Professional Documents
Culture Documents
Construction
Management
CONSTRUCTION MANAGEMENT 1
OVERVIEW:
PROJECT COST
MANAGEMENT
2
25/12/2023
The primary objective is to complete the project within the approved budget.
4
25/12/2023
4 Types of Costs
Traced Back Examples:
1. Direct Costs
Measured Direct Materials
2. Indirect Costs Specifically Identified Direct Labor
Use of Equipment
3. Variable Costs
Use of Facilities
4. Fixed Cost Costs Salaries of project staff
2. INDIRECT COSTS
Example:
• Indirectly Identifiable Fringe Benefits
Project Product Indirect Construction Expenses
Core Supporting Business General Indirect Expenses
Assigned Projects or Individual Contract General and Administrative Expenses
6
25/12/2023
Determine:
Amount of Cost Required to Complete (Project Work)
8
25/12/2023
Estimating Activity Duration is NOT EASY Who Provides the BEST Estimates?
Estimating as Accurately as Possible is a) Those Who KNOW the Work
Important, but: b) Those Who are ACCOUNTABLE for
Time/Cost/Quality Affect each Other the Work
Estimating Methods Affect Accuracy c) Those Who DO the Work
How much Detail do you Need?
Top Down Estimation Methods and Techniques
Bottom up 1) Expert Judgement
2) Analogous Estimating
In the Real World, Estimates and Actuals 3) Parameter Estimating
are usually different. 4) Bottom-Up Estimating
5) Three Point Estimating
10
25/12/2023
11
Analogous Estimating
Analogous estimating is a technique that uses information from a similar past project in order
to estimate the Cost and Duration of a Planned Project.
A technique that centers on COMPARISON
Often used when there is limited data available for a project
The more Data is Available, a Better Estimate would be Generated.
Example:
If the team is working on a new project and doesn't have any data to rely on, it may reference
a previously completed project to receive an estimate of the cost and budget according to
these numbers.
12
25/12/2023
13
Examples:
In construction, use the per square meter
of floor area to estimate cost.
14
25/12/2023
15
16
25/12/2023
17
18
25/12/2023
OUTPUTS
Estimates Reserve Analysis Baseline
Basis of Estimates Historical Project Funding
Scope Baseline Relationships Requirements
Project Schedule Funding Limit Project
Resource Calendars Reconciliation Documents
Contracts Updates
Organizational
Process Assets
19
1. Materials 3. Equipment
List of equipment that complies with the
Quantity and details of material to be used requirements of the Work Item and Specification.
as per Specification requirement of the Productivity rate of equipment to determine the
Work Item. number of hours or days to perform and complete
Unit Price of each material as per the Work Item.
Specification requirement and prevailing Rental rate or price rate per hour or per day of each
market prices. equipment based on prevailing market rates.
20
25/12/2023
CASE STUDY:
Below are two (2) Item of Works extracted from a proposed Barangay Road (PCCP) Project.
1. Concreting Works: 120.40 cu.m
2. Rebar Works : 984.88 kgs.
Prepare the DUPA for each Work Item.
21
DUPA EXERCISE:
2. LABOR
Name & Specification Qty Unit Price Amount
Crew composition required for 2 units Concreting Work (PCCP) 120.4 cu.m
Labor (Batching & Casting-in-Place)
One(1)-Bagger Mixer is shown in the Crew Composition (Concrete mixing and casting in place)
Table. 1 Foreman 8.5 days 850.00 7,225.00
4 Mason 8.5 days 525.00 17,850.00
The productivity output of the crew is 2 Carpenter 8.5 days 525.00 8,925.00
dependent on the productivity rate of 24 Laborers 8.5 days 450.00 91,800.00
Subtotal 125,800.00
One(1) bagger concrete mixer which is Unit Price/cu.m= 1,044.85
65 cement bags per day. For 2 units, 1-
bagger mixer, the productivity output
will be 130 cement bags per day. Unit Price of Labor required for the Work Item = (total labor
cost divided by total quantity) of the Work Item.
Number of days required for both
Equipment & Crew:
Days = (1,096/(65x2)) = (1,096/130)
Days = 8.43 or 8.50 days
Amount of Labor = Unit rate (per day) x
Qty (days) x # of pax.
22
25/12/2023
DUPA EXERCISE:
3. EQUIPMENT Name & Specification Qty Unit Price Amount
Concreting Work (PCCP) 120.4 cu.m
Equipment:
Productivity Output: 65 cement bags/day (1-Bagger Mixer)
The equipment requirement for the 2 One-Bagger Mixer 8.5 days 5,584.00 94,928.00
crew composition is shown in the Table. 2 Concrete Vibrator 8.5 days 3,768.00 64,056.00
1 Water Truck (500 gals Capacity) 8.5 days 5,850.00 49,725.00
Number of days required for both Minor Tools (10% of labor cost) 1 lot 12,580.00
Subtotal 221,289.00
Equipment & Crew is 8.50 days as Unit Price/cu.m= 1,837.95
previously computed.
Direct Cost (Materials+Labor+Equipment)= 809,929.00
Unit Price/cu.m= 6,726.99
Cost of Equipment = Unit rate (per
day) x (No. of days used) x ( No. of
Unit Price of Equipment required for the Work Item = (total
equipment units)
equipment cost divided by the total quantity) of the Work Item
Minor tools provision equivalent to 10%
The Direct Cost of Work Item = Cost of Materials + Labor +
of labor cost will cover consumable
Equipment.
tools used by construction crew during
construction. Unit Price of Work Item = Direct Cost divided by Total Quantity of
Work Item.
23
1. MATERIALS 2. LABOR
Tie Wire = 15 kg/ ton of RSB The Labor Unit Price per kg. of RSB =
Subtotal Amount of Labor divided by
Reqd. Tie Wire= (wt. of RSB / 1000) x 15
total weight of RSB.
Reqd Tie Wire = 14.77 kgs
Amount = Unit Price x Quantity 3. EQUIPMENT
Unit Price of Material/kg = Subtotal
Number of days required for
Amount divided by total weight of RSB)
Equipment is the same with Crew.
2. LABOR The Eqpt. Unit Price per kg. of RSB =
Number of days required for both Subtotal Amount of Eqpt. divided by
Equipment & Crew will be derived total weight of RSB.
from the Productivity Rate of Crew
equal to 750kg/day.
Reqd No. of Days = (Total Wt. of RSB)
divided by productivity rate = (984.88/750)
No. of Days = 1.31 or 1.50 days (rounded)
24
25/12/2023
25
1. The weight of reinforcing bar of any diameter can be 2. There is a Philippine Standard Method of
derived using the weight density of steel at 7,850 Measurement (PSMM) for Building Works that
kg/cu.m and using the universal value of =22/7. has been published and used by Quantity
Check the weight of any standard RSB diameter and Surveyors in the construction industry since
length using this simple formula: 1997.
Wt.= (6.168 x 10-3) x (D)2 x L Refer to the Handout:
PSMM, 7th Edition 2014.
Wt.= (1/162.13) x (D)2 x L By: Langdon & Seah
Where: Philippines Inc.
Wt. = weight of RSB in kilograms (kg)
D = Diameter of RSB in millimeter (mm)
L = length of RSB in meters (m)
26
25/12/2023
27
28
25/12/2023
Earned Value
Management (EVM(
Forecasting Forecasting
To Complete
Performance Index
(TPCI)
To Complete Performance Index (TPCI)
Performance
Reviews
Performance Review
29
DETERMINE
Planned Cost
Schedule Performance
30
25/12/2023
Work Planned
AC
Actual Cost (AC)
Deadline
Cost Incurred of the EV
Work Performed
Earned Value (EV)
Estimated Value of the
Work Performed
TIME
31
COST VARIANCE
Amount of Budget Deficit or Surplus at a Given Point in Time
32
25/12/2023
SCHEDULE VARIANCE
Measure of Schedule Performance
If Resulting Amount = + VE
(AHEAD of Planned Delivery Date)
If Resulting Amount = - VE
(BEHIND Planned Delivery Date)
33
Measurement Date
Project Budget
THREE PARAMETERS OF
PV, EV & AC PV
COST
TIME
34
25/12/2023
PROJECT COST
MANAGEMENT
35
2. What is the process of forecasting the financial and other resources needed to complete
a project within a defined scope?
5. Which of the following that supply and support field operations so that work schedules can
be met, and cost schedules can be kept within construction budget:
o Financial management o Time management
o Equipment management o All of the above
o Resource management
36
25/12/2023
Duration Note:
Code Description Qty Unit Cost
(Days) A gang of steel-fixers is used to cut
A Layout foundation 250 sq.m and bend reinforcement and
B Excavation 72.75 cu.m
C Obtain Concrete Materials 45.05 cu.m
another gang is used for placing
D Place Concrete 45.05 cu.m reinforcement.
E Obtain Steel Reinforcement 3,532.88 kgs. The first part of reinforcement can
F1 Cut and Bend Reinforcement (Part 1) 2,367.03 Kgs. be placed during formwork
F2 Cut and Bend Reinforcement (Part 2) 1,165.85 Kgs.
G1 Place Reinforcement (Part 1) 2,367.03 Kgs.
erection while the second part
G2 Place Reinforcement (Part 2) 1,165.85 Kgs. should wait for completion of
H Obtain Formwork 181.75 sq.m formwork erection.
I Erect Formwork 181.75 sq.m
J Remove Formwork 181.75 sq.m
K Clean Up 250 sq.m
37