PROJECT : CONSTRUCTION OF FISHERY PROCESSING AND TRAINING CENTER

UNIVERSITY OF RIZAL SYSTEM, CARDONA CAMPUS

BAR CHART AND S-CURVE


1 2 3 4 5 6 7 8
ITEM DESCRIPTION AMOUNT REL. WT. WEEK
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
I MOBILIZATION & DEMOB. 143,936.10 1.619
TEMP FACILITIES, WATER
II 29,484 0.332
AND ELETRICITY
III SAFETY AND HEALT REQ. 54,337.50 0.611

IV EARTHWORKS 480,423.26 5.404

V REBAR WORKS 1,583,618.63 17.814

VI CONCRETING WORKS 2,336,531.59 26.283

VII MASONRY WORKS 536,098.89 6.03

VIII WATERPROOFING WORKS 51,040.08 0.574

VIX TILING WORKS 542,953.98 6.108


PLUMBING WORKS
X 206,163.72 2.319
(FIXTURES)
PLUMBING WORKS
XI 99,794.52 1.123
(WATER LINE)
PLUMBING WORKS
XII 28,090.44 0.316
(SEWER AND DRAINAGE LINE)
XIII STEEL WORKS 619,115.97
6.964
XIV TINSMITHRY WORKS 253,799.60
2.855
XV ELECTRICAL WORKS 1,001,175.84
11.262
XVI PAINTING WORKS 402,956.82
4.533
XVII DOORS AND WINDOWS 287,418.60
3.233
XVIII CEILING WORKS 144,144
1.621
XIX MISCELLANEOUS ITEMS 88,870.32
1

CASH FLOW
MONTHLY ACCOMPLISHMENT IN % 8 17 12 13 14 12 13 11
CUMMULATIVE MONTHLY ACCOMPLISHMENT IN % 25 37 50 64 76 89 100
MONTHLY ACCOMPLISHMENT IN 711196.308 1511292.155 1066794.462 1155694.001 1244593.539 1066794.462 1155694.001 977894.9235
COMMULATIVE MONTHLY ACCOMPLISHMENT IN 2222488.463 3289282.925 4444976.925 5689570.464 6756364.926 7912058.927 8889953.85

PREPARED BY : S B SORIANO CONTRACTION