You are on page 1of 85

Projects Management

Prepared , Collected, and Concise


By Eng. Ahmed Said

1
7- Cost Management

2
References ‫اﻟﻤﺮاﺟﻊ‬
‫اﺣﻣد ﺳﻌﯾد‬/‫ﻣﺣﻣود اﻟطﺣﺎوى و م‬/‫ م‬Earned Value management .1
‫اﺣﻣد ﺳﻌﯾد‬/‫ﻣﺣﻣود اﻟطﺣﺎوى و م‬/‫ م‬Cash Flow .2
Engineering Finance Economy ‫ﺳﻠﺳﻠﺔ ﺷوم‬ .3
PMP ‫ﻣﮭﻧدس ﻣﺣﻣد ﺣﻼوه ﻣﺣﺎﺿرات اﻋداد ﻟـ‬ .4
(IPMA‫ﻣﺣﺎﺿرات ﻟﻠدﻛﺗور ﻋﺎدل ﺟوده )دورة‬ .5
Project Management in construction Sidney M. levy .6
PMBOK .7
PMP Exam. Preparation Rita Mulcahy .8
Wiley – Project management a system approach .9

3
 Introduction

4
 Introduction

5
Chapter 7 – Project Cost Management

 Project Cost Management


◦ Ensure that the project is completed within budget
◦ Concerned with cost of resources needed to
complete activities; consider effect of project
decisions on cost of using product “life-cycle costing”
◦ Most prospective financial impact of using the product
is outside the project scope
◦ Consider information needs of stakeholders,
controllable and uncontrollable costs (budget
separately for reward and recognition systems)

6
Chapter 7 – Project Cost Management

 Project Cost Management


◦ Estimating should be based on WBS to improve accuracy
◦ Estimating should be done by the person performing the work
◦ Having historical records is key to improving estimates
◦ Costs (schedule, scope, resources) should be managed to
estimates
◦ A cost (schedule, scope, baseline) should be kept and not
changed
◦ Plans should be revised as necessary during completion of work
◦ Corrective action should be taken when cost problems
(schedule, scope and resources) occur.

7
Chapter 7 – Project Cost Management

 Resource Planning:
◦ Determining what physical resources and quantities
are needed to perform work
 Inputs to Resource Planning:
◦ Work Breakdown Structure
◦ Historical Information
◦ Scope Statement – justification & objectives
◦ Resource Pool Description – what resources are
potentially available for resource planning
◦ Organizational Policies – staffing, procurement

8
Chapter 7 – Project Cost Management

 Inputs to Resource Planning:


◦ Work Breakdown Structure
◦ Network Diagram
◦ Schedule
◦ Risks
◦ Historical Information
◦ Scope Statement – justification & objectives
◦ Resource Pool Description – what resources are
potentially available for resource planning
◦ Organizational Policies – staffing, procurement

9
Chapter 7 – Project Cost Management

 Resource Planning Tools & Techniques


◦ Expert Judgment
◦ Alternatives Identification
 Resource Planning Outputs:
◦ Resource Requirements – what type & how
many resources are needed for each activity
in the Work Breakdown Structure

10
Chapter 7 – Project Cost Management

 Cost Estimating:
◦ Develop approximate costs of resources
◦ Distinguish estimating from pricing
 Estimating – likely amount
 Pricing – business decision
◦ Identify alternatives and consider realigning
costs in phases to their expected savings

11
 Introduction

12
 Introduction

13
 Introduction

14
Chapter 7 – Project Cost Management

 Cost Estimating Inputs:


◦ Work Breakdown Structure
◦ Resource Requirements
◦ Resource Rates (if known)
◦ Activity Duration Estimates
◦ Historical Information – (project files, commercial
cost databases, team knowledge
◦ Chart Of Accounts – coding structure for accounting;
general ledger reporting

15
Chapter 7 – Project Cost Management

 Cost Estimating Tools & Techniques


◦ Analogous Estimating – “top down”; using actual costs from
previous project as basis for estimate
 Reliable when previous projects are similar and individuals have
expertise – form of expert judgment
◦ Parametric Modeling – uses project characteristics in
mathematical models to predict costs (e.g. building houses)
 Reliable when historical information is accurate, parameters are
quantifiable, and model is scalable
 2 types: Regression analysis, Learning Curve
◦ Bottom Up Estimating – rolling up individual activities into
project total – smaller work activities have more accuracy -
◦ Computerized tools – spreadsheets, software

16
Chapter 7 – Project Cost Management

 Cost Estimating Tools & Techniques


◦ Pro’s and Con’s
◦ Analogous Estimating
 Quick - Less Accurate
 Tasks don’t need to be identified – Estimates prepared with
little detail and understanding of project
 Less costly – Requires considerable experience to do well
 Gives PM idea of management expectations – Infighting at high
levels of organization
 Overall project costs are capped – Difficult for projects with
uncertainty

17
Chapter 7 – Project Cost Management

 Cost Estimating Tools & Techniques


◦ Pro’s and Con’s
◦ Bottom Up Estimating
 More Accurate – Takes time and expense
 Gains buy-in from the team – Tendency for team to pad
estimates
 Based on detailed analysis of project – Requires that project
be defined and understood
 Provides a basis for monitoring and control – Team infighting
to get biggest piece of pie

18
Chapter 7 – Project Cost Management

 Outputs from Cost Estimating


◦ Cost estimates – quantitative assessments of likely costs of resources
required to complete tasks
 For all resources of the project (labor, materials, supplies, inflation allowance,
reserve)
 Expressed in units of currency
◦ Supporting Detail
 Description of scope (reference to the WBS)
 Documentation how estimate was developed
 Indication of range of possible results
 Assumptions
◦ Cost Management Plan – how cost variances will be managed
◦ Cost Risk: associated to seller for Fixed Price; associated to buyer for
Time and Materials budget

19
Chapter 7 – Project Cost Management

 Cost Budgeting
◦ Involves allocation of total estimate to individual work
to establish a cost baseline to measure performance
 Cost Budgeting Inputs
◦ Cost Estimate
◦ Work Breakdown Structure
◦ Project Schedule – includes planned start and finish
dates for items costs are allocated to
 Needed to assign costs during the time period when the
actual cost will be incurred

20
 Introduction

21
 Introduction

22
 Introduction

23
Chapter 7 – Project Cost Management

 Cost Budgeting Tools & Techniques


◦ same as Cost Estimating Tools and Techniques
 Outputs from Cost Budgeting
◦ Cost Baseline – time phased budget to measure and
monitor cost performance
 Developed by summing estimated costs by period (S curve of
values vs. time)
 Larger projects have multiple baselines to measure different
aspects of cost performance

24
Chapter 7 – Project Cost Management

 Cost Control
◦ Concerned with influencing factors that create changes to the
cost baseline that are beneficial
◦ Determining that the cost baseline has changed
◦ Managing actual changes as they occur
 Monitor cost performance to detect variances
 Record all appropriate changes accurately in the cost baseline
 Preventing incorrect, unauthorized changes being included in the cost
baseline
 Informing stakeholders of authorized changes
 Determine the “why’s” of positive and negative variances
 Integrated will all other control processes (scope, change, schedule, quality)

25
 Introduction

26
 Introduction

27
 Introduction

28
Chapter 7 – Project Cost Management

 Inputs to Cost Control


◦ Cost Baseline
◦ Performance Reports – meet, exceed budget
 50/50 Rule – task is considered 50% complete when it begins and gets credit for
remainder 50% only when completed
 20/80 Rule - task is considered 20% complete when it begins and gets credit for
remainder 80% only when completed
 0/100 Rule – task only credited when fully completed
◦ Change Requests
◦ Cost Management Plan
 Tools & Techniques of Cost Control
◦ Cost Change Control System – defines the procedures by which the cost
baseline may be changed
◦ Performance Measurement – assess magnitude of cost variations (Earned Value
Analysis) and what is causing the variance
◦ Additional Planning – examine alternatives
◦ Computerized Tools – forecast planned costs, track actual costs, forecast effect
of cost changes

29
Chapter 7 – Project Cost Management

 Cost Control Outputs


◦ Revised Cost Estimate
 Modifications to cost information; require stakeholder approval and
adjustments to other project areas
◦ Budget Updates – changes to approved cost baseline; revised in
response to scope changes
◦ Corrective Action
◦ Estimate at completion – (EAC) – forecast of total expenditures
 Actual to date plus remaining budget modified by a factor (cost performance
index)
 Current variances are seen to apply to future variances
 Actual to date plus new estimate for remaining work
 Original estimates are flawed, or no longer relevant
 Actual to date plus remaining budget
 Current variances are typical and similar variances will not occur in the future
◦ Lessons Learned

30
Chapter 7 – Project Cost Management

 Earned Value Analysis


◦ Integrates cost, schedule and scope
◦ Better that comparing projected vs. actual because
time and cost are analyzed separately
◦ Terms:
 BCWS – Budgeted Cost of Work Scheduled (how much work
should be done)
 BCWP – Budgeted Cost of Work Performed a.k.a. Earned
Value (how much work is budgeted, how much did we budget)
 ACWP – Actual Cost of Work Performed (how much did the
completed work cost)

31
Chapter 7 – Project Cost Management

 Earned Value Analysis


◦ Terms:
 BAC – Budget at Completion (how much did you
budget for the total job)
 EAC – Estimate at Completion (what do we expect
the total project to cost)
 ETC – Estimate to Completion (how much more
do we expect to spend to finish the job)
 VAC – Variance at Completion (how much
over/under budget do we expect to be)

32
Chapter 7 – Project Cost Management

 Earned Value Analysis


◦ Formulas
 Variance (Plan – Actual)
 Cost Variance (CV): BCWP – ACWP; negative is
over budget
 Schedule Variance (SV): BCWP – BCWS; negative is
behind schedule
 Cost Performance Index (CPI): BCWP
ACWP
 I am only getting x¢ out of every $

33
Chapter 7 – Project Cost Management

 Earned Value Analysis


◦ Formulas
 Schedule Performance Index (SPI): BCWP
BCWS

 I am only progressing x % of the planned rate


 Estimate at Completion (EAC): BAC
CPI

 As of now we expect the total project to cost x$


 Estimate to Complete (ETC): EAC – ACWP; how much will it
cost from now to completion
 Variance at Completion: BAC – EAC; when the project is over
how much more or less did we spend (most common way of
calculating EVA

34
Examples
 There are thirteen different combination of planned BCWS
vs. actual ACWP and earned BCWP. These are shown in table
below, along with a description of each situation.
 First calculate the EAC,
 Draw a sketch to show the BCWP and ACWP
Example

BAC BCWS BCWP ACWP EAC


(PV) (EV) (AC)

1 2000 1000 1000 1000


2 2000 1000 800 800
3 2000 1000 1000 800
4 2000 1000 1200 800
5 2000 1000 800 1000
6 2000 1000 1200 1000
7 2000 1000 800 1200
35
Examples

Example
BAC BCWS BCWP ACWP EAC
(PV) (EV) (AC)

8 2000 1000 1000 1200


9 2000 1000 1200 1200
10 2000 1000 600 800
11 2000 1000 800 600
12 2000 1000 1400 1200
13 2000 1000 1200 1400

36
Examples
BAC BCWS BCWP ACWP SV CV CPI EAC NOTES
(PV) (EV) (AC) = = = =
Example

EV-PV EV-AC EV/AC BAC/CPI

1 2 3 4 5=3-2 6=3-4 7=3/4 8=1/7

1 2000 1000 1000 1000 0 0 1 2000 As Budget On Schedule

2 2000 1000 800 800 -200 0 1 2000 As Budget Behind


Schedule
3 2000 1000 1000 800 0 200 1.25 1600 Cost On Schedule
Under run
4 2000 1000 1200 800 200 200 1.5 1333.3 Cost Ahead of
Under run Schedule
5 2000 1000 800 1000 -200 -200 0.8 2500 Cost over Behind
run Schedule
6 2000 1000 1200 1000 200 -200 1.2 1666.6 Cost Ahead of
Under run Schedule
7 2000 1000 800 1200 -200 -400 0.66 3030.3 Cost over Behind
run Schedule

37
Examples
BAC BCWS BCWP ACWP SV CV CPI EAC NOTES
(PV) (EV) (AC) = = = =
Example

EV-PV EV-AC EV/AC BAC/CPI

1 2 3 4 5=3-2 6=3-4 7=3/4 8=1/7

8 2000 1000 1000 1200 0 -200 0.833 2400.0 Cost over On


run schedule
9 2000 1000 1200 1200 200 0 1 200 As budget Ahead of
schedule
10 2000 1000 600 800 -400 -200 0.75 2666.66 Cost over Behind
run schedule
11 2000 1000 800 600 -200 200 1.33 1500 Cost under Behind
run schedule
12 2000 1000 1400 1200 400 200 1.167 1713.8 Cost under Ahead of
run schedule
13 2000 1000 1200 1400 200 -400 0.857 2333.3 Cost over Ahead of
run schedule

38
‫‪False Example‬‬
‫ﻣﻊ ﻣﻼﺣظﺔ أن اﻟﺗﻌﺎﻣل ﻣﻊ ﺗﻛﻠﻔﺔ اﻟﻧﺷﺎط ﻋﻠﻰ اﺳﺎس اﻧﮫ اﺟﻣﺎﻟﻰ اﻟﺗﻛﻠﻔﺔ ﻋن‬
‫زﻣن اﻟﻧﺷﺎط )‪ (A=15000/3months=5000/month‬ﺑﻣﻌﻧﻰ اﻟزﯾﺎده ﻓﻰ‬
‫زﻣن ﺗﻧﻔﯾذ ﯾﻘﺎﺑﻠﮭﺎ زﯾﺎده ﻓﻰ اﻟﻘﯾﻣﮫ اﻟﻣﺳﺗﺣﻘﮫ ﻋن اﻟﻣده)و ھذه اﻟﺣﺎﻟﺔ ﻻ ﺗﺣدث‬
‫اﻻ ﻋﻧد اﻟﺗﻌﺎﻣل ﻣﻊ اﻧﺷطﮫ ﺗﺗﺄﺛر ﻛﺛﯾرا ﺑﺄﺟور اﻟﻌﻣﺎﻟﮫ و اﻟﻣﻌدات اﻟﯾوﻣﯾﮫ ﻓﻘط(‬

‫‪39‬‬
BCWS BCWP ACWP SV CV NOTES

Actual Time
(PV) (EV) (AC) = =
Schedule
Example

EV-PV EV-AC
time

2 3 4 5=3-2 6=3-4

A 3 3 15 15 20 0 -5 Cost over run On schedule

B 6 7 60 70 75 10 -5 Cost over run Behind schedule

C 2 1 30 15 25 -15 -10 Cost under A head of


run schedule

D 4 7 20 35 30 15 5 Cost under Behind schedule


run

E 5 IP 25

F 4 IP

G 2 PL

150 135 150 -15 -15

40
Solving Examples – Quantity is the key

41
Examples – Money is the key

BAC BCWS BCWP ACWP SV CV CPI EAC NOTES


(PV) (EV) (AC) = = = =
Example

EV-PV EV-AC EV/AC BAC/CPI

1 2 3 4 5=3-2 6=3-4 7=3/4 8=1/7

200 150 125 150 -25 -25 0.833 240 Cost over Behind
run schedule

‫اﺛﺑﺎت ﻛﻣﺎ اﻋﻠﻰ‬ 200 150 135 150 -15 -15 0.9 222.2 ‫؟‬ ‫؟‬
42
‫اﺿف اﻟﻰ ﻣﻌﻠوﻣﺎﺗك‬

‫‪43‬‬
44
45
‫أﻋد اﻟﻌرض م‪/‬أﺣﻣد ﺳﻌﯾد‬ ‫ﻗﺎم ﺑﺎﻟﺗرﺟﻣﮫ م‪/‬ﻣﺣﻣود اﻟطﺣﺎوى‬

‫‪09/08/2008‬‬ ‫‪46‬‬
‫ﻣﺪﺧﻞ و أﻫﺪاف‬

‫‪09/08/2008‬‬ ‫اﻋد اﻟﻌرض م‪/‬أﺣﻣد ﺳﻌﯾد‬ ‫ﻗﺎم ﺑﺎﻟﺗرﺟﻣﮫ م‪/‬ﻣﺣﻣود اﻟطﺣﺎوى‬ ‫‪47‬‬
‫‪09/08/2008‬‬ ‫اﻋد اﻟﻌرض م‪/‬أﺣﻣد ﺳﻌﯾد‬ ‫ﻗﺎم ﺑﺎﻟﺗرﺟﻣﮫ م‪/‬ﻣﺣﻣود اﻟطﺣﺎوى‬ ‫‪48‬‬
‫‪09/08/2008‬‬ ‫اﻋد اﻟﻌرض م‪/‬أﺣﻣد ﺳﻌﯾد‬ ‫ﻗﺎم ﺑﺎﻟﺗرﺟﻣﮫ م‪/‬ﻣﺣﻣود اﻟطﺣﺎوى‬ ‫‪49‬‬
‫‪09/08/2008‬‬ ‫اﻋد اﻟﻌرض م‪/‬أﺣﻣد ﺳﻌﯾد‬ ‫ﻗﺎم ﺑﺎﻟﺗرﺟﻣﮫ م‪/‬ﻣﺣﻣود اﻟطﺣﺎوى‬ ‫‪50‬‬
‫ﻣﺎ ﻣﺪى اﻻﺳﺘﻔﺎدﻩ ﻣﻦ اﺳﺘﺨﺪام اﻟـ‪EVM‬‬

‫‪09/08/2008‬‬ ‫اﻋد اﻟﻌرض م‪/‬أﺣﻣد ﺳﻌﯾد‬ ‫ﻗﺎم ﺑﺎﻟﺗرﺟﻣﮫ م‪/‬ﻣﺣﻣود اﻟطﺣﺎوى‬ ‫‪51‬‬
‫‪09/08/2008‬‬ ‫اﻋد اﻟﻌرض م‪/‬أﺣﻣد ﺳﻌﯾد‬ ‫ﻗﺎم ﺑﺎﻟﺗرﺟﻣﮫ م‪/‬ﻣﺣﻣود اﻟطﺣﺎوى‬ ‫‪52‬‬
‫‪09/08/2008‬‬ ‫اﻋد اﻟﻌرض م‪/‬أﺣﻣد ﺳﻌﯾد‬ ‫ﻗﺎم ﺑﺎﻟﺗرﺟﻣﮫ م‪/‬ﻣﺣﻣود اﻟطﺣﺎوى‬ ‫‪53‬‬
‫‪09/08/2008‬‬ ‫اﻋد اﻟﻌرض م‪/‬أﺣﻣد ﺳﻌﯾد‬ ‫ﻗﺎم ﺑﺎﻟﺗرﺟﻣﮫ م‪/‬ﻣﺣﻣود اﻟطﺣﺎوى‬ ‫‪54‬‬
‫‪09/08/2008‬‬ ‫اﻋد اﻟﻌرض م‪/‬أﺣﻣد ﺳﻌﯾد‬ ‫ﻗﺎم ﺑﺎﻟﺗرﺟﻣﮫ م‪/‬ﻣﺣﻣود اﻟطﺣﺎوى‬ ‫‪55‬‬
‫‪09/08/2008‬‬ ‫اﻋد اﻟﻌرض م‪/‬أﺣﻣد ﺳﻌﯾد‬ ‫ﻗﺎم ﺑﺎﻟﺗرﺟﻣﮫ م‪/‬ﻣﺣﻣود اﻟطﺣﺎوى‬ ‫‪56‬‬
‫‪09/08/2008‬‬ ‫اﻋد اﻟﻌرض م‪/‬أﺣﻣد ﺳﻌﯾد‬ ‫ﻗﺎم ﺑﺎﻟﺗرﺟﻣﮫ م‪/‬ﻣﺣﻣود اﻟطﺣﺎوى‬ ‫‪57‬‬
‫‪09/08/2008‬‬ ‫اﻋد اﻟﻌرض م‪/‬أﺣﻣد ﺳﻌﯾد‬ ‫ﻗﺎم ﺑﺎﻟﺗرﺟﻣﮫ م‪/‬ﻣﺣﻣود اﻟطﺣﺎوى‬ ‫‪58‬‬
‫‪09/08/2008‬‬ ‫اﻋد اﻟﻌرض م‪/‬أﺣﻣد ﺳﻌﯾد‬ ‫ﻗﺎم ﺑﺎﻟﺗرﺟﻣﮫ م‪/‬ﻣﺣﻣود اﻟطﺣﺎوى‬ ‫‪59‬‬
‫‪09/08/2008‬‬ ‫اﻋد اﻟﻌرض م‪/‬أﺣﻣد ﺳﻌﯾد‬ ‫ﻗﺎم ﺑﺎﻟﺗرﺟﻣﮫ م‪/‬ﻣﺣﻣود اﻟطﺣﺎوى‬ ‫‪60‬‬
‫‪09/08/2008‬‬ ‫اﻋد اﻟﻌرض م‪/‬أﺣﻣد ﺳﻌﯾد‬ ‫ﻗﺎم ﺑﺎﻟﺗرﺟﻣﮫ م‪/‬ﻣﺣﻣود اﻟطﺣﺎوى‬ ‫‪61‬‬
‫‪09/08/2008‬‬ ‫‪62‬‬
‫اﻋد اﻟﻌرض م‪/‬أﺣﻣد ﺳﻌﯾد‬ ‫ﻗﺎم ﺑﺎﻟﺗرﺟﻣﮫ م‪/‬ﻣﺣﻣود اﻟطﺣﺎوى‬
‫‪09/08/2008‬‬ ‫اﻋد اﻟﻌرض م‪/‬أﺣﻣد ﺳﻌﯾد‬ ‫ﻗﺎم ﺑﺎﻟﺗرﺟﻣﮫ م‪/‬ﻣﺣﻣود اﻟطﺣﺎوى‬ ‫‪63‬‬
‫‪09/08/2008‬‬ ‫اﻋد اﻟﻌرض م‪/‬أﺣﻣد ﺳﻌﯾد‬ ‫ﻗﺎم ﺑﺎﻟﺗرﺟﻣﮫ م‪/‬ﻣﺣﻣود اﻟطﺣﺎوى‬ ‫‪64‬‬
‫‪09/08/2008‬‬ ‫اﻋد اﻟﻌرض م‪/‬أﺣﻣد ﺳﻌﯾد‬ ‫ﻗﺎم ﺑﺎﻟﺗرﺟﻣﮫ م‪/‬ﻣﺣﻣود اﻟطﺣﺎوى‬ ‫‪65‬‬
‫‪09/08/2008‬‬ ‫اﻋد اﻟﻌرض م‪/‬أﺣﻣد ﺳﻌﯾد‬ ‫ﻗﺎم ﺑﺎﻟﺗرﺟﻣﮫ م‪/‬ﻣﺣﻣود اﻟطﺣﺎوى‬ ‫‪66‬‬
‫‪09/08/2008‬‬ ‫اﻋد اﻟﻌرض م‪/‬أﺣﻣد ﺳﻌﯾد‬ ‫ﻗﺎم ﺑﺎﻟﺗرﺟﻣﮫ م‪/‬ﻣﺣﻣود اﻟطﺣﺎوى‬ ‫‪67‬‬
‫‪09/08/2008‬‬ ‫اﻋد اﻟﻌرض م‪/‬أﺣﻣد ﺳﻌﯾد‬ ‫ﻗﺎم ﺑﺎﻟﺗرﺟﻣﮫ م‪/‬ﻣﺣﻣود اﻟطﺣﺎوى‬ ‫‪68‬‬
‫‪09/08/2008‬‬ ‫اﻋد اﻟﻌرض م‪/‬أﺣﻣد ﺳﻌﯾد‬ ‫ﻗﺎم ﺑﺎﻟﺗرﺟﻣﮫ م‪/‬ﻣﺣﻣود اﻟطﺣﺎوى‬ ‫‪69‬‬
‫‪09/08/2008‬‬ ‫اﻋد اﻟﻌرض م‪/‬أﺣﻣد ﺳﻌﯾد‬ ‫ﻗﺎم ﺑﺎﻟﺗرﺟﻣﮫ م‪/‬ﻣﺣﻣود اﻟطﺣﺎوى‬ ‫‪70‬‬
‫‪09/08/2008‬‬ ‫اﻋد اﻟﻌرض م‪/‬أﺣﻣد ﺳﻌﯾد‬ ‫ﻗﺎم ﺑﺎﻟﺗرﺟﻣﮫ م‪/‬ﻣﺣﻣود اﻟطﺣﺎوى‬ ‫‪71‬‬
‫‪09/08/2008‬‬ ‫اﻋد اﻟﻌرض م‪/‬أﺣﻣد ﺳﻌﯾد‬ ‫ﻗﺎم ﺑﺎﻟﺗرﺟﻣﮫ م‪/‬ﻣﺣﻣود اﻟطﺣﺎوى‬ ‫‪72‬‬
‫‪09/08/2008‬‬ ‫اﻋد اﻟﻌرض م‪/‬أﺣﻣد ﺳﻌﯾد‬ ‫ﻗﺎم ﺑﺎﻟﺗرﺟﻣﮫ م‪/‬ﻣﺣﻣود اﻟطﺣﺎوى‬ ‫‪73‬‬
‫‪09/08/2008‬‬ ‫اﻋد اﻟﻌرض م‪/‬أﺣﻣد ﺳﻌﯾد‬ ‫ﻗﺎم ﺑﺎﻟﺗرﺟﻣﮫ م‪/‬ﻣﺣﻣود اﻟطﺣﺎوى‬ ‫‪74‬‬
‫‪09/08/2008‬‬ ‫اﻋد اﻟﻌرض م‪/‬أﺣﻣد ﺳﻌﯾد‬ ‫ﻗﺎم ﺑﺎﻟﺗرﺟﻣﮫ م‪/‬ﻣﺣﻣود اﻟطﺣﺎوى‬ ‫‪75‬‬
‫‪09/08/2008‬‬ ‫اﻋد اﻟﻌرض م‪/‬أﺣﻣد ﺳﻌﯾد‬ ‫ﻗﺎم ﺑﺎﻟﺗرﺟﻣﮫ م‪/‬ﻣﺣﻣود اﻟطﺣﺎوى‬ ‫‪76‬‬
‫‪09/08/2008‬‬ ‫اﻋد اﻟﻌرض م‪/‬أﺣﻣد ﺳﻌﯾد‬ ‫ﻗﺎم ﺑﺎﻟﺗرﺟﻣﮫ م‪/‬ﻣﺣﻣود اﻟطﺣﺎوى‬ ‫‪77‬‬
‫‪09/08/2008‬‬ ‫اﻋد اﻟﻌرض م‪/‬أﺣﻣد ﺳﻌﯾد‬ ‫ﻗﺎم ﺑﺎﻟﺗرﺟﻣﮫ م‪/‬ﻣﺣﻣود اﻟطﺣﺎوى‬ ‫‪78‬‬
‫‪09/08/2008‬‬ ‫اﻋد اﻟﻌرض م‪/‬أﺣﻣد ﺳﻌﯾد‬ ‫ﻗﺎم ﺑﺎﻟﺗرﺟﻣﮫ م‪/‬ﻣﺣﻣود اﻟطﺣﺎوى‬ ‫‪79‬‬
‫‪09/08/2008‬‬
‫اﻋد اﻟﻌرض م‪/‬أﺣﻣد ﺳﻌﯾد‬ ‫ﻗﺎم ﺑﺎﻟﺗرﺟﻣﮫ م‪/‬ﻣﺣﻣود اﻟطﺣﺎوى‬ ‫‪80‬‬
‫‪09/08/2008‬‬ ‫اﻋد اﻟﻌرض م‪/‬أﺣﻣد ﺳﻌﯾد‬ ‫ﻗﺎم ﺑﺎﻟﺗرﺟﻣﮫ م‪/‬ﻣﺣﻣود اﻟطﺣﺎوى‬ ‫‪81‬‬
‫‪09/08/2008‬‬ ‫اﻋد اﻟﻌرض م‪/‬أﺣﻣد ﺳﻌﯾد‬ ‫ﻗﺎم ﺑﺎﻟﺗرﺟﻣﮫ م‪/‬ﻣﺣﻣود اﻟطﺣﺎوى‬ ‫‪82‬‬
83
84
‫‪09/08/2008‬‬ ‫اﻋد اﻟﻌرض م‪/‬أﺣﻣد ﺳﻌﯾد‬ ‫ﻗﺎم ﺑﺎﻟﺗرﺟﻣﮫ م‪/‬ﻣﺣﻣود اﻟطﺣﺎوى‬ ‫‪85‬‬

You might also like