Professional Documents
Culture Documents
Public Toilet
Public Toilet
SLAB
X- Directio Bottom Top Total Length Total Length Total Length
NAME No. Direction n Shorter Longer Shorter Longer 8mm dia 10mm dia 12mm dia
Ware house
S1 8 3.3 3.425 17 17 17 17 1008.40
S2 4 3.3 5.15 17 26 17 26 759.60
S3 2 8.19 3.425 41 17 41 17 722.03
S4 1 5.875 5.15 29 26 29 26 305.13
S5 1 2.3 5.15 12 26 12 26 236.90
S6 1 2.9 5.15 15 26 15 26 298.70
Guard room
3.6 3.6 18 18 24 24 172.80 129.6
Generator room
1 4.1 5.3 21 27 21 35 370.82
Ramp
1 3.05 2.68 15 13 15 13 163.48
Total Weight 4037.85 129.60 0.00
8mm 10mm 12mm
Detailed Estimate for Public Toilet
F0R KAIMUR
GENRAL ABSTRACT OF COST
BUILDING PORTION:-
In Flooring
C.T Room 1 2.50 2.50 0.10 = 0.63
Entrance Lobby 1 2.50 2.15 0.10 = 0.538
Gents yard 1 4.38 2.20 0.10 = 0.964
Ladied Yard 1 3.25 2.20 0.10 = 0.715
Male & Female WC (Top & 2 7 1.20 1.00 0.10 = 1.680
Bottom)
Gents Bath 1 1.30 1.00 0.10 = 0.130
Gents Urinal 3 0.90 1.00 0.10 = 0.270
Stroe & Pump Room 1 1.60 1.00 0.10 = 0.160
Female Bath 1 1.40 1.00 0.10 = 0.140
Side Appron 2 5.40 0.50 0.10 = 0.540
Main Step 1 3.00 1.50 0.10 = 0.450
Front Appron 1 8.63 0.50 0.10 = 0.432
Column 18 1.00 1.00 0.15 = 2.700
9.34
7 5.1.2/45 Providing RCC in M-20 of Column Footings foundation to plinth level, Ground beam with approved quality of stone 4.375 Cum 3881.20 16980.74
chips 20 mm to 8 mm size graded stone and clean coarse sand etc. fo all complete as wer building specification
and direction of E/I.
11.30
Deduction
Cut Out in Slab 2 0.90 0.75 0.11 = 0.149
11.15
11 5.29.7B/ 47 M.S Reinforcement 2237.23 Kg 65.30 146091.12
Roof Beam
2 2 11.12 0.25 = 11.12
Lintel Beam
2 11.12 0.15 = 3.34
2 3 4.38 0.15 = 3.94
2 3 3.25 0.15 = 2.93
2 4 5.40 0.15 = 6.48
2 2.50 0.15 = 0.75
2 2.50 0.15 = 0.75
2 2.75 0.15 = 0.83
Chajja in C.T. Room
1 2.50 0.60 = 1.50
53.06
IV 5.14.3/46 RCC Roof Slab 63.74 Sqm 379.40 24184.47
1 11.42 5.70 = 65.09
Deduction
Cut Out in Slab 2 0.90 0.75 = 1.35
63.74
V 5.14.5/46 Sunshade in Main Entrance 3.51 Sqm 385.80 1354.16
1 3.00 0.90 = 2.70
2 0.90 0.10 = 0.18
Window Chajja
1 1.20 0.45 = 0.54
2 0.45 0.1 = 0.09
3.51
VI 5.14.3/46 Wash basin in Slab 1.00 Sqm 275.60 275.60
2 1.00 0.50 = 1.00
1.00
13 5.3/45 Providing RCC in M-20 in Wash Basin Slab 0.08 Sqm 3881.20 291.09
2 1.00 0.50 0.08 = 0.08
0.08
14 5.29.7B/ 47 M.S Reinforcement in Wash Basin Slab 6.28 kg 65.30 410.08
a @ 1% = (0.08 x 1.00 x 7850)/100 = 6.28
6.28
15 6.1.11A/49 First Class Brick Work in cm (1:6) ground level to plinth including all materials, labour for completionof work (250 12.42 Sqm 3992.90 49590.32
mm thick wall)
Horizontal Wall
2 11.12 0.25 0.60 = 3.34
2 4.38 0.25 0.60 = 1.31
2 3.25 0.25 0.60 = 0.98
1 2.50 0.25 0.60 = 0.38
Vertical Wall
4 4.90 0.25 0.60 = 2.94
Front Appron
1 8.63 0.25 0.45 = 0.97
Side Appron
2 5.40 0.25 0.45 = 1.22
Main Step
1 2.50 1.50 0.15 = 0.56
1 2.50 1.25 0.15 = 0.47
1 2.50 1.00 0.15 = 0.38
1 2.50 0.75 0.15 = 0.28
1 2.50 0.50 0.15 = 0.19
1 2.50 0.25 0.15 = 0.09
13.09
Deduction RCC Column
GL TO PL 18 0.25 0.25 0.60 = 0.675
12.42
16 4.25/44 DPC 50 mm thick in 1:2:4 on Wall 11.73 Sqm 218.10 2557.22
Horizontal Wall
2 11.12 0.25 = 5.56
2 4.38 0.25 = 2.19
2 3.25 0.25 = 1.63
1 2.50 0.25 = 0.63
Vertical Wall
4 4.90 0.25 = 4.90
14.90
Deduction Door & Openings
1 2.50 0.25 = 0.63
3 0.90 0.25 = 0.68
10 0.75 0.25 = 1.88
3.18
So, Net DPC 11.73
17 6.1.14A + First Class Brick Work in cm (1:6) superstructure including all materials, labour etc. for completion of work (250 26.20 Cum 3377.10 88463.98
6.3A/49 mm thick wall)
Horizontal Wall
2 11.12 0.25 2.75 = 15.29
2 4.38 0.25 2.10 = 4.60
2 3.25 0.25 2.10 = 3.41
1 2.50 0.25 2.75 = 1.72
Vertical Wall
4 4.90 0.25 2.75 = 13.48
38.50
Parapet Wall Pillar
11 0.25 0.25 0.15 = 0.10
38.60
Deduction : RCC Column
15 0.25 0.25 2.75 = 2.58
3 0.25 0.25 2.10 = 0.39
Door & Opening
Channel Gate 1 2.50 0.25 2.10 = 1.31
Door, D1 3 0.90 0.25 2.10 = 1.42
Door, D2 10 0.75 0.25 2.10 = 3.94
Urinal (O) 1 2.95 0.25 2.10 = 1.55
Ventilator 14 0.60 0.25 0.45 = 0.95
Window 1 0.90 0.25 1.20 = 0.27
TOTAL 12.40
So, Net Brick Work (38.60 - 12.40) 26.20
18 6.18.3A + First Class Brick Work in cm (1:3) superstructure including all materials, labour etc. for completion of work (125 29.14 Sqm 559.70 16308.82
6.19A mm thick wall)
+
6.21A/ 49
WC Partition Wall
5 1.20 2.25 = 13.50
2 1.00 2.90 = 5.80
Below Wash Basin Parapet 4 0.50 1.20 = 2.40
Sign Board 2 11.72 0.15 = 3.52
2 5.45 0.15 = 1.64
1 3.00 0.90 = 2.70
29.55
Deduction
Pillar in Parapet Wall 11 0.25 0.15 = 0.41
So, Net Brick Work 29.14
19 13.24.1/89 Providing 6 mm thick, Cement Plaster over Ceiling in cm (1:3) including all materials, labour for completion of 61.13 Sqm 82.90 5067.84
work.
24 Providing Chamber including all materials, labour for completion of work 6.00 Nos. L.S 30000.00
25 11.36/78 Providing & Fixing first Quality Ceramic Glazed Wall Tiles Confirming to I.S. 15622 in wall skirting 94.36 Sqm 754.20 71167.52
28 11.48.3/80 Kota Stone Slab Flooring over 25 mm (average) thick base laid over and jointed with grey cement slurry mixed with 31.62 Sqm 968.00 30606.71
pgiment to match the shade of the slab including rubbing and polishing
10 0.75 = 7.50
Window 2 1.20 = 2.40
1 0.90 = 0.90
Door D1 6 2.10 = 12.60
3 0.75 = 2.25
67.65
So, Weight of M.S Iron Frame
67.65 Rmt @ 3.50Kg/Rmt = 236.78
31 P/F Iron Hold Fast 82.00 Kg 65.00 5330.00
For Door 13 6 = 78.00
2 3 0.60 = 3.60
1 3 0.90 = 2.70
6.30
36 9.219.1 P/F of Aluminium tower boly with necessary Screws & bolt all complete. 26.00 Nos. 114.10 2966.60
37 9.222.1/70 P/F of Aluminium handles with necessary Screws & bolt etc. complete. 26.00 Nos. 71.00 1846.00
38 9.223/70 P/F of Aluminium hanging Floor Door, Stopper etc. Complete 3.00 Nos. 82.70 248.10
39 13.79.1/93 Finishing Walls with Water Proofing Cement Paint (New Work 3 or more coats) 485.21 Sqm 60.50 29355.27
44 Providing Rain spot for the Rain Water 15 Nos. L.S 1000.00
45 17.1.1 P/F of IWC Orissa pan 7 Nos. 3035.40 21247.80
46 17.2.1 P/F of EWC Orissa pan 1 Nos. 2953.50 2953.50
47 17.7.1 P/F of Hand Wash Basin 4 Nos. 2120.30 8481.20
48 P/F of Towel Rail 4 Nos. L.S 1500.00
49 17.31 P/F of Mirror (600 mm x 450 mm size) 4 Nos. 694.40 2777.60
51 18..48 P/F of 2000 Litre Capacity PVC Tank (2 Nos) 4000 Ltr. 6.80 27200.00
52 P/F of Granite Stone inauguration Slab 4 Job L.S 10000.00
53 22.3 Grading roof for water proofing tratment with Cement Mortar………. 1.30 Cum 358.60 466.85
11.42 5.7 0.02 = 1.30
54 Site Development & beautifying the area 1 Job L.S 10000.00
TOTAL 1,000,490
Total 1129097.31
Estimated Cost for Construction of 7 Seated Sulabh Toilet Complex at patna
SEPTIC TANK:-
(B) 75 dia HCI Vent Pipe (2 Nos. x 3.60m = 7.20m) 7.20 Rmt L.S 2000.00
TOTAL 178,442.61
Total Rs 212968.52
Estimated Cost for Construction of 7 Seated Sulabh Toilet Complex at patna
SOAKAGE PIT
Total 81544.39
Estimated Cost for Construction of 7 Seated Sulabh Toilet Complex at patna
P.H WORK:-
Sl.
No. Items of Work Qty. Unit Rate Amount
Groves cutting for taking out G.I Pipe, Wall & making good
4 the same including cost of conveyance of all materials to
site
TUBE WELL:-
Sl.
Items of Work Qty. Unit Rate Amount
No.
4 Providing
Cost of Mateirlas
(a) 125 mm dia PVC casing (80 schedule)
(b) 25 mm dia G.I Pipe Line
( c) Cost of G.I Flange, rubber insertion nut bolt etc.
(d) Cost
of lowering of rising pipe & installation of submersible
pump
(e) Providing hand pump with all fittings
Supplying , fitting and fixing 1.5 HP Submercible Pump with
5 starter and all necessary fittings including cost &
convenience all material to site ( as per actual basis)
TOTAL
Material Statement
Cement Course Stone Bricks Local
Sl.No. Item of Work Quantity (MT) Sand Chips (Nos.) Sand Bitumen Filler Emulsion
1 Local Sand Filling 39.79 - - - - 39.79
2 B/F Flat Soling 90.12 - - - 2907.271 1.3518
3 B.E.S 0 0
4 PCC (1:2:4) 1.75 0.56 0.77875 1.5575 - -
4 PCC (1:3:6) 9.34 2.0548 4.3898 8.7796 - -
5 RCC (1:1½:3) 23.52 9.408 9.996 19.992 - -
6 B/w (1:6) 38.62 2.41375 10.31154 - 19078.28 -
7 B/w (1:4) 0 0 - 0 -
7 Half B/w (1:3) 29.14 0.4161192 0.8730344 - 1646.41 -
8 6mm CP (1:3) 61.13 0.1672517 1.124792 - - -
9 12MM CP (1:6) 424.08 1.526688 6.530832 - - -
10 20MM CP (1:3) 0 0 - - -
11 Wall Tiles 105.4 0.8959 2.4242 - - -
12 Vitrified Flooring 47.03 0.399755 1.08169 - - -
13 Marbel Flooring 0 0 - - -
14 Granite 0 0 - - -
15 Chequred Tiles 0 0 - - -
16 G.S.B 0.00
17 W.M.M 0
18 Primer coat 0
19 Tack coat 0
20 B.M 0 0 0 0 0 0.00
21 S.D.B.C 0 0.00 0.00
22 D.L.c 0 0 0
Total : - 17.84 37.51 30.33 23631.96 41.14 0.00 0.00 0.00
1
32.26 0.015
53.76 0.03
0.32 0.445 0.89
0.22 0.47 0.94
0.4 0.425 0.85
0.0625 0.267 494
0.095 0.267 494
0.095 0.267 494
0.002736 0.0184
0.0036 0.0154
0.011 0.0239
0.0085 0.023
0.0085 0.023
0.0073 0.0154
0.0073 0.0154
0.0085 0.023
1.28
1.32
0.0006
0.0002
1.415 0.0724
1.461 0.114 0.0442
0.15 0.45 0.9
Material Statement
Sl.No. Item of Work Quantity Cement Course Stone Bricks Local Bitumen Filler Emulsion
(MT) Sand Chips (Nos.) Sand
Local Sand
1 Filling 0.26 - - - - 0.26 1