Location: #89 Gen. Segundo St. Heroes Hills Subdivision, Brgy. Sta. Cruz, Diliman Quezon City Owner: Mr. Joseph Yu Subject: Construction Schedule and Cash Flow
ITEM DESCRIPTION AMOUNT
I. GENERAL REQUIREMENTS 957,234.67
II. EARTHWORKS 6,671,103.37 III. STRUCTURAL WORKS 1.00 CONCRETE WORKS 8,555,436.93 2.00 REBAR WORKS 6,008,049.14 3.00 FORMWORKS AND SCAFFOLDING 3,184,968.63 4.00 STEEL & METAL WORKS 5,355,275.00 IV. ARCHITECTURAL WORKS 4,033,687.10 V. ROOFING WORKS 9,600,730.00 VI. PAINTING WORKS 2,823,545.80 VII. ELECTRICAL WORKS 2,846,338.30 VIII. SANITARY / PLUMBING WORKS 1,063,631.08 IX. PAVEMENT 900,000.00