Professional Documents
Culture Documents
1
Objectives
At the end of this chapter, students should be able to
Explain basic cost management principles, concepts and terms
Describe the resource planning, cost estimating, cost budgeting, and cost
control processes
Explain the different types of cost estimates
Understand what is involved in preparing a cost estimate for an information
technology project
Perform calculations for earned value analysis
Understand the benefits of using earned value analysis
2
The Importance of Project Cost Management
8
Cost Estimating
An important output of project cost management is a
cost estimate
There are several types of cost estimates, and tools and
techniques to help create them
It is also important to develop a cost management plan
that describes how cost variances will be managed on the
project
9
Cost Estimation Tools and Techniques
11
Typical Problems with Cost Estimates
Developing an estimate for a large software project is a
complex task requiring a significant amount of effort.
Remember that estimates are done at various stages of
the project
Many people doing estimates have little experience doing
them. Try to provide training and mentoring
People have a bias toward underestimation. Review
estimates and ask important questions to make sure
estimates are not biased
Management wants a number for a bid, not a real
estimate. Project managers must negotiate with project
sponsors to create realistic cost estimates 12
Cost Budgeting
Cost budget involves allocating the project cost
estimate to individual work items and providing a
cost baseline
For example, in the Business Systems Replacement
project, there was a total purchased costs estimate
for FY97 of $600,000 and another $1.2 million for
Information Services and Technology.
13
Cost Control
Project cost control includes
monitoring cost performance
ensuring that only appropriate project changes are included in a
revised cost baseline
informing project stakeholders of authorized changes to the
project that will affect costs
16
Earned Value Method data sources
Planned value (PV), formerly called the budgeted cost
of work scheduled (BCWS), also called the budget, is that
portion of the approved total cost estimate planned to be
spent on an activity during a given period
Actual cost (AC), formerly called actual cost of work
performed (ACWP), is the total of direct and indirect
costs incurred in accomplishing work on an activity
during a given period
Earned value (EV), formerly called the budgeted cost
of work performed (BCWP), is the percentage of work
actually completed multiplied by the planned value
17
Rules of Thumb for EVA Numbers
18
Cont…
Schedule Variance (SV): Schedule variance is the difference
between your planned progress and your actual progress to
date.
The SV calculation is EV (earned value) - PV (planned value).
Let’s assume you have a four-month-long project, and you’re
two months in, but the project is only 25% complete. In this
case, your EV = 1 months (25% of four months), and your PV
= 2 months. Therefore your SV is 1 - 2 = -1. Since the number
is negative, it indicates you’re behind schedule.
19
Cost Variance (CV): Similar to SV, cost variance is the
difference between how much you planned on spending
thus far and your actual costs to date.
The CV calculation is: CV = EV - AC (actual cost).
example. Your project budget is $100,000 and you’re
60% done, which means your EV is $60,000. If you’ve
spent $70,000 so far to get to this point in the project,
your CV is -$10,000.
You can tell you’re over budget because the number is
negative, which may indicate a problem with the project or
that the project could go over budget or run out of money.
20
Project efficiency indexes
Schedule Performance Index (SPI): The SPI is an indicator of
the efficiency of the program of a project.
it is the ratio between the earned value (EV) and the planned
value (PV): SPI = EV / PV.
If the SPI is equal to or greater than one, this indicates a
favorable condition. This means that the project is being carried
out efficiently.
21
Cont…
Cost Performance Index (CPI): is the indicator of economic
efficiency of a project and is the ratio between the earned value
(EV) and the actual costs (CA):
CPI = EV/AC.
When CPI is over 1.00, you’re under budget, and when it’s
under 1.00, you’re overspending.
22
Cont…
23
Example
Suppose you have a budgeted cost of a project at Birr
900,000.
The project is to be completed in 9 months. After a
month, you have completed 10 percent of the project
at a total expense of Birr 100,000. The planned
completion should have been 15 percent.
Given:
PV to date = Birr 900,000
AC = Birr 100,000
24
…solution
Earned Value = Percent Completed (%) * Planned
Valued to date
= 10% * Birr 900,000
= Birr 90,000
25
…continued
CV = EV – AC The project is
costing more
= 90,000 – 100,000 than planned and
because CV is
less than zero.
= -10,000
SV = EV – PV
= 90,000 – 900,000 The project is
taking longer
= - 810,000 than planned
because SV is
less than zero.
26
…continued
CPI= EV / AC
= $90,000 / $100,000
It shows Poor
= 0.90 Performance
SPI= EV/PV because CV
and SV are
= 90,000 / 900,000 less than one.
= 0.1
27
Exercise
Assume you have a project to be
completed in 12 months. Its budgeted
cost is Birr 2,000,000. After 3 months,
you have completed 18% of your project
at a total cost of Birr 250,000. The
planned completion should have been
20%.
28
Questions
a) EV
b) CV
c) CPI
d) Is the project is costing more than planned,
less than planned, or according to the
planned? Why?
e) Is the project showing poor performance,
exceptional performance, or it is
performing according to the plan? Why?
29
Thank You
30