You are on page 1of 1

Contract ID : 20EG0081

Contract Name : Repair/Maintenance of Bridge Decks Asphalt Overlay


Location : Calatobog Bridge K0029+870, Nagsaguipi Bridge K0031+391 and
Tapul Bridge K0037+283, Puerto Princesa City North Road,
Puerto Princesa City

Department of Public Works and Highways


PRELIMINARY EXAMINATION OF TECHNICAL COMPONENT OF THE BID
Date of Submission/Opening of Bids : May 19, 2020 @ 10:00 a.m.
Name of Contractor : AR Lustre Construction Corporation
Approved Budget for the Contract (ABC) :Php 1,679,105.00

ANTHONY ENRICO LL. LIM

ALBINO D. SOCRATES, JR.


BENJAMIN Q. MAULEON
AGUSTIN Q. BACALTOS
ROY D. VALDEZ
DPWH-PPCITY
1 PhilGEPS Certificate of Registration and Membership
2 aIf not enrolled in CWR: following Class A and B Documents not covered by PhilGEPS Certificate 1
PCAB License and Registration
2 Statement of All Ongoing Government and Private Projects
3 SLCC
4 NFCC Computation and Statement of Total Assets and Liabilities
5 JVA, if applicable
b If enrolled in CWR: Class A and B Documents in CWR, if any, to be updated.
3 Bid Security in the prescribed form, amount and validity period.
Acceptable Forms : Cash, Cashier's Bank Draft/Guanrantee, or Surety Bond callable upon Bid Securing
Check, Manager's Irrevocable Letter of Credit demand issued by a surety Declaration
Check, issued by a issued by a Universal or or insurrance company
Universal or Commercial Bank (If duly certified bythe
Commercal Bank (2% issued by a Foreign Bank it Insurrance Commission as
a. of ABC) shall be confirmed or authorized to issue such
authenticated by a security (5% of ABC)
Universal or Commercial
Bank (2% of ABC)

Form Submitted by Contractor


Amount Required :
b.
Amount Submitted by Contrcator ( ) Sufficient ( ) Insufficient
c. Validity Period :
d. Issuing Company/Bank :
e. Official Receipt No. :
f. Callable on Demand
g. Certificate from Insurance :
Commission
ANTHONY ENRICO LL. LIM

ALBINO D. SOCRATES, JR.


BENJAMIN Q. MAULEON
CONRADO P. AGUILA III
ROY D. VALDEZ
DPWH-PPCITY

Bid Security in Prescribed Form, Amount and Validity Period.


4 Project Requirements:
a. Organizational Chart for the contract to bid.
b. List of Contractor's Key Personnel, (see Clause 14.2a(3)(b), BDS to be assigned to the contract
Documents) to assigned to the contract, with their complete qualification data.
iii. List of Contractor's Major Construction and Laboratory Equipment Units owned, leased and/or
under purchase agreements, supported by proof of ownership/lease/purchase and certification of
availability of equipment from lessor/vendor for the duration of the project.
(see Clause 14.2a(3)(c ), BDS of BDs)
4 Omnibus Sworn Statement in the form prescribed by GPPB.

Note: Any missing, incomplete or patently insufficient document in the above-mentioned


checklist is a ground for outright rejection of the bid.

Overall rating: ( ) Passed ( ) Failed