You are on page 1of 40

Project 

managing, 
Scheduling and 
Jobsite 
Planning II
Module 5: Project Schedule & 
Cost Control
1
Project Managing, Scheduling and Jobsite Planning II

Module 3 & 4 Review
 Schedule and Cost Management Processes

 Schedule components: WBS,WPs,Activity

 Develop Project Schedule

 Develop Project Budget

 Project Budget Components

MODULE 5- Project time and cost control 2


Project Managing, Scheduling and Jobsite Planning II

PMBOK‐Figure 6‐1:Project 
Time Management Overview

MODULE 5- Project time and cost control 3


Project Managing, Scheduling and Jobsite Planning II

PMBOK‐Figure 7‐1:Project 
Cost Management Overview

MODULE 5- Project time and cost control 4


Project Managing, Scheduling and Jobsite Planning II

Project Budget Components

MODULE 5- Project time and cost control 5


Project Managing, Scheduling and Jobsite Planning II

Module 5 Agenda
 S‐curve

 Earned Value Management (EVM) Technique

 The Key Parameters of EVM

 Forecasting

MODULE 5- Project time and cost control 6


Project Managing, Scheduling and Jobsite Planning II

S‐curve (Cost Baseline)

MODULE 5- Project time and cost control 7


Project Managing, Scheduling and Jobsite Planning II

S‐Curve (Cost Baseline)
• S curve consists of “a display of cumulative cost, labour hours or 
other quantities plotted against time” 
• Time‐phased Cost baseline 
• Name derives from the S‐like shape of the curve which is flatter at 
beginning and end and steeper in middle where more of the 
resources are used 
• Known also as Budget At Completion, or Planned Value (PV) 
• There can be multiple S‐curves to represent planned or target 
values, and actual progress completed.

MODULE 5- Project time and cost control 8


Project Managing, Scheduling and Jobsite Planning II

Earned Value Management (EVM)
• Earned value management (EVM) is a methodology that combines scope, 
schedule, and resource measurements to assess project performance and 
progress.
• It is a commonly used method of performance measurement for projects. 
It integrates the scope baseline with the cost baseline, along with the 
schedule baseline, to form the performance baseline, which helps the 
project management team assess and measure project performance and 
progress. 
• It is a project management technique that requires the formation of an 
integrated baseline against which performance can be measured for the 
duration of the project. The principles of EVM can be applied to all projects 
in any industry

MODULE 5- Project time and cost control 9


Project Managing, Scheduling and Jobsite Planning II

Earned Value Management (EVM)
• EVM is a project tool of performance measurement for:
– Assessing project trends
– Determining schedule (ahead/behind)
– True budget status (over/under) 

• Reporting project status to senior management 
• The project’s WBS is divided and subdivided into logical, measurable
work packages
• Work packages provide the units for comparing progress in work
planned, work completed or earned and funds spent 

MODULE 5- Project time and cost control 10


Project Managing, Scheduling and Jobsite Planning II

Key Parameters of EVM
• EVM develops and monitors three key dimensions for each work 
package and control account:

Planned Value (PV): Budgeted Cost for Work Scheduled (BCWS)

Earned Value (EV): Budgeted Cost for Work Performed (BCWP)

Actual Cost (AC): Actual Cost for Work Performed (ACWP)

MODULE 5- Project time and cost control 11


Project Managing, Scheduling and Jobsite Planning II

Key Parameters of EVM

EV PV
Planned Value (PV): What did we plan to 
achieve by now?
 Earned Value (EV): What have we 
AC
achieved so far?
 Actual Cost (AC): What have we spent so 
far? EVM

MODULE 5- Project time and cost control 12


Project Managing, Scheduling and Jobsite Planning II

Key Parameters of EVM
• Planned value (PV) is the authorized budget assigned to scheduled work. 
• It is the authorized budget planned for the work to be accomplished for an 
activity or work breakdown structure component, not including 
management reserve. 
• At a given moment, planned value defines the physical work that should 
have been accomplished.
• The total of the PV is sometimes referred to as the performance 
measurement baseline (PMB). The total planned value for the project is 
also known as budget at completion (BAC).

MODULE 5- Project time and cost control 13


Project Managing, Scheduling and Jobsite Planning II

Key Parameters of EVM
• Earned value (EV) is a measure of work performed expressed in terms of the 
budget authorized for that work.
• It is the budget associated with the authorized work that has been completed. 
• The EV being measured needs to be related to the PMB, and the EV measured 
cannot be greater than the authorized PV budget for a component.
• The EV is often used to calculate the percent complete of a project. 
• Progress measurement criteria should be established for each WBS component to 
measure work in progress. 
• Project managers monitor EV, both incrementally to determine current status and 
cumulatively to determine the long‐term performance trends. 

MODULE 5- Project time and cost control 14


Project Managing, Scheduling and Jobsite Planning II

Key Parameters of EVM
• Actual cost (AC) is the realized cost incurred for the work performed 
on an activity during a specific time period. 
• It is the total cost incurred in accomplishing the work that the EV 
measured. 
• The AC needs to correspond in definition to what was budgeted in the 
PV and measured in the EV (e.g., direct hours only, direct costs only, 
or all costs including indirect costs). 
• The AC will have no upper limit; whatever is spent to achieve the EV 
will be measured. 

MODULE 5- Project time and cost control 15


Project Managing, Scheduling and Jobsite Planning II

Example? Simple project
Activity Predecessor Duration(days) Cost/day Total Cost
A ‐ 2 300 600
B A 3 400 1200
C B 3 400 1200
D B 2 200 400
E D 3 100 300

MODULE 5- Project time and cost control 16


Project Managing, Scheduling and Jobsite Planning II

Example? 
Reporting date: At the end of day 7

Activity Actual  % Complete Incurred Cost


A 100 600
B 100 1400
C 33 500
D 50 200
E 0 0

MODULE 5- Project time and cost control 17


Project Managing, Scheduling and Jobsite Planning II

Example? 
Reporting date: At the end of day 7

Activity Planned Value (PV) Earned Value (EV) Actual Cost (AC)

A
B
C
D
E
Total to Date

MODULE 5- Project time and cost control 18


Project Managing, Scheduling and Jobsite Planning II

Calculate Variance

Schedule  Cost 
Variance Variance

MODULE 5- Project time and cost control 19


Project Managing, Scheduling and Jobsite Planning II

EVM Measures & Indices
• Schedule variance (SV) is a measure of schedule performance expressed 
as the difference between the earned value and the planned value. 
• It is the amount by which the project is ahead or behind the planned 
delivery date, at a given point in time.
• The EVM schedule variance will ultimately equal zero when the project 
is completed because all of the planned values will have been earned. 
• Equation: SV = EV − PV

MODULE 5- Project time and cost control 20


Project Managing, Scheduling and Jobsite Planning II

EVM Measures & Indices
• Cost variance (CV) is the amount of budget deficit or surplus at a given point 
in time, expressed as the difference between earned value and the actual 
cost.
• It is a measure of cost performance on a project. The cost variance at the end 
of the project will be the difference between the budget at completion (BAC) 
and the actual amount spent.
• The CV is particularly critical because it indicates the relationship of physical 
performance to the costs spent. Negative CV is often difficult for the project 
to recover. 
• Equation: CV= EV − AC. 

MODULE 5- Project time and cost control 21


Project Managing, Scheduling and Jobsite Planning II

EVM Measures & Indices
• The SV and CV values can be converted to efficiency indicators to reflect 
the cost and schedule performance of any project for comparison 
against all other projects or within a portfolio of projects. The variances 
are useful for determining project status.
 Schedule performance index : SPI = EV/PV

Cost performance index : CPI = EV/AC

MODULE 5- Project time and cost control 22


Project Managing, Scheduling and Jobsite Planning II

Example: Variances? 
Reporting date: At the end of day 7

Activity Planned  Earned  Actual  CV CPI SV SPI


Value  Value  Cost 
(PV) (EV) (AC)
A 600 600 600
B 1200 1200 1400
C 800 400 500
D 400 200 200
E 0 0 0
Total to  3000 2400 2700 ‐300 0.89 ‐600 0.8
Date

MODULE 5- Project time and cost control 23


Project Managing, Scheduling and Jobsite Planning II

Forecasting
• As the project progresses, the project team may develop a forecast for 
the estimate at completion (EAC) that may differ from the budget at 
completion (BAC) based on the project performance.
• If it becomes obvious that the BAC is no longer viable, the project 
manager should consider the forecasted EAC.
• Forecasting the EAC involves making projections of conditions and 
events in the project’s future based on current performance information 
and other knowledge available at the time of the forecast. 

MODULE 5- Project time and cost control 24


Project Managing, Scheduling and Jobsite Planning II

Forecasting
• EACs are typically based on the actual costs incurred for work completed, plus 
an estimate to complete (ETC) the remaining work.
• It is incumbent on the project team to predict what it may encounter to 
perform the ETC, based on its experience to date. The EVM method works 
well in conjunction with manual forecasts of the required EAC costs. 
• The most common EAC forecasting approach is a manual, bottom‐up 
summation by the project manager and project team. The project manager’s 
bottom‐up EAC method builds upon the actual costs and experience incurred 
for the work completed, and requires a new estimate to complete the 
remaining project work. Equation: EAC = AC + Bottom‐up ETC.

MODULE 5- Project time and cost control 25


Project Managing, Scheduling and Jobsite Planning II

Forecasting: Common Methods
• EAC forecast for ETC work performed at the budgeted rate.
o Equation: EAC = AC + (BAC − EV)
• EAC forecast for ETC work performed at the present CPI.
o Equation: EAC = BAC / CPI
• EAC forecast for ETC work considering both SPI and CPI factors.
o EAC = AC + [(BAC − EV) / (CPI × SPI)]

MODULE 5- Project time and cost control 26


Project Managing, Scheduling and Jobsite Planning II

To‐Complete Performance Index (TCPI)
• The to‐complete performance index (TCPI) is a measure of the cost 
performance that is required to be achieved with the remaining resources 
in order to meet a specified management goal, such as the BAC or the 
EAC. If it becomes obvious that the BAC is no longer viable, the project 
manager should consider the forecasted EAC. Once approved, the EAC 
may replace the BAC in the TCPI calculation. 

• TCPI = Work Remaining (BAC‐EV)/Funds Remaining (BAC‐AC)or(EAC‐AC)

MODULE 5- Project time and cost control 27


Project Managing, Scheduling and Jobsite Planning II

Figure 7‐12 (PMBOK): EV,PV,AC,BAC,EAC,ETC
MODULE 5- Project time and cost control 28
Project Managing, Scheduling and Jobsite Planning II

EVM Summary tables

MODULE 5- Project time and cost control 29


Project Managing, Scheduling and Jobsite Planning II

EVM Summary tables

MODULE 5- Project time and cost control 30


Project Managing, Scheduling and Jobsite Planning II

EVM Summary tables

MODULE 5- Project time and cost control 31


Project Managing, Scheduling and Jobsite Planning II

Example: Home Renovation Project

MODULE 5- Project time and cost control 32


Project Managing, Scheduling and Jobsite Planning II

Example: Home Renovation Project
• The Home Renovation Project has a total budget of $400,000 and a 
schedule of 100 days.
• Project reporting is scheduled at periods of 25 days. At the end of the 
first period  the project should have achieved $120,000 worth of work. 
Before the P1 status meeting the project manager found out from the 
PM team that the work completed had a value of $140,000. In addition, 
the expenditures and commitments to date for that completed work 
totaled $100,000.

MODULE 5- Project time and cost control 33


Project Managing, Scheduling and Jobsite Planning II

Example: Home Renovation Project
• Questions
1. Should the project manager be pleased or not? Why?
2. What is the Cost Variance in dollars?
3. What is the Schedule Variance in dollars?
4. What is the Cost Performance Index?
5. What is the Schedule Performance Index?
6. What is the estimated cost at completion (EAC) for the project at this 
point? 

MODULE 5- Project time and cost control 34


Project Managing, Scheduling and Jobsite Planning II

Example: Home Renovation Project
• Answers
1. Yes, the project is ahead of schedule and under budget.
2. CV = EV – AC = $140,000 – $100,000 = $ 40,000
3. SV = EV – PV = $140,000 – $120,000 = $ 20,000
4. CPI = Earned Value/Actual Cost = 140,000 /100,000 = 1.4
5. SPI = Earned Value/Planned Value = 140,000 / 120,000 = 1.17
6. EAC = Total Budget / CPI = $ 400,000 / 1.4 = $ 285,714 

MODULE 5- Project time and cost control 35


Project Managing, Scheduling and Jobsite Planning II

Example: Home Renovation Project

MODULE 5- Project time and cost control 36


Project Managing, Scheduling and Jobsite Planning II

Review
 EVM Parameters?

 How to calculate project variance?

 How to forecast project completion?

MODULE 5- Project time and cost control 37


Project Managing, Scheduling and Jobsite Planning II

Topic for Oral Presentation
 Explain a sample project (case study) using EVM System

MODULE 5- Project time and cost control 38


Project Managing, Scheduling and Jobsite Planning II

Next Module
 Case study: Construction Project time and Cost control

MODULE 5- Project time and cost control 39


Project Managing, Scheduling and Jobsite Planning II

Thank you for your Attention

MODULE 5- Project time and cost control 40

You might also like