Professional Documents
Culture Documents
Project Identifications
Project Feasibility Studies
Market & Demand Analysis
Technical Analysis
Project Cost Estimates
Financial Appraisal
The totals from the budget should still match the estimated totals
approved by the strategic decision makers. As u see it, an estimate
is used to make the decision about a destination, but a budget
provides the detailed road map on how to get there. So you will
generally need both because they are each prepared and presented
for different purposes.
Your estimate should be as close to the final budget as possible,
but this comes with experience and expertise
Project Cost Management 12
Determine Budget
A Project Budget is the total amount of monetary resources that are
allocated for particular goals and objectives of the project for a specific
period of time. The purpose of project budget management is to estimate
and control project costs within the approved budget and to achieve the
stated goals of the project
Having a thorough budget the project manager can make better decisions
regarding the constraints (time, cost and scope) to successfully complete
the project while satisfying stakeholders’ needs and understanding the
implications on the PM schedule and resource allocation.
Project Cost Management 13
Budgeting Approaches
There are two main approaches you can take when creating a
budget:
Top-down approach: deciding how much the project will cost
and dividing the amount between the work packages.
Bottom-up approach: estimating the total cost of the project
by costing the lowest-level work packages and rolling up.
The team, often involving the final budget holder, identify the
tasks and activities needed to complete the project. The project
is based on the lowest-level work packages and rolled up to
arrive at the total project cost. The direct and indirect costs are
calculated for each work package.
PV = FV / (1 + r)n
IRR is the discount rate that makes the Net Present Value
(NPV) of the Project EQUAL to ZERO.
An investment to be accepted if its IRR is higher than its Cost
of Capital and should be rejected, if lower.
IRR can be interpreted as a measure of profitability of its
expected cash flows.
IRR takes into account Time Value of money and risk of
investment
Benefit Cost Ratio (BCR ) / Profitability Index(PI) /
Desirability Index (DI).
PI = 1 Uncertainty
PI > 1 Accept
PI < 1 Reject
Limitations of Financial appraisal
The concept of ‘Financial appraisal’ works completely fine in a
world where there is a well-defined benefit for a well-defined
investment. Although, reality is not always that simple. A
quantitative and conventional approach is particularly
problematic where:
There is no guaranteed return
The benefit is made in terms of reduction of labour
The project is considered to be strategic in nature – e.g. a new
computer system being installed in a company, resulting in a
speed up of the transfer of information and a more integrated
organization – this will be challenging to show as a cash
return.
The organization is a non-profit sector – e.g. government or
charity
NPV = ? PI = ?
1,00000 1.5
Example : 2
NPV = ? PI = ?
2,00000 1.25
Case is recommended