Professional Documents
Culture Documents
500 - Drainage and Service Ducts PDF
500 - Drainage and Service Ducts PDF
Contents
507 Chambers 11
March 2003 1
Volume 1 Series 500
Specification for Road Works Drainage and Service Ducts
501 Pipes for Drainage and for Service than those included in Table 5/1 shall be
Ducts permitted provided that they hold a
current Malta Transport Authority
General certificate (or equivalent) stating that
they are a suitable alternative for the
1 Where the term drain is used in this usage specified in Table 5/1. On
Series it shall be deemed to include the completion of the whole of the drainage
terms sewer and piped culvert. The works, the Contractor shall provide the
Contractor shall design the piped Overseeing Organisation with a schedule
culverts listed in Appendix 1/10 in showing details of all pipe types used,
accordance with the requirements of including quality, joints and name of
Clause 106. manufacturer.
March 2003 2
Volume 1 Series 500
Specification for Road Works Drainage and Service Ducts
March 2003 3
Volume 1 Series 500
Specification for Road Works Drainage and Service Ducts
March 2003 4
Volume 1 Series 500
Specification for Road Works Drainage and Service Ducts
Polypropylene (PP) Filter drains BS 4660 or Perforated with not less than 1000mm² of holes
per metre length of pipe. The perforation shall
Polyethylene (PE) BS 5481 or BS EN 1401 not reduce the pipe stiffness by more than 5%.
(PVC-U) Circular perforations not greater than 10mm
nor less than 3mm in diameter or rectangular
MSA 1852-1 (PP) slots not greater than 4mm nor less than 0.6mm
in width
PrEN 12666-1 (PE)
Thermoplastics structured Surface water drains Clause 518 Unperforated with watertight joints and with a
wall pipe and fittings not pipe stiffness class, creep ration and impact
exceeding 900mm diameter resistance as described in Appendix 5/1
All drains exceeding 900mm internal diameter shall comply with series 2500.
March 2003 5
Volume 1 Series 500
Specification for Road Works Drainage and Service Ducts
502 Excavation for Pipes and Chambers described in sub-Clause 1(i) of this
Clause;
1 Excavation shall comply with Clause 602
and with the following: (iii) any excavation greater than the net
volume required for the Permanent
(i) soft spots existing below the bottom of Works below the level of any pipe
an excavation shall be removed and surround shall be made good as
the resulting voids backfilled with described in (i) above.
Type 1 subbase material complying
with Clause 803 or pipe bedding 2 Unless otherwise described in Appendix
material complying with Clause 503, 5/1, all pipes in or under new embankments
both well compacted, or mix ST1 shall be laid only when the embankment has
concrete; been formed and compacted to formation
level under paved areas, to finished
(ii) any additional excavation below the earthworks level in other areas, or to a level
bottom of an excavation that is which will give a minimum cover of 1.2 m
required because the Contractor has to the pipes, whichever is the lowest.
allowed the bottom to become soft or
otherwise unacceptable for the
construction of the pipeline or
chambers shall be made good as
March 2003 6
Volume 1 Series 500
Specification for Road Works Drainage and Service Ducts
503 Bedding, Laying and Surrounding of Numbers F1 and F2, and shall comply with
Pipes the following:
1 Immediately following the excavation of (i) For pipes on beds shown on HCD
the trench, the pipes shall be laid and Drawing Number F1 as Types B, F
jointed on the pipe bed. Pipes shall be laid so and S the granular material consisting
that each one is in contact with the bed of natural and/or recycled coarse
throughout the length of its barrel. The pipes aggregate or recycled concrete
shall be laid at the level and gradients shown aggregate shall have:
on the Drawings and schedules. The
deviation in level rom that specified at any a) a grading in accordance with
point shall not exceed 20 mm and in addition Table 5/3; and
the algebraic difference of the deviation in
level at any two points on each pipe shall not b) a water soluble sulfate content
exceed 30 mm. In the case of socketed or of less than 1.9 grams of sulfate
sleeve jointed pipes the bed shall be cut (as SO3) per litre when tested in
away and removed at each socket or sleeve accordance with BS 812 : Part
to give a clearance of at least 50 mm, or 100 118 Clause 5.
mm for trenches in material designated as
Hard Material, so that the socket or sleeve (ii) For pipes on beds shown on HCD
does not bear on the bed. Pipes shall be laid Drawing Number F1 as Types N and
on setting blocks only where a concrete bed T the granular material consisting of
or cradle is used. Pipes and fittings shall be natural and/or recycled coarse
examined for damage and the joint surfaces aggregate or recycled concrete
and components shall be cleaned aggregate shall comply either with
immediately before laying. Measures shall sub-Clause 3(i) of this Clause or with
be taken to prevent soil or other material Table 5/4, with the water soluble
from entering pipes, and to anchor each pipe sulfate content complying with (i)
to prevent movement before the work is above.
complete.
TABLE 5/3: Granular Materials to BS
2 Pipes complying with BS 4962 : 1989 882 and Recycled Aggregates to Clause
which are corrugated coilable perforated 710
pipes shall, unless otherwise permitted in
Appendix 5/1, be laid only by automatic Normal Pipe BS 882 : 1992 Coarse Aggregate (Table 3)
Diameter
single pass drain laying machines. Graded Single Sized
Aggregate Aggregate Sizes
Ranges (mm) (mm)
3 Drainage pipe and bedding combinations
shall be selected from the alternatives Not exceeding 20 to 5 or 14 to 5 10
140
described in Appendix 5/1. Where recycled Exceeding 140 10,14 or 20
coarse aggregate or recycled concrete but not
exceeding 400
aggregate is used in this Series, it shall have Exceeding 400 14 to 5, 20 to 5 or 40 to 5 10, 14, 20 or 40
been tested in accordance with Clause 710.
Pipe bedding, haunching and surrounding
material shall be as shown on HCD Drawing
March 2003 7
Volume 1 Series 500
Specification for Road Works Drainage and Service Ducts
March 2003 8
Volume 1 Series 500
Specification for Road Works Drainage and Service Ducts
3 Watertight joints shall comply with the Clause 501.6 (iv) and the manufacturer’s
appropriate ADT Standards, the instructions.
manufacturer’s instructions and the
following: 5 Where a concrete bed, cradle, arch or
surround is used with rigid pipes having
(i) Rigid joints shall be used only where flexible joints, joint filler board complying
permitted in Appendix 5/1. Spigots with Clause 1015 shall be placed in contact
and sockets of rigid joints may be with the end of the socket at a pipe joint and
caulked with tarred rope yarn or shall extend through the full thickness of the
equivalent and the socket completely concrete in contact with the pipe. Such joints
filled with mortar designation (i) in the concrete bed, haunch or surround shall
complying with Clause 2404, be at intervals not exceeding 5 metres except
excluding lime; a fillet of mortar being where the spacing of joints in the pipe
worked around the socket extending exceeds 5 metres when they shall be at each
for a length of not less than 50 mm pipe joint.
from the face of the socket. Iron pipes
with open sockets shall have rigid 6 Joints in pipes for filter drains shall
joints caulked with lead wool or comply with the appropriate ADT and with
equivalent. the following:
(ii) Joints in PVC-U pipes shall not be (i) Non-porous and unperforated concrete
made with plastic solvent. and clay pipes with spigot and socket,
rebated or ogee joints shall be laid
(iii) Flexible mechanical joints may be with unsealed joints and with a gap of
used with surface water pipes 10 mm between the end of the pipe
complying with BS 65. and the inner end of the socket or
rebate. The pipes shall be supported
(iv) Joints for cast iron pipes to BS 437 with tarred rope yarn or equivalent
shall comply with BS 6087. flexible jointing material within the
sockets over the lower third of the
(v) Joints in thermoplastics structured wall circumference so that there are no
pipe shall comply with clause 518. vertical steps between one pipe and
another. Such pipes shall only be used
4 Partly watertight joints for surface water with Type B filter material as
drains shall be tested in accordance with described inClause 505.
sub-Clause 509.7 and shall be ADT Standard
joints or non- ADT Standard joints. Push fit (ii) The ends of perforated, castellated or
joints shall have a register to ensure that the porous concrete pipes with rebated
pipe is fully pushed into the joint. joints and perforated clayware pipes
Corrugated steel pipes of lock seam with rebated or with flexible sleeve
fabrication, not exceeding 900 mm internal joints shall be pushed tightly together.
diameter, shall be joined in accordance with The width of slots measured along the
the manufacturer’s instructions. Bolted length of the pipeline formed by
segmental plate pipe arches or circular pipes, jointing castellated pipes shall not
not exceeding 900 mm internal diameter, exceed 10 mm.
shall be joined in accordance with sub-
March 2003 9
Volume 1 Series 500
Specification for Road Works Drainage and Service Ducts
March 2003 10
Volume 1 Series 500
Specification for Road Works Drainage and Service Ducts
TABLE 5/5: Grading Requirements for Organisation a copy of the record of the
Filter Drain Material connections made the previous day. Where
pipe connections are made to existing brick
Percentage by Mass Passing Sieve
concrete or stone drains, chambers or
BS Sieve Sizes channels, the pipes shall be well and tightly
Millimetres Micr built into the concrete, brick or masonry
63 37.5 20 10 5 1.18
s
600 1
work and be so placed as to discharge at an
angle not greater than 60° to the direction of
Type A 10 100 85-100 50-100 35-90 15-50 5-35 0
Type B 85-100 0-25 0-5 flow of the drain or channel and with the end
Type C As described in Appendix 5/1
of the pipe carefully cut to the necessary
angle. Where the connections are between
pipe drains, special connecting pipes shall be
6 Except in carriageways, other paved areas laid and jointed as described in Appendix
and locations described in Appendix 5/1, 5/1.
backfill of trenches shall be brought up to
ground level. Where topsoil is at the surface 2 Before entering or breaking into an
on the line of the trench the upper section of existing sewer or drain, the Contractor shall
the backfill shall be topsoil of the thickness give notice of his intention to do so to the
described in Appendix 6/8, or of the same authority responsible for the pipeline to
thickness and quality of topsoil as the which the connection is to be made.
surrounding ground where no thickness is
specified. For trenches in carriageways or 3 Existing drains no longer required shall, as
other paved areas the backfill shall be required by Appendix 5/1, be sealed with
brought up to formation level, or sub- mix ST2 concrete or removed and replaced
formation level where capping is required, with general fill material complying with
unless a lower level is described in Clause 601 and Table 6/1 and compacted in
Appendix 5/1. Sheeting and other compliance with Clause 612, or grouted with
excavation supports shall be removed as the a 1:10, cement: pfa mix. The grout shall use
filling proceeds unless otherwise described the minimum quantity of water to ensure the
in Appendix 6/3. fluidity necessary to render it capable of
being pumped to the ends of the pipe. It shall
7 The position of service ducts shall be be used within one hour of mixing but when
marked where the trenches are backfilled the mix contains a retarding admixture this
and permanent marker blocks and location time may be extended in accordance with the
posts provided as described in Appendix 5/2. manufacturer’s instructions. The cement
Volume 1 home page shall comply with BS 12 and the pulverised-
fuel ash (pfa) with BS 3892 : Part 2, fineness
506 Connecting to Existing Drains to Zone B and sulfate content not exceeding
Chambers and Channels 1.5%.
chambers, draw pits and walled soakaways. 5911 : Part 200 and the particular
Chambers shall be of the type specified in requirements described in Appendix 5/1.
Appendix 5/1, constructed in accordance They shall be surrounded with well graded
with HCD Drawing Numbers F3 to F12 and granular material Class 6M as described in
F25 to F27 as appropriate to that type. Table 6/1 compacted in accordance with
Chambers for use in motorway Clause 612.
communications installations shall comply
with Series 6 Where the depth of invert of chambers,
1500. excluding inspection chambers, exceeds 900
mm below the finished surface of the
2 Foundations to chambers shall be of mix carriageway or the adjacent ground, manhole
ST4 concrete. Channels for chambers shall steps complying with BS 1247 : Part 1 or
be formed and finished smooth in the Part 2 shall be built in as specified in BS
foundation concrete or constructed of 5911 : Part 200. Steelwork used for ladders,
preformed half circle channels, with sides handholds and other fittings shall comply
benched in mix ST4 concrete, or mortar with BS 970 : Part 1 and be galvanized in
designation compliance with Clause 1909 after
fabrication. Threaded components shall be
(i) complying with Clause 2404 excluding galvanized in compliance with Clause 1909.
lime. Alternatively for inspection
chambers not exceeding 1.3 metres in 7 Excavation around chambers, except those
depth to invert, complete plastics units described in sub-Clause 5 of this Clause,
or other units in equivalent material shall be backfilled with general fill material
surrounded by 150 mm of mix ST4 as described in Table 6/1 and compacted in
concrete may be used. compliance with Clause 612. Where
mechanical compaction is impracticable, the
3 Brickwork shall comply with Series 2400 excavation shall be backfilled with mix ST2
and be built with mortar designation (i) in concrete. Where there are precast concrete
English bond. The joints of brickwork where access shafts to precast concrete chambers,
exposed shall be finished as specified for the shafts shall be surrounded by a minimum
unpointed joints in Clause 2412. The ends of thickness of 150 mm of mix ST4 concrete,
all pipes shall be neatly built into the and the remaining excavation backfilled
brickwork and finished flush with mortar with general fill material as described in
designation (i). Table 6/1 compacted in compliance with
Clause 612.
4 Precast concrete chambers shall comply
with BS 5911 : Part 200. Cast in situ 8 Chambers for foul drains shall be tested
concrete chambers shall be constructed of for watertightness as and where required in
mix ST4 concrete complying with Clause Appendix 5/1.
2602 unless otherwise described in
Appendix 5/1. 9 Chamber covers, gratings and frames shall
be as described in Appendix 5/1 and shall
5 Corrugated galvanized steel chambers comply with BS EN 124 and sub-Clauses 10
shall comply with Clause 501 with in situ and 15 of this Clause.
mix ST4 concrete inverts and precast Volume 1 ho
concrete cover slabs complying with BS
March 2003 12
Volume 1 Series 500
Specification for Road Works Drainage and Service Ducts
10 Class D 400 units and above shall 17 For all pipelines except those constructed
incorporate a permanent non-rock feature with corrugated pipes the nearest joint to any
either triangular point suspension or chamber shall be not more than 500 mm
machined faces. from the inner face of the wall and shall not
be restricted by any concrete. Between this
11 Bolts supplied for loosely coupling and the next joint, the length of the
separate sections of covers and gratings shall articulated pipe shall be in accordance with
be steel hexagon headed, complying with the Table 5/6.
requirement of ISO 4016, 4018 and 4034
and be galvanized in compliance with TABLE 5/6: Length of Articulated Pipe
Clause 1909. They shall not be less than size
M16 complete with hexagon nut and shall be Nominal Pipes Diameter (mm) Length of Pipe (mm)
provided with means to prevent undue 450 and less 500 to 750
tightening of unit sections.
Greater than 450 750 to 1000
March 2003 13
Volume 1 Series 500
Specification for Road Works Drainage and Service Ducts
508 Gullies and Pipe Junctions Brickwork shall comply with sub-Clause
507.3.
1 Gullies shall be trapped or untrapped as
described in Appendix 5/1 and be in 6 Backfilling to precast gullies shall be
accordance with HCD Drawing Numbers carried out up to sub-formation level with
F13 and F14. general fill material Class 1, as described in
Table 6/1 compacted in compliance with
2 Gullies shall be constructed so that no part Clause 612. Where mechanical compaction
of the spout or trap has a cross-sectional area is impracticable, the backfilling shall be in
less than 2/3rd that of the outlet. The depth of mix ST2 concrete. The remainder of the
water seal in trapped gullies shall be not less backfilling shall be in appropriate capping
than 50 mm. and road pavement materials except that
where mechanical compaction of capping or
3 Precast concrete gullies shall comply with granular sub-base is impracticable mix ST2
BS 5911 : Part 230 and clay gullies with BS concrete shall be used.
EN 295. In situ concrete gullies shall be as
described in Appendix 5/1 and constructed 7 Gully connection pipes shall be either
of mix ST4 concrete of 150 mm minimum flexible or rigid not exceeding 0.7 m in
thickness, using permanent or removable length with flexible joints for a distance of 2
shuttering. Where in situ concrete gullies are m from the gully and shall be in accordance
formed with permanent shuttering, such with sub-Clause 507.17 when entering
shuttering shall have a current British Board chambers. Junction pipes shall be
of Agrement Roads and Bridges Certificate manufactured of the same type and class of
(or equivalent) . material as the remainder of the pipes in the
run. Junction pipes which are laid but not
4 Gully gratings, kerb type gully covers and immediately connected, shall be fitted with
frames shall comply with BS EN 124 and temporary stoppers or seals and the position
the following and shall be of the classes and of all such junctions shall be clearly defined
sizes described in Appendix 5/1. by means of stakes or tracing wires properly
marked or labelled. Saddles may be used to
5 The upper surface of gully gratings shall form junctions only where permitted in
be flat except where otherwise described in Appendix 5/1. No internal projections
Appendix 5/1. Slots in gratings or between greater than 5 mm will be permitted. Saddles
gratings and frames shall not be orientated for asbestos cement and plastics pipes shall
parallel to the direction of traffic except be installed in accordance with the
where the slots are less than 150 mm long or manufacturer’s recommendations. Saddles
less than 20 mm wide. Minimum waterway with clay pipes shall be jointed with mortar
areas shall be as specified in Appendix 5/1. designation (i) complying with Clause 2404,
Unless otherwise specified in Appendix 5/1, excluding lime. Saddles and pipes shall be
all gratings and frames shall be supplied in a surrounded with mix ST2 concrete.
fine cast (uncoated) condition. Where a
coating is specified in Appendix 5/1, the 8 Where the adjustment or replacement of
coating shall only be applied when the existing frames and gratings is required, the
surfaces of the casting are clean, free from units shall be taken up and re-fixed or
rust and dry. Frames shall be bedded on removed and replaced with new units
mortar complying with sub-Clause 507.16. complying with sub-Clauses 4 and 5 of this
March 2003 14
Volume 1 Series 500
Specification for Road Works Drainage and Service Ducts
March 2003 15
Volume 1 Series 500
Specification for Road Works Drainage and Service Ducts
510 Surface Water Channels and 4 Severed mole drains shall be led straight
Drainage Channel Blocks into new drains; alternatively they shall
where required in Appendix 5/1 be
1 Surface water channels and drainage intercepted by the construction of a land
channel blocks shall be constructed as drain. Where they have been disturbed mole
described in Appendix 5/3. channels shall be cleaned out and filled
locally with Type A filter material or as
2 Surface water channels shall comply with otherwise described in Appendix 5/1.
Clause 1103.
March 2003 16
Volume 1 Series 500
Specification for Road Works Drainage and Service Ducts
March 2003 17
Volume 1 Series 500
Specification for Road Works Drainage and Service Ducts
March 2003 18
Volume 1 Series 500
Specification for Road Works Drainage and Service Ducts
March 2003 19
Volume 1 Series 500
Specification for Road Works Drainage and Service Ducts
March 2003 20
Volume 1 Series 500
Specification for Road Works Drainage and Service Ducts
March 2003 21
Volume 1 Series 500
Specification for Road Works Drainage and Service Ducts
(vi) Apply increasing increments of normal (a) the applied normal stress shall be
load to the specimen. Determine the the greater f the value given in
short term equivalent load which shall Table 5/7 for sub-Clause 15) or
be the load which when applied for a the mean short term equivalent
period of 20±5 minutes produces a stress as determined in sub-
specimen thickness equal (within an Clause 14 (vi) of this Clause;
accuracy of ±0.05 mm) to the long
term thickness of the specimen (b) the sample shall be tested such
obtained at (v) above. Repeat the test that the measured flow (or flows)
on the other two specimens. is in the same direction as the
principal flow (or flows) when
(vii) The report shall include: the fin drain is in service;
(a) a reference to this method; (c) the foam rubber option of the
test procedure shall be used
(b) sample identification details; (details of the foam rubber to be
used may be obtained from the
(c) the initial thickness of the Overseeing Organisation);
sample;
(d) the hydraulic transmissivity shall
(d) the applied load; be reported for each of the
hydraulic gradients employed.
(e) the thickness of each sample at
100 and 1000 hours and the Test Methods
mean of the three results;
16 Notwithstanding the requirements of sub-
(f) a plot of percentage reduction in Clauses 13, 14 and 15 of this Clause,
thickness against logarithmic variations in the test methods specified
time; therein shall be made where deemed
necessary by the ADT following
(g) the mean long term thickness; consultation with the manufacturer. All such
variations shall be recorded in the report.
(h) the mean short term equivalent
load; Certification
(i) any deviations from the specified 17 Fin drains and constituent materials shall
test procedure. have a current British Board of Agrement
Roads and Bridges Certificate (or
equivalent) certifying the appropriate
March 2003 22
Volume 1 Series 500
Specification for Road Works Drainage and Service Ducts
March 2003 23
Volume 1 Series 500
Specification for Road Works Drainage and Service Ducts
March 2003 25
Volume 1 Series 500
Specification for Road Works Drainage and Service Ducts
4 Width and depth of channel units shall not 8 Joints between units comprising the
exceed the dimensions given in Appendix system and between adjacent construction
5/6. and the system shall be designed to avoid
5 Dimensions of inlet slots shall comply leakage of surface water. Joints between
with the following criteria: The width of bridge deck waterproofing and component
straight slots orientated along axes between parts passing through the waterproofing shall
0° and 45°, also between 135° and 180° to be watertight. Sealants shall also be
the direction of traffic flow shall be between compatible with the waterproofing system.
10 mm and 32 mm. Slots within these
orientations which are less than 18 mm in 9 Junctions, connecting pipes and other
width shall not be restricted as to their fittings comprising the linear drainage
length, but slots greater than 18 mm in width channel system shall comply with sub-
shall not exceed 170 mm in length. Clause 501.3 and shall be as described in
Appendix 5/6. The linear drainage channel
Straight slots orientated along axes between shall incorporate measures to enable rodding
45° and 135° to the direction of traffic flow of the outfall pipework and adequate access
shall be between 10 mm and 42 mm in width for flushing by water jetting equipment into
and shall not be restricted as to their length. the system.
Slots in other shapes, eg curved slots, shall
be designed such that a 170 mm x 170 mm x 10 The system shall be cleaned out in
20 mm gauge is unable to enter the slot. A accordance with sub-Clause 516.7.
tolerance of ± 0.5 mm shall apply to the
gauge dimensions. Manufactured Systems
These slots shall also have adequate 11 Manufactured systems shall be comprised
hydraulic capacity in accordance with sub- of either one-piece preformed channel units
Clause 17 of this Clause. with a closed profile incorporating a
continuous or intermittent longitudinal inlet
6 Linear drainage channel systems shall be slot on the top, or alternatively of units with
set flush with contiguous surfaces falling integral or non-integral grating systems. An
towards the systems and shall permit entry integral grating system is a system in which
of surface water from such surfaces. the grating is either:
Notwithstanding other tolerances in the
Specification, the finished level of the units (a) cast or preformed as part of the
comprising the system shall not be higher channel; or
nor more than 10 mm lower than the
finished level of the adjacent carriageway. (b) chemically bonded to the
channel base unit by the
7 When used adjacent to porous asphalt manufacturer.
surfacing materials, units shall also
incorporate side entry inlets to permit A non-integral grating system is one which
drainage of water held within the porous requires the connection of gratings to
asphalt. Inlets shall comply with the channel base units to be made by bolts or
requirements of Appendix 5/6 and shall have other suitable means.
the capacity to drain porous asphalt.
March 2003 26
Volume 1 Series 500
Specification for Road Works Drainage and Service Ducts
The Contractor shall provide attested and for the purpose. At gully positions the inner
documented evidence to demonstrate the former should be pre-sleeved with a suitable
integrity of fixity of all grating systems both pipe or similar former fit for the purpose
for manufactured and in-service conditions. which shall be of sufficient length to overlap
the two joints on either side of the gully.
Non-integral grating systems shall be 15 The central void shall be checked in
acceptable with Class C channel systems accordance with sub-Clause 509.4.
only and shall not be acceptable with Class Verification of slot widths shall be
D channel systems. determined by suitable templates.
Joints shall be designed to avoid leakage of 16 Reinforcement shall comply with Series
water, with a smooth transition and with no 1700. Cover to reinforcement shall be not
constriction of the cross-section. less than 75 mm.
March 2003 27
Volume 1 Series 500
Specification for Road Works Drainage and Service Ducts
March 2003 28
Volume 1 Series 500
Specification for Road Works Drainage and Service Ducts
March 2003 29
Volume 1 Series 500
Specification for Road Works Drainage and Service Ducts
The term fitting shall mean a product used in soil drainage shall incorporate slots or holes
conjunction with the pipe to form the system with a minimum cross sectional area of 1000
but excluding gullies manhole chambers, mm2 per metre run of pipe.
inspection chambers and access chambers.
The bore of the pipe and fittings shall be in
Materials accordance with the standard tolerances for
nominal bores given in BS EN 476.
2 The materials from which the pipe and
fittings are made, shall be treated so that Appearance
they are protected from the deleterious
effects of short term exposure to ultraviolet 4 The system shall have a smooth bore and
light, and shall be resistant to degradation by be free from any burs, flash or other
acids, alkalis, common chemicals, bacteria, inconsistencies that could have a detrimental
fungi and moulds occurring in soil, road effect on the performance of the system.
construction materials and road drainage Pipes and fittings for drainage should be
systems. In addition, the materials from externally coloured either terracotta or black.
which the pipe and fittings are made, shall The colour of ducting pipes should be in
not incorporate any additives in quantities accordance with requests of ADT. Any
sufficient to cause microbiological variation in the colour shall be described in
degradation or to impair the conformity to Appendix 5/2.
the chemical, physical and mechanical Volume 1 home page
properties or impact resistance requirements Structured Wall Pipe
given in sub-Clause 5 of this Clause. The
specification of the raw material shall be 5 The structured wall pipe shall have the
agreed between the certification body, as properties defined in Table 5/9.
defined in sub-Clause 15 of this Clause, and
the manufacturer and may incorporate re-
processable and/or recyclable material. The
agreed specification shall incorporate
tolerances for each of the relevant
characteristics defined in the appropriate
clause of pr EN 13476. The Contractor shall
submit to the Overseeing Organisation, prior
to commencement of the Works, completed
information sheets in accordance with
Appendix 5/7.
Dimensions
March 2003 30
Volume 1 Series 500
Specification for Road Works Drainage and Service Ducts
March 2003 31
Volume 1 Series 500
Specification for Road Works Drainage and Service Ducts
Fittings
March 2003 32
Volume 1 Series 500
Specification for Road Works Drainage and Service Ducts
Test Method for Longitudinal Bending (f) record the difference in readings
as a percentage of pipe length.
11 (i) The test specimen shall be a six
metre length of pipe or the maximum
length available from the
manufacturer (if less than six Test Method for Rodding Resistance
metres). (Internal Puncture)
March 2003 33
Volume 1 Series 500
Specification for Road Works Drainage and Service Ducts
12 (i) The test specimens shall be: (c) condition the test specimens in
air at a temperature of 4°C ± 2°C
(a) twenty specimens cut from the for a period of at least one hour
structured wall pipe, each before the test;
specimen to be 242 mm to 246
mm in length and a quarter (d) locate the box under the drop
section of the circumference or; tube of the impact apparatus;
(b) twenty specimens cut from a (e) embed the specimen into the
number of identical fittings. sand using a vibrator with the
inner surface exposed and facing
(ii) The apparatus shall include: upwards;
(a) a standard drop weight pipe (f) locate the specimen such that the
testing apparatus capable of marked point of impact is under
dropping a tup from a height of 1 the centre line of the tup;
m;
(g) drop the tup from a height of 1 m
(b) a 300g tup which can be varied on to the inner surface of the
in 30g multiples with a striker specimen within 10 seconds of
consisting a steel rod 18 mm in removing the specimen from the
diameter with a 9 mm conditioning environment;
hemispherical end;
(h) examine the specimen for
(c) a 250 mm x 250 mm box damage. Damage is defined as a
containing dry Leighton Buzzard puncture or crack of the inner
sand (Garside quarry) such that layer. Ductile bending or
there is at least 100 mm of sand “whitening” is not considered to
beneath the test specimen when be damage;
bedded down.
(i) if the specimen exhibits no
(iii) Procedure shall be as follows: damage the next test should be
conducted with a tup of 30 g
(a) mark the intended point on the greater mass. If the specimen
inside of the pipe on the does exhibit damage the next test
intersection of the center lines. should
With profiled pipes the point of be conducted using a tup of 30 g
impact shall be at the point smaller mass;
nearest the intersection that mid
way between the ribs or in the (j) after having completed the 20
middle of a hollow corrugation; strikes calculate the average of
the energies where a pass (no
(b) alternatively mark the intended damage) was recorded and the
point of impact on the section of average of the energies where a
fitting; failure (damage) was recorded,
March 2003 34
Volume 1 Series 500
Specification for Road Works Drainage and Service Ducts
(iv) The test report shall include: (d) set the machine to lower at a rate
of 5 mm/min;
(a) identification of the samples;
(e) allow the rod to travel into the
(b) the overall average; pipe a distance equal to 10% of
the nominal internal diameter of
(c) whether or not the specimens the pipe (T10 mm) or until the
were damaged. pipe wall is perforated. When the
outer skin of a twin wall pipe is
Test Method for Resistance to Sharp perforated before 10% is
Objects attained, the rod travel up to the
point of failure shall be recorded
13 (i) Test specimens shall be three (Tf mm) and the rod allowed to
samples of duct each 300 mm long. travel to the inner wall. The rod
travel shall be continued to a
(ii) The apparatus shall include: total of 10% (ie T10 - Tf) or
until complete penetration
(a) a compression testing machine; occurs.
(b) a 4.7 mm diameter steel rod with (iv) For each test specimen: pipe size,
an hemispherical end; reference, maximum load and rod
travel shall be recorded.
(c) and a 120° steel vee block at
least 300 mm long. 14 Notwithstanding the requirements of sub-
Clauses 11, 12 and 13 of this Clause,
(iii) The test method shall be as follows: variations in the test methods specified
therein shall be made where deemed
(a) condition the test specimens for necessary by the British Board of Agrement
at least 1 hour at 23°C ± 2°C; Roads and Bridges Certificate (or
equivalent) following consultation with the
(b) insert the steel rod in the jaws of manufacturer and in agreement with the
the moveable platen of the Overseeing Organisation. All such variations
compression testing machine so shall be recorded in the report.
that the hemispherical end
protrudes at least 15% of the Certification
nominal pipe diameter;
15 Pipes and fittings shall have a current
(c) position the specimen in the vee British Board of Agrément Roads and
block and placed directly below Bridges Certificate (or equivalent) certifying
the steel rod, for twin-walled the appropriate physical properties when
pipe the specimen shall be tested in accordance with this Clause.
positioned firstly so that the rod
strikes on the corrugation or rib,
March 2003 35
Volume 1 Series 500
Specification for Road Works Drainage and Service Ducts
March 2003 36
Volume 1 Series 500
Specification for Road Works Drainage and Service Ducts
place from a chamber, although it may 8 Oil separators shall be refilled with
be necessary to make a temporary uncontaminated water following the
excavation into the pipeline in some cleaning operation.
circumstances.
9 The Contractor shall dispose of all surplus
(ii) If the Contractor finds it is not possible water, debris and arisings from the works off
to flush in an upstream direction, the Site.
pipe shall be plugged below the
blockage and the jetter then used to Cleaning or Testing of Piped Drainage
“back flush” to a suction pipe. Systems and Subway Drainage Channels
March 2003 37
Volume 1 Series 500
Specification for Road Works Drainage and Service Ducts
(iii) sweeping.
March 2003 38