Professional Documents
Culture Documents
The cost of individual work packages or activities is estimated with the greatest
level of specified detail.
The detailed cost is then summarized or “rolled up” to higher levels for subsequent
reporting and tracking purposes.
The cost and accuracy of bottom-up cost estimating is typically influenced by the
size and complexity of the individual activity or work package.
Advantages and disadvantages of
Bottom-up Estimating
7.2.2 Estimate Costs:
Tools and Techniques
7.2.5 Three-Point Estimates
The accuracy of single-point activity cost estimates can be improved by
considering estimation uncertainty and risk.
This concept originated with the program evaluation and review technique
(PERT).
PERT uses three estimates to define an approximate range for an activity’s
cost:
• Most likely (cM). The cost of the activity, based on realistic effort assessment
for the required work and any predicted expenses.
• Optimistic (cO). The activity cost based on analysis of the best-case scenario
for the activity.
• Pessimistic (cP). The activity cost based on analysis of the worst-case scenario
for the activity.
Two commonly used formulas are triangular and beta distributions.
The formulas are:
• Triangular Distribution. cE = (cO + cM + cP) / 3
• Beta Distribution : cE = (cO + 4cM + cP) / 6
7.2.2 Estimate Costs:
Tools and Techniques
.6 Reserve Analysis
Cost estimates may include contingency reserves (sometimes called
contingency allowances) to account for cost uncertainty.
Reserves are added to costing to manage risks, cost overruns and
error associated with costing.
More details about reserve analysis in Risk Management
Since the cost estimates that make up the cost baseline are directly
tied to the
schedule activities, this enables a time-phased view of the cost
baseline, which is typically displayed in the form of an S-curve,
7.3.3 Determine Budget: Outputs
Cost Baseline, Expenditures, and Funding Requirements
7.3.3 Determine Budget: Outputs
Project Budget Component
• Management reserves are added to the cost baseline to produce the project budget.
• As changes warranting the use of management reserves arise, the change control
process is used to obtain approval to move the applicable management reserve
funds into the cost baseline.
7.3.3 Determine Budget: Outputs
Project Budget Component
7.3.3 Determine Budget: Outputs
continu….
• Project schedule.
7.4 Control Costs
Control cost is the processes of monitoring the status of project based on
cost baseline
Any change in authorized funding shall only be done through integrative
change control.
Project cost control includes:
Influencing the factors that create changes to the authorized cost baseline;
Ensuring that all change requests are acted on in a timely manner;
Managing the actual changes when and as they occur;
Ensuring that cost expenditures do not exceed the authorized funding by period,
by WBS component, by activity, and in total for the project;
Monitoring cost performance to isolate and understand variances from the
approved cost baseline;
Monitoring work performance against funds expended;
Preventing unapproved changes from being included in the reported cost or
resource usage;
Informing appropriate stakeholders of all approved changes and associated
cost; and
Bringing expected cost overruns within acceptable limits.
Control Costs: Inputs, Tools &
Techniques, and Outputs
Progress reporting
7.4.1 Control Costs: Inputs
7.4.1.1 Project Management Plan
The project management plan contains
Cost baseline. compared with actual results to determine if a change, corrective
action or preventive action is necessary.
Cost management plan. describes how the project costs will be managed .
7.4.1.2 Project Funding Requirements
7.4.1.3 Work Performance Information
Work performance information includes information about project progress,
7.4.14 Organizational Process Assets
• Existing formal and informal cost control-related
policies, procedures, and guidelines;
• Cost control tools;
• Monitoring and reporting methods to be used.
7.4.2 Control Costs:
Tools and Techniques
7.4.2.1 Earned Value Management
Earned value management (EVM) in its various forms is a
commonly used method of performance measurement.
Earned value management will indicate status and health of
project at any time and can predict possible outcomes.
EVM can be used for analysis of cost and schedule baselines
Sample :
Work package XX have a 4 stages and each stage
will take one week to complete with $500
estimated cost per stage.
What is the PV on 3rd Week = Total value of
planned work to be completed 3 on third week in
monetary terms (500 X 3 = 1500)
7.4.2 Control Costs:
Tools and Techniques • Earned value.
Sample :
Work package XX have a 4 stages and each stage
will take one week to complete with $500
estimated cost per stage. End of 2nd week 3 stages
were completed what is the PV and EV
PV on 2nd Week = Total value of planned work to
be completed on second week in monetary terms
(500 X 2 = 1000)
EV on 2nd week = Estimated value of work
completed (500 X 3 = 1500)
7.4.2 Control Costs:
Tools and Techniques • Actual cost.
Sample :
Work package XX have a 4 stages and each stage will take
one week to complete with $500 estimated cost per stage.
End of 2nd week 3 stages were completed and contractor has
As the project progresses, the project team can develop a forecast for the estimate at
completion (EAC) that may differ from the budget at completion (BAC) based on the project
performance.
Forecasts are generated, updated, and reissued based on work performance information
(provided as the project is executed.
The work performance information covers the project’s past performance and any information
that could impact the project in the future.
EACs are typically based on the actual costs incurred for work completed, plus an estimate to
complete (ETC) the remaining work.
The most common EAC forecasting approach is a manual, bottom-up summation by the project
manager and project team.
The personnel who are performing the project work have to stop working to provide a
detailed bottom-up ETC of the remaining work.
EAC = AC + bottom-up ETC.
7.4.2 Control Costs:
Tools and Techniques .2 Forecasting
The project manager’s manual EAC can be quickly compared with a
range of calculated EACs representing various risk scenarios. While
EVM data can quickly provide many statistical EACs,
Only three of the more common methods are described as follows:
• EAC forecast for ETC work performed at the budgeted rate.
This EAC method accepts the actual project performance to date
(whether favorable or unfavorable) as represented by the actual costs, and
predicts that all future ETC work will be accomplished at the budgeted rate.
EAC = AC + BAC – EV.
(BAC – EV ) المبلغ الواجب إنفاقه من اآلن حتى انتهاء المشروع
• EAC forecast for ETC work performed at the present CPI.
This method assumes what the project has experienced to date can be
expected to continue in the future.
If the cumulative CPI falls below the baseline plan , all future work of the project will need to immediately be performed in
the range of the TCPI (BAC) to stay within the authorized BAC.
Once management acknowledges that the BAC is no longer attainable, the project manager will prepare a new estimate at
completion (EAC) for the work, and once approved, the project will work to the new EAC value.
This level of performance is displayed as the TCPI (EAC) line. The equation for the TCPI based on the EAC
1. TCPI= (BAC – EV) / (EAC – AC).
7.4.2 Control Costs:
Tools and Techniques .4 Performance Reviews