Professional Documents
Culture Documents
EVMS
Cost Schedule
PROJECT MANAGEMENT
USING EARNED VALUE
(and the Problems & Lessons
Learned from it)
Jim Pennington – Business Operations Director
jim.pennington@lmco.com
Dated November 2007
1
Technical
EVMS AGENDA
Cost Schedule
Backup Charts
• Essential Elements of EVM
• Tailored Earned Value Management
2
Technical
What is Earned Value and when does OMB
EVMS
Cost Schedule
want it implemented
According to the Third Edition of Earned Value Project Management by Fleming and Koppelman,
"Earned Value is a technique to better manage projects. It is not intended for use on continuing
business processes, operations that have no unique deliverables. Earned Value is for the
management of one-time-only projects, and portfolios of projects within an organization".
In alignment with this statement OMB mandates the use of EVMS within OMB Circular A-11 for
major development/ modernization/enhancement (DME) projects, but not all DME projects.
3
Technical
Where is the Earned Value Requirements and
EVMS
Cost Schedule
Standards the Process Defined
4
Technical
EVMS
Cost Schedule
Technical
EVMS
Cost
Schedule
5
Technical
EVMS
Why is Earned Value Information important
Cost Schedule to the Program Manager
Problems in one area can, and usually will, cause problems in the
other areas
You can design and build the fastest, toughest and lightest widget
in the world, but if it costs too much, or is late:
It may adversely affect the total funding required to
complete
Could impact ability to get funding for future projects or may
required greater effort to obtain enough funding for
programs later in the future
6
Technical
EVMS
Cost Schedule
# of Pages
# of Sys Lines of
Reqmts Code
# of Widgets
7
Technical
8
Technical
EVMS
Some Implementing Directives
Cost Schedule
GOVERNMENT
• Mandatory procedures for major defense acquisition programs (DoDI
5000.2-R)
• Defines policies governing earned value
• Earned Value Management Information Guide (EVMIG)
• Provides detailed discussions of the EV criteria
• Written for the Government program offices
• OMB Directives to Agencies:
• OMB Circular A-11, Part 7, Federal Acquisition Regulation Case 2004-019
• OMB Memorandum M-04-24 (dated 8/23/04)
• OMB Memorandum M-05-23 by using the NDIA EVMS Intent Guide, NDIA
PMSC Surveillance Guide (dated 8-4-05)
INDUSTRY
• Industry guidelines for Earned Value Management Systems (ANSI-ESI
748)
• Industry Standard for Earned Value
• Incorporated in DoDI 5000.2R
9
Technical
10
Technical
TRADITIONAL VS EARNED VALUE
EVMS
Cost Schedule ACCOUNTING
Budget versus Actuals
Time
Now
Time
Time
Now
Time
EVMS
Cost Schedule
13
Technical
EVMS
Cost Schedule
Initiate • Organize
Project Management Cycle
Close Out
14
Technical
EVMS
Cost Schedule
15
Technical
Initiate Phase of Program
EVMS
Cost Schedule
Problems and Lessons Learned
Problems Lessons Learned
• Baseline is not stable • Establish early baseline basis
• EVM Staffing Resources not in place • Have contractor or internal personnel
at time of ATP
identified during negotiations
• Program Management as not assigned
• PMs must plan to execute program like
responsibilities to CAMs
• it was proposed (Work per SOW)
Program Team is not experienced or
trained • Have Program Team (PMs, CAMs,
• IBR (Integrated Baseline Review) EVM and Customer) trained together
Deliverables not defined • Establish specific contract SOW app.
• Contracting Officer or COTR wants to for EVM and for Integrated Schedule
deviate from SOW or Contract EVM • Keep CO and COTR (& PM) diligent on
direction w/o proper modifications proper contracting practices
• Different set of assumptions from the • Develop clear walkdown of deltas in
proposal submittal
Scope and assumptions (document)
• Variance Thresholds are not defined
• Variance Thresholds by % & $ off plan
• Variance Analysis Guidelines not
agreed upon prior to start • Analysis must be to a specific level of
WBS, contents identified & Corr. Action
16
Technical
Planning Phase of Program
EVMS
Cost Schedule
Problems and Lessons Learned
Problems Lessons Learned
• No set deadline to freeze plan • Establish a EVM Implementation
(Continuous Churn) schedule and hold everyone to it
• IPTs (Integrated Product Teams) are • IPTs must complete earlier for IMS
not working to same schedule
integration with other teams and tasks
• Baseline Changes are not controlled at
the beginning (Loss of string from Prop • Contractor should be able to walkdown
to Baseline-Rates, Sch, Scope) Proposal as Submittal to IBR Baseline
• IBR (Integrated Baseline Review) • Push to hold IBR schedule and work
delayed due to baseline flux or SOW, schedule or scope changes later
continued negotiations (as formal changes / plan maintenance)
• No plan for Contract Changes (No • Must have established CCB with PM,
CCB board and/or no COTR involved ) Finance, Contracts, IPTs (Govt / Contr)
• Program Management Reserve and • Undistributed Budget is not Reserve, if
Undistributed Budget not well defined
it is not needed convert to PM Reserve
• Current Forecasts and recovery plans
do not change the baseline planning • Only Customer approved changes
impact the Baseline (Establish a
window for change approval and
freeze the plan for near term changes)
17
Technical
Execution Phase of Program
EVMS
Cost Schedule
Problems and Lessons Learned
Problems Lessons Learned
• Program seems to not meet the EVM • Establish a EVM Status and Reporting
reporting schedule Business Rhythm
• Status or Earned Performance inputs • EVM Staffing Resources not in place at
are not consistent with period cutoffs time of ATP
• No established Performance Criteria • Must have EV method and completion
identified for tasks and completion criteria defined for tasks (agreed upon)
• Errors or Inconsistent Reporting • CAM/EV data reviews prior to release
• Inconsistent Subcontractor or • Establish a ICD approach for Vendor and
Procurement Status Subcontractor Accruals / Receipts
• No reconciliations of Ledger Actuals to • Have defined reconciliation process to
EVM (Accrued Costs) validate EVM ACWP reported & deltas
• Program Management does not use or • Make EV data part of monthly review
analyze the EVM information deliverables and status reviews
• PMs manage to the IMS or Schedule • Report number of late IMS workpackage
and EVM data must be incorrect starts and completions by WBS
• Program Plan Risks are not defined or • Risks that have not been realized should
PM Reserve is not earmarked have MR allotted plus mitigation plans
18
Technical
Control Phase of Program
EVMS
Cost Schedule
Problems and Lessons Learned
Problems Lessons Learned
• Contract Changes are too frequent and • CCB process should be defined and
formal plan changes are not timely IPT provide estimates at CCB meetings
• Variance Analysis is too vague or is not • EVM and variance root cause analysis
determined in a timely manner must be timely to be effective
• IPTs do not take ownership of their • IPT must be given labor reports by
variances or mitigation plans name to validate charges and resp.
• Program has a large cost and/or • Program should establish a over target
schedule variance that plan is relevant or baseline replan to make plan valid
• Program does not properly close • You must close incomplete tasks and
workpackages when replanned replan them as new tasks with replan
• Scope Creep and workscope/rate trades • Small unapproved changes and creep
from well minded PMs and CO/COTRs drive variances & impacts future work
• Inconsistent EVM performance and • Contractor should have proven and
reporting over the life of the program documented process to operate
• EVM process adherence is not consistently
objectively evaluated or tested • Establish a Joint Surveillance Plan
19
Technical
Close Out Phase of Program (or task)
EVMS
Cost Schedule
Problems and Lessons Learned
20
Technical
Closing Comments
EVMS
Cost Schedule
• With the problems on the FBI Virtual Case File Program, IT programs will
continue to have additional OBM scrutiny and needs for oversight
• Manage the EVM process, do not let the process manage you
• Do not just look at the big variances, drive for better analysis and corrective
actions that are meaningful (remember you have a boss too!)
• One little rule: If your TCPI is 1.06 after being more than 15%,
You will not recover to the original baseline! (LMC history)
21
Technical
EVMS
Questions and Answers
Cost Schedule
Comments or Questions??
22