Professional Documents
Culture Documents
1
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
2
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
Project Cost Management Processes
4
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.1 Plan Cost Management
Inputs Tools & Techniques Outputs
5
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.1.1 Plan Cost Management – Inputs
2. Project Charter
6
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.1.2 Plan Schedule Management– Tools & Techniques
1. Expert Judgment
2. Analytical Techniques:
3. Meetings
7
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.1.3 Plan Cost Management - Outputs
Level of precision
Reporting formats
Process Descriptions
9
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.2 Estimate Costs
What will be estimated?
Generally work packages
cost and activity cost will be
estimated.
Work
Package
Cost
Activity Cost
10
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.2 Estimate Costs
What will be estimated? Project
Cost
However, for larger projects,
cost might more practical to Control
Account
estimate and control at a Cost
higher level. This is called a
control account and it is one Work
Package
level higher than the work Cost
11
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.2 Estimate Costs
All the work needed to complete the project is also estimated, including:
Quality efforts
Risk efforts
Costs directly associated with the project, including training for the project, paper,
pencils, needed labor
12
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.2 Estimate Costs - Types of Cost
Direct costs - These costs are attributed directly to the project work and
cannot be shared among projects (airfare, hotels, and long distance phone
charges, and so on).
Indirect costs -These costs are representative of more than one project
(utilities for the performing organization, access to a training room, project
management software license, and so on).
Fixed costs -These costs remain constant throughout the project (the cost
of a piece of rented equipment for the project, the cost of a consultant
brought onto the project, and so on).
Sunk cost - Money that has been spent in the past; when deciding what
projects to invest in or continue, you should not include sunk costs
13
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.2 Estimate Costs
Things about Estimating to know for the exam
Estimating should be based on a WBS to improve accuracy
Estimating should be done by the person doing the work whenever possible
A cost baseline should be kept and not changed except for approved
project changes
14
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.2 Estimate Costs
Things about Estimating to know for the exam
A project manager should never just accept requirements from
management, but rather analyze the needs of the project, come up with his
own estimates and reconcile any differences to produce realistic objectives.
A project manager may continually calculate the estimate to complete for
the project in order to make sure there are adequate funds available for the
project
Padding is not an acceptable project management practice
The project manager must meet any agreed upon estimates
Clear procedures should exist to determine what to do with the estimates
when received
Project Manager should keep the estimates realistic
15
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
Cost Management Plan
17
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
Cost Management Plan
Cost Risk
Who has the cost risk in a fixed price contract, the buyer or the seller?
18
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.2 Estimate Costs
Inputs Tools & Techniques Outputs
1. Cost Management 1. Expert Judgement 1. Activity Cost Estimates
Plan 2. Analogous estimating 2. Basis of Estimates
2. Human Resource 3. Parametric estimating 3. Project document updates
Management Plan 4. Bottom-up estimating
3. Scope Baseline 5. Three-point estimates
4. Project Schedule 6. Reserve Analysis
5. Risk Register 7. Cost of Quality
6. Enterprise 8. Project Management
Environmental Estimating Software
Factors 9. Vendor Bid Analysis
7. Organizational 10. Group Decision Making
Process Assets Techniques
19
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.2.1 Estimate Costs - Inputs
3. Scope Baseline
Project Scope Statement
Including any Cost Constraint
The schedule management plan is needed so that the project manager and the
project team can estimate how much the resources will cost the project, when the
funds will be used to employ or consume the resources, and the cost impact should
the identified resources miss deadlines within the project.
5. Risk register
The risk register should be reviewed to consider risk mitigation costs .
As a general rule , when the project experiences a negative risk event , the near
term cost of the project will usually increase , and there will sometimes be a
delay in the project schedule
21
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.2.1 Estimate Costs - Inputs
5. Enterprise Environmental Factors
Company culture and existing systems that the project will have to deal
with or can make use of. For cost, this includes marketplace conditions
and commercial cost databases
22
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.2 Estimate Costs
Inputs Tools & Techniques Outputs
1. Cost Management 1. Expert Judgement 1. Activity Cost Estimates
Plan 2. Analogous estimating 2. Basis of Estimates
2. Human Resource 3. Parametric estimating 3. Project document updates
Management Plan 4. Bottom-up estimating
3. Scope Baseline 5. Three-point estimates
4. Project Schedule 6. Reserve Analysis
5. Risk Register 7. Cost of Quality
6. Enterprise 8. Project Management
Environmental Estimating Software
Factors 9. Vendor Bid Analysis
7. Organizational 10. Group Decision Making
Process Assets Techniques
23
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.2.2 Estimate Costs – Tools & Techniques
1. Expert Judgement
2. Analogous Estimating
Analogous estimating relies on historical information to predict the
cost of the current project. It is also known as top-down estimating.
The cost of the historical project is applied to the cost of the current
project, taking into account the scope and size of the current
project as well as other known variables.
The current project, King Park, will have a similar surface and will
cover 4,500 feet by 6 feet. The analogous estimate for this project,
based on the work in Lagoon Park, is Dhs. 323,190.
25
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.2.2 Estimate Costs – Tools & Techniques
3. Parametric Estimating
Parametric estimating uses a mathematical model based on known
parameters to predict the cost of a project.
26
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.2.2 Estimate Costs – Tools & Techniques
The parametric cost model using a scalable cost-per unit
approach is depicted below:
27
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.2.2 Estimate Costs – Tools & Techniques
There are two types of Parametric
Estimating:
3.a) Regression analysis
29
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.2.2 Estimate Costs – Tools & Techniques
4. Bottom-up Estimating
Bottom-up estimating starts from zero, accounts for each individual
component of the WBS, and arrives at a sum for the project.
It is completed with the project team and can be one of the most
time-consuming methods used to predict project costs.
30
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.2.2 Estimate Costs – Tools & Techniques
5. Three-Point Estimates
Originated with PERT
Optimistic(CO)
Pessimistic (CP)
31
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.2.2 Estimate Costs – Tools & Techniques
6. Reserve Analysis
Estimators generally include cost reserves called Contingency Reserve.
This is traditionally set aside for cost overruns to deal with anticipated but
not certain, risk events.
These events are “known unknowns” and are part of the project scope and
cost baselines.
32
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.2.2 Estimate Costs – Tools & Techniques
34
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.2 Estimate Costs
Inputs Tools & Techniques Outputs
1. Cost Management 1. Expert Judgement 1. Activity Cost Estimates
Plan 2. Analogous estimating 2. Basis of Estimates
2. Human Resource 3. Parametric estimating 3. Project document updates
Management Plan 4. Bottom-up estimating
3. Scope Baseline 5. Three-point estimates
4. Project Schedule 6. Reserve Analysis
5. Risk Register 7. Cost of Quality
6. Enterprise 8. Project Management
Environmental Estimating Software
Factors 9. Vendor Bid Analysis
7. Organizational 10. Group Decision Making
Process Assets Techniques
35
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.2.3 Estimate Costs - Outputs
1. Activity Cost Estimates
The output of cost estimating is the actual cost estimates of the resources
required to complete the project work.
Each resource in the project must be accounted for and assigned to a cost
category. Categories include the following:
Labor costs
Material costs
Travel costs
Supplies
Hardware costs
Software costs
37
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.2.3 Estimate Costs - Estimating Accuracy
Rough order of magnitude This estimate is “rough” and is used
during the initiating processes and in top-down estimates. The range
of variance for the estimate can be from −25 percent to +75 percent.
Budget estimate This estimate is also somewhat broad and is used
early in the planning processes and also in top-down estimates. The
range of variance for the estimate can be from −10 percent to +25
percent.
Definitive estimates This estimate type is one of the most
accurate. It’s used late in the planning processes and is associated
with bottom-up estimating. The range of variance for the estimate
can be from −5 percent to +10 percent.
38
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.2.3 Estimate Costs - Outputs
2. Basis of Estimates
Once the estimates have been completed, supporting detail must be organized
and documented to show how the estimates were created.
40
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.2 Estimate Costs
Inputs Tools & Techniques Outputs
1. Cost Management 1. Expert Judgement 1. Activity Cost Estimates
Plan 2. Analogous estimating 2. Basis of Estimates
2. Human Resource 3. Parametric estimating 3. Project document updates
Management Plan 4. Bottom-up estimating
3. Scope Baseline 5. Three-point estimates
4. Project Schedule 6. Reserve Analysis
5. Risk Register 7. Cost of Quality
6. Enterprise 8. Project Management
Environmental Estimating Software
Factors 9. Vendor Bid Analysis
7. Organizational 10. Group Decision Making
Process Assets Techniques
41
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
42
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.3 Determine Budget
44
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.3 Determine Budget
Cost budgeting and cost estimates may go hand-in-hand, but
estimating should be completed before a budget is
requested—or assigned.
45
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
46
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.3 Determine Budget
47
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.3.1 Determine Budget - Inputs
2. Scope Baseline
4. Basis of Estimates
5. Project Schedule
Used to aggregate costs to the calendar periods
6. Resource Calendars
Used to indicate resource costs over the duration of the project
7. Risk Register
48
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.3.1 Determine Budget - Inputs
8. Contracts
49
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.3.2 Determine Budget – Tools & Techniques
1. Cost Aggregation
2. Reserve Analysis
3. Expert Judgement
4. Historical Relationships
50
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.3.2 Determine Budget – Tools & Techniques
1. Cost Aggregation
Project Cost
51
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.3.2 Determine Budget – Tools & Techniques
2. Reserve Analysis
There can two types of reserves to be considered;
2. Contingency reserve.
52
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.3.2 Determine Budget – Tools & Techniques
Management Contingency Cost reserves are generally to deal
with “unknown unknowns” within a project. The Management
Contingency Reserve is NOT part of the project’s cost baseline,
but is included as part of the project budget. Project Manager
has to obtain approval before spending this reserve for
unplanned changes to Project Scope and Cost.
Contingency reserve is for the risks remaining after risk
response planning. It is reserve for anticipated but not certain
risk events.
The cost baseline will contain the contingency reserve and the cost
budget will include the management reserve. (Refer next slide
diagram)
53
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.3.2 Determine Budget – Tools & Techniques
COSTING
54
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.3.2 Determine Budget – Tools & Techniques
3. Expert Judgement
Judgement provided based upon expertise in an application area,
Knowledge Area, discipline, industry etc as appropriate for the
activity being performed should be used in determining the budget.
Consultants
Industry groups
55
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.3.2 Determine Budget – Tools & Techniques
4. Historical Relationships
It involves using project characteristics (parameters) in a
mathematical model to predict total project costs. Models can be as
simple ( e.g., residential home construction will cost a certain
amount per square foot of living space) or complex.
Both the cost and accuracy of parametric models may vary widely.
They are most likely to be reliable when:
The historical information used to develop the model is accurate
The model is scalable, such that it works for a large project as well as a
small one.
56
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.3.2 Determine Budget – Tools & Techniques
5. Funding Limit Reconciliation
Funding limit reconciliation is an organization’s approach to
managing cash flow against the project deliverables based on a
schedule, milestone accomplishment, or data constraints.
This helps an organization plan when monies will be devoted to a
project rather than using all of the funds available at the start of a
project.
If the project doesn’t hit predetermined dates and products that
were set as milestones, the additional funding becomes
questionable.
57
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.3.3 Determine Budget – Outputs
1. Cost baseline
58
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.3 Determine Budget
1. Cost baseline
A project’s cost baseline shows what is expected to be spent on
the project. It’s usually shown in an S-curve.
60
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.3.3 Determine Budget – Cost Baseline
The idea of the cost baseline allows the project manager and
management to predict when the project will be spending
monies and over what time period.
61
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.3.3 Determine Budget – Outputs
62
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.3.3 Determine Budget – Outputs
Cost Estimates
Project Schedule
63
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
64
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.4 Control Costs
Inputs Tools & Techniques Outputs
1. Project 1. Earned Value Management 1. Work Performance
Management Plan 2. Forecasting Information
2. Project Funding 3. To-complete Performance 2. Cost Forecasts
Requirements Index (TCPI) 3. Change Requests
3. Work Performance 4. Performance Reviews 4. Project Management Plan
Data 5. Project Management updates
4. Organizational Software 5. Project document updates
Process Assets 6. Reserve Analysis 6. Organizational Process
Assets updates
65
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.4 Control Costs
66
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.4 Control Costs
Specifically, cost control focuses on the following activities:
Controlling causes of change to ensure the changes are actually needed
67
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.4 Control Costs
Inputs Tools & Techniques Outputs
1. Project 1. Earned Value Management 1. Work Performance
Management Plan 2. Forecasting Information
2. Project Funding 3. To-complete Performance 2. Cost Forecasts
Requirements Index (TCPI) 3. Change Requests
3. Work Performance 4. Performance Reviews 4. Project Management Plan
Data 5. Project Management updates
4. Organizational Software 5. Project document updates
Process Assets 6. Reserve Analysis 6. Organizational Process
Assets updates
68
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.4.1 Control Costs - Inputs
70
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.4 Control Costs
Inputs Tools & Techniques Outputs
1. Project 1. Earned Value Management 1. Work Performance
Management Plan 2. Forecasting Information
2. Project Funding 3. To-complete Performance 2. Cost Forecasts
Requirements Index (TCPI) 3. Change Requests
3. Work Performance 4. Performance Reviews 4. Project Management Plan
Data 5. Project Management updates
4. Organizational Software 5. Project document updates
Process Assets 6. Reserve Analysis 6. Organizational Process
Assets updates
71
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.4.2 Control Costs – Tools & Techniques
2. Forecasting
4. Performance Reviews
6. Reserve Analysis
72
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.4.2 Control Costs – Tools & Techniques
73
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.4.2 Control Costs – Tools & Techniques
Acronym Term Interpretation
PV Planned Value What is the estimated value of the work planned to be done ?
BAC Budget At Completion How much did we BUDGET for the TOTAL project effort?
EAC Estimate At Completion What do we currently expect the TOTAL project to cost?
ETC Estimate to Complete From this point on, how much MORE do we expect it to cost
to finish the project?
VAC Variation at Completion How much over or under budget do we expect to be at the
end of the project?
74
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.4.2 Control Costs – Tools & Techniques
EVM, in regard to cost management, is concerned with the
relationship between three formulas that reflect project
performance.
Planned value (PV) Planned value is the work scheduled and the
budget authorized to accomplish that work.
The total Planned Value for the project is also called Budget At
Completion (BAC).
77
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.4.2 Control Costs – Tools & Techniques
78
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.4.2 Control Costs – Tools & Techniques
Cost Variance
The cost variance (CV) is the difference between the earned value and
the actual costs (ACs).
For example, for a project that has a budget of $200,000 and has
earned or completed ten percent of the project value, the EV is
$20,000.
However, due to some unforeseen incidents, the project manager had
to spend $25,000 to complete that $20,000 worth of work.
The AC of the project, at this point, is $25,000, and the cost variance is
–$5,000.
Thus, the equation for cost variance is CV = EV − AC.
The CV is critical as it indicates physical performance to costs spent.
Negative CV is non-recoverable to the project generally. 79
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.4.2 Control Costs – Tools & Techniques
Schedule Variance
A schedule variance (SV) is the value that indicates whether a project is
falling behind it’s baseline schedule
For example, consider a project with a budget of $200,000 that’s expected
to last two years. At the end of year one, the project team has planned that
the project be 60-percent complete. Thus, the planned value (PV) for 60-
percent completion equates to $120,000—the expected worth of the
project work at the end of year one.
But let’s say that at the end of year one the project is only 40-percent
complete. The EV at the end of year one is, therefore, $80,000. The
difference between the PV and the EV is the SV: –$40,000.
The equation for schedule variance is SV = EV − PV.
SV will be Zero when project is completed since all the PV values
have become EV values.
SV is used in conjunction with the Critical Path Methodology 80
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.4.2 Control Costs – Tools & Techniques
Calculating the Cost Performance Index
The cost performance index (CPI) shows the amount of work
the project is completing per dollar spent on the project.
In other words, a CPI of .93 means it is costing $1.00 for every 93
cent’s worth of work. Or you could say the project is losing seven
cents on every dollar spent on the project.
CPI = EV ÷ AC
81
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.4.2 Control Costs – Tools & Techniques
Let’s say a project has an EV of $25,000 and an AC of $27,000. The CPI
for this project is thus .93. The closer the number is to 1, the better the
project is doing. The equation for cost performance index is CPI = EV/AC.
82
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.4.2 Control Costs – Tools & Techniques
Cumulative CPI (CPIC) is a commonly used calculation to
predict project costs at the completion of the project. It also
represents the cumulative CPI of the project at the point the
measurement is taken.
The formula looks just like the CPI formula only it uses the
sums as follows:
CPIC = EVC ÷ ACC
83
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.4.2 Control Costs – Tools & Techniques
The difference between this and the CPI formula earlier is that the
CPI formula is used for a single work component whereas the CPIC
is calculated using the sum of all the costs of all the work
components.
Additionally, you may also use CPI to calculate the total cost of a
work component like a deliverable for example.
84
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.4.2 Control Costs – Tools & Techniques
Finding the Schedule Performance Index
The schedule performance index (SPI) is very similar to the CPI.
The SPI, however, reveals how closely the project is on schedule.
Again, as with the CPI, the closer the quotient is to 1 the better.
The formula is EV divided by the PV.
In our example, the EV is $20,000, and let’s say the PV, where the
project is supposed to be, is calculated as $30,000. The SPI for
this project is then .67—way off target!
The equation for schedule performance index is SPI = EV/PV.
85
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.4.2 Control Costs – Tools & Techniques
2. Forecasting
2. Estimate At Completion
86
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.4.2 Control Costs – Tools & Techniques
1. Forecasting Technique - Estimate to Complete
87
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.4.2 Control Costs – Tools & Techniques
88
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.4.2 Control Costs – Tools & Techniques
CASE 1 Example
Assuming our EVC value is 725, CPIC value is 1.12, and BAC is
1000, let’s plug in the numbers:
89
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.4.2 Control Costs – Tools & Techniques
When you believe that future cost variances will not be
similar to the types of variances you’ve seen to date, you’ll
use this formula to calculate ETC:
ETC = (BAC – EVC)
90
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.4.2 Control Costs – Tools & Techniques
91
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
EAC Calculations
Common EAC Approach
EAC = AC + bottom-up ETC
EAC forecast for ETC work considering both SPI and CPI
EAC = AC + [(BAC – EV) / (cumulative CPI x cumulative SPI)] 92
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.4.2 Control Costs – Tools & Techniques
Many approaches to Calculating EAC.
Based on BAC,
(BAC – AC)
94
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.4.2 Control Costs – Tools & Techniques
3. To-complete Performance Index (TCPI) (Contd…)
Based on EAC,
(EAC – AC)
95
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.4.2 Control Costs – Tools & Techniques
96
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.4.2 Control Costs – Tools & Techniques
4.1 Performance Review - Variance Analysis
Variance at completion (VAC) calculates the difference between
the budget at completion and the estimate at completion.
The negative number means you’re not doing as well with costs as
you anticipated and that variance exists. As the project progresses,
variances will become smaller.
97
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.4.2 Control Costs – Tools & Techniques
4.2 Performance Review - Trend Analysis
According to A Guide to the PMBOK, trend analysis determines if
project performance is improving or worsening over time by
periodically analyzing project results.
There are several formulas you can use to predict project trends,
but it’s outside the scope of this book to go into them.
98
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.4.2 Control Costs – Tools & Techniques
99
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.4.2 Control Costs – Tools & Techniques
5. Project Management Software
Project managers can rely on project management software and
spreadsheet programs to assist them in calculating actual costs,
earned value, and planned value. It may also assist in forecasting
6. Reserve Analysis
Status of Management and Contingency Reserves
100
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.4.3 Control Costs – Outputs
1. Work Performance Information
2. Cost Forecasts
3. Change Requests
101
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.4.3 Control Costs – Outputs
1. Work Performance Information - The calculated CV,SV,CPI,SPI
values for WBS components, are documented and communicated
to the stakeholders
3. Change Requests
Analysis of project performance can result in a change request to the cost
performance baseline or the Project Management Plan.
Corrective Actions
Lessons Learned
103
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
7.4.3 Control Costs – Outputs
Considering the Cost Control Results
104
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved
Rules of Thumb for Earned Value Numbers
Negative numbers for cost and schedule variance indicate
problems in those areas
105
Chicago Management Training Institute LLC. Email: info@chicagomti.com www.chicagomti.com. © 2009 All rights reserved