You are on page 1of 7

6/29/2020 What is Earned value management system (EVM) · Quantity Surveyor blog

What is Earned value management system


(EVM)
September 3, 2019 raoneqs QS 1

Earned value management system (EVM) is a practice which project management professionals developed
to evaluate performance & progress of a project. Implementation of this system in a project can provide,

An early indication of budget or time overrun


More sensitive data for effectual decisions.
Enhance the process of planning
Indicate potential risks
Increases accountability of project
Make clear & consistent communication to all management levels.

Image by PublicDomainPictures from Pixabay

Key elements of the Earned value management (EVM)


system can be identified as follows,

Contents hide
1 Key elements of the Earned value management (EVM) system can be identified as follows,
1.1 Planned value [PV]
1.2 Earned Value [EV]
1.3 Actual Cost [AC]
1.4 Cost variance [CV]
1.5 Cost performance index [CPI]
1.6 Scheduled variance [SV]
1.7 Schedule performance index [SPI]
1.8 Estimate to complete [ETC]
1.9 Estimate at completion [EAC]
1.10 Work breakdown structure for EVM system

https://quantitysurveyor.blog/2019/09/03/what-is-earned-value-management-system-evm/ 1/7
6/29/2020 What is Earned value management system (EVM) · Quantity Surveyor blog

Planned value [PV]

Expected budget estimated (as per the work) based on the work breakdown structure is called as planned
value. This should be identified based on the project schedule. Values should be identified in accordance with
the project time frame. Based on the project programme each month planned value should be derived.

Earned Value [EV]

This is the Key element of Earned value management system(EVM). Project manager should be determining
the actual accomplishment of work on a given date based on the work breakdown schedule.

Actual Cost [AC]

This is the actual cost of the each element based on the work breakdown schedule.

Cost variance [CV]

This indicates the cost performance of the project, particular work or element. CV is the difference between
Earned value & actual cost [CV =EV- AC]. If cost variance is a positive value it shows complimentary
indication of the project, particular work or element.

Cost performance index [CPI]

This shows cost efficiency of the project, specific work or element. Formula to derive CPI is EV/AC (ratio
between earned value & actual cost). If this value is equal or greater than the one it means efficiency of
expenditure of the project, specific work or element is good.

Read : 6 Steps of Value Engineering Methodology

Scheduled variance [SV]

This shows whether the project is achieving the baseline schedule or not (whether project, work or element is
behind the schedule or ahead the schedule) in accordance with the WBS. Formula to scheduled variance is
difference between the EV and PV.

Schedule performance index [SPI]

this shows work efficiency of the project or work element. Formula to derive SPI is EV/PV (ratio between
earned value & planned value). If this value is equal or greater than the one it means efficiency of work done
of the project or the specific work is good.

Estimate to complete [ETC]

This is the cost required to complete all the balance work of the project or specific work. Calculation of ETC
should be more accurate and it can be difficult.

Estimate at completion [EAC]

EAC is the value of actual cost plus estimated to complete (EAC= AC+ETC) or the anticipated total cost of
the completion of the project or the work element.

For implementation of Earned Value Management (EVM) process Project Manager should make a
comprehensive plan for both budget & time of the project. This should be planned & implement before project
starts, budget and time should be according with the work breakdown structure (WBS).

Major works should be identified and time and cost should be allocated among each element in accordance
with the work schedule. At the execution period PM should asses below three things to asses earned value.

1. Value should have done at any date given as per the project plan
2. Produced value at the time
3. Amount of money spent

Work breakdown structure for EVM system


Preparation of work breakdown structure or the WBS is an important process in construction project
management. This is the process of identification of major elements in a project and distributing the time and
cost among these major elements according to the work programme. Sample work breakdown structure
prepared to use in Earned Value Management system (EVM) is as follows,

https://quantitysurveyor.blog/2019/09/03/what-is-earned-value-management-system-evm/ 2/7
6/29/2020 What is Earned value management system (EVM) · Quantity Surveyor blog

Above graph the works has been segregated in to major categories in building construction. In detailed WBS
schedule these work should be more categorize under these major headings. Simple example of excavation
works for small 3 building construction as follows,

Read : 3 Corporate social responsibilities of a sustainable company

As per above graph it is clearly showing this work has been delayed for 11 days. Management can
easily identified where the delay occur (item nr 2.3 has delayed 2 days, item nr 2.4 has delayed 4 days
& item nr 1 has delayed 2 days. Due to these delays commencing dates of other works such as
cleaning & clearing also delayed). But the good thing is that work has been finished within the
original budget.

Further to the above example, below shows how EVM can used for track time & cost of a project.
These examples has given for compete project (on month of May status).

As per the below example 1- planned value is 130,000, ETC is 170,000 and project programme has
exceeded from 12 months to 14 months. Earned value as per month of May is 40,000.

https://quantitysurveyor.blog/2019/09/03/what-is-earned-value-management-system-evm/ 3/7
6/29/2020 What is Earned value management system (EVM) · Quantity Surveyor blog
Graph 1

As per above graph 1,

Planned value of the project is 130,000.00


Estimated at completion is 173,000.00
As per May 2018 earned value is 40,000.00 & actual cost is 68,000.
Which as per the planned value on May is 55,000.00
There for schedule variance is EV-PV (40,000-55,000=-15,000) is a negative value which is progress is
behind the baseline schedule.
Cost variance is EV-AC (40,000-68,000= -28,000) is a negative value which means project completion
date is going to be seriously delayed.
Cost performance index- as per above graph is EV/AC (40,000/68,000=0.58) lesser than the 1.
Schedule Performance Index will be EV/PV ((40,000/55,000=0.72) is also lesser than the 1.
As per above two points it indicates that, Project is not running in expected efficiency. Serious control
to budget and time acceleration should be done.

As per the below example 2- planned value is 130,000, ETC is 170,000 and project programme has
exceeded from 12 months to 14 months. Earned value as per month of May is 58,000.

Read : Key stages of whole life cost (of a building)

Graph 2

As per above graph 2,

Planned value of the project is 130,000.00


Estimated at completion is 173,000.00
As per May 2018 earned value is 58,000.00 & actual cost is 68,000.
Which as per the planned value on May is 55,000.00
There for schedule variance is EV-PV (58,000-55,000=3,000) is a positive value which is progress is
ahead the baseline schedule.
Cost variance is EV-AC (58,000-68,000= -10,000) is a negative value which means project completion
date is going to be slightly delayed and expenditures is more than the planned budget.
Cost performance index as per above graph is EV/AC (58,000/68,000=0.85) lesser than the 1.
Schedule Performance Index will be EV/PV ((58,000/55,000=1.05) is Higher than the 1
As per above two points it indicates that, Project is running in expected efficiency but should be
focused on cost controlling. If still project manager need to finish the project on expected date as per
initially agreed, should be need to consider time acceleration.

As per the below example 2- planned value is 140,000, ETC is 130,000. Earned value as per month of
May is 58,000.

https://quantitysurveyor.blog/2019/09/03/what-is-earned-value-management-system-evm/ 4/7
6/29/2020 What is Earned value management system (EVM) · Quantity Surveyor blog

Graph 3

As per above graph 3,

Planned value of the project is 140,000.00


Estimated at completion is 130,000.00
As per May 2018 earned value is 58,000.00 & actual cost is 50,000.00
Which as per the planned value on May is 55,000.00
There for schedule variance is EV-PV (58,000-55,000=3,000) is a positive value which is progress is
ahead the baseline schedule.
Cost variance is EV-AC (58,000-50,000= 8,000) is a positive value which means project running well
within the estimated budget & time.
Cost performance index as per above graph is EV/AC (58,000/50,000=1.15) greater than the 1.
Schedule Performance Index will be EV/PV (58,000/55,000=1.05) is Higher than the 1
As per above two points it indicates that, Project is running smoothly well within the estimated cost &
time.

Check our latest article on Value management here

Share this:

Share WhatsApp Email

Like this:

Loading...

Related

What is Value management Procurement methods in Project cash flow- Construction


September 11, 2019 Construction/ types of contracts cost management
In "QS" August 5, 2019 February 25, 2020
In "Contracts" In "QS"

PREVIOUS NEXT

https://quantitysurveyor.blog/2019/09/03/what-is-earned-value-management-system-evm/ 5/7
6/29/2020 What is Earned value management system (EVM) · Quantity Surveyor blog
What is the process of Mediation in Why Remeasurement(Re measurable)
construction contracts / Unit price contracts

1 COMMENT

nuwan
OCTOBER 10, 2019 AT 3:48 PM

good job,
read more article’s about quantity surveyor duties

http://quantitysurveyor4u.blogspot.com/2019/09/quantity-surveyor-duties-in-pre-contract-stage.html

Loading...

REPLY

Leave a Reply
This site uses Akismet to reduce spam. Learn how your comment data is processed.
HIRE US CONTACT US

Quantitysurveyorblog@gmail.com

LIKE US

Like us

SUBSCRIBE TO BLOG VIA EMAIL

Enter your email address to subscribe to this blog


and receive notifications of new posts by email.

https://quantitysurveyor.blog/2019/09/03/what-is-earned-value-management-system-evm/ 6/7
6/29/2020 What is Earned value management system (EVM) · Quantity Surveyor blog
Join 3,314 other subscribers
Email Address

Subscribe

Copyright quantitysurveyor.blog 2019 ©

CONTACT US

Quantitysurveyorblog@gmail.com

https://quantitysurveyor.blog/2019/09/03/what-is-earned-value-management-system-evm/ 7/7

You might also like