Professional Documents
Culture Documents
Costs Types:
• Indirect: All the costs that are not linked with the project’s activities
directly, like mobilization, office preparation, taxes, telephones.
• Direct: All the costs that are linked to project’s activities directly like
material costs that are subject to the variable quantities in the project.
Cost Management Course – Saad Almeri
• Brainstorming
• Nominal Group Techniques
• Delphi Technique
Cost Management Course – Saad Almeri
Basis of Estimates
Project Budget
Cost Baseline
Tools &
Inputs Outputs
Techniques
.1 Earned value management .1 Work performance information
.1 Project management plan
PV Planned Value
SPI Schedule Performance Index
BAC = Budget Budget At Completion
CPI Cost Performance Index
EAC Estimate At Completion
EV
SPI = SV = EV PV
PV
EV
CPI = CV = EV AC
AC
Cost Management Course – Saad Almeri
SPI
Over Budget Under Budget
Ahead of Schedule Ahead of Schedule
0 1
CPI
Over Budget Under Budget
Behind Schedule Behind Schedule
0
Cost Management Course – Saad Almeri
+
SV
Over Budget Under Budget
Ahead of Schedule Ahead of Schedule
- 0 +
CV
Over Budget Under Budget
Behind Schedule Behind Schedule
-
Cost Management Course – Saad Almeri
After 5 Days:
• We spent 600 SAR
40
• We Finished 40% of the Field %
What is SPI,CPI,CV,SV for this activity?
Cost Management Course – Saad Almeri
1200
Over Budget
1000 AC
EV
Behind Schedule AC
EV
800 AC
EV
AC
EV
600 AC AC
EV
PV
400 EV
200
0
Day 1 Day 2 Day 3 Day 4 Day 5 Day 6 Day 7 Day 8 Day 9 Day 10
Cost Management Course – Saad Almeri
= 0.67 PV
400 CPI EV
0
Day 1 Day 2 Day 3 Day 4 Day 5 Day 6 Day 7 Day 8 Day 9 Day 10 + Day 10
Cost Management Course – Saad Almeri
200
VAC = BAC - EAC
0
Day 1 Day 2 Day 3 Day 4 Day 5 Day 6 Day 7 Day 8 Day 9 Day 10 +Day 10
Cost Management Course – Saad Almeri
1600
ETC = (BAC – EV) / CPI x SPI
0.8
1400
SPI= BAC
,
1200
EAC = ETC + AC = 0.67
1000 CPI AC
EV AC
EV
AC
EV
800 AC
EV
AC
EV
600
= 0. 67 AC AC
EV
CP I PV
400 EV
VAC = BAC - EAC
200
0
Day 1 Day 2 Day 3 Day 4 Day 5 Day 6 Day 7 Day 8 Day 9 Day 10 + Day 10
Cost Management Course – Saad Almeri
)
𝐸𝐴𝐶=𝐵𝐴𝐶/𝐶𝑃𝐼 𝐸𝐴𝐶= 𝐴𝐶+
(𝐵𝐴𝐶− 𝐸 V )
𝐶𝑃𝐼𝑥𝑆𝑃𝐼
Cost Management Course – Saad Almeri
EAC = BAC
EAC
ETC = EAC – AC BAC
T CPI
=
CPI
0 . 67
CPI =
VAC = 0
Cost Management Course – Saad Almeri
TCPI: The required CPI to finish the project on the original budget
It is the most index to tell us what is the performance of the project
Cost Management Course – Saad Almeri
40 BAC = 1000
% SPI = 0.8
CPI = 0.67
Cost Management Course – Saad Almeri
• Variance Analysis
• SV
• CV
• VAC
• The Accepted Variance get decrease with project progress
• Trend Analysis