fittings on masts should be checked against "as erected" drawings and
any variation should be recorded and reported to Assistant Manager or
Manager (Traction)/O&M for changing the drawings.
iii. The position of splice should be recorded in the relevant lay out plans.
iv. In case of a major OHE break down, it is advisable to examine critically
the bracket assemblies in about 8 to 10 spans on either side for cracks,
twists, bends or other defects which may cause failures later on.
v. Aluminium bronze fittings, bolts and nuts should be cleaned and carefully
examined, if necessary, with a magnifying glass. Particular care should be
taken to see that the threads are in good condition. The cracked fittings
should invariably be discarded.
vi. All G.I. fittings and pipes should be examined for deterioration of
galvanization. Minor chippings may be repaired by using cold galvanizing
paint. (Sand or emery paper should never be used for cleaning).
vii. The regulating equipment should be dismantled and every part should be
cleaned. Any grazing or rubbing on pulleys should either be repaired if
possible or the damaged equipment should be replaced. All lubricating
holes should be free for passage of grease. The stainless steel rope
should be closely examined for damage to the strands. Particular
attention should be given to the end fittings on the stainless steel rope.
Only approved lubricant should be used for regulating equipment
components.
Depending upon the condition of the fittings, rehabilitation of the OHE may be
undertaken after a period of 20 years. HOD (Electrical)/O&M may decide the
assemblies to be replaced after a special drive.
Fig. 203-47
Fig. 203-48
Section Insulators
Periodicity: Section insulators should be checked half yearly and
insulator should be cleaned.
SI is provided only in Phase-I sections (VV to CTST in line-2, RCK to
MDHS in Line-3). In Phase-II sections Insulated overlaps are provided.
Activities in cleaning of SI:
i. Check the wear of the contact shoes.
ii. Check up runners for flash mark.
iii. Check up level of the assembly and adjust as required.
iv. Check if pantograph passes under the section insulator smoothly.
Bi-metallic clamps
Periodicity: 6 months.
Check for tightness and signs of overheating.
Earth Connections:
Periodicity: One year
Apart from general inspection of earth connections during foot patrolling,
all earth connections should be specially checked for continuity and
soundness of connections once in a year.
ii. Check all steel parts and remove rust of any painted steel work
wherever found. Rusty portions after cleaning must be given two coats
of zinc chromate primer followed by aluminium paint.
iii. In the curve with a super elevation of the track, the rail-bar must be
perpendicular at the current collector bow of the pantograph to ensure
good current collection
iv. Check height and stagger at random locations to observe the
behaviour of supports.
v. Check the insulator condition and clean the insulators.
Hanger Clamp
i. Check that each threaded M16 bolt rod is vertical & not in torsion
ii. Check closing of the hanger clamp and the torque value C = 8 Nm
iii. Check the state of the Teflon bearing
Fig. 203-49
Splice Assembly
i. Check the torque value of the 16 bolts with torque wrench: C = 20 Nm.
ii. Check that there is a washer between the aluminium profile and the
head of the bolt.
General
i. Check all Earth Connections thoroughly. Defects of Earth Connections
must be rectified and missing Cables and Connections to be replaced.
ii. Inspect and tighten all G I bolts, SS bolts.
iii. Inspect all galvanized parts and fittings. Where galvanization is found
to be chipped off, the same or pipe may be replaced. Minor chippings
may be repaired using "cold galvanizing paint".
iv. Clean all insulators; carefully check for cracks and replace insulators
which are cracked or chipped. Check tightness of bolts, nuts.
v. Check and adjust height and stagger.
vi. Check presence of prescribed sign boards such as caution notice
boards, number plates, Clearance Boards, etc. Ensure that they are
all well secured.
Contact Wire
Check the contact surface and note if there are any arcing spots causing
damage to contact wire .If the contact wire is damaged & some portion needs
replacement, the replacement piece/should not be less than 2 m length. Find
out the reasons for damage & take necessary action, which may be due to
hard point/bad adjustment.
Stranded Conductors
i. Thoroughly examine condition of OPC, RC Conductor and tunnel
Earth wires, particularly for broken strands.
ii. Any stranded conductors should be spliced if more than 20% of the
strands are found broken. If less than 20% of strands are cut, the
conductor shall be wrapped with tape or binding wire to prevent
strands coming out.
iii. Check jumpers and jumper clamps and their tightness. If necessary,
the new clamps to be provided for the defective clamps, after thorough
inspection.
Transition Element
i. Check the torque value of the 7 bolts that ensure the pinching profile.
ii. Check the torque value of 6 bolts of the contact wire splice.
iii. The contact wire splice must be in contact with the side of the profile
on the conventional catenary side.
iv. Check that the contact wire is perfectly straight at the exit of the
transition element and check also the position of element regarding
the track.
Fig. 203-50
Turnouts/Crossovers
i. With catenary vehicle running on main line, check up if the loop or
secondary line OCS contact wire passes smoothly under the panto.
ii. With catenary vehicle running on loop lines, secondary track check up
if the main line OCS passes smoothly under the panto.
iii. Check up stagger at turn out of both the OCS with respect to both the
loop and main lines.
Anchor clamp
i. Check the torque Value (8 Nm)
ii. Check that each anchor clamp is in contact with the hanger clamp.
iii. Check that each clamp is well inserted in the profile ribs and in contact
with the top surface of the profile.
iv. Check that the surface of the aluminium profile is not marked by the
anchor Clamp.
Earth Connector:
Check the torque value (50 Nm) and contact area.
Protective Cover
i. Check that the cover is well inserted. If not replace it.
ii. Replace the cover if found damaged.
iii. Check that the cover is not too dirty, clean it with a rag.
Air gap
i. Check up height and stagger of OCS in the Air Gaps.
ii. Check up whether the normal minimum horizontal separation of 400 is
available between the two OCS in an insulated overlap and 200 mm in
the case of un-insulated overlap.
vi. Check for all the connections of ITL, MET & TEW. Inspect all Earthing
stations and record the earth resistance values and if the resistance is
more than limit it should be attended/treated.
RC and OPC
Check for broken strands at the clamps & for proper. The Sag in the Spans
should be checked.
Air Gaps
Check and adjust if necessary the position of conductor Rails with respect to
tracks to comply with approved drawings.
Turnouts /Crossovers:
Carefully check and adjust the position of the conductor Rails with respect to
the track and for compliance with approved drawings.
Section Insulators
The Section insulator provides Electrical separation in OCS but maintains
Mechanical continuity for uninterrupted Power Supply to the Rolling Stock
when traversed by it. Normally OCS on both sides of the Section Insulator
remains energized. OCS on one or other side of the Section insulator can be
made dead by switching operation and when this is done, no pantograph shall
be allowed to approach or cross the Section insulator which will otherwise
cause fault in OCS system. Section insulators are used
i. On crossovers,
ii. In sidings / Loop lines,
iii. On Mainlines where Air Gaps are difficult to create.
Fig. 203-51
Fig. 203-52
Feeder connections
Check the connection of the feeder that should be proper.
Fig. 203-53
i. The following rules are supplementary to the General Rules and other safety
instructions of this ACTM.
ii. Printed boards containing instructions regarding treatment of persons
suffering from electric shock should be exhibited in every OHE maintenance
depot, equipment room, switching station, Catenary Track Motor Car/ OHE
Maintenance car depot, and also in offices of Station Controllers.
iii. First Aid Boxes should be kept at every maintenance depot, in OHE
Inspection Car, breakdown vehicle and wiring train.
Ropes, Come-along clamps, Tirfor, Pull-lift etc. should be tested once in three
months, in the presence of a SSE/SE/ASE In-charge, and record of such tests
maintained in each depot.
i. The SSE/SE (OHE) or other officials supervising OHE work shall have with
him a complete set of structure erection drawings, lay out plans, sectioning'
diagram and general supply diagram etc. pertaining to the overhead
equipment under his charge.
ii. It shall be the responsibility of the SSE/SE/ASE/JE (OHE) or in his absence
the senior-most official in-charge of the work to ensure that all safety rules
prescribed are actually observed by the staff when carrying out work on
traction installations. It shall be the duty of the supervisor to remind the staff
periodically of the various safety rules to be observed at work site. Mock drills,
as prescribed in mock drill booklet issued) are to be carried out periodically in
depots in presence of SSE/SE (OHE) to ensure the safe working and to
enhance the skills of staff. Records of same are to be kept in his office.
Before commencing work on any part of the dead OHE or within 2 m of live OHE,
a permit to work shall be obtained from TPC or other authorized person.
Standard Procedures order issued may be adhered to.
i. All metallic parts within reach (either directly or through tools etc.) shall be
earthed, after they are de-energised.
ii. Each working party shall be protected by at least two independent earths, one
on each side of a working party.
iii. Earthing should be done individually by each working party as close to the
work spot as possible. The distance between the two earths shall not exceed
1 km.
iv. If the distance between the working parties exceeds 100 m, intermediate
earths shall be provided in such a manner so as to ensure that the distance
between earths does not exceed 100 m.
v. Even when earthing is provided by isolator switches with earthing heels,
additional temporary earths, as above, shall also be provided.
i. During Emergency Blocks, men shall be posted on both sides of the site
of work to warn the working party of any approaching train on the same
track and adjacent track.
ii. The permit-to-work shall be obtained prior to commencing work to make
sure that power supply has been switched off.
iii. For providing temporary earth on the OHE or other equipment after it has
been made dead, only discharge rod, specially designed for this purpose,
alone should be used. The cable shall be flexible and should have
adequate cross-section to be able to withstand short circuit currents.
iv. Fix the earthing-clamp securely to a mast at least one span away on one
side of the work site after making sure that the mast-to-OPC bond of this
mast is intact. The mast-end or rail-end clamp of the discharge /earthing
pole assembly should be checked for tightness just before connecting the
top clamp on to the OHE.
v. Hook securely with a snap action the top clamp of discharge/earthing pole
assembly to the OHE conductor close to the mast/ structure and tie the
earthing pole to the mast/ structure. Never hook on the top hook of the
earthing cable to the OHE, till the other end has been first connected to
earth.
vi. The earthing clamps should always be fixed to the mast/structure first and
then the top clamp should be hooked to the OHE which is to be earthed.
vii. Repeat operations iv. & v. for the second temporary earth on the other
side of the working party.
viii. After temporary earths have been fixed on the OHE on both sides of the
work site, staff may proceed with the maintenance work.
ix. After work is completed and men, materials and tools have been removed
and the OHE is clear, the above earthing rods may be removed in the
reverse order i.e., first remove the hook on the OHE and then the clamp
fixed to the rail or mast/structure. After warning all staff that supply will be
restored and that they should keep away from live equipment, the permit-
to-work may be returned and supply restored.
i. The continuity of the cable connection between the top clamp and the
earthing clamp shall be checked by shift in charge once in a month.
ii. Cable used should be of copper of size75 mm2 (total 248 strands).
iii. Cable should be renewed if more than 20% strands are broken. (i.e. 50
strands out of total 248 strands) During use, cable should be continually
examined for fraying and breakage of strands.
iv. SSE/SE (OHE) should inspect Discharge/Earthing pole assembly once in two
months.
v. During accidents when slewing the OHE and in similar circumstances, the
discharge/ earthing pole assembly should be provided at a location where it is
not likely to be interfering with the crane working or due to any work on the
track.
When work is to be carried out on OHE or conductors, which are not electrically
bonded, following additional precautions are required:
i. The two sections of conductors or ends of conductor, which may have
snapped may be at different potentials. Each end should, therefore, be
separately earthed at two points after switching off supply to both parts of
the OHE or conductor.
ii. This precaution should also be observed when working on or in the
vicinity of a sectioning point and cut-in insulators.
iii. Neutral Sections should be treated as live equipment and earthed
separately at two points on either side of the work party before
commencing the work.
iv. When work is to be carried out on an isolator, both sides of the isolator
should be earthed at two points.
At the work-site, staffs is advised to wear helmets to protect their heads against
any tools or equipment which may drop down accidentally, as well as to minimize
head injury in case of accidental fall from a height.
i. The useful cross section of a conductor shall not be reduced while making
joints.
ii. Any contact with conductors, which are not specifically earthed, is forbidden.
iii. The strength of the anchoring rope should be not less than that of the cable to
be anchored.
No work on any span of any overhead line (LT power line or other line) running
parallel to an electrified track where the minimum distance between the nearest
conductor of the overhead line and the centre-line of the nearest electrified rack
is less than 8m,should be done without switching off power from the 25 kV
traction line (in addition to making dead and earthing the overhead line on which
work is to be carried out, in the normal manner) excepting for the following
specific items for work :
i. Replacement of lamps, if below line.
ii. Painting of structures / poles upto a distance of 2 m from the live wires of
the power line.
iii. Reinforcement of foundations where such reinforcement does not involve
any prior weakening of the foundation at any time during the work.
203-63 Isolators
xx. Register Main line discharge rod maintenance as per Proforma No. 3-20.
xxi. Register of Competency Register as per Proforma No. 3-21.
xxii. Register of CB Tripping as per Proforma No. 3-22.
xxiii. Register of Tools and plants for shift duty as per Proforma No. 3-23.
xxiv. Train Foot Plating Register Proforma No. 3-24.
xxv. Register of Staff training as per Proforma No. 3-25.
xxvi. Register of Break Down Vehicle (Tools & Material) as per Proforma No.
3-26.
xxvii. Register of Joint Panto Inspection as per Proforma No. 3-27.
xxviii. Register of Bird nest & kite thread Removal as per Proforma No. 3-28.
xxix. Register of Jumper as per Proforma No. 3-29.
xxx. Register of Neutral Section as per Proforma No. 3-30.
xxxi. Register of Mock drill as per Proforma No. 3-31.
Registers may also be maintained for any other additional items in the Proforma
prescribed by Dy. HOD (Traction)/O&M. The Supervisor of the depot will be held
responsible for ensuring that these registers are maintained up-to-date. Officers
and Senior Supervisors during their inspections should scrutinize these registers
and initial a few important entries. The above Proforma are common for both
Flexible OHE and Rigid OCS as per their applicability.
Manager/AM
S.No. Nature of Inspection SSE/SE/ASE
(Traction)
1 Cab Inspection 2 4
2 OHE Inspection Car 1 4
3 OHE Depot 1 4
4 Station/ASS 4 6
5 RSS/AMS/TSS 1 2
6 SSP/SS 1 2
7 SP 1 1
8 Current Collection Half Yearly Half Yearly
9 Platform SI inspection --- 6
Manager/AM
S.No. Nature of Inspection SSE/SE/ASE
Traction
1 Cab Inspection 2 4
2 Rigid OCS Inspection Car 1 4
3 OHE Depot 1 4
4 Station/ASS 4 6
5 RSS/AMS/TSS 1 2
6 SSP/SS 1 2
7 SP 1 1
8 Current Collection Half Yearly Half Yearly
9 Platform SI inspection 4 6
2 Station
2.1 Station Controller room
i. SWRs with latest correction slips.
ii. Display of traction working diagram and its correctness at SM room & cabins.
iii. Knowledge of traction working of Station Controllers on duty.
iv. Validity of the competency certificate of Station Controllers.
v. Discharge rod
2.2 ASS
i. Fire extinguishers, sand/water buckets, Respiration chart, First Aid Box, Tools &
Plants.
ii. ASS diagram
iii. Cleanliness of ASS
3 Cab Inspection
3.1 Condition of OHE
i. Flashed/damaged insulators
ii. Displaced fittings & droppers
iii. Balance weight in reference to upper & lower limits marked on masts. Ram
extension of Gas ATD.
iv. Number plates, warning board for rusting & tightness.
v. BT Oil leakage and deposits of pollutants on Insulators
4.5 Overlaps
i. Height and stagger of OHE in the overlap section.
ii. Whether normal minimum clearance of 500mm is available between the two
OHEs in insulated overlap and 200 mm in the case of un-insulated overlap.
iii. Check up whether lifting of out-of-run contact wire is correct.
2 Station
2.1 Station Controller room
i. SWRs with latest correction slips.
ii. Display of traction working diagram and its correctness.
iii. Knowledge of traction working of Station Controller on duty.
iv. Validity of the competency certificate of Station Controller.
v. Discharge rod.
2.2 ASS
i. Fire extinguishers, sand/water buckets, Respiration chart, First Aid Box,
Tools & Plants.
ii. ASS diagram.
iii. Cleanliness of ASS.
3 Cab Inspection
3.1 Condition of Rigid OCS
i. Flashed/damaged insulators.
ii. Displaced fittings & jumper connections.
iii. Number plates, warning board for rusting & tightness.
iv. deposits of pollutants on Insulators.
4.5 Overlaps:
i. Height and stagger of Rigid OCS in the overlap section.
ii. Whether normal minimum clearance of 400mm is available between the
two Rigid OCSs in an insulated overlap and 200 mm in the case of un-
insulated overlap.
Depot:
Section:
Name:
ii. Mast deflected away from track other than those already
PORTALS
Checked by
SSE/SE/ASE/JE (OHE)
i. Insulator Damaged
ASSEMBLY
RIGID OCS
SUPPORT
SPAN
OCS
Checked by
SSE/SE/ASE/JE (Rigid OCS)
Cleaning of ST
Half Yearly
and BT
9 As per Polluted zone list. (May and
insulators of
November)
polluted zones
Proforma 3-01
Staff detail
Sl. No. Name Designation Reporting
Time
Block Detail
From To
Power/Traffic Block asked (time)
Power/Traffic granted (time)
Section (location)
Power/Traffic Block cancelled
Work Detail
Progress
Any defect observed
filled in
Sl. during Foot Patrolling/
Work Carried out concern
No. Plating with name of
register
observer
(Yes/No)
Supervisory Detail
Name of Shift In-charge Signature Date
Proforma 3-02
Note - One Page to be allotted for each section (between two adjacent stations)
Proforma 3-03
Kilometre Station
Note -
i. Each km should start with a fresh page.
ii. Type of location should indicate BWA (Balance weight), FTA (Fixed termination),
IR (In-run wire), OOR (Out-of run wire) etc.
iii. When POH is carried out on individual cantilevers, the date should be recorded in
red.
Proforma 3-04
Proforma 3-05
FOB/ROB/Station structure No
Contact Clearances of Clearances as
wire Catenary wire Contact adjusted Contact
height wire height
nd nd Remarks,
Date above st II height st II as per
I End I End if any
rail End adjusted End SED
(cm) (cm)
level (cm) to (cm) (m)
(m)
Line
Span
Push up
Clearance
As per profile
Note:
Each line under FOB/ROB/Station structure is to be allotted a separate page.
Proforma 3-06
Note -
i. Half page to be allotted for each pit.
ii. Earth test should be carried out on a dry day preferably in March/April once a
year.
Proforma 3-07
By
Train Approx Action Remarks
Date whom Location Observation Date
No Time. taken
Done
Note:-
One page to be given to each block section (up and down lines separately).
Proforma 3-08
Implantation (m)
Block Location Line As
Sl. No. Date Remarks
Section No No Actual checked
per SED
Note: -
One page in the Register to be allotted for each location
Proforma 3-09
i. Date of accident/break-down
ii. Station
iii. OHE Locations affected
iv. Details of damages
v. Probable cause
vi. Brief description and remedial action taken
vii. Reference to detailed reports sent
viii. Remarks, if any
Note:-
One page in the register to be allotted for each case.
Proforma 3-10
Date
Adjustme
of Final
Noted value nt Adjustment done by
Date Tensi adjus Te Values Wheth Wheth
required
S.N of on tment m er er Signature of Remar
o Che length Tem p greas replace Sup. ks
Y X/Z Y Turn Catena Contac 0 X/Z
ck m p X/Z C Y ed d
m m m Buc ry wire t Wire mm
C0 mm mm
m m m kle cut Cut
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
Proforma 03-11
Proforma 3-12
Proforma 3-13
Height of
Amount of leaning in Amount of leaning in
HRL mark Action
Date mm at cont. wire level mm at 1.85 m from HRL
S.No Implantation noted taken, if Remarks
Checked
Above rail Towards Away from Towards Away from any
level (+) Track (+) Track(-) Track (+) Track(-)
1 2 3 4 5 6 7 8 9 10
Location:
Type of Mast:
Type of Foundation:
Type of Soil:
Whether the foundation is situated on embankment / cutting, bridge, flyover, tunnel etc
Implantation as per SED:
(N.B\One Page for each masts / location )
Proforma 3-14
Block Section:
1 2 3 4 5 6 7
Proforma 3-15
Section: Location:
Type (UIOL/IOL): HTL/TL (In Meter):
Contact Wire
Stagger
S. Height Parallel
Date Checked by Remarks
No. Run
IR1 IR2 IR1 IR2
1.
2.
Proforma 3-16
Stagger Whether
Height of SI Runner Gap Dia of Sign of
Date of in (mm) Any
S. No. Contact Remark Supervis
Checking Adjustment
East West East West Wire or
Done
2 3 4 5 6 7 8 9 10 11
1
Proforma 3-17
Section/Station: LOCATION:
Type (A/B/C): HTL/TL (in meter):
Gas ATD Sl.No.: Date of commissioning :
Whether
Oil Remarks
Ram Ram Gas
Tem Pressure leaka Ram Date of if any/
S.N Dat Exten Extension Leakage Other defect
p. gauge ge conditio Gas re- Sign of
o. e sion is , if any
(°C) status on n filling Supervis
(mm) as per if any
Ram or
data sheet
Proforma 3-18
Location
No. of Cables from Track
No. of Cables from RC
No. of Cables from OPC
No. of Cables from BEC
Sl.
Date of Checking Defects attended if any Remarks Sign of Supervisor
No.
1.
2.
Proforma 3-19
KM Location Line
1.
2.
Proforma 3-20
Proforma 3-21
Traction Distribution Section
Competency Register
Proforma 3-22
Proforma 3-23
Observation/ Checked
Date and detail Attended by/
S.No. Date of Checking Any defect by/ Remark
of rectification Signature
noticed Signature
Proforma 3-24
Time Name of
Train Name of Remark, if
S.No. Date Section Train Observations Sign.
From To set no. Supervisor any
Operation
Proforma 3-25
Proforma 3-26
Observation/ Checked
Date and detail Recouped by/
S.No. Date of Checking Any deficiency by/ Remark
of recoup Signature
noticed Signature
N.B.:
If any OHE spare is consumed at site, then it has to be recouped on the same day.
Single page to be allotted for particular breakdown Vehicle
Proforma 3-27
Reason of Signature of
Date and Signature of
S.No. Train set no. Panto Observation Supervisor/ Remark, if any
Time Supervisor/ RS
Inspection OHE
Proforma 3-28
Proforma 3-29
Proforma 3-30
Signature:
Name:
SSE/SE/ASE/OHE:
Date
Sl. Items to be
Check List Remarks Observations
No. checked
Proforma 3-31
Format of observation
Date/Time:
Location:
Staff on Duty
Please Tick (√) or (x)
CHAPTER - 4
SUPERVISORY CONTROL AND DATA ACQUISITION
(SCADA) SYSTEM
204-00 Introduction
204-01 SCADA Equipment
204-02 SCADA Software
204-03 Operational Principles
204-04 Transmission Path
204-05 Master Station Equipment
204-06 Man-Machine-Interface: Work Stations
204-07 Large Video Screen (LVS)
204-08 Blue Light Station with Emergency Trip Switch (ETS)
204-09 Transmission and Coding System
204-10 Historical Data Storage
204-11 UPS and Batteries at OCC
204-12 Remote Terminal Unit (RTU),
204-13 Alarm and Event Management in SCADA
204-14 SCADA Equipment Capacity
204-15 Speed of Transmission and Update Time
204-16 Communication Interface
204-17 Substation Automation through Bay Controller
204-18 Airport Line
204-19 Additional features of Phase III SCADA system
204-20 Duties of Supervisor in-charge (SCADA)
204-21 Operation of SCADA Equipment
204-22 Investigation of Failures by Supervisor in-charge
(SCADA)
204-23 Maintenance Schedule
204-00 Introduction
Supervisory, Control and Data Acquisition (SCADA) system has been used in
DMRC for control and monitoring of traction as well as 33KV auxiliary network. If
power supply failure occurs due to any problem in grid supply, power supply is
promptly switched over to alternate source to maintain punctuality of trains.
Remote control of electric traction and auxiliary power supply is supervised and
controlled by Traction Power Controller (TPC) sitting in Operation Control Centre
(OCC).
SCADA system involves:
i. Supervision:
Traction Power Controller (TPC) supervises the receiving sub-stations,
25kV AC traction network as well as 33kV/415V auxiliary sub-stations
from OCC through SCADA system.
ii. Control:
Traction Power Controller (TPC) performs control operations of circuit
breakers, interrupters, isolators and tap changers provided in different
substations as per need.
One common software platform MicroSCADA PRO9.3 is used for control and
monitoring of new lines under phase-2 as well as old lines of phase-1. To achieve
this, SCADA control of phase-1 was shifted to Phase-2 SCADA servers running
on MicroSCADA PRO 9.3 platform. IEC 61850 protocol has been adopted for
receiving substations of Phase-II for bay protection, control & monitoring through
Intelligent Electronic Devices (IEDs) whereas IEC 60870-101 protocol has been
used for remote monitoring and control of auxiliary substations and 25KV traction
network.
i. Remote monitoring:
The TPC supervises RSS, TSS, AMS, ASS and 25KV control posts from
OCC. There are 04 monitors per TPC on which synoptic screen
displaying real time status of substation can be visualized. LVS (Large
Video Screen) is installed for viewing the overview of traction and auxiliary
network. When any abnormality occurs, TPC gets audible/visual alarm
depending upon the criticality of signal.
TPC can control the circuit breakers, isolators and interrupters of RSS,
TSS, AMS, ASS and 25KV control posts from OCC. In case of an
emergency or abnormal situation, the TPC is able to isolate the faulty
section as per prescribed fault segregation procedure. TPC can restore
the normal configuration after the fault has been rectified.
The operating system used is suitable for multi-user, multi- tasking, networking
and real time applications. Functionally speaking, the SCADA system can be
broken down into the following two subsystems:
Second Stand-by
Main Control
Line First Stand-by /
Centre
Local Control
i. Kashmiri Gate/RSS: For
Shadhara to Rithala
OCC/Shastri
Line-1 OCC/Metro Bhawan ii. Rithala RSS (For
Park
Kanhiya Nagar -Rithala
section)
Local SCADA at
i. Jahangir Puri /RSS
OCC/ Shastri ii. Chattarpur/RSS
Line-2 OCC/Metro Bhawan
Park iii. Sushantlok/RSS
iv. New Delhi/RSS
v. Kashmiri Gate/FP
i. Subash nagar/RSS (For
Inderprastha-Dwarka
Sector -9)
ii. Dwarka/RSS (For
OCC/Metro
Line-3/4 OCC/ Shastri Park Inderprastha-Dwarka
Bhawan
Sector -9)
Local SCADA at
i. Inderprastha/RSS
ii. Botanical Garden/RSS
OCC/ Metro Local SCADA at
Line-5 OCC/ Shastri Park
Bhawan i. Mundka/RSS
Local SCADA at
OCC/ Metro
Line-6 OCC/ Shastri Park i. Park street/RSS
Bhawan
ii. Sarita Vihar/RSS
CTPC should ensure that separate user-IDs are issued for every TPC. While handing
over the charge, TPC should log-off and TPC taking over charge should log-in. While
making operation of breaker, user name appears on the event list. In order to prevent
anybody else from using assigned user name and authority profile, assigned user to
always logout while leaving the control room. Logout means that name and user
authority are cleared.
IEC
1 Phase-I L2 (UG) ELIOP Serial 60870-5-
101
IEC
L1 EX. (JLML-DSG) ABB RTU560 Serial 60870-5-
101
IEC
3 Airport Line SIEMENS TCP/IP 60870-5-
104
Optical Fibre cable is used all along the viaduct and tunnel for transmitting the
signals from OCC to Remote Terminal Units (RTU) and vice-versa.
Hardware Configuration:
Operating Supported
Item Description MicroSCADA Software
System Protocols
MAIN SCADA SERVERS and FRONT END SERVER at OCC/SHPK and OCC/MB
ISBT Server
Windows
Make : HP RP570 MicroSCADA 8.4.3 Classic
2003 Server
RI Server
Windows
Make : HP RP570 MicroSCADA 8.4.3 Classic
NT
Local SCADA Server (ND RSS, KG FP)
Windows IEC 60870-5-
Make : HP Sherpa PC
2000 101
Local SCADA Server(JGPI RSS, STLK RSS, BCGN RSS, MUDK RSS, STVR RSS,
AIRPORT RSS/CST RSS)
IEC 60870-5-
Make: PORTWEL Windows
101 & MicroSCADA Pro 9.2
LAXSONS 2003 Server
IEC 61850
SCADA Server and Front End Server at OCC/DW21 and Airport RSS
Windows
IEC 60870-5-
Make : IBM 2003 POWERCC
104
Server
Each main server at OCC interfaces with its front-end processors, multi port
controller and interface convertors for communication with RTUs to provide up-to-
date network data and to issue commands. In case of failure of one computer
system, the ‘hot standby’ system takes over automatically.
Printers are provided to take print-out of events, energy data and graphs as per
need.
Each TPC is provided with 4 monitors which are controlled by 2 work stations.
i. Full graphic colour display of the complete section with relevant indication
of devices can be seen on the monitor of the work-station. The SCADA
software is designed with necessary process display screen to provide
graphical depiction of the power supply network for the Rail/Metro
Corridor. This includes the Receiving Substations (RSS), Auxiliary Main
Substation, Traction Substation, local auxiliary power distribution of RSS,
Auxiliary Substations and 25 kV control posts.
ii. There is separate picture for all the substations showing the single line
diagram of that sub-station. There is navigating buttons for next view and
previous view. The static and dynamic objects are shown in the window
as per the approved drawings.
iii. Apart from individual pictures, overview pictures of traction and auxiliary
systems are provided for each line and are displayed on LVS.
iv. Busbar Coloration: The status of bus bars is red for de-energized, green
for energized, yellow for earthed and magenta for
unknown/communication failure. Busbar coloration is based on PT voltage
for complete OHE section. While in ASS, AMS and RSS, coloration is
based on breaker position indication. Colouring of Traction Network is
done based on Voltage of Traction Line coming from PTs. PTs are
provided in every individual elementary section. When the Voltage of
Section is > 18.5 KV, it has to be shown in green colour. When the
voltage of section is >7.5KV & < 18.5KV it shall change to Orange colour
and when Section voltage is less than 7.5 KV its colour shall change to
red colour.
The status of battery chargers shall be indicated in SCADA as per the following
conventions
Projector based Large Video Screen (LVS) running on DLP (Digital Light
processing) technology is provided at Metro Bhawan and Shastri Park OCCs.
The LVS depicts the traction power supply diagram, indicating the energize/de-
energize condition of the Traction and Auxiliary network, status of the interrupters
(BM) and CBs at RSS, AMS, TSS & ASS, SSP and SP. The Mimic Diagram
Boards sole purpose is, therefore, to give an overall view of the traction and
auxiliary power supply system to the operator. LVS at OCC will be getting data
from main server.
Blue Light stations with Emergency Trip Switch (ETS) boxes are provided at
following locations to de-energize the OHE of relevant section.
Location of ETS
i. Two ETS boxes are installed at each Station Control Room (SCR) in U/G
section, one for UP line and another for DN line.
ii. Four ETS boxes are installed at platform ends, two for UP line and two for
DN line at both the platform ends
iii. In Tunnel (UP/DN) near cross passage.
The master station equipment normally scans continuously all the RTUs/Bay
Controllers in a pre-defined cyclic sequence, in order to update the equipment
status, alarms, events and measurands. Exchange of information between
Master Station and RTUs takes place on interrogation by master followed by
reply from RTU. The communication technique is based on Digital Address Time
Division Multiplexing. Every data exchange is based on well-defined transmission
protocol. The transmitted information contains sufficient parity check bits to detect
transmission errors. Necessary threshold is kept to prevent increased data traffic
due to analogue values.
i. Events.
ii. Alarms.
iii. Graphs.
iv. Measurement reports.
The UPS comprises of AC/DC converter (battery charger), battery, inverter, static
bypass switch, emergency switch and AC output protection circuit breaker. At
OCC/Metro Bhawan, a common UPS is provided to provide uninterrupted power
supply to OCC equipment of different wings.
All the RTUs are linked to the OCC and BCC. RTU is microprocessor based and
includes its associated digital Input/output modules and has following
characteristics:
i. Data processing.
ii. Data transfer with several Control Centres.
iii. High time resolution of 1ms.
iv. Connection with protection relays.
v. Sequential switching programs through Local Automation Function.
vi. Modular design.
vii. Easy to extend with additional I/O modules.
Fig. 204-03
The main function of alarm is to draw the attention of TPC and ensures that the
information is taken into consideration. Mainly there are two types of alarm:
i. Audio-visual Alarm: Only critical events such as breaker tripping, PT
values out of range relay indication, SF6 Gas Pressure etc. are configured
as audio-visual alarm. When such type of events occurs in field, visual
display on the monitor with an audible sound shall appear on the TPC
workstation.
ii. Visual Alarm: Less critical events such as breaker local/remote indication,
battery charger indications etc. are configured as visual alarm only. Visual
alarm is presented as a single alarm text line. This text line consists of
equipment name with station ID, time stamp (date and time).
The default colours and related status texts of the different types of alarm are as
follows:
Alarm type Colour Remarks
Alarm is still persisting in field and not
Active unacknowledged Red
acknowledged by TPC
Alarm is still persisting in field but
Active acknowledged Blue
acknowledged by TPC
These are fleeting alarms. Inactive
unacknowledged alarms remain in black
Inactive unacknowledged Black
colour. After acknowledgement, these
alarms disappear from the list.
Persisting Alarms
Fig. 204-04
Fleeting Alarms
Fig. 204-05
In other words it shall be able to deal with all the events functionally significant to
which the system is likely to be subjected. The SCADA equipment is generally
designed for the tele-commands, tele-signals and tele-metered parameters for a
typical RSS, TSS, AMS, ASS, SS, SSP & SP of a double line section.
Total 30 lines can be configured in each Front-end Server and 18 remote desktop
clients can be opened maximum of each server.
The communication between the master station and the RTUs is at a suitable
transmission speed. Serial transmission speed chosen in DMRC is at a baud rate
of 19200 bits/sec. The time required transmitting data between the supervised or
controlled equipment and the operator must be less than 3.5 seconds whatever
the circumstances.
ethernet LAN on fibre optic medium and shall communicate as per the IEC-61850
standard.
Two control centres are provided for monitoring the entire Airport Line: -
i. Main Control Centre OCC at Metro Bhawan
ii. Backup Control Centre BCC at Airport RSS
Fig. 204-06
The OCC system comprises of Database server with shared Cluster, Real-time
Server and User Interface workstation in redundant configuration. The servers
communicate with each other over a dual LAN configuration i.e. SCADA LAN 1
and SCADA LAN 2. The communication servers communicate with the RTUs
using dual communication LAN i.e. CS LAN 1 and CS LAN2.
ix. Co-ordinate with supervisors of PSI & OHE for manning the controlled
posts in consultation with TPC in the event of persisting faults in the
SCADA equipment.
x. Check all the records maintained in SCADA office for proper entry.
xi. Keep his superior officer fully informed of all-important developments and
seek their guidance when required.
xii. Carry out such other duties as may be allotted by his superior officers.
The OCC is the nerve centre of the traction system, from which full control over
every switching operation on the entire route is exercised. It should, therefore, be
kept in perfect operating condition at all times. No one, other than an authorized
official, shall at any time operate the equipment. Any defects observed in
operation should immediately be reported to the supervisor in charge/SCADA and
the entry should be made in the log book. Any excessive delay in rectification
shall be brought to the notice of Manager (SCADA).
TPC shall once a day contact on telephone the Operators of each Grid sub-
station from which traction power supply is obtained and ensure that the
communication facilities are intact.
CHAPTER - 5
OPERATION OF TRACTION POWER CONTROL
OCC comprises of Traffic Controller (TC), Rolling Stock Controller (RSC), Fault
Management Controller (FMC), Auxiliary System Controller (ASC) and Traction
Power Controller (TPC). Control of Traction and Auxiliary Power System is
centralized and performed by Traction Power Controller (TPC) who performs
remote switching operations through SCADA. Working of TPC is supervised by
Chief Traction Power Controller (CTPC).
The Traction Power Controller in OCC shall be manned throughout the 24 hours
and there will be at least one Traction Power Controller (TPC) in each shift for
control of one line. The Traction Power Controller will be directly responsible for
the correctness of all-switching operations and entries in the Logbook. No person
is permitted to operate the control switches except with the specific permission
and knowledge of TPC. No person shall be permitted to work as a CTPC/TPC,
unless so authorized by the Competent Authority.
Traction Power Controller shall be fully conversant at all times with the rules and
regulations laid down by the Administration as well as with the details of the
electrical distribution System. He shall keep all instructions issued from time to
time as well as copies of documents like General Rules, Traction Manual, Lay out
plan, Single Line Diagram of respective lines etc., ready at hand. He shall
maintain all records up-to-date. Authorisation to work as TPC has to be given
only after going through specified Training of SCADA System, electrical OHE,
and PSI System. The competency certificate is issued to TPC by the Authorised
Officer or his representative after specified Training of TPC working.
No person is permitted to enter the OCC unless he has an authority for the
purpose. The authorized person is issued with Proximity Card. The TPC who
are on duty shall not be disturbed or distracted.
A shift Duty Register/log book shall be maintained in which every change of shift
duty shall be noted. Before handing over the charge, the outgoing Traction Power
Controller shall record in the Shift Duty Register all points (shut downs, Power
blocks, defects in plant, any special instructions received, pending message, if
any etc.) requiring the attention of the Traction Power Controller who takes over.
Before taking over in any shift duty, the Traction Power Controller shall scrutinize
all the entries recorded during the previous shift in the Shift Duty Register, event
log, study the entire mimic diagram in the presence of the previous shift Traction
Power Controller and clear all points of doubt, if any. He should then sign with
time in the Shift Duty Register, thereby admitting having taken over correctly and
assuming full responsibility from then onwards.
i. Traction Power Controller shall not repair, adjust or any way interfere with any
of the SCADA equipment at the OCC except for carrying out switching
operations. Every defect shall be reported at once to the supervisor in-charge
of SCADA wing, who is responsible for the maintenance work.
ii. No work may be commenced by any person on SCADA or Power supply
equipment at the OCC or any control post without prior intimation to and
approval of the TPC on duty, who shall record the event in the Logbook. At
the end of the work, the TPC should test the equipment from SCADA and
satisfy himself that everything is in order.
Since circuit breakers, interrupters and motorised Isolators are operated through
SCADA, the Traction Power Controller will have control over the switching
operations over a wide area. The time required for each operation is of the order
of only a few seconds. Every switching operation should, therefore, be carried out
as per procedure in vogue for fault segregation, power block and only after due
thought & deliberation. Operation of several switches simultaneously should be
avoided as far as possible, as it may lead to wrong operations.
While the Traffic Controller is directly in charge of all movements of Trains, TPC
is directly responsible for maintaining the Power supply to OHE. For operation of
the Train services, it is necessary that a close liaison be maintained between the
Traffic Controller and the TPC at all times. CTPC/TPC should also be in touch
with the Operators at the various Grid Substations and State Load Dispatch
Centre (SLDC).
Traction Power Controller shall attend promptly to all calls received on any of the
telephones at TPC/OCC, however, priority being given to emergency calls of
Traffic Controller, Traction Field Supervisors/staff and Power Supply Authority.
It is also the duty of the TPC to keep a track of the movements of all maintenance
staff of the Traction Distribution Branch so that in an emergency, he is in a
position to summon the nearest gang/person, if required. It is primarily the duty of
the maintenance staff to keep the TPC informed of their movements - which shall
be recorded in a “Register of Staff Movement”.
At every change of shift, the Traction Power Controller taking over shall check all
the alarms on TPC Workstation.
He is the official in direct charge of the control of Power supply System and shall
be fully acquainted with all the Receiving, Traction and Auxiliary Power supply
Installations, and sectionalising arrangements. All shift TPCs report to him. The
Chief Traction Power Controller shall perform the following duties:
i. Study all daily failure reports of OHE, PSI, switching stations specially
which affect the operation of trains and submit connected periodical
reports to Controlling Officer. He shall maintain complete statistical data
relating to operation of SCADA equipment and ensure that the schedules
of maintenance are carried out regularly;
ii. Scrutiny of Traffic delays shown against the Traction Distribution Branch
and liaison with the Chief Controller, as necessary, for ensuring the
correctness of the records;
iii. Maintenance of close contact with the Operation Control Manager, Chief
Traffic Controller, Traffic Controllers, TPC, O&M officers and study of all
problems relating to Train operations, as far as the Traction Distribution is
concerned.
iv. Scrutinize the Log of events Book and the Shift Duty Register once a day
and ensure that they are properly maintained and action as necessary is
taken,
v. In an emergency or any unusual occurrence related to power supply, he
shall be in direct touch with the Traffic Controller, Traction officials and
help in every way to restore and maintain the Train services and take over
operation of Power control himself, if required. He shall rush to OCC in
case of breakdowns so as to coordinate the restoration from the OCC,
from the perspective of Traction Distribution.
vi. Ensure that TPCs are adhering to the rules and instructions in force.
Study all the rules in force and suggest amendments, modifications,
corrections as may be found necessary in practice;
vii. Co-ordinate the Weekly Power Block Program of all Traction staff and
other departments and finalize it in consultation with the Traffic
Department. Take steps to adhere to the agreed program as far as
practicable. He should always try to take maximum advantage of
integrated power blocks and the shadow blocks being taken by various
departments from time to time.
viii. Compile periodical statistics from the data collected on SCADA System
and as per instruction of Dy. HOD (Traction)/O&M including the analysis
of failures on the SCADA System, and submit that to
Dy.HOD(Traction)/O&M.
ix. Report daily to HOD’s office all matters as assigned to him by HOD
(Traction)/O&M.
x. Carry out any other work assigned to him.
There will be a Traction Power Controller in each shift in the OCC. While in
daytime he will monitor the uninterrupted supply and Train running, in night shift
he will plan the maintenance blocks vis-à-vis the arrears and record the progress
of maintenance. The essential duties of the Traction Power Controller are as
under:
i. While taking over shift duty, he should acquaint himself with the prevailing
position of the entire section including working of the SCADA equipment,
condition of all transformers, circuit breakers, interrupters and isolators,
sections under Power block, any special Instructions to be carried out,
movements of important officials connected with the Traction Distribution
System, position of the CMV (Catenary Maintenance Vehicle)/RRV etc.
ii. Scrutiny of Traffic delays shown against the Traction Distribution Branch
and liaison with the Traffic Controller, as necessary, for ensuring the
correctness of the records;
iii. Maintain continuous liaison with the Power Supply Authorities.
iv. Maintain continuous contact with the Traffic Controllers in regard to Power
supply affecting Train movements, imposition of Power blocks etc.
v. Power supply Interruptions or other failures, take prompt action in
accordance with prescribed rules and local instructions for restoration of
supply. In the event of Power supply failures, OHE breakdowns, accidents
etc. advise promptly the concerned field supervisors and officers, and
keep them posted with all important developments;
vi. Power blocks as required, following the prescribed procedure and safety
rules. Compile periodical statistics from the data collected on SCADA
system.
vii. Maintain “Event Log Book” record on prescribed Performa, full details of
all switching operations carried out, Power blocks imposed, burst or
refused (or delayed) and other occurrences in the distribution System;
viii. Maintain the following registers and records in the Performa prescribed:-
a. Shift Duty Register indicating points of importance including
messages, Power blocks and other details to be noted by following
shifts.
b. Power block register.
c. TPC to Traffic Control (TC) register.
d. Register of Staff Movements;
e. Message book with Power Supply Authorities.
f. Record of standing instructions and temporary Instructions Assurance
Register.
In the event of above failures, TPC will take appropriate action as per laid down
procedures.
In the event of failure of Grid Power supply at a sub-station; the Traction Power
Controller should immediately initiate emergency working extending the feed from
the adjacent substation up to the failed sub-station, as a first step. He should
inform the Officials concerned along with Traffic Controller of this situation. He
should also keep in continuous communication with the Grid sub-station; pursue
so as to restore supply to OHE, as quickly as possible.
Any fault on OHE and 25 kV feeder lines will cause the corresponding feeder
circuit breaker to trip, thus interrupting supply to the corresponding sector. When
this happens TPC shall reclose the feeder CB once immediately. If it trips again
he shall segregate the fault as per laid down procedures. If faulty section is
identified, TPC shall isolate it and charge the remaining healthy sections. TPC
then shall inform the TC about the faulty and healthy sections.
Before concluding that the fault is on the OHE, the TPC should first make sure
that there is no defective Train in the faulty section, which is causing tripping of
the circuit breaker. He should arrange to have its pantograph lowered to
ascertain if the fault is on the OHE or on the Rolling Stock.
The faulty section shall be kept isolated. Feed to all other sections shall be
restored. Traffic Controller shall be immediately informed by the TPC of the faulty
and healthy sections.
For restoration of OHE in the faulty section, not only the faulty section is to be
identified but also the healthy section in the vicinity of faulty section has to be
identified, which may get infringed because of restoration work in the faulty
section. TPC has to keep close liaison with Traffic control for this.
i. Faulty Section
Traffic Controller shall immediately be informed by the TPC to take all
precautions as per Station Working Rules and restoration measures be
initiated at the same time by informing all concerned.
Only when the OHE staff are able to inspect and find out the nature of the
fault, it will be possible for them to forecast how long it will take to rectify the
fault and restore the Power supply. The Traffic Controller shall decide
whether single line working is to be Introduced or not, taking into account the
following factors:
i. The Traffic Controller shall give top priority for the movement of the
maintenance staff by Train, CMV (Catenary Maintenance Vehicle)/RRV (if
movement required and permitted) to reach the faulty section. It is the duty of
all concerned to reach the break-down site either by Train or by road in the
quickest possible time with breakdown vehicle and required T&P items to
attend breakdown. TRD Site in charge for restoration should be in continuous
touch with TPC by means of radio communication (TETRA SET) or mobile
phones.
ii. TRD Site in charge for restoration shall, after analysing the fault, inform TPC
the time expected to be taken for rectifying the same. TPC shall pass on this
Information to the Traffic Controller.
iii. The OHE staff shall then take a permit-to-work and proceed to rectify the fault
duly observing the safety instructions.
iv. The TPC after locating the fault shall reduce the section under Power block to
the elementary section concerned by opening of concerned
interrupters/breakers/isolators.
v. The OHE staff shall then take a permit-to-work and proceed to rectify the fault
duly observing the rules for the purpose.
The TPC shall always be in a state of readiness to take quick and prompt action
to tackle any breakdown or emergencies. He will keep liaison with not only the
field officials at site who are engaged in restoration of affected section, but also
the Head Quarter officials, giving details of the breakdown to the extent, they are
known apart from assistance from the neighbouring Depots as the circumstances
warrant.
CHAPTER – 6
POWER BLOCKS AND PERMIT TO WORKS
206-00 Introduction
206-01 Definitions Related To Power Blocks
206-02 Power Blocks
206-03 Locally Arranged Power Blocks
206-04 Emergency Power Blocks
206-05 Pre-arranged Power Blocks
206-06 Identification of the Section where shut down is
required
206-07 Communication
206-08 Planning for Obtaining Traffic and/or Power Blocks
and Permit to Works
206-09 Procedure for Pre-arranged Power Blocks
206-10 Pre–block preparation and post–block site
Management.
206-11 Work by other than Authorised Persons
206-12 Power Blocks Process
206-13 Restoration of Supply after ‘Permit to Work’ is
Returned
206-14 Cancellation of Power Blocks
206-15 Local Cancellation of Permit to Work when
Communication is interrupted
206-16 Integrated Blocks (IB) involving Multiple Working
Parties
206-17 Entries in the Logbook
206-18 Standard Forms for Power Blocks Messages
206-00 Introduction
“Non-traffic hours are defined as the hours between the passage of the last train
including any work train and before start of first train in the morning as per
scheduled time table”.
Metro Traffic is peculiar in nature and is normally operated as per time table
during fixed hours of day and night. Special time table is followed for services on
Sundays and Holidays. All work which are planned to extend beyond non-traffic
hours into the hours when train services would normally operate, must be notified
at least one week in advance unless it is an „Emergency‟. All such works must
take place during Engineer‟s Possession.
Works which are planned to be carried out within non-traffic hours without an
Engineer‟s Possession but which are delayed by unforeseen circumstances must
be protected by an Engineer‟s Possession.
vi. Elementary Sections: are referred to by four/five digit numbers. The sections
are numbered serially in the direction of power supply i.e., from the feeding
post/substation towards the neutral section or the terminal point. At each
feeding post/sub-station a new series of number starts. The first two/three
digits represent the Interrupter/Feeder Circuit breaker controlling feed to the
section and the last two digits indicate serial number of the elementary
section. Up line elementary sections have progressively odd numbers and DN
line elementary sections have progressively even numbers.
Whenever there is a doubt in the description, the person asking for power
block shall state clearly the track and OHE structure numbers between which
works is required to be done.
department official, not below the rank of maintainer, who have been deputed
for shadow power block to other department shall be called as Traction Staff.
to the concerned section until the authorised official at the site communicates
the cancellation of Power Block after removal of men, material and temporary
earth as per standard procedures.
Pre arranged power blocks are planned to coincide with non revenue period.
Maintenance staffs maintain liaisons with TPC for obtaining pre arranged power
blocks. In view of large scope of availability of power blocks during night hours of
non revenue period, pre arranged/shadow power block are granted by TPC in
consultation with TC for carrying out maintenance activities of all the discipline
requiring power blocks. Pre arranged power block/shadow power block is in the
form of weekly general orders issued by OCM on every Saturday.
a. By TPC:
After switching off OHE, TPC shall check the status of electrically
dead OHE on his monitor. When energized, the voltage at PT is
indicated as 25 KV. After switching off it is indicated as 0.2 to 0.5 KV.
After providing discharge rod on OHE it is shown as zero kV. Traction
staff‟s confirmation about providing discharge rod on OHE shall be re-
confirmed by TPC on his monitor by checking the status of PT
Voltage. The elementary section/line is shown in one colour in TPC‟s
monitor, when OHE is charged. After switching off the OHE colour
changes.
b. By Traction Staff:
On confirmation of status of electrically dead OHE from TPC, Traction
staff shall provide discharge rod on OHE in his own presence and
inform the same to TPC.
i. There are only two main running tracks, one Up and one Down,
ii. There are no loop tracks, except for stabling lines in between some
stations for the purpose of stabling a disabled or healthy rake.
iii. There are no yards, except for the Depots.
Therefore, the pattern of the track repeats between two adjacent stations, over
most of the entire section.
It is important for Delhi Metro Railway official, who is authorised to ask for Power
block, to know the correct method of identifying and describing any section of the
OHE where shutdown is required. He should have with him the up-to-date OHE
sectioning diagram for the section, showing all relevant particulars such as station
names, position of all isolators, interrupters, circuit breakers, "up" and "down"
tracks, section insulators, sectors, sub-sectors and elementary section numbers.
206-07 Communication
All messages relating to Traction power supply shut down, permit to work etc,
issued over direct line telephone/Tetra Set with exchange of private numbers are
recorded and can be retrieved for analysis. Following procedure shall be
followed:
i. Messages should be brief and to the point and shall be written properly in
full before sending it. The description of the section on which Power Block
is required should be unambiguous. All messages regarding permit to
work shall be as per prescribed form.
ii. The same person, who asks for and obtains a power block, should also
cancel it before power supply is restored. If required, power block can be
transferred to other competent staff who further can cancel the power
block. The persons exchanging the private numbers should identify
themselves by name over the telephone.
iii. The person who receives message shall confirm the correctness of every
message by repeating it. Each message shall be recorded by the sender
as well as by the receiver in message book maintained for the purpose.
iv. To avoid confusion, words “Open” and “Close” shall be used instead of
phonetically similar words such as “Switch Off”, “Switch On”. Whenever
necessary words may have to be spelt out.
v. In case of any mishap the record should be retrieved, sealed and kept in
safe custody as an evidence for further inquiry.
206-08 Planning for Obtaining Traffic or Power Blocks and Permit to Work
While scrutinizing the requisition for power block and permit to work by
CHC & CTPC following may be given due consideration:
a. All the Receiving Stations have two sets of Transformers; therefore,
total shut down is not necessary to attend to any fault/breakdown in
the system. Whenever any maintenance or breakdown is required to
be attended in the Traction Substation, the permit-to-work shall be
obtained by the competent traction staff from TPC and after
completing the work, the permit to work shall be returned by the
competent traction staff to the TPC.
b. There are a number of Auxiliary Substations where power from 33 kV
is stepped down to 415V by Auxiliary Transformer to feed air-
conditioning and ventilation plants, lighting, pumps, escalators and
communication system etc. These supplies are obtained from the
same 220/ 132/66 kV source which feeds Traction power supply also.
Therefore permit-to-work for any equipment up to 415V Main
distribution board (MDB) of Rail corridor and incomer side of CB of
underground stations should be obtained from TPC and after
completion of work, the same should be returned to TPC. 415V MDB
onwards the responsibility will be with JE/ASE/SE/SSE/E&M.
The Metro Railway operates trains, depending upon the nature and direction of
flow of commuters. Therefore, the maintenance staffs have to maintain daily
liaison with the TPC for obtaining pre-arranged Power Blocks. Unless there is an
emergency, when a Pilot has to proceed before opening the service for traffic,
such power blocks have necessarily to be planned to coincide with non traffic
periods. However, on weekdays regular maintenance shall be planned only after
revenue hours at night and work should be completed well before beginning of
revenue services.
In view of large scope of availability of power block during night hours and in mid-
day on any pre-planned day (if services are reduced), all maintenance work shall
be planned and carried out to suit this service schedule. However, in summer
time air-conditioning and ventilation plants may have to be kept running to
maintain the comfort condition inside the station building before resuming the
day's service.
i. All pre block preparations must be completed beforehand so that the work
required to be undertaken during actual duration of block is completed
well within the time limit.
ii. Before a block is physically taken availability of required men materials
and tools at site should be ensured.
iii. Adequate required safety precautions and protection systems must be in
position. These include all PPEs, banner flags, Torch signals, walkie-
talkie/ Mobile sets etc.
iv. Standard output expected to be achieved during block are available for
different types of activity. It must be ensured that these targets are
adhered to.
v. Official in charge of block working will ensure that there is no infringement
by unloaded material at the work site before the section is physically
cleared.
vi. Similarly, released material from work site should also be cleared
expeditiously in order to prevent these from being misused by
unscrupulous elements for sabotage activities etc.
vii. Maintenance work should be so planned and executed that no speed
restrictions are required to be imposed after the completion of work.
i. Granting Power Blocks on Main Line: On the basis of weekly general order
and after acknowledgement in the register of TC, TPC shall grant power
blocks to authorized DMRC staff as per laid procedure in vogue.
ii. Power Blocks Coordination between Traction Power Controller & Traffic
Controller: The Traction Power Controller shall maintain a Register & shall
obtain signature from the traffic Controller as acknowledgement as given
below:
a. Before granting Power Blocks
b. After granting Power Blocks
c. Before cancelling Power Blocks
d. After cancelling Power Blocks
iii. Any alteration in the Power Blocks Program shall be advised prior to the grant
of Power Blocks by Traffic Controller to the Traction Power Controller in
writing duly taking his signature as acknowledgement.
iv. If due to any reason, Traction Power Controller is not able to grant Power
Block, he shall advise the same to Traffic Controller duly taking his signature
as acknowledgement.
On completion of work, the person who had received the Permit-to-work shall
ensure that:
i. All men and materials have been withdrawn from the electrical equipment
and its vicinity,
ii. All earths provided for the protection of the working parties have been
removed,
iii. All staff who has been deputed to work is warned that the power supply is
being restored,
iv. Power Block is to be cancelled by Traction staff after ensuring that all
shadow power blocks authorized by him are cancelled,
v. Traction staff shall inform the Traction Power Controller by a message
duly exchanging private no. that all shadow power blocks have been
cancelled, all men, materials and temporary earths have been removed &
all working parties have been informed that OHE is going to be energized,
OHE is fit for the restoration of the Power Supply & fit for the electric
traffic,
vi. After obtaining the Message for Cancellation of Power Block from the
person to whom Power Block was granted by Traction Power Controller,
the Traction Power Controller shall inform the Traffic Controller that the
concerned Power Block has now been cancelled & OHE is going to be
energized as per procedure, duly obtaining the Signature of the Traffic
Controller as acknowledgement. Before giving acknowledgement to TPC,
TC shall ensure that all PTWs issued for work under provision of power
block/Shadow power block have been cancelled. This shall be considered
as cancellation of the power block,
vii. After energisation of OHE, the Traction Power Controller shall confirm the
same immediately to the Traffic Controller in writing and take his
acknowledgment in the register and
viii. TPC should then inform the OHE Supervisor that OHE of availed power
block section has been charged successfully.
i. Power Block is to be cancelled by Traction staff after ensuring that all shadow
power blocks authorized by him are cancelled.
ii. Traction staff shall inform the Traction Power Controller by a message duly
exchanging private no. that all shadow power blocks have been cancelled, all
men, materials and temporary earths have been removed & all working
parties have been informed that OHE is going to be energized, OHE is fit for
the restoration of the Power Supply & fit for the electric traction.
iii. After obtaining the Message for Cancellation of Power Block from the person
to whom Power Block was granted by Traction Power Controller, the Traction
Power Controller shall inform the Traffic Controller that the concerned Power
Block has now been cancelled & OHE is going to be energized as per
procedure, duly obtaining the signature of the Traffic Controller (TC) as
acknowledgement. Before giving acknowledgement to TPC, TC shall ensure
that all PTWs (permit to work) issued for work under provision of power
block/Shadow power block have been cancelled. This shall be considered as
cancellation of the power block.
iv. After energisation of OHE, the Traction Power Controller shall confirm the
same immediately to the Traffic Controller in writing and take his
acknowledgment in the register.
Integrated Blocks (IB) are given for working simultaneously in a portion of track or
on a line segment for a specified period of time by multiple parties without
affecting track integrity during non-revenue hours with/without power block.
i. Integrated Block (IB) will be notified in the Weekly General order issued
by OCM (Operation Control Manager).
ii. The period and area of the IB shall be so earmarked that there is no
concurrent Engineer's Possession to cause conflict & affect safety of
persons.
iii. In IB, movement of any self propelled vehicle (OHE/Non OHE) or non self
propelled vehicle (including lorry, trolley etc.) is strictly not allowed.
iv. EPIC/Sub-EPIC along with gang members will enter in the concerned
station through designated entrance during non revenue hours and make
entry in station access register meant for the purpose. For the purpose of
entry / exit, only one manned access point will be provided for all
concerned during non-revenue hours at a station. The security staff
deployed at the access point will first ascertain the photo identity of all the
entrants.
v. EPIC/Sub-EPIC along with gang members will directly contact the Station
Controller of the concerned stations at least 30 minutes in advance for
taking possession.
vi. If all the gang members of contractor‟s personnel are required to enter
from the stations other than EPIC/Sub-EPIC, they shall be accompanied
by authorized DMRC staff of the concerned department.
vii. Station Controller shall confirm from weekly general order as well as
OCC/TC with the exchange of Private Number about the IB for which the
EPIC/Sub-EPIC has contacted him, and shall also verify the requirement
of Power/Shadow Power Block. If OCC/TC approves the said IB, Station
Controller shall issue approved Permit to Work (PTW) to the EPIC/Sub-
EPIC. PTW format which is attached as Annexure-A.
viii. No OHE Power Block/Shadow Power Block is required for any
maintenance work on Signals, Points Track Circuits, PIDS, PAS Clocks or
any other S&T equipment of Station/Outdoor/Viaduct Equipments of
S&T/O&M as either they do not come within a radius of 2mtrs from OHE
or, are well protected by protective Earth Mesh (Screen). However,
dismantling of complete signal unit from the Signal Post will require
Power/Shadow Block.
ix. If one department requires Power/Shadow Power Block in the same
direction where other(s) do not require it, the granting of PTW to the
departments which does not require Power/Shadow Power Block shall not
be delayed on account of the last train not reaching its final destination or
for OHE Shutdown (Power Block) in the section. It shall be granted as
soon as the last train clears the section mentioned in PTW.
x. The EPIC applying for the PTW to work in „OHE Charged‟ condition shall
give his/ her request in writing to the SC of the station where he/she
intend to work, specifically mentioning that he/she intends to carry out the
work in „OHE Charged‟ condition and is having competency to work
accordingly. The SC shall ensure the receipt of such a request in writing,
shall verify the same from weekly General Order, before granting a PTW
in „OHE Charged‟ condition, with permission from OCC.
xi. EPIC/Sub-EPIC will provide in advance a list of the gang members duly
furnishing details in Annexure-A1 with PTW to all the stations from where
the gang has to enter the section for the IB & also from where they have
to exit. Before entry to the section, EPIC/Sub-EPIC shall ensure that all
the gang members including him are protected with PPE (personal
protection equipment) & have provision for mobile communication. After
getting confirmation in writing on the PTW by EPIC/Sub-EPIC, entry will
be permitted by SC. All gang members along with EPIC/Sub-EPIC will be
responsible for their safety & observe all safety rules & regulations during
the course of work.
xii. If some of the gang members are entering from station other than that of
EPIC/Sub-EPIC, SCs of other stations from where remaining gang
members intend to enter the section will contact SC of PTW issuing
station and seek details under exchange of private number regarding
names of gang members furnished by EPIC/Sub-EPIC and record these
details in possession register. SC will then allow them to enter the desired
section conveying the same to OCC maintaining name & time wise
record.
xiii. PTW (Performa at Annexure-A) will only be granted to EPIC/Sub-EPIC
from the station from where he is entering the section. For other gang
members entering from other stations for the same IB, no separate PTW
will be issued. However, station controller of other stations will verify from
OCC about the approval of the IB under the exchange of private numbers.
xiv. Normally, the exit station for the gang members will be from the station
mentioned in the PTW. However, in emergent circumstances, the exit
point may vary. The responsibility of ensuring that the gang members
have exited should be with the concerned EPIC/Sub-EPIC. The gang
members should talk to EPIC/Sub-EPIC on phone from the station &
confirm the same, The SC will permit the use of phone for this purpose.
xv. In the PTW, the nature of work, location & name of gang members should
be clearly mentioned.
xvi. For Permit to Work requiring discharge of OHE, (to be issued by OHE
wing of O&M), permission shall be issued by supervisor availing the
power block from TPC at nominated place/stations of each line to
concerned EPIC/Sub-EPIC, duly indicating the OHE location numbers
between which the concerned wing is permitted to work. Station
Controllers on verification of their identities shall permit them as
EPIC/Sub-EPIC.
xvii. OCC/TC will co-ordinate with different stations and approve first PTW
under exchange of private number with SC. Subsequent PTWs under
similar conditions i.e. under power block/ shadow power block or without
power block strictly as per weekly general order may be permitted by SC.
xviii. OCC/Station Controllers shall maintain a record of the timings at which
various EPIC/Sub-EPIC along with gang members have entered the
sections for availing IB. This will be recorded in possession register with
details.
xix. Any abnormality, which requires extension of IB is to be immediately
informed by EPIC/Sub-EPIC to OCC & Station controller concerned for
further necessary action.
xx. After completion of work, EPIC/Sub-EPIC should clear the section of men,
materials, equipments and all infringements and cancel the PTW by
submitting a form of cancellation to the concerned SC. EPIC/Sub-EPIC
will also undertake the responsibility of clearance of all the gang members
mentioned in his request while entering the section (irrespective of their
entry and exit points).
xxi. PTW issuing and cancellation stations may be different. However the
same shall be mentioned by EPIC/Sub-EPIC in the PTW form at the time
of applying for PTW. PTW issuing Station Controller shall inform Station
Controller of station where PTW is intended to be cancelled giving
complete details. Both Station Controllers shall make corresponding
entries in Engineers possession register. After PTW has been cancelled,
Station Controller of PTW cancelling station shall inform Station Controller
of PTW issuing station giving complete details under exchange of private
numbers. In this case PTW cancellation to OCC/TC shall be given by
PTW issuing Station Controller.
xxii. No PTW will be treated as cancelled until all EPIC/Sub-EPIC have
submitted Form for Cancellation (Annexure-B) of PTW at the concerned
station. Only the same person to whom the PTW was issued is authorized
to cancel PTW. However in unavoidable circumstances person authorized
as per procedure and having written authorization from EPIC/Sub-EPIC
whom PTW was issued may cancel PTW with the coordination of
concerned controller in OCC. Currently returning of PTW (Annexure-A) in
original is not in practice and need not to be returned as it is an EPIC
copy.
xxiii. SC, after acknowledging the cancellation form for all PTWs issued at his
station, will inform OCC/TC under exchange of private number regarding
cancellation of IB.
xxiv. OCC, before acknowledging cancellation of power block with TPC must
ensure that all the SCs have confirmed that all the EPIC/Sub-EPIC have
submitted PTW cancellation forms at the exit stations.
xxv. Other than metro employees no one shall be permitted to enter the Right
of Way unless they have been:
a. Authorized by the competent authority.
b. They have signed an indemnity bond in the Performa. Annexure-C
c. All O&M contractors' staff, who are required to enter the Right of Way,
will need to be covered by a general indemnity bond or a general
provision in the contract indemnifying DMRC of all consequences
during such visits.
xxvi. Whenever work has to be carried out by more than one working party,
within a sub-sector, the permit to work /Power block shall be issued by
TPC only to one authorised person who alone shall be responsible for all
work on the portion of electrical equipment specified in the permit to work
/Power block. Other party or parties may work on the same portion of
electrical equipment only with the permission of this authorised person.
The authorised person shall cancel the permit to work only when he has
satisfied himself that all working parties who have been permitted by him
to work in the section covered by the permit to work have withdrawn their
men and materials and have removed from the electrical equipment on
which they had worked by confirming through exchange of private
number.
xxvii. Where the two parties work at far away from each other, the party who
has to work for a longer period shall take permit to work and then permit
the other party to start his work by a message supported by a private
number. The second party shall inform the party from whom he got the
permit to work of completion of work and removal of earths and
withdrawal of men and material by a message by exchange of private
number.
The number of each permit-to-work/ Power block issued must be entered in the
Logbook by TPC together with the particulars and time when the equipment is
made dead and re-energized after completion of the work, as per information
received from the authorised person concerned.
Typical forms for power block messages are attached at the end of this chapter
as
Annexure-A : Granting of Permit to Work
Annexure-A1 : Proforma for Gang Members
Annexure-B : Cancellation of Permit to Work
Annexure-C : Indemnity Bond
Annexure-D : Format of message sent/received for Power Block.
Annexure-E : Sub-Epic authorization
Annexure-F : Sub Epic cancellation
Annexure-G : Procedure for award of competency to SC for applying discharge
rods and procedure for maintenance thereof.
Annexure – A
Permit to Work
Sl. No.:
Station:
Date:
Time:
I……………..…………………….......................(Name of the Authorized Person)
……………….. (Emp. No.)...…………… (Designation) ……………… (Department)
………………………….. along with ……………… number of DMRC/Contractor Staff want
to Inspect / Maintain the
Area/Equipment……………………………………………………………………………………
…………….……………from……………….Hrs.to………………Hrs.for………………………
………………………………………………………………………………………………………
………………………………………………………………………………………………………
……………………………………………………………………………………………………..
It is certified that all the Staff including myself are equipped with Personal Protection
Equipment (PPE)
Point Machine Manual Operation Key (EKT Key) for Point Nos. …………………… along
with Crank Handle is Needed / Not Needed and may be Issued / Not issued to me.
Private Number –
OCC / Station: ……………….
EPIC / Sub-EPIC: ……………………
Station Seal
Important to Note:
1. Take all the Safety Precautions during the Work.
2. Keep Sharp Look-out on the Track and of the Train Movements.
3. Only the same person to whom the PTW was issued is authorized to cancel
PTW. Only in emergent cases person having written authority by EPIC/SUB EPIC
/ may cancel PTW.
Annexure – A1
Designation &
Emp. No. (for
Sl. Name of Gang Contractor/ DMRC staff) / Entry
Exit Station
No. Members DMRC staff ID details (for Station
Contractor
staff)
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
Annexure – B
S. No. …………
Proforma for the Cancellation of
Engineer’s Possession / Permit to Work / Traffic Block
with respect to PTW No. ………………………………
(To be filled in Duplicate)
1. Station: …………………………………..
2. Name of the Station Controller: ………………………….
3. Date of Cancellation: ……………………………………..
4. Time of Cancellation: …………………………..
5. Private Number of the Station Controller: ……………………………
6. Private Number of other Station Controller: ……………………….
7. Point Machine EKT Key for Point Nos. ……………………… along with Crank
Handle received back/was not issued.
8. Entry in Possession Register for return of Point Machine EKT Key with Crank
Handle is made/not needed.
(Strike out whichever is not applicable)
Signature of Station Controller
Name: …………………………
Date:
Time:
Annexure – C
INDEMNITY BOND
I hereby further state that no claims / damages, whatsoever, shall be made by myself or
my representatives against DMRC on the aforesaid context before any Court / Statutory
Authorities.
Signed: ………………………………………
Name of the Visitor: …………………………………………
Address: …………………………………………………..
…………………………………………………………………
…………………………………………………………………
Witnessed by:
Name: …………………………………..
Address: ………………………………
……………………………………….…
……………………………………….…
Proof of Identification: ……………………………………….
Name: …………………………………………
Address: ……………………………………………
…………………………………………………………..
……………………………………………………………
Proof of Identification: ………………………………………
Annexure – D
PROFORMA FOR EXCHANGE OF MESSAGES
Message Sent / Received
Message:
Annexure – E
AUTHORISATION PROFORMA FOR SUB-EPIC
Date: …………………………..
Location: ……………………………………..
Time: ……………………………
Annexure – F
Date: ………………………….
Location: ……………………………
Time: ……………………………………
i. All Men & Materials. Tools & Plants and Equipment etc. have been taken out
of the section.
ii. There are no Infringements caused to the Schedule of Dimensions.
iii. Power Block has been Cancelled, OHE is in the Charged Condition & OHE is
also „Fit‟ for the movement of Traffic.
iv. Track is „Fit‟ for movement of Traffic.
v. All S&T Gears/Installations are „Fit‟ for movement of Traffic.
vi. The Point Machine EKT Key for Point No. ………………… along with Crank
Handle is hereby returned/was not issued to me.
Signature of EPIC/Sub-EPIC
Name: ……………………………
Designation: ……………………
ACKNOWLEDGEMENT OF CANCELLATION:
CHAPTER - 7
BREAKDOWNS
I GENERAL
207-00 Knowledge of Rules
207-01 Types of Breakdowns
207-02 Breakdown Gangs
207-03 Emergency Stores and Breakdown Equipment
207-04 Record of Maintenance Gang movements
207-05 Summoning of Emergency Staff
IV OHE BREAKDOWNS
207-13 Importance of Expeditious Repairs
207-14 Types of OHE Breakdowns
207-15 Reporting of OHE Defects
207-16 Action to be taken by TPC
207-17 Protective Steps
207-18 Breakdown Staff
207-19 Officers and Supervisors to Proceed to Site
207-20 Assistance to be sought
207-21 Continuous Communication with TPC
207-22 Detailed Assessments by the first Supervisor/Officer
Reaching Site
V ROAD VEHICLES
207-31 Use of Road Vehicles during Emergencies
207-32 Duties of Vehicle Drivers
BREAKDOWNS
I GENERAL
All Officers and Supervisors of the Traction Branch should be fully conversant
with the instructions in force for dealing with accidents and breakdowns. The
instructions given in the following paragraphs are to be treated as supplementary
instructions applicable specifically to traction installations; they should not be
taken as nullifying or contradicting the instructions contained in other official
manuals.
Accidents and breakdowns involving traction installations and electric rolling stock
should normally be attended to by-the maintenance gangs themselves. It is,
however, essential that adequate number of experienced traction staff should be
selected and housed close to traction installations, so that their services can be
utilized at short notice for dealing with breakdowns and accidents whenever
required.
In case of Delhi Metro Rail Corporation ‘Breakdown gangs' of adequate strength
are located at depots to deal promptly with OHE failures, particularly during the
hours of peak traffic.
i. For OHE depot, the actual quantity of OHE stores like masts, conductors,
insulators, fittings etc. that should be earmarked especially for use in
breakdowns will be laid down by Dy. HOD/Traction (O&M). To start with, all
materials required for one kilometre of single line may be kept. Based on
experience, the minimum and maximum quantities may be, revised from time
to time. An inventory of such OHE stores should be maintained by the
supervisor-in-charge of the depot and stocks recouped periodically so as to
ensure that minimum quantity is always available. During periodic inspections
by officers, scrutiny of this inventory should be one of the important items in
order that the required stores are always made available.
ii. OHE Inspection Cars, breakdown vehicles and all break-down tools, tackles,
straining screws, clamps, ladders etc. shall be maintained in good condition
and kept ready for use at all times.
It will be the primary responsibility of the supervisor in-charge of the OHE
depot to ensure that all breakdown equipment is in good working order.
Supervisors and officers at all levels should specially check their condition
during their periodical inspections. A periodic review should also be made
regarding the adequacy of such spares and tools.
iii. Supervisor in-charge of traction wing should also have in their custody spares
and tools pertaining to their work as per scale to be laid down by Dy. HOD
(Traction)/O&M for dealing with breakdowns and accidents.
TPC should, even when everything is normal, keep a continuous record of the
movements of maintenance gangs so that he can contact the gangs immediately
whenever required to attend to any emergency.
To enable the TPC to summon staff and inform Officers as required, an updated
register showing the latest contact numbers, residential addresses of specified
staff of the Traction Distribution branch, particularly those residing close to
stations/ depots, should be maintained Depot-wise by TPC. The list of office and
contact numbers of officers and supervisors should also be kept up-to-date by
him for ready reference.
Failure of traction transformers, requiring the lifting of core and winding are
extremely rare. Therefore, instead of creating any facility for its repair
necessitating core lifting etc it is deemed fit to get them repaired from outside
agency on contractual basis. However, for carrying out running repairs the
following minimum facilities should be made available in some selected
substations, so that all other substations may utilise those equipments whenever
needed:
Every traction sub-station of Delhi Metro Rail Corporation should have all weather
road access for transporting heavy equipment to and from the installations. For
switching stations too road access should be provided wherever possible;
however road access may not be feasible for all posts as mostly these are being
provided on viaduct. Suitable fittings and tackle should be provided to move an
Interrupter or circuit breaker from the maintenance depots on Catenary Motor
Vehicle/ Overhead maintenance Vehicle, breakdown road vehicle.
In charge of SCADA wing shall arrange for expeditious rectification of the defect
and restoration of remote control. It is undesirable to continue any switching post
on manning for prolonged periods.
IV OHE BREAKDOWNS
The Train Operator of all trains should keep a sharp lookout and should report to
the TPC immediately via Traffic controller (TC) on radio communication, if any
defect is noticed in the OHE.
All breakdowns or defects in OHE, which are likely to affect the train services,
noticed by any Delhi Metro Railway official, shall be reported immediately to TPC.
If TPC cannot be contacted, the nearest Station controller/Station Manager shall
be advised. The SCR/SM to whom such breakdowns or defects are reported shall
convey the information immediately to TPC/OCC through other means of
communication available. The person reporting a breakdown to TPC/OCC should
give as much detailed Information as possible on the nature of the breakdown, its
location, whether masts have been uprooted or both lines in a double track
section have been affected etc.
The person conveying the information to TPC should not leave the vicinity of the
available communication site without TPC's permission, as the latter may want to
contact him again to elicit further information.
If any derailment has taken place or any other material like mast etc is reported to
be infringing the track, TPC should immediately first of all switch off the power; so
as to prevent any further derailment/accident taking place.TPC should inform
Traffic Controller also about this immediately. Once this has been done, TPC
shall direct the nearest available Electrical Department official to proceed to site
to obtain full details. He shall also inform the concerned Supervisor in charge,
AM/Manager, Dy. HOD (Traction)/O&M and HOD (Traction)/O&M, preferably in
this order.
Though initially power may have to be switched off over a whole sub-sector, the
faulty elementary section should be identified and isolated as quickly as possible
so that power supply may be restored to the healthy sections and normal train
operation resumed, after ensuring that safety is in no way getting compromised.
i. On receipt of the first report about the breakdown, TPC shall direct the
nearest available OHE maintenance gang, to proceed to site immediately with
the available breakdown vehicle. If the breakdown vehicle is not available for
some reason, TPC may decide to send few staff by road/metro/foot
depending upon the gravity of the situation.
ii. A quick assessment should be made on the basis of information available and
where necessary one or more gangs from both sides of the site may be asked
to proceed to the site. If the accident spot cannot be reached by train borne
on account of the line being blocked by other trains, road vehicles equipped
with emergency stores, tools and staff may be directed to the site. As in case
of Delhi Metro Rail, roads are running alongside the track; this method may
help in tackling the repairs much more quickly.
iii. If the CMV(Catenary Maintenance Vehicle/RRV(Rail cum Road Vehicle) is
required to attend the breakdown, the Chief Controller/ traffic controller, on
request from TPC shall arrange for quick passage to the CMV/RRV to the site
of the accident.
The first Supervisor or Officer of the Traction Branch reaching the site of the
breakdown should make a quick assessment of the extent of damage and the
time required for restoration. He will ascertain from TPC the details of breakdown
gangs and equipment directed to the site and if the circumstances warrant, ask
for additional assistance and breakdown equipment to be sent to the site. On
receipt of these details, TPC should arrange for additional gangs and equipment
to be sent to the site expeditiously. In the meanwhile, isolation and repair works
should be started at site.
When a pantograph gets entangled with the OHE, it is often very difficult to
establish whether the damage originated from a faulty pantograph or a defect on
the OHE.
The first Officer or Supervisor of the Electrical Department arriving at site of a
breakdown should make a very careful note of all relevant details pertaining to
the breakdown and also prepare a sketch indicating the particulars. He will also
arrange for preservation of such evidence like photograph of damaged OHE,
entangled pantograph, foreign material if any etc. as may be useful subsequently
for investigating the cause of the breakdown. (Ref. Annexure 7-02.)
While speed is the essence of emergency working, rules prescribed for safe
working shall never be infringed. Repair work may commence only after an
emergency power block has been obtained and all other precautions necessary
for protection of the staff taken. On completion of the repair work, the power block
may be cancelled according to the prescribed procedure.
In the first instance, repairs to the OHE should be kept to the barest minimum
necessary for restoration of traffic within least possible time. Restoration work
should be planned to proceed simultaneously at many points, so as to restore the
traffic at the earliest. After effecting temporary repairs, the Officer or Supervisor
in-charge of the work should personally check the whole area and satisfy himself
that the Installations are in order and safe. He may impose such speed restriction
as necessary for movement of trains till permanent repairs are carried out.
Permanent repairs should be arranged and speed restrictions removed at the
earliest opportunity during non-traffic hours.
If the OHE has suffered extensive damage, Catenary Motor Vehicle/ Overhead
Maintenance vehicle should be requisitioned to speed up the work.
Each car should be provided with 2 drums of Wire (one drum of messenger wire
and one drum of contact wire), an adequate quantity of OHE spares, floodlights,
torches, TETRA. The car has swivelling platforms with side-railings to facilitate
working on the roof.
In clearing the line for traffic, breakdown staff is forbidden to disturb the OHE
masts or to cut the OHE conductors except under the specific orders of Manager
(Traction)/O&M or a senior Traction (O&M) officer. If it becomes necessary to
slew the OHE conductors to facilitate crane working from road side, this should
be arranged to be done by the Electrical Department Staff. It should be borne in
mind that indiscriminate cutting of OHE conductors will necessitate introduction of
splices which are not conducive to good current collection. Also introduction of
such splices is liable to delay restoration of normal train services.
i. In all major breakdowns, TPC, senior officials and Officers concerned shall
maintain a detailed log of events noting the time and brief details, which may
help in fixing the responsibility for any avoidable delay in restoration.
ii. The concerned Dy.HOD (Traction)/ O&M should submit to
HOD(Electrical)/O&M and Director(O&M) a detailed report covering every
major breakdown of OHE or other traction installations giving all essential
information including-
a. Nature of break-downs and lines affected with detailed sketch;
b. Chronological account of action taken to effect repairs and restore traffic;
If there is movement of the cranes from road side, it shall be carefully controlled
by the person in-charge so as not to come within 2 m of live OHE, in addition to
the usual precautions necessary to prevent infringement of adjacent tracks, which
have not been blocked for traffic.
V ROAD VEHICLES
Road Breakdown vehicles like motor trucks and other breakdown vehicles
available with maintenance officials should be maintained in proper condition with
requisite materials at all times, as they are liable to be called for use in attending
to breakdowns or emergencies.
Annexure 7-01
On viaduct, OHE masts shall be bolted on parapet by means of a welded steel base
plate. Therefore, these masts are not vulnerable like the masts of conventional OHE.
However, in remote case even if the mast gets knocked down it may be possible to erect
another mast.
If it is not possible to erect a mast on the viaduct in quickest possible time, height of OHE
on either side of the mast should be raised to maximum possible extent and the smallest
size of the droppers should be provided in the mid-span to take care of the sag and to
get a minimum height of contact wire from rail level. OHE can then be made fit with 15
kmph speed restriction.
Annexure 7-02
i. Location
ii. Height of contact wire of main line above R.L.
iii. Height of contact wire of turn-out/cross-over above R.L.
iv. Stagger of contact wire of main line,
v. Stagger of contact wire of turn-out/cross-over.
vi. Length of steady arm holding main line contact wire.
vii. Length of steady arm holding turn-out/crossover contact wire.
viii. Position of Registration tube and register arm dropper clip.
ix. Track separation at obligatory point.
x. Position at which horn of pantograph jumped above contact wire.
xi. Vertical height of steady arm clamp from register arm.
xii. Hitting marks on the steady/Registration arm tube, P.G. clamps droppers, contact
wire, dropper clip, splices, and jumpers, if any.
xiii. Condition of cracked or broken OHE fittings such as clamps, splices and clips etc.
Check whether the cracks are fresh or old.
xiv. Check free vertical movement of the steady arm.
Above observations will be made on every mast within at least 500 m in the rear of the
location of entanglement.
CHAPTER - 8
PREPARATION FOR COMMISSIONING OF ELECTRIC TRACTION
208-00 Introduction
208-01 Reference to Rules and Statutory Rules
208-02 Pre-Commissioning Inspections
208-03 Defect and Deficiency Lists
I RECEIVING SUB-STATIONS
208-04 Power Supply
208-05 Commissioning of Traction/ AMS Transformers
208-06 Precautions during Commissioning of Traction/AMS
Transformer
208-07 Tests on Transformer
208-08 Circuit Breakers and Interrupters
208-09 Isolators
208-10 Potential Transformers, CVT and Current transformer
208-11 Lightning Arrestors
208-12 Shielding and Earthing
208-13 Bus bars and Insulators
208-14 Clearances
208-15 Auxiliary Substation Transformer in RSS
208-16 Batteries & Battery Charger
208-17 General
208-18 General Inspection of Substations and Commissioning
VI OVERHEAD EQUIPMENT
208-57 Detailed Joint Inspection of OHE
208-58 Compliance to Approved drawings
208-59 Infringements
208-60 Important Point to be checked
208-61 Notices to be Displayed–Caution Boards and Number
Plates
208-62 Recording of Defects and Rectifications
208-63 General Inspection of the OHE by Delhi Metro Rail
Corporation Officers
208-64 Lapping and Polishing of OHE
208-65 Procedure for Final Test of OHE
208-66 Insulation Tests
208-67 Continuity Tests
208-68 Energisation Certificate
208-00 Introduction
The safety of travelling public, Metro Railway staff and property shall be ensured by
strict compliance with the rules laid down in standards. During the preparations for
commissioning, the provisions of all these rules shall be kept in view.
Methods/procedures indicated in the manual are only for guidance and may be
modified as per latest methods/standards prescribed and approved by HOD
(Electrical) of DMRC.
i. In-plant testing
In plant or Factory testing of equipment consists of type and routine tests
a. Type tests are tests performed on one or two equipment of series
b. Routine test are tests performed on each lot of equipment as per relevant
standard
These tests will enable checking the quality of the equipment and its compliance
with the specifications. Once the equipment have passed the in-plant acceptance
tests, it will be cleared for dispatch, delivered and installed under the
responsibility, of the contractor / nominated agency.
ii. After shipment and preliminary tests
a. After shipment
Tests carried out on receipt of equipment at site for verifying whether any
damage has taken place during transportation.
b. Preliminary tests
Performed to verify that equipment have been installed and assembled
correctly.
They should include, at least, the following:
i) All test listed in the column “on site “ of each equipment test sheet
ii) Conformity of the assembly and wiring with the contractor‟s drawings and
instructions
iii) Sealing of all pipe junctions, and the tightness of bolts and connections;
iv) Proper function of each part of equipment, & equipment as whole of
sections
v) Cleanliness of installations
Officers and staff of various sections should associate themselves with the
installations and satisfy themselves about high standards and quality of work and get
the defects noticed rectified, then and there, while work is in progress.
When the work is declared as having been completed and ready for Inspection, the
field officers and senior subordinates of O&M wing, along with representative of
contractor/nominated agency, will carry out joint checks. The checks should be
thorough and cover every part of the installation. In making these checks the latest
drawings should only be used (superseded versions can be misleading and should
be positively avoided).
All defects noticed during such joint checks should be rectified before the section is
taken over by O&M organisation. The defects will be categorized in following three
types and jointly signed lists are prepared accordingly:
Category-A - Defects concerning vital safety items and serious shortcomings, which
must be rectified before even test charge
Category-C - Minor defects, which need not hold up commissioning and can be
rectified after commissioning in a reasonable time.
During the preparatory period, these lists should be constantly reviewed jointly and
progress of rectification to be watched.
I RECEIVING SUB-STATIONS
i. Sub-stations play a vital role in electric traction and, therefore, considerable care
during erection and commissioning is required. A high standard of workmanship
is essential and the pre-commissioning tests should be systematically carried out
by competent staff, using dependable and calibrated instruments.
ii. The connection of the substations to the transmission lines of different phases
should be in cyclic order so that the load due to electric traction on the grid
system is well balanced and remain within the permissible limits of unbalance.
i. Drying out of transformer shall be undertaken as per the procedure laid down.
ii. Tap-changing mechanism shall be checked for being in perfect operating
condition, both electrically and mechanically. Ratio test should also be done
in this procedure.
iii. Transformer bushings should be paid special attention to ensure that the
manufacturer seal is intact and the bushings are in excellent condition. The
Insulation Resistance (IR) of the bushing should be around 10,000 Mega
Ohm.
iv. All gaskets should be properly compressed and tight fitted. No leakage of oil
should be visible from valves, pipe joints, gauge glass, radiators or any other
parts of transformer. The welded joints should also be checked for seepage if
any.
v. Sub-station transformers should preferably be identical.
vi. The oil filled in transformer should be fully de-aerated to avoid false operation
of Buchholz relay.
vii. The Buchholz relay should be erected as per instructions of the makers and
tested for correct operation.
viii. All accessories like silica gel, breather vent pipe, explosion vent diaphragm,
circulating oil pump and special cooling equipment, if any should be checked.
ix. In addition to Buchholz relay, other protective devices provided for the
protection of transformer should be examined and checked carefully and
tested after erection at site.
x. Earthing of transformers and its neutral terminal shall be done in accordance
with the "Code of Practice for Earthing of Power Supply Installations".
(Appendix III of Volume 3 of DMRC ACTM). It may be noted that even the
wheels of the transformer are earthed separately by fixing them in position by
wedges etc.
Pre-commissioning checks
i. Check all the gasket joints to ensure that there is no leakage of transformer
oil at any point.
ii. Check any breakage or cracks or any other defects in porcelain bushing and
replace if necessary. Oil level in condenser type bushings should be up-to the
level mark on oil gauge on side of top cap.
iii. Check the tightness of top cap for condenser bushing.
iv. Release trapped air through air release plugs and valves fitted for the
purpose on various fittings like headers, radiators, and oil communicating
bushings, Buchholz petcock etc.
v. Check alarm and trip contacts of Buchholz relay, WTIs, dial type
thermometer, magnetic oil level gauge, oil flow indicator, pressure relief
device etc.
vi. Ensure that conservator is filled up-to the filling level mark on prismatic oil
level gauge side and corresponding to the pointer reading on MOLG
(Magnetic Oil Level Gauge) side. Special attention needs to be paid for
conservator with fixed separator.
vii. Make sure that neutral bushings are effectively earthed.
viii. Tank and radiator bank should be earthed at two points through tank CT.
ix. Check the direction of rotation of fan blades to ensure right blast towards
radiators.
x. Check the direction of rotation of pumps.
xi. Ensure that silica gel in the breather is active and color is blue and oil in the
breather cup is present.
xii. Check that the thermometer pockets on tank cover, header etc. is filled with
oil.
xiii. CTs secondary unused terminals must be shorted and earthed.
xiv. Check that the proper terminals in the marshalling box are connected to WTI
CT terminals
xv. Check for tightness of all external electrical connections
xvi. Check for the arcing horn gap on bushings if provided.
xvii. Clear off extraneous materials like tools, earthing rods, pieces of clothes,
waste etc
xviii. Lock the rollers for accidental movement on rails.
xix. Insulating pad between tank and roller frame should be provided.
xx. All marshalling box on the transformer should be earthed through tank CT or
it should be fixed on the tank with insulation pads.
i. Test on Insulation:-
Insulation resistance readings should be recorded with a 2.5 kV or 5 kV megger.
The following are the minimum permitted values at an ambient temperature of
300 C. Temperature has a material influence on insulation resistance, and
therefore the test should not be conducted when oil is hot.
2000 Mega Ohm between HV winding and earth
400 Mega Ohm between LT winding and earth
2500 Meg Ohm between HV and LT windings
The installation of circuit breakers and interrupters should be carefully done as per
Instruction Manual of OEM. The following special checks may be made.
Check, first of all, if the circuit breaker mounting is quite vertical and the base firmly
secured. Examine the operating mechanism in the weatherproof housing for
cleanliness, free movement of rollers, bearings and sliding surfaces, which should be
very lightly oiled. Open and close the breaker several times to check that everything
is working smoothly. Make sure that all pins, locking plates and split-pins are in
place.
On the electrical side, examine the condition of the wiring, its insulation resistance
and tightness of the terminal screws. Check if the opening and closing solenoid or
motor when electrically operated does operate satisfactorily with battery voltage 20
% less and 10 % more than the rated voltage. Check also the manual operation and
record the operating time for closing and opening. Observe if the auxiliary contacts
are clean and good and the terminal block well secured.
Examine particularly if there is any strain on the circuit breaker porcelain housing
because of misalignment or rigidity of the connection from its terminals to the bus
bars. Usually this is made through flexible connectors; nevertheless, it is wise to
check the position of the connecting leads when the bolts are loosened. Make sure
also that the metal-to-metal contact is perfect at the terminal connections. Any
imperfection here will result in overheating of the terminal, which may even lead to
eventually fracture of the housing itself. It is best to measure the contact resistance
by "Ductor" (low resistance Ohmmeter) or similar low-resistance-reading instrument.
The breaker with air system is to be tested for compressed air leakage in CLOSED
condition as well as in the OPEN condition. The duration of test should be at least 8
hours but to the extent possible 24 hours.
Finally, Check the I/O signals on local SCADA, general condition of the equipment,
finish, weather-proofing of the cabinet and whether it is insect-proof, whether fuses
are intact, and if the operation counter, where provided, works properly and if the
metal supports and frame are well earthed.
208-09 Isolators
Examine the insulators carefully for any surface cracks and make sure if the surface
is clean. Check operation of isolator through motor or manually to see if the
movement is free and smooth, and if the switchblades are fully open or fully closed
when the motor reaches its extreme stroke. Examine the contacts and check if the
spring pressure is adequate and blades make full contact. Check terminal
connections, preferably by a "Ductor", Examine whether the Isolator functions
properly and the isolator frame is solidly connected to earth by two independent
connections.
i. Check and record the insulation resistance of primary and secondary with
respect to earth and between primary and secondary. Check, earth
connections, oil level in PT (220 kV) as also its dielectric strength,
capacitance & Ten-delta, Ratio error test.
ii. Insulation resistance, winding resistance, polarity test and ratio test are
carried out on CTs preferably after they are erected and before they are
taken into service.
iii. The above tests which are carried out during routine test in factory are
sufficient to give us information that the CT is OK and ready to perform its
Make a thorough visual examination of the outer porcelain housing for hairline cracks
and chipped sheds. Clean all dust of the outer surface. The connecting leads to the
arrestor should be solid and direct. The earth terminal of the lightning arrester should
be connected to the independent earth electrode provided very close to the arrestor
and main earth mat at the substation.
Check whether the whole of the sub-station area is well protected against
atmospheric surges by screening conductors strung between substation structures or
spikes provided on each tower/high mast provided in the sub-station and solidly
connected to the earth system in accordance with the approved drawing.
Check visually whether the metallic casing of every substation equipment and the
neutral terminals of the power transformers are solidly connected to the sub-station
earthing grid, and confirm that the "Code for Earthing Power Supply Installations" is
complied with in all respects.
A careful inspection should be made of every insulator supporting a bus bar to detect
any minute cracks on the surface; Paint marks or dust should be removed and the
surface gloss should be restored.
Time spent in checking the current carrying joints on bus bars and terminal
connections will pay ample dividends. The contact surface should be clean, smooth
and without any irregularities and burrs, so that when they are tightened the area of
contact is large. The pressure should also be adequate. Particular care should be
taken when joints are made between two dissimilar metals like aluminum and
copper. Special bimetallic fittings should be used in such cases to prevent electrolytic
corrosion. Connections should be such as to produce no strain on the equipment.
208-14 Clearances
The Battery room should be particularly well ventilated, protected, dust-free and dry.
Examine the logbook for the period during which the battery was given its first charge
and make sure that the manufacturer's instructions have been adhered to as regards
the rate of charge and the number of charge and discharge cycles.
The battery shall consist of nickel-cadmium cells of sufficient capacity. Battery shall
be delivered complete with all accessories and components required to connect the
cells in series.
Battery cells shall be mounted on open stands. The max & minimum electrolyte
levels marked in the cells shall be clearly visible.
Check if all the inter-cell connectors are tight and Vaseline applied. Check finally if
the battery fuses are of the correct capacity and there is no possibility of battery
supply failure. Make sure that the alarm bell goes off if the supply is interrupted for
any reason to the control panels.
The AC and DC terminal strips shall be separated from each other. The battery
charger should be inspected to make sure that its capacity is sufficient and that it
complies with the technical specifications, that the meters provided are indicating
properly and it is complete with necessary fuses and indicating lamps. The metal
casing should have two independent earths.
208-17 General
Inspect the substation area to make sure that it has good drainage. Ensure that
baffle wall in between Traction & Auxiliary transformer and suitable oil drainage
arrangement with an oil soak pit has been made in accordance with the
specifications. The numbering of transformers, interrupters, circuit breakers,
incoming transmission lines and outgoing feeder lines should be checked to see if it
has been correctly done, and does correspond with the numbering scheme on the
control panels at the sub-station control room, and also on the mimic diagram board
at the OCC. Fire extinguishers and fire-buckets filled with sand shall be kept ready at
hand. Station name-board, Danger and Caution boards, Protected Area board,
Emergency contact numbers etc. shall be well displayed.
After defects observed during detailed inspection have all been rectified, the
Manager/Traction shall carry out a general inspection of every part of the sub-station
along with the contractors' representative. Considering that these are high voltage
installations, the inspection should be thorough. As many spot checks as possible
should be conducted to ascertain the condition of the equipment and the care taken
during erection. Particular attention should be paid to the safety aspects like
clearances, operation of protective relays and functioning of the trip circuits and
earthing. The statutory regulations such as the Indian Electricity Act and CEA
(Measures relating to Safety & Electric Supply) Regulations, 2010 should be strictly
complied with and the inspecting officers shall personally satisfy himself by tests and
measurements that the installations are fit in every way to be energized and then
issue a joint certificate to that effect.
For the first three days after commissioning, the substation equipment shall be kept
under careful observation by a senior and experienced supervisory official.
Thereafter daily inspection should be continued for the first fortnight.
Immediately after energisation the correct operation of every protective relay shall be
checked and the substation should be taken over on remote control/SCADA.
The work shall strictly comply with Indian Electricity Act and CEA (Measures relating
to Safety & Electric Supply) Regulations, 2010, the contract specifications and
approved parameters, particularly in respect to clearances between ground (and
other structures) to live conductors including sag-tension charts.
This will cover every location and crossing across Metro / railway tracks, roads etc.,
special attention being paid to workmanship, completeness of installations as per
approved drawings.
208-22 Earthing
EHV cables sheath to be connected to ground as per type of bonding, which could
be single point, midpoint and cross bonding depending upon length of cable.
The following site tests shall be conducted on a completed power cable installation
as per specification IEC 60840 latest version:
i. Visual Inspection and Continuity Check: Visual inspection shall include check
for satisfactory workmanship Continuity check shall be carried out on the cable
to ensure that the cable is continuous.
ii. DC voltage test over sheath: The test shall be conducted as per Clause 15.1 of
IEC 60840.
iii. AC voltage test for the installation: The test shall be conducted as per Clause
15.2 of IEC 60840.
iv. The insulation resistance of the cable shall be checked before & after the HV
test on cable: The core resistance shall be measured and the value corrected
in accordance with clause 5 of IEC 60228.
v. The cable must be discharged on completion of DC High Voltage Test and the
cable shall be kept earthed until it is put into service.
The values obtained during these tests shall be in conformity with the values
obtained during inspection of the materials at the manufacturer‟s works.
208-25 Accessories
During detailed inspection, it should be verified whether proper cable route markers
have been provided on the entire route.
After defects noticed during detailed inspection are rectified, Manager/Traction shall
carry out general Inspection to make sure that the installation is in good order.
During this inspection, the inspection party will carry out as many spot checks as
possible to confirm that the detailed inspection has been properly carried out earlier.
On the basis of their personal observations, a joint certificate will be issued by the
inspecting officers and contractor/nominated agency representative, confirming that
the installation is fit in every respect for energisation.
After getting sanction of the Electrical Inspector to the Metro Railway and clearance
certificate from all concerned in a manner similar to the procedure for energizing
OHE, the transmission line may be energized provided the sub-station and the
connected protective gear have already been tested and commissioned
208-27 25 kV Feeders
Detailed and general inspection of 25 kV feeder lines should be carried out on the
same lines as described for the transmission lines and the OHE. No earthed
structure, other than the earthed supporting structure of the 25 kV feeder lines and
earthed roof structure in certain cases shall be nearest than 2 m from the live OHE.
If the substation is already energized, the 25 kV feeder lines can also be energized
on lines similar to procedure described for the transmission lines and the OHE after
taking all precautions for safety of equipment and staff working on contiguous
sections.
In carrying out the tests, the manufacturers' instruction manuals should be followed.
The commissioning engineer should be well acquainted with the principles of
operation, constructional features and the traction load conditions, so that the relays
may be correctly set. Test report format should be in accordance to protection
philosophy and O&M consent should be taken before finalizing testing protocol.
i. All relay settings may be calculated as per the fault level at each and every
node in the network.
ii. The CT Ratio and polarity, proper connections, must be checked by
competent protection engineer.
iii. All protection schemes may be tested from primary side, i.e. primary injection.
iv. All configurations, LED indication, Tripping time, relay operation times may be
tested at site as per scheme.
v. All unit protections, such as REF, Differential, Bus bar differential protection
etc, must be tested for stability.
vi. The actual CT ratio in field and relay configuration should also be included in
site test report.
vii. Each and every relay should be tested for all its protections, irrespective of
back-up or main protection.
viii. Transformer Vector Group configuration in relay should also be included in
Site test report.
ix. The tank earth protection case, transformer must be tested for its insulation
from earth and also to be ensured that it is earthed at one point only.
x. Ferrules labeling of control cables may be verified with as built drawing.
The performance of the relay for different settings should then be checked using
standard relay testing equipment, making such adjustments as may be found
necessary. A detailed report on the test set up and the test reports should be kept as
permanent record. A test certificate should be issued to the field officer for record.
Simultaneously, maximum demand meters and energy meters should also be got
calibrated and sealed in consultation with the Supply Authority.
The following protective and indicating devices are provided for each traction
transformer:
Proper functioning of each of these relays and the contact mechanism of each
should be checked individually. At the same time, the correct operation of the
following annunciations and the associated cancelling buttons should also be
checked:
Check should be made of all indicating instruments on the control panel to see if the
movements are free and the readings are correct. Test plugs, where provided for
checking relay operation, should be examined if they fit properly. Indicating lamps
should be functioning properly, but a switch should be provided to cut them out when
the station is unattended.
Check should also be made for proper functioning of device provided for tripping CBs
in the event of 110 V DC supply failure.
control panels with respect to the approved wiring diagram. Insulation and continuity
tests should also be carried out and values recorded.
A word of caution is necessary here. The detailed diagrams of control circuit and
wiring of control panel supplied by the manufacturers should not merely be taken on
trust, but subjected to careful scrutiny for their correctness. Errors do occur in
drawings and if they are not detected at the very early stage itself, they may cause a
great deal of confusion and trouble later. The best method of detecting errors in
detailed wiring diagram is to prepare a simplified schematic or functional diagram so
that the circuit arrangements become quite clear and obvious. It will then be known
what exactly to do for any test, what links to close or open and what connections to
make or break. To restore the connections back to normal after the tests have been
successfully completed, a detailed diary should be kept of every change or alteration
made for purpose of test. If any modifications are required to correct the errors
discovered, the manufacturer should be advised immediately and his confirmation
obtained. When the work is completed, overall operation may be checked by
manually closing the relay contacts and finding out whether the appropriate device
has operated or not.
208-32 Fuses
Control circuit fuses shall be of correct rating. If the trip battery circuit fuse is under-
rated, it is liable to deteriorate due to excessive heating and fail ultimately, which
could indeed be dangerous. To guard against this possibility, alarms are sometimes
provided to draw the attention of the operator in the event of fuse failure. In AC
traction, failure of battery fuse is automatically relayed to the OCC but the TPC
cannot replace the fuse by remote control, someone has to go and replace it, which
may take considerable time. For the same reason all connections in the trip circuit
should be well made and the fixing screws kept tight, but not over-tight which may
cause excessive pinching of the connecting lead and may eventually cause a
breakage.
Insulation resistance should be measured. Any connection to earth and wiring made
deliberately such as earthing links on current and voltage transformers and on DC
supply should be removed before the test and care should be taken to put them back
as soon as the test is over. Measure and record the insulation resistance of the
following circuits:
When measuring the insulation resistance to earth of an individual circuit, all other
circuits should be normal i.e., earth links closed to ensure that the insulation is
satisfactory both to earth and all circuits.
Lead burden should be measured between current transformer and the relays to
ensure that the burden imposed on the CT is within its capacity. This test will reveal if
there is any poor contact in the secondary circuit of the CT or if the distance between
the transformer and the control panel is too long. With a CT rated at 5A, lead
resistance is particularly important.
Every CT should be individually tested to verify whether the polarity markings on the
primary and secondary terminal are correct, using the set up shown in Figure 208-
01. „A' should be a moving coil centre zero type low range ammeter. A 6V storage
battery may be used to energize the primary winding through a single pole push-
button switch. On closing the push button, the DC ammeter should show a positive
flick, and on opening a negative flick.
POLARITY TEST OF CT
PUSH BUTTON
T +
T1 T2
Fig. 208-01
This check is carried out with a “primary injection set”, which is usually connected to
the 240V supply mains and furnishes heavy current at a low voltage. Provision
usually exists to connect the secondary windings of the test set either in series or in
parallel to get the necessary output. A 10 kVA test set usually permits currents up to
1000A to be obtained with four secondary windings in parallel and up-to 250A at a
higher voltage with the windings in series. When dealing with very large currents, it is
essential that the connecting leads and area of contact and contact pressure should
be adequate enough, otherwise, higher values of current will not flow. The merit of
primary injection test is that it gives an overall check on the correctness of the entire
circuitry.
Polarity of the potential transformer could also be checked using the same method
described for current transformer testing. In this case, however, care should be taken
to connect the battery supply to the primary winding with the moving coil ammeter
connected to the secondary winding.
These tests are done with a secondary injection test set. For directional relays,
directional characteristics are checked.
Ensure that all fuses, links, trip latches etc. are in normal position. By operating each
relays manually, verify if the appropriate circuit breaker trips. Inter-tripping of primary
and secondary circuit breakers should also be checked. There should be no normal-
operation of any other circuit. In every case of tripping, the appropriate flag indication
should take place on annunciator, accompanied by operation of the alarm.
After the section is commissioned, a final check should be made of the proper
operation of all voltmeters, ammeters and relays when normal load currents are
flowing through the circuits. For differential circuits, spill currents should be
measured to prove that protection will be stable under external faults, by shorting the
secondary terminal on one current transformer and operation under an internal fault
should also be checked. The directional features of directional relays should also, be
checked. This ensures that the, relative polarity of CT and PT is correct.
i. After OHE has been successfully charged at 25 kV for a short time, it is de-
energized to conduct final confirmatory test on the operation of OHE protective
relays. Although relays would necessarily have been tested on the test bench in
the laboratory and subsequently in the field after erection, a final confirmatory
field test is essential before declaring the section as fit for commercial operation
to ensure that in the event of a fault the relays do trip.
ii. The over current and minimum impedance protection relays should all be set for
instantaneous operation as mentioned earlier. In all, the following two tests are
necessary and in each case all the feeder circuit breakers and their associated
relays should be tested one after another:
a. A fault at the farthest end of a single line section under emergency feed
conditions to check the operation of the minimum impedance relay and also
the under-voltage relay at the sectioning post.
b. Closing the bridging interrupter at sectioning post to check the operation of
minimum impedance relay.
iii. In carrying out Tests (a) and (b) one must provide and be prepared for the very
remote contingency of the minimum impedance relay failing to trip the circuit
breaker when it is closed on the fault. Before starting the test, trip circuit
operation should be checked by manual closing of the relay contacts. A
responsible official should remove the minimum impedance relay cover and be
ready to close the relay contacts manually and trip the circuit breaker, should it
fail to do so automatically when the circuit breaker is closed on the fault. Should
this happen, the connecting leads on the minimum impedance relay should be
reversed and the test repeated.
iv. For carrying out the short circuit tests, care should be taken to earth the line by a
105 mm2 solid flexible jumper to an earthed structure. A thin wire such as 14
SWG should never be used for connection to earth, under the mistaken
impression that the fuse would blow out and not jeopardize system stability,
should the 25kV circuit breaker fail to trip. It should be remembered that the
circuit breaker is designed to clear the fault whereas the improvised fuse is not.
When it blows on account of heavy short circuit current, the flash over caused by
it can damage the galvanization of the mast and perhaps shatter any insulator
nearby.
v. A point to be ensured in particular is that none of the relays at the grid substation
trips during any of these short circuit tests. This can be ensured earlier by proper
co-ordination of relay settings at the traction sub-station. Normally, the traction
circuit breaker trips within about 150 ms from the occurrence of short circuit. The
Supply authorities should be requested to set their relays allowing a time lag of
0.5 seconds to ensure that the substation circuit breaker does not trip on account
of faults in Delhi Metro traction system.
vi. It is quite possible that during short circuit tests, more than one relay associated
with the feeder circuit breaker may operate e.g. the minimum impedance relay in
addition to the over-current relay, even for a fault close to the sub-station. This is
quite in order, since this automatically gives back up protection. A note should be
made as to which relays have operated to ascertain which of the protective
relays have operated during each test.
vii. The operation of the under voltage relay at the sectioning post for a fault at the
farthest end under emergency feed conditions can be checked by posting
someone at the sectioning post. The test could however be postponed by a few
days and conducted after introduction of commercial services.
viii. Since these confirmatory tests are to be conducted after successful energisation
of the OHE and before introduction of commercial operation, it is essential to
complete the tests in the shortest possible time. However, being the most severe
tests these should not be repeated too often. This can be ensured by organizing
the work properly by posting testing parties at the right places and controlling all
operations through the TPC and by SCADA.
415V, 3 Phase Power supply for all switching stations is arranged from ASS (at
stations) through MDB‟s and miniature circuit breakers.
The installation of every item of equipment like interrupters, isolators, bus bars,
lightning arresters and wiring from equipment to the control panel in the switching
stations cubicle, 110 V batteries and battery chargers etc. should be, checked,
keeping the points referred to in Para 208-15 to 208-18 in mind, except for the
following minor variations:
208-44 Clearances
ii. Distance between any live part (25 kV) and 500 mm
earthed part or part likely to be earthed
(In special circumstances and with the approval
of the design office this can be 450 mm)
iii. Between any live part (3 kV) and earthed part 150 mm
such as return conductor or return feeder
Check and ensure that the distance from the centre of the nearest track to the face of
the switching station gantry is not less than that specified in SOD (Schedule of
Dimensions)
These should be inspected and tested in accordance with the procedure earlier
stipulated under “Substation” part above. The mounting of these transformers should
be checked to ensure proper fitment and conformity with schedule of dimensions and
electrical clearances. The jumper connections in particular should be checked to
ensure electrical clearances especially during windy conditions. Four pedestal
insulators should be used for BT jumpers support (2 vertical and 2 horizontal) at BT
locations.
208-46 General
Facility for spare loading and unloading of heavy materials transported by OHE
inspection car/road vehicle should be available.
208-47 Interlocking
Verify whether the isolator associated with every interrupter is equipped with an
interlock and is functioning properly. It should not be possible to open or close the
isolator unless the interrupter is locked in the open position as the isolator is not
permitted to operate on load. Interlocks for the bridging interrupter at the sectioning
post (SP) provide for the following:
This is achieved by utilizing 110 V AC supply from potential transformers provided for
this purpose at the sectioning post. Provision is also made for the bridging interrupter
to trip if the catenary voltage drops too low. This setting is adjustable and should be
set at 19kV.
At SPs, interlocking to prevent bridging of supply from both ends should be checked.
If a 25kV bus is energized, bus incomer shall not be closed. Incoming feeders from
UP & DN tracks of main lines should also be interlocked. At depot feeding post,
feeds from TSS and main Line should be interlocked. In depots where OHE runs
inside sheds like IBL (Inspection Bay Line). Interlocking is provided between double
pole isolator (with earthing heel) & gate to overhead platform/walkway. Any other
interlocks as defined in design shall be checked. Some of the interlocks are
implemented through SCADA.
At locations where the traction substation is far away, the feeding post close to the
tracks will receive 25kV supply from the traction substation, with 25kV feeder circuit
breakers located at the substation end and isolators at the feeding post end.
The return current at the feeding post is collected through return cables connected to
an ITL/IB (Integral Transverse Link/Impedance Bond) which is formed by bonding of
the track rails, RC, OPC and civil structures (viaduct piers, segments/girders,
parapets, handrails, track plinth etc). The rails may be connected to the bond directly
(e.g. Line 3&4 and airport line of DMRC where one rail of each track is designated as
traction rail for connection to bond) or through an impedance bond as per advice of
signaling department. The return cables carry return current from the ITL at feeding
post to a Bus/Buried Earth Rail at traction substation. This Bus/Buried Earth Rail in
turn is connected to neutral terminal on secondary side of traction transformer
through a set of return cables. These connections are vitally important for the proper
and safe working of the traction system and under no circumstances these should be
broken.
Examine all the connections and make sure that the cables are well bonded to the
rails with sufficient length left free for flexibility. The return cables should be well
protected mechanically to prevent being cut and stolen.
Check the numbering of the interrupters, isolators, PTs and then jumper connections
to the OHE to see if they do correspond to the numbering scheme as per the
approved drawings and these should match the numbering scheme in SCADA
system.
Check also if the following boards and fittings are provided at each switching station
if located in a separate enclosure or room:
The structural steel work and the metal case of every electrical equipment shall be
connected by two independent connections to earth in accordance with the “Code for
Earthing Traction Power Supply Installation”. According to this code, HT and LT
earths should be provided separately, but interconnected together by a link.
During detailed inspection, the resistance of each electrode should be measured and
recorded by a megger earth tester so that the combined resistance of the HT
earthing system is within the specified limits.
Traction Power Control center in the OCC is the nerve centre of the traction system,
from where full control over every switching operation on the entire electrified route is
exercised; its efficient operation is, therefore, of prime importance for successful
working of the system. It is desirable to complete all tests and trials on the remote
control equipment at the OCC and at the switching stations and to make them fully
functional before Energisation of OHE. To achieve this, tests and trials should start
about a month earlier, by which time the following item of work should be ready.
The switching station attendants should be given adequate training in their duties
and should normally be available from about a month before the date of
commissioning. A log book should be maintained.
208-53 SCADA
Before carrying out of tests at site, contractor should supply the copies of all
approved drawings, schemes, testing procedure for each test, list of testing
equipment required at site, copies of routine and type tests and reports for system
integration tests done at factory for reference.
i. The type and routine test reports should be seen and thereafter tests should be
conducted during commissioning given in ensuing paragraph. The erection and
commissioning tests of SCADA equipment shall be carried out as per test
procedure. Particular care shall be made for testing the Telecommunication
parameters required to be checked, so as to ensure the effective working of the
SCADA system.
ii. Tests shall be carried out on the complete equipment in the presence of the
representative of Delhi Metro Rail Corporation to check the proper erection and
successful commissioning of the equipment. This shall include functional tests,
checking of adjustment of transducers, limit settings of measurands, cyclic
update time, and Tele-command Execution Time, scan time measurement, signal
levels for satisfactory operation of the equipment.
iii. It will be required to conduct tests on the communication cable on which the RTU
has to be connected. Measurement of the communication cable parameters shall
be done for each section before connection of the RTU to the cables. The test
shall be conducted for all the cable parameters as specified in the specification.
Response time of the SCADA system shall be actually measured and recorded
so as confirm it with what has been theoretically calculated and mentioned in the
specification.
After successful completion of all type tests, integration tests, routine tests and after
commissioning of the system at site SAT shall be carried out. Hardware vendor shall
have the responsibility of SAT. SAT shall be carried out in presence of hardware and
software vendor.
All these tests carried out jointly shall be recorded so as to establish, authentic initial
record of the performance of the equipment to ensure that the RC equipment is
complete and trouble free.
As given in Para 208-47, interlocking is necessary for safe operation. Some of the
interlocking is implemented through SCADA using input from 25kV Line PTs such as
Interlocks in the RC equipment for the bridging interrupter at the sectioning post
provide for the following:
This is achieved by utilizing 100 V AC supply from potential transformers provided for
this purpose at the sectioning post. Provision is also made for the bridging interrupter
to trip if the catenary voltage drops too low. This sectioning is adjustable and should
be set at 19kV. The above interlocks should be thoroughly checked when
commissioning RC equipment at sectioning posts.
After defects noticed during the detailed inspection as above have been rectified, the
Manager (Traction/Project) together with the Contractors representative shall carry
out general inspection of the entire installation to make sure that it is in good working
condition. During the inspection verification of as many tele-command and tele-
signals operations as possible shall be carried out from the control centre. Inspection
of all the SCADA installations and RTUs at every receiving sub-station and switching
posts shall also be carried out. Level and frequency measurements should be taken
at random at a few points to compare the result obtain with those recorded during the
detailed inspection.
When fully satisfied with their observations and tests, they should certify that the
remote control installations are fully fit for commissioning. Thereafter, the remote
control may be put into regular services and its operation closely watched by
manning the switching stations and sub-stations as mentioned earlier. TPC and the
maintenance officials shall immediately thereafter maintain detailed record of every
failure. Each of these failure should be gone into fully to ascertain the cause of
failure, which incidentally would give the staff excellent opportunity to get familiar
with the circuitry and fault- finding procedure. Such failures should be brought into
the notice of Project officials, SCADA contractor; whenever deemed necessary.
VI OVERHEAD EQUIPMENT
The importance of OHE arises from the fact that it is extensive, with a very large
number of insulators, fittings and component parts, failure of any one of which may
result in dislocation of traction services for appreciable periods until the defect is
rectified. The adjustment work is particularly important at crossover and over-lap
spans since any wide departures from the standards laid down could cause
entanglement of the pantograph with the OHE, with serious repercussions. Section
insulators, neutral sections if not adjusted properly, could get damaged or could
cause damage to pantograph. Use of wrong connectors for jumpers, missing/wrong
material of pins/incorrectly installed pins, inadequate clearances especially during
windy conditions, trees close to OHE, improper materials/design of components,
loose building materials, places for bird nesting, insufficient C-jumpers, incorrectly
installed jumpers, loose/inadequate earthing & bonding, damaged conductors, could
cause serious OHE failures and traffic disruptions. The need for a very thorough
detailed inspection of every part of the installation, post by post is essential
requirement for safety and reliability of the system.
When the OHE contractor reports completion of all adjustment work, detailed
inspection will be carried out by the Manager-Traction (Project) and representatives
of the Contractor, using Catenary maintenance vehicle tower wagon or ladders as
may be convenient.
The OHE design and execution should be strictly in compliance with the latest
approved General Power Supply Diagram, Sectioning Diagram, Layout Plan and
Structure Erection Drawing, particularly in regard to
208-59 Infringements
None of the wayside or over-line structures shall cause infringement of the Schedule
of Dimensions. Every such infringement shall be individually recorded and action
taken immediately either to have them removed or, where this is not possible, to
obtain sanction from the Commissioner of Metro Railway Safety.
i. Cantilever Assemblies:
Every cantilever assembly shall be adjusted strictly in accordance with the
approved structure erection drawing, especially in regard to the positioning of
stay arm, bracket tube and register arm. The projection of bracket tube and
register arm and the allowance in the stay arm shall be sufficient for slewing
of tracks wherever required. All nuts should be tightened and locking plates
provided with split pins or check nuts. Make sure that all temporary earths
provided by contractor's men during construction work have been removed.
iv. Insulators:
Insulators shall be perfectly clean, damage free. Should the surface be
polluted by dust, it should be cleaned and gloss restored in case of ceramic
insulators. All insulators on out-of-run wires should be so located that they do
not foul but are well away from the zone swept by the pantographs. The
runners of section insulators should be so located as to be beyond the zone
of sweep of pantographs running on adjacent tracks. There should be no
undue sag due to the section insulators, the runners should be level and not
be tilted to one side so that the pantograph may pass smoothly.
viii. Stagger:
Stagger in tangent track shall be to the left and to the right alternatively, not
exceeding 200 mm on either side of the centre line of the track, except where
otherwise specified in Structure Erection Drawings. Stagger for in-run OHE
shall not be more than 300 mm at the mast/ structure on the outside of curves
except in case of overlap spans and also at the turn-outs. Stagger of contact
wire at mid-span in transition portion of the curves shall be within 200 mm.
x. Clearances:
The live metallic caps of insulators on out of run wires shall be atleast 2m
away from adjacent earthed mast/structure (other than the OHE structure).
The distance of these insulators shall be 3 m from the bracket supporting the
OHE in case of insulated overlaps. Clearance of 2 m shall normally exist from
nearest point of two adjacent elementary sections except at the section
insulators. Where clearance of 2 m is not available, it shall be not less than
the minimum specified electric clearance in any case. Whenever the OHEs of
two elementary sections cross one another, necessary cut-in insulators shall
be provided. All clearances as per SOD must be ensured. Other than the
clearances at overlaps, clearances of RC to anticreep wire, RC to OHE
xi. Bonding:
Every mast/structure supporting OHE as well as platform structures, foot over
bridges, railings etc. shall be properly bonded to the OPC/BEC and earthed in
accordance with the bonding and earthing code. All bonding connections
should be firm as per the approved drawings. The isolator mast in front of
feeding post should be connected to BEC also besides proper connection to
OPC. OPC must be provided with tapping at all clamp locations.
xiii. Pins:
Make an inventory of all split pins as per drawings/specifications which
should clearly indicate the material and size of these pins. A detailed list of
components with matching pins should be used as a check list and it should
be ensured that split pin of only right material and proper size is used. Ensure
that split pins are properly installed and expanded.
xv. Droppers:
All droppers should be provided as per dropper schedule at the time of
installation following correct methodology of crimping.
xx. Trees:
Check if any tree branches in the vicinity of OHE are likely to infringe the
clearances. Such branches need to be pruned.
iv. Insulators:
Insulators shall be perfectly clean. Should the surface be polluted by dust, it
should be cleaned.
vi. Stagger:
Stagger in tangent track shall be to the left and to the right alternatively, not
exceeding 200 mm on either side of the centre line of the track, except where
otherwise specified in Structure Erection Drawings.
viii. Clearances:
The clearance between 25kV live parts to earth shall not be less than 270mm
& 170mm for static & dynamic cases respectively.
ix. Bonding:
Every mast/structure supporting OHE as well as platform structures, foot over
bridges etc. shall be properly bonded to the OPC and earthed in accordance
with the bonding and earthing code.
x. Jumper connections:
The connections of feeding cables return cables and jumpers to be checked.
During the detailed inspection, special attention should be paid to verify whether the
following notices have actually been displayed at the various locations indicated
below:-
ii. General ‘Caution Notices’ regarding danger of high voltage traction wires
shall be displayed for public at various entrances to station and for staff at
prominent places at each station, particularly on stations or pillars supporting
platform roof.
iii. 25kV Caution Boards and mast number plates shall be provided on all
masts/portal/TTC uprights.
iv. “25 kV Cautions Boards” shall be affixed on to the screens erected on foot
over, road over bridges and both ends of platform.
viii. Boards for "Switching on" and "Switching off" of power at neutral sections.
Four boards are required for each track.
xiv. BT overlap caution: Identify the viaduct locations where halting of train of
any formation (4, 6 or 8 coach) could cause bridging of BT overlap with
pantograph. Paint these viaduct locations in red colour to facilitate TO (Train
Operator) not to stop the train in red painted zone.
During the detailed inspection, defects and deficiency lists as indicated in Para 208-
03 shall be jointly prepared. As soon as the defects are rectified, the Manager
(Traction/Project) should be advised and suitable remarks made against each Item of
the list. If deemed necessary, re-check the Installation, to ensure rectification of
defects.
208-63 General Inspection of the OHE by Delhi Metro Rail Corporation Officers
After all major defects observed during detailed inspection have been rectified;
Manager (Traction/Project) shall carry out a General Inspection of the entire section
proposed for energisation, along with the contractor's representative. For this
purpose, an OHE inspection car fitted with pantograph shall be used and run at a
speed not exceeding 8 km/h observing all safety precautions laid down, such as
earthing the OHE. The pantograph may be used to measure height and stagger of
contact wire, which should be test checked at least at two locations per track KM.
The object of this "General Inspection" is to make sure that the OHE and connected
installations are in good order and are fit for energisation. During this inspection, the
whole installation shall be inspected visually observing, in particular, the following
details and looking for anything unusual or abnormal in the installation:
After the OHE is ready in all respect, lapping and polishing of contact wire shall be
undertaken to remove all dirt collected on the contact face with the pantograph. For
this purpose self propelled vehicle CCMV/tower wagon with raised pantograph may
be use at a speed of 15 to 20kmp/h during the first run and not more than 40kmp/h in
subsequent runs. It is an advantage if before lapping by pantograph under side of
contact wire is manually cleaned by rubbing and wiping with a wet cloth and
detergent and finally wipe out with clean cloth. Normally 3 to 4 runs for lapping and
polishing may be done.
When lapping and polishing is in progress, suitable safety precautions to block the
section and earthing of the line as per rules should be taken and work is supervised
at a level not less than SE/OHE.
After the OHE is declared fit for energisation and all construction staff has been
withdrawn from the field, insulation and continuity test shall be conducted jointly by
officers with assistance of senior subordinates. This should be done before
energisation. This test should be conducted for every elementary section. The
following preliminary action shall be taken to prepare the circuit for the test.
To carry out the test in a systematic manner, a detailed program of work should be
prepared. A senior, experienced official should be nominated for controlling the
movements of all working parties each of whom will be given a copy of the program
with specific instructions so that proper sequence of switching operations is carried
out. This preliminary action should be taken at least a week in advance of the date
fixed for the test.
On the day of test, interrupters and circuit breakers at all switching stations shall be
taken on „local‟ control and remote control are put out of operation. All interrupters
and double-pole switches are then opened and locked in the open position ‟Danger-
Men Working‟ boards should be attached to the operating handle of each 25 kV
isolator at feeding post. All potential transformers at switching stations and lighting
arresters should be temporarily disconnected from the bus bars. All other isolating
switches in the yard and depots and other locations provided for isolation of
elementary section is also to be placed in the “off” position. When all these operation
are completed a confirmatory message shall be sent to the TPC.
The test shall be controlled by one senior official who shall continuously remain at
the OCC and direct all operations as required. Basically, these tests comprise:
The test shall be carried out by one party with the assistance of two or more field
parties as required. The control party alone will carry with it all test instruments and
take measurements. The field parties will merely carry out instructions given. They
should have with them necessary jumper connection and earthing poles for earthing
the equipment when directed to do so. The field parties are forbidden to carry out
any operations on their own. As the different working parties will be working at
different locations, independent from one another, they should carry with them
portable communication equipment through which they will remain in continuous
contact with TPC.
Along with the control party carrying out the tests, the contractors shall attach a work
party who will accompany the control party from location to location and rectify any
defects, which may come to light during the tests.
Starting from the feeding post, the control party will measure and record the
insulation resistance of every elementary section to earth by a 2500 V megger, after
arranging with the out-field parties to
If the tests for all elementary sections at that location are satisfactory, the control
party may proceed to the next elementary section and carry out similar tests. When
all elementary sections at a particular station have been tested, the control party will
move to the next station, directing the field parties to do likewise and carry out the
tests on each elementary section at that station as before until every elementary
section in the sector has been tested.
During the course of construction work, erection staff usually provides temporary
earths, on the OHE at certain locations to safeguard themselves, but after the work is
completed these temporary earths may not have been removed by oversight. Such
temporary earths on the OHE will give misleading readings during the final insulation
test. To prevent this, remove all such temporary earths before the testing
commences.
It is very difficult to lay down any specific rules in regard to the minimum permissible
values, as they depend upon a number of factors, which should be taken into
account when fixing the value in any given case. Some of these factors are
mentioned below:
Larger the number of leakage paths, lower would the insulation value. For the
same reason, the insulation resistance of 25 kV OHE tends to be quite low.
Assuming that each support Insulator has a value of 500 mega Ohm, an
elementary section may have 50 of them in parallel, bringing down the overall
value to 10 mega Ohm. Pollution will greatly diminish this too. A single badly
polluted section insulator may bring down the value to 0.5 mega Ohm or even
less. While one would not be switching on supply to a 3.3 kV transformer
showing so low a reading, 25 kV supply is commonly switched on to the OHE
even in such cases since the accumulated dust and smoke particles, which
are responsible for the low value of resistance, soon get burnt out, and the
insulation resistance usually improves greatly after energisation. As a thumb
rule, a minimum IR value of 25 mega ohm is desirable on new OHE
installations. On sections having pollution and several section insulators,
however, a value of 1 mega Ohm may be acceptable for charging which
needs to be improved subsequently.
When insulation tests are completed for all the elementary sections, the control party
may proceed in the reverse direction towards the feeding posts carrying out
continuity tests as described below -
In this test, the various control switches, which might have been opened out earlier
should be put back to their final positions as indicated in the Station Working Rules,
as in normal operation. Any temporary earths provided for earthing adjacent sections
shall be removed. When this is done, the various elementary sections are
automatically joined up electrically and each sub-sector is made through the
continuity test is then conducted by a low reading ohm-meter by measuring the
resistance of each sub-sector from the feeding post and with each sub-sector
earthed at the farthest point towards the neutral section. The through continuity of
every sub-sector shall be checked individually. It is important to note that a insulation
tester is unsuitable for measuring continuity as it may read zero even when the
resistance is as high as 1000 ohms.
If the tests show up any defects on the line, they should be rectified at once.
Sometimes, it may be found that although the insulation resistance is all right, there
is no through continuity on some sub-sectors. The most probable cause for this is a
disconnected jumper connection at an overlap span. This should also be immediately
traced and rectified.
The test results shall be recorded and signed by Manager-Traction (Project) and
forwarded to Electrical Inspector, along with other papers for sanctioning
Energisation.
While the engineers are busy carrying out tests and trials of electric equipment to get
everything ready by the target date fixed for commissioning, several steps
simultaneously have to be taken to be ready to operate the electrified services when
the section is commissioned.
The Supervisor P-Way and the maintenance gangs should be particularly advised
that the alignment of the ballasted track with respect to the OHE structures should be
strictly preserved and maintained. The need for this should be explained to them.
CHAPTER - 9
COMMISSIONING OF ELECTRIC TRACTION
209-00 Preparation
209-01 Technical Clearance of Metro systems by Railway
Board
209-02 Power & Telecommunications Co-ordination
Committee (PTCC) Clearance
209-03 No Objection Certificate from DOT Railway
Electrification unit
209-04 Organization for Inspection and Taking Over
209-05 Duties of Dy. HOD/Traction (O&M)
209-06 Notification regarding Energisation of OHE
209-07 Display of Caution Boards and Notices
209-08 Sanction of Electrical Inspector to the Metro Railway
209-09 Commissioning of RSS and TSS
209-10 Procedure for Energisation of OHE
209-11 Precautions to be taken for Progressive Energisation
of OHE
209-12 Anti-theft Energisation
209-13 Application to Commissioner Metro Railway Safety
209-14 Final Inspection by Commissioner Metro Railway
Safety for the Introduction of Commercial Services
209-15 Sanction of Commissioner Metro Railway Safety
209-16 Responsibility for Maintenance and Provisional
Acceptance Certificate
209-17 Contractor's Responsibility during DLP/Guarantee
Period
209-18 Failure of Equipment during the DLP/Guarantee Period
209-19 History Sheet
209-20 Final Acceptance
209-21 Standard Forms
209-00 Preparation
i. Apply and obtain approval of Railway Board as per RDSO Procedure for
Safety Certification and Technical Clearance of Metro Systems (January
2013) or latest.
ii. Apply and obtain PTCC clearance for all HT power lines to be laid for the
metro corridor.
iii. Apply and obtain No Objection Certificate from Department of
Telecommunication Railway Electrification (DoT RE) Unit for 25 kV AC
traction line.
iv. Create an organization, with sufficient number of trained personnel, to
take over the operation and maintenance of assets.
v. Recruitment and training of operation and maintenance staff;
vi. Have close interface between O&M and Project wings of DMRC during
final stages of erection and adjustment work to get them acquainted with
details of installation.
vii. Carry out detailed inspection of the works by Officers and senior
subordinates followed by general inspection by Senior Officers for getting
all defects rectified.
viii. Apply and obtain sanction for the Energisation of substations, switching
stations and OHE from nominated Electrical inspector of DMRC.
ix. Issue of Notification regarding Energisation of OHE
x. Energisation of OHE, tests and trials with rolling stock
xi. Final Inspection of traction installations by Commissioner Metro Railway
Safety.
xii. Commissioning and putting into commercial services.
xiii. Post-commissioning work, operation and maintenance.
xiv. Operationalisation of Preventive Maintenance Programme – In house or
through AMC.
Section 160 of the Electricity Act, 2003 gives directions about the Protection of
Telegraphic, Telephone and Electrical signalling systems. In this regard, a
standing committee formed by Central Government by the name of “Central
Power & Telecommunication Co-ordination Committee” (PTCC) is authorised to
issue clearance before charging of all HT Power lines. As a part of metro system,
HT lines are required to be laid to carry electricity from state supply network to
RSS and then to end-use points. Clearance of PTCC is required to be taken for
all these HT lines.
Information and guidelines regarding procedure for applying and obtaining PTCC
clearance are contained in PTCC Manual 2010 published by CEA (Central
Electricity Authority).
i. Create and fill up in advance all the posts of officers and staff in
accordance with the norms of DMRC.
ii. Recruit maintenance and operating staff and train them to man the
services, so as to position adequate number of trained staff in time to take
over the services.
iii. Position the supervisory cadre to ensure compliance with the laid down
requirements station by station.
iv. Expedite the completion of facilities for setting up OHE and PSI depot and
arrange to equip the emergency vans, OHE Inspection Cars and other
maintenance vehicles to undertake the maintenance and operation.
i. The Press
ii. The Commissioner Metro Railway Safety
iii. The Chief Electrical Inspector/Electrical Inspector
iv. CPMs & Other HODs of DMRC concerned with the line to be charged.
v. Power Supply Authorities as applicable
vi. DOT ( Railway Electrification unit)/PTCC authority as applicable
vii. Contractors of all departments engaged in the project through concerned
HODs
viii. Chief Security Commissioner, DMRC
Wherever Height Gauges are provided for road users crossing tracks to be
energised (in depot etc), warning boards at approach should be provided to
indicate about danger of 25kV electricity in OHE.
the meters jointly sealed by the Manager-Traction and the Officers of the
Supply Authority. After final meggering of the whole installation, all circuit
breakers and isolators are kept in the open position and the 'remote/local'
switch put in the 'local' position.
Power supply may then be switched on step by step to the incomer cables,
transformers and bus bars and the indications on the control panel checked.
iv. The two transformers may then be kept energized continuously. An
experienced supervisory official should be deputed to keep a close watch on
the equipment for the first three days, followed by a detailed inspection after a
week and then after fortnight.
v. Should a circuit breaker trip during this period; the cause should be carefully
investigated. The annunciator panel should be checked to ascertain which of
the relays have operated. Occasionally the Buchholz relay may operate. A
probable cause for this is when a transformer is energized for the first time air
bubbles which may have been entrapped between the windings when oil is
filled into the transformer tank, may get released when the transformer oil and
winding gets warmed up and may cause operation of the Buchholz relay.
However, a careful check is still necessary to ascertain the cause of every
tripping.
vi. 25 kV power supply may be extended up to the feeding posts if all work on 25
kV feeders and the feeding posts has been completed in all respects, after
taking the usual safety precautions.
vii. If the OHE is ready, Earth fault test for tripping of relays in RSS should be
conducted by connecting OHE to rail clamped with discharge rod.
viii. Proper record for all these tests and fault tripping should be maintained right
from day one.
The entire Energisation operation shall be carried out under HOD/ Traction
(Project) or his senior authorized DMRC representative nominated for the
purpose.
Sometime it may not be possible to energize the entire length between two
neutral sections served by a sub-station, but it is still desirable to resort to
progressive Energisation of one sub-sector after another as an anti-theft measure
keeping pace with the completion of work by the Contractors. In such cases of
partial Energisation, it is essential to take special precautions to protect men who
may be working on the OHE on sections adjacent to the energized and the live
OHE. The disconnection may be either an insulated overlap or an isolator or two
section insulators in series on the contact wires with corresponding isolation of
the Messenger Wire so as to ensure buffer section.
The double protection is necessary to provide for the possibility, however remote,
of an overlap span becoming short-circuited because of a stray fault. The action
to be taken is illustrated in Figure 209-01, which shows a single-track section but
the method applies equally to a double track section.
E A B C
In the figure–
i. The inspection of the entire section will be carried out by Commissioner Metro
Railway Safety accompanied by concerned officers. All necessary
documents, manuals, tools and tackles for measurements concerning the
traction installation must be kept ready.
ii. During this inspection, particular attention is paid to the safety and operational
aspects of the train movements and that staff are in possession of statutory
rule books, Instructions Book, Registers, forms etc. and that Operations,
Electrical, P-Way and S&T staff are fully acquainted with their duties and test
the knowledge of the staff such as engineering gangs, substation staff,
transportation staff at stations etc.
iii. A special train shall be kept ready at an appropriate location to take
Commissioner Metro Railway Safety, along with concerned officers for a final
Although during this period the equipment is operated and maintained by the
Delhi Metro Railway, the procedure described below should invariably be
followed to ensure that defects noticed during the DLP / guarantee period are
rectified by contractor / Manufacturers under contractor‟s responsibility under the
DLP / Guarantee Clause.
Typical forms for issue of notifications and certificates mentioned below are
appended at the end of this chapter.
Proforma 9-01
“PUBLIC NOTIFICATION"
Notice is hereby given to all users of Delhi Metro Railway lines and premises situated on
the completed section of the under- noted section of the Delhi Metro Railway that the
25000 Volt, 50 Hz., AC overhead traction wires will be energized on or after the date
specified against the section. On and from the same date the Overhead Traction Line
shall be treated as live at all times and no unauthorized person shall approach or work in
the proximity of the said overhead line.
HOD
(Traction/Project)
(To be published in all the leading Newspapers in English, Hindi and local language for
one day at least a week in advance before the date of commissioning.
Proforma 9-02
To
HOD (Traction or any other as applicable/Project)
i. The OHE in the above-mentioned section has been erected as per approved and
standard specifications and there are no infringements to the Schedule of
Dimensions (including the Rules applicable for 25 kV AC traction) except when
approval of competent authority has been obtained. The OHE has been
inspected and found to comply with the above requirements.
ii. The above Overhead Equipment have been jointly checked for completeness,
electrical clearances and tested for insulation and continuity, electrical
independence of different elementary sections as also bonding and earthing etc.
and found to be in order.
iii. The above Booster Transformer*, Feeder Lines* and Switching stations have
been jointly checked and tested for completeness, correct electrical connections
including cross-feeder connections, electrical clearances, insulation resistance,
earthing and bonding etc. and found to be in order. Test reports are separately
submitted.
iv. The work has been completed in accordance with the latest approved Generally
Power Supply diagram and sectioning diagrams etc. and complies in all respects
with the requirements of "Manual of AC Traction Maintenance and Operation" /
Standard specification and approved design/drawings/special instructions on the
subject and CEA (Measures relating to Safety & Electric Supply) Regulations,
2010.
v. All our staff have been withdrawn and warned that the line will be charged at 25
kV AC immediately. Clearance Certificates to the same effect have been obtained
from all the Contractors working on the above section. No work on the above
section will be taken up hereafter without obtaining a power block from an official
authorized by Dy. HOD (Traction/O&M).
vi. All safety precautions necessary have been taken in accordance with "Manual for
AC Traction Maintenance and Operation" / standard specification and approved
Place ........................
Date ..........................
Proforma 9-03
ii. Certified that bonding and earthing of the section have been carried out as per
the "Bonding & Earthing Code" and as per approved drawings.
Place ........................
Date ..........................
Proforma 9-04
ii. Certified that requisite instructions in connection with working on tracks and areas
equipped with 25kV AC traction have been issued to all categories of staff of
various departments working on and required to work on the section.
Further, it is certified that all staff have been made fully conversant with the safety and
precautionary measures to be taken when working in the electrified areas.
Countersigned
Director (Operation)
Proforma 9-05
Director (Operation)
Proforma 9-06
To
HOD (Traction/Project)
i. All signalling works have been carried out to make the installations suitable for
introduction of 25 kV AC traction.
ii. Signalling has been installed as per approved drawings and standard
specifications. Signalling has been installed as per approved drawings and
standard specifications under the relevant Rules applicable for opening of the
Metro Railways for Public Carriage of Passenger Rules, 2013; Metro Railways
General Rules, 2013, in-principle technical clearance given by Ministry of
Railways (Railway Board) for Signalling, Signal & Train Control Systems and
provision under 25 KV AC Traction Manual, Signal Engineering Manual and
Signal & Train Control Manuals for Delhi Metro.
iii. Signals have been erected without infringement to the „Schedule of Dimensions‟
except where approval of competent authority has been obtained. (Copy
attached)
iv. Necessary Rule books in connection with working in the section energized with
25 kV AC has been issued to the staff concerned. Specified tools suitable for
working in above 25KV single phase AC installation have been issued to the S&T
staff.
v. The signalling works mentioned above have been done according to the "Manual
of Instruction for Installation of S&T Equipment on 25 kV, 50 Hz AC Electrified
Sections".
vi. The undersigned has no objection to the energisation of the section mentioned
above on 25 kV AC with effect from.............
Proforma 9-07
To
HOD (Traction/Project)
Proforma 9-08
To
Dear Sir,
i. It is hereby certified that all our work on the above section has been completed.
ii. It is hereby certified that all our staff have been withdrawn and warned that the
above section would be energized on ................ and that no one may henceforth
carry out any work on the above section without obtaining a permit-to-work from
an official authorized by Dy. HOD (Traction/O&M).
iii. Adequate precautions will also be taken by our staff when working in areas
contiguous to the section electrified on ac 25 kV systems or on parallel lines.
iv. The dead overhead sections contiguous and adjacent to the electrified sections
have been and will be kept solidly earthed. The installations on the above section
are now ready and safe for Energisation. They may now be charged at 25 kV AC,
50 Hz, supply.
Date
Yours faithfully,
(Name)
For M/s.................
Contractor for OHE.
Proforma 9-09
To
HOD (Traction or any other as applicable/Project)
It is certified that:
i. The above RSS/TSS/AMS/ASS* have been jointly checked and tested for
completeness, correct electrical connections including cross-feeder connections,
electrical clearances, insulation resistance, earthing and bonding etc. and found
to be in order. Test reports are separately submitted.
ii. The works have been completed in accordance with approved drawings and
comply in all respects with the requirements as per the relevant Rules applicable
for 25 kV AC Traction System in opening of the Metro Railways for Public
Carriage of Passenger Rules, 2013; Metro Railways General Rules, 2013, in-
principle technical clearance given by Ministry of Railways (Railway Board) for
traction system & proviso under 25 kV AC Traction Manual for Delhi Metro/ the
Electricity Act, 2003 & its relevant Rules incl. procedures provided in Central
Electricity Authority (Measures relating to Safety & Electricity Supply) Regulation,
2010 and special instructions on the subject.
iii. All our staff have been withdrawn and warned that the TSS/AMS will be charged
at 220/132/66/33/25/0.415 kV* AC immediately. Clearance Certificate to the
same effect has been obtained from all the Contractors working on the above
section. No work on the above TSS/AMS will be taken up hereafter without
obtaining a power block from an official authorized by Dy. HOD (Traction/O&M)
iv. All other safety precautions necessary have been taken.
The ……TSS/AMS/ASS* referred to above are now clear and fit for energisation on
25/33 kV AC with effect from…………………
Place ........................
Date ..........................
Proforma 9-10
To
Dear Sir,
It is certified that all physical works have been completed on 220/132/66/33/ 25/0.415 *
kV TSS/ AMS/ASS at …... and that this TSS/ AMS/ASS* is fit to be charged on
220/132/66/ 33/ 25/0.415 kV AC, 50 Hz* with effect from................
All men, materials and temporary earths have been removed from the substation and
adjoining to OHE.
Place ........................
Date ..........................
Yours faithfully,
(Name)
For M/s .........................
Contractor for TSS/AMS