Professional Documents
Culture Documents
CHAPTER THREE:
DETERMINE BUDGET
1
Introduction
✓ Determine Budget is the process of aggregating the estimated
costs of individual activities or work packages to establish an
authorized cost baseline. The key benefit of this process is that
it determines the cost baseline against which project
performance can be monitored and controlled.
2
• The WBS is a required input to the cost budgeting
process since it defines the work items
3
Determine Budget
2. Basis of Estimates
✓ Supporting detail for cost estimates contained in the basis for
estimates should specify any basic assumptions dealing with
the inclusion or exclusion of indirect or other costs in the
project budget.
5
3. Scope Baseline
✓ Project scope statement. Formal limitations by period for the
expenditure of project funds can be mandated by the organization,
by agreement or by other entities such as government agencies.
These funding constraints are reflected in the project scope
statement.
5. Resource calendars
7. Agreements
8
8. Organizational Process Assets
• Reporting methods.
9
Determine Budget: Tools and techniques
1. Cost Aggregation
• Cost aggregation is defined as summing the cost for the individual
work package to control the financial account up to the project level.
• This is achieved by the summation of the lower-level cost estimates that
are associated with different work packages within the work breakdown
structure.
• The work package cost estimates are then aggregated for the higher
component levels of the WBS (such as control accounts) and ultimately
for the entire project.
• This will allow project managers to see the activities as well as the
corresponding costs
• The main output of cost aggregate is the determination of the cost-
performance baseline 10
2. Reserve Analysis
• Budget reserve analysis can establish both the contingency
reserves and the management reserves for the project.
11
3. Expert Judgment
• Expert judgment, guided by experience in an application area,
Knowledge Area, discipline, industry, or similar project, aids in
determining the budget. Such expertise may be provided by any
group or person with specialized education, knowledge, skill,
experience, or training. Expert judgment is available from many
sources, including, but not limited to:
• Other units within the performing organization,
• Consultants,
• Stakeholders, including customers,
• Professional and technical associations, and
• Industry groups.
12
4. Historical relationships
• Any historical relationships that result in parametric estimates
or analogous estimates involve the use of project
characteristics (parameters) to develop mathematical models to
predict total project costs. Such models may be simple (e.g.,
residential home construction is based on a certain cost per
square foot of space) or complex (e.g., one model of software
development costing uses multiple separate adjustment factors,
each of which has numerous points within it).
13
Historical relationships
• Both the cost and accuracy of analogous and parametric
models can vary widely. They are most likely to be reliable
when:
✓ Historical information used to develop the model is
accurate,
✓ Parameters used in the model are readily quantifiable,
and
✓ Models are scalable, such that they work for large
projects, small projects, and phases of a project.
14
5. Funding Limit reconciliation
• There are different tools that allow project managers to do cost
budgeting and one of the methods is the funding limit
reconciliation.
• It involves the comparison and adjustment of the funding limits
and the estimated costs by refining the scope and schedule of the
project activities.
• A variance between the funding limits and the planned
expenditures will sometimes necessitate the rescheduling of
work to level out the rate of expenditures.
15
Funding Limit reconciliation
16
Determine Budget: outputs
1. Cost Baseline
• The cost baseline is the approved version of the time-phased project
budget, excluding any management reserves, which can only be
changed through formal change control procedures and is used as a
basis for comparison to actual results. It is developed as a
summation of the approved budgets for the different schedule
activities.
19
Management reserves are added to the cost baseline to produce the project budget. As changes warranting the
use of management reserves arise, the change control process is used to obtain approval to move the applicable
management reserve funds into the cost baseline.
7
Project Management
Budget Reserve
Activity Cost
Estimates
Total Amount
• You may also need to set aside budget for miscellaneous items (e.g.
transportation, exam Prep book , mock exams etc.): US$300
• Certification Cost: US$1043 which is the cost estimate for the Project
22
• Ali will also need to set aside budget for any identified risks (e.g. unable
to finish preparation on time — postpone the exam, need extra learning
aids as the exam is unexpected difficult, re-exam after a fail, etc.) which is
expected to be US$500 (Contingency Reserve).
• Ali is also advised to set aside money for any unknown unknowns which is
set at around 10% of the Cost Estimate at this time (according to his own
decision), i.e. US$100 (Management Reserve) .
• Project documents that may be updated include, but are not limited
to:
✓ Risk register,
✓ Activity cost estimates, and
✓ Project schedule.
25
26