You are on page 1of 22

Technical

EVMS
Cost Schedule

PROJECT MANAGEMENT
USING EARNED VALUE
(and the Problems & Lessons
Learned from it)
Jim Pennington – Business Operations Director
jim.pennington@lmco.com
Dated November 2007
1
Technical

EVMS AGENDA
Cost Schedule

• OMB objections and requirements for EVMS


• What is EVMS?
• Implementing Directives
• Traditional versus Earned Value Accounting
• How does EV fit into the Program Management Life Cycle
• Problems and Lessons Learned over the PM EVM Life Cycle
• Comments

Backup Charts
• Essential Elements of EVM
• Tailored Earned Value Management

2
Technical
What is Earned Value and when does OMB
EVMS
Cost Schedule
want it implemented

According to the Third Edition of Earned Value Project Management by Fleming and Koppelman,

"Earned Value is a technique to better manage projects. It is not intended for use on continuing
business processes, operations that have no unique deliverables. Earned Value is for the
management of one-time-only projects, and portfolios of projects within an organization".

In alignment with this statement OMB mandates the use of EVMS within OMB Circular A-11 for
major development/ modernization/enhancement (DME) projects, but not all DME projects.

OMB Circular A-11 defines a major project as:


– A system or project requiring special management attention because of its importance to
the mission or function of the Agency, a component of the Agency, or another organization;
– Is for financial management and obligates more than $500,000 annually;
– Has significant program or policy implications;
– Has high executive visibility;
– Has high development, operating, or maintenance costs; or
– Is defined as major by the Agency’s capital planning and investment control process
– In addition, OMB memorandum M-05-23 asked each agency to work with OMB to identify
“high risk” projects by August 15, 2005. Circular A-11 defines high-risk projects as those
requiring special attention from oversight authorities and the highest levels of agency
management.

3
Technical
Where is the Earned Value Requirements and
EVMS
Cost Schedule
Standards the Process Defined

Agencies follows the requirements set forth in:


• ANSI/EIA STD – 748
• OMB Circular A-11, Part 7, Federal Acquisition Regulation Case
2004-019
• OMB Memorandum M-04-24 (dated 8/23/04)
• OMB Memorandum M-05-23 by using the NDIA EVMS Intent
Guide, NDIA PMSC Surveillance Guide (dated 8-4-05)
• NDIA* Program Manager’s Guide to the Integrated Baseline
Review (IBR) Process, and EVM Implementation Guide

To provide for a uniform approach to implementing EVMS and to


confirm that the processes and procedures continue to satisfy
the guidelines as they change

Note * = NDIA – National Defense Industry Association Program Management Systems


Committee Working group

4
Technical

EVMS
Cost Schedule

Technical

EVMS
Cost
Schedule

EVMS is the primary project management tool that


integrates the technical, schedule and cost aspects
of the project or contract scope of work

5
Technical

EVMS
Why is Earned Value Information important
Cost Schedule to the Program Manager

A Program or Project’s Technical, cost and schedule performance


are interrelated

Problems in one area can, and usually will, cause problems in the
other areas

You can design and build the fastest, toughest and lightest widget
in the world, but if it costs too much, or is late:
 It may adversely affect the total funding required to
complete
 Could impact ability to get funding for future projects or may
required greater effort to obtain enough funding for
programs later in the future

6
Technical

EVMS
Cost Schedule

Earned Value (EV)


...is a predetermined amount of value that is claimed, or earned,
when the corresponding work is accomplished.

# of Pages

# of Sys Lines of
Reqmts Code

# of Widgets

7
Technical

EVMS Earned Value Management provides


Cost Schedule

• Objective rather than subjective project status information


• Cost and Schedule impact of known problems
• Identification of problems not previously recognized
• Capability to trace the problem to the source
• Quantitative measure of schedule deviation in dollars
• Performance measured against a program oriented
baseline

EARNED VALUE DOES NOT GUARANTEE SUCCESS

8
Technical

EVMS
Some Implementing Directives
Cost Schedule

GOVERNMENT
• Mandatory procedures for major defense acquisition programs (DoDI
5000.2-R)
• Defines policies governing earned value
• Earned Value Management Information Guide (EVMIG)
• Provides detailed discussions of the EV criteria
• Written for the Government program offices
• OMB Directives to Agencies:
• OMB Circular A-11, Part 7, Federal Acquisition Regulation Case 2004-019
• OMB Memorandum M-04-24 (dated 8/23/04)
• OMB Memorandum M-05-23 by using the NDIA EVMS Intent Guide, NDIA
PMSC Surveillance Guide (dated 8-4-05)

INDUSTRY
• Industry guidelines for Earned Value Management Systems (ANSI-ESI
748)
• Industry Standard for Earned Value
• Incorporated in DoDI 5000.2R

9
Technical

EVMS Earned Value Management Terms


Cost Schedule

ACWP = Actual cost of work performed (Basically costs


extracted from work in process)
BCWP = Budgeted cost of work performed (Earned
Value)
BCWS = Budgeted cost of work scheduled (Budget
spread to time)
BAC = Budget at completion (Total budget for a given
task)
CVAR = Cost variance (BCWP-ACWP)
EAC = Estimate at completion
SVAR = Schedule variance (BCWP-BCWS)

10
Technical
TRADITIONAL VS EARNED VALUE
EVMS
Cost Schedule ACCOUNTING
Budget versus Actuals

Time
Now

Time

All we really know is that we spent more than we planned


11
Technical TRADITIONAL VS EARNED VALUE
EVMS
Cost Schedule ACCOUNTING
(Using EVM approach)

Time
Now

Time

Earned value provides an objective measure of work


accomplished. It tells you what you got for what you spent
12
Technical

EVMS
Cost Schedule

PROGRAM MANAGEMENT PROCESS


PROGRAM MANAGER NEEDS

Initiate Develop a realistic


Organize
Project Management Cycle

work and plan of work scope,


teams budget, and
Plan schedule

Authorize work properly


Execute
Control Performance Understand
Changes reporting variances
Control
Corrective Forecast of
Actions final cost and
Close Out schedule

13
Technical

EVMS
Cost Schedule

PROGRAM MANAGEMENT PROCESS


EARNED VALUE MANAGEMENT

Initiate • Organize
Project Management Cycle

• Plan work scope – schedule and budget


• Authorize work
Plan • Control changes
• Report performance
Execute • Understand variances
• Corrective actions
• Forecast final cost and schedule
Control

Close Out

14
Technical

EVMS
Cost Schedule

Earned Value Problems


&
Lessons Learned
over the Program Management
EVM Life Cycle

15
Technical
Initiate Phase of Program
EVMS
Cost Schedule
Problems and Lessons Learned
Problems Lessons Learned
• Baseline is not stable • Establish early baseline basis
• EVM Staffing Resources not in place • Have contractor or internal personnel
at time of ATP
identified during negotiations
• Program Management as not assigned
• PMs must plan to execute program like
responsibilities to CAMs
• it was proposed (Work per SOW)
Program Team is not experienced or
trained • Have Program Team (PMs, CAMs,
• IBR (Integrated Baseline Review) EVM and Customer) trained together
Deliverables not defined • Establish specific contract SOW app.
• Contracting Officer or COTR wants to for EVM and for Integrated Schedule
deviate from SOW or Contract EVM • Keep CO and COTR (& PM) diligent on
direction w/o proper modifications proper contracting practices
• Different set of assumptions from the • Develop clear walkdown of deltas in
proposal submittal
Scope and assumptions (document)
• Variance Thresholds are not defined
• Variance Thresholds by % & $ off plan
• Variance Analysis Guidelines not
agreed upon prior to start • Analysis must be to a specific level of
WBS, contents identified & Corr. Action

16
Technical
Planning Phase of Program
EVMS
Cost Schedule
Problems and Lessons Learned
Problems Lessons Learned
• No set deadline to freeze plan • Establish a EVM Implementation
(Continuous Churn) schedule and hold everyone to it
• IPTs (Integrated Product Teams) are • IPTs must complete earlier for IMS
not working to same schedule
integration with other teams and tasks
• Baseline Changes are not controlled at
the beginning (Loss of string from Prop • Contractor should be able to walkdown
to Baseline-Rates, Sch, Scope) Proposal as Submittal to IBR Baseline
• IBR (Integrated Baseline Review) • Push to hold IBR schedule and work
delayed due to baseline flux or SOW, schedule or scope changes later
continued negotiations (as formal changes / plan maintenance)
• No plan for Contract Changes (No • Must have established CCB with PM,
CCB board and/or no COTR involved ) Finance, Contracts, IPTs (Govt / Contr)
• Program Management Reserve and • Undistributed Budget is not Reserve, if
Undistributed Budget not well defined
it is not needed convert to PM Reserve
• Current Forecasts and recovery plans
do not change the baseline planning • Only Customer approved changes
impact the Baseline (Establish a
window for change approval and
freeze the plan for near term changes)

17
Technical
Execution Phase of Program
EVMS
Cost Schedule
Problems and Lessons Learned
Problems Lessons Learned
• Program seems to not meet the EVM • Establish a EVM Status and Reporting
reporting schedule Business Rhythm
• Status or Earned Performance inputs • EVM Staffing Resources not in place at
are not consistent with period cutoffs time of ATP
• No established Performance Criteria • Must have EV method and completion
identified for tasks and completion criteria defined for tasks (agreed upon)
• Errors or Inconsistent Reporting • CAM/EV data reviews prior to release
• Inconsistent Subcontractor or • Establish a ICD approach for Vendor and
Procurement Status Subcontractor Accruals / Receipts
• No reconciliations of Ledger Actuals to • Have defined reconciliation process to
EVM (Accrued Costs) validate EVM ACWP reported & deltas
• Program Management does not use or • Make EV data part of monthly review
analyze the EVM information deliverables and status reviews
• PMs manage to the IMS or Schedule • Report number of late IMS workpackage
and EVM data must be incorrect starts and completions by WBS
• Program Plan Risks are not defined or • Risks that have not been realized should
PM Reserve is not earmarked have MR allotted plus mitigation plans

18
Technical
Control Phase of Program
EVMS
Cost Schedule
Problems and Lessons Learned
Problems Lessons Learned
• Contract Changes are too frequent and • CCB process should be defined and
formal plan changes are not timely IPT provide estimates at CCB meetings
• Variance Analysis is too vague or is not • EVM and variance root cause analysis
determined in a timely manner must be timely to be effective
• IPTs do not take ownership of their • IPT must be given labor reports by
variances or mitigation plans name to validate charges and resp.
• Program has a large cost and/or • Program should establish a over target
schedule variance that plan is relevant or baseline replan to make plan valid
• Program does not properly close • You must close incomplete tasks and
workpackages when replanned replan them as new tasks with replan
• Scope Creep and workscope/rate trades • Small unapproved changes and creep
from well minded PMs and CO/COTRs drive variances & impacts future work
• Inconsistent EVM performance and • Contractor should have proven and
reporting over the life of the program documented process to operate
• EVM process adherence is not consistently
objectively evaluated or tested • Establish a Joint Surveillance Plan

19
Technical
Close Out Phase of Program (or task)
EVMS
Cost Schedule
Problems and Lessons Learned

Problems Lessons Learned


• Last months of program, data appears • Be sure contractor does not get sloppy
to be incorrect w/ charging practices (>95%)
• Final Estimates to Complete are off by a • Be sure final EACs include remaining
large amount material commitments, labor suspense
• Costs continues to come into the • Be sure all charge accounts closed,
workpackage after it is completed clear suspense & transfer bad charges
• Indirect rate impacts hit after the • Understand contractor financial
program or task is completed calendar and rate adjustment process
• Subcontract or Material Costs does not • Have contractor complete a walk-down
match Ledger of the EVM ACWP and the ledger $s
• Final EVM Report does not match • Contractor should create a projection
current Invoice Totals or Balances when all costs will be final and on the
books of record

20
Technical
Closing Comments
EVMS
Cost Schedule

• With the problems on the FBI Virtual Case File Program, IT programs will
continue to have additional OBM scrutiny and needs for oversight

• If you are going to spend the money on EVM, use it (effectively!)

• Manage the EVM process, do not let the process manage you

• Do not just look at the big variances, drive for better analysis and corrective
actions that are meaningful (remember you have a boss too!)

• One little rule: If your TCPI is 1.06 after being more than 15%,
You will not recover to the original baseline! (LMC history)

21
Technical

EVMS
Questions and Answers
Cost Schedule

Comments or Questions??

22

You might also like