Brick Masonry

Sr. No. Description Quantity Unit

1 Proportion of Mortar 1 6

2 Volume of brick masonry 10 cu.m.

4 Dry volume of Mortar( with frog filling, wastage, etc.) 3.5 cu.m.
Cement 0.50 cu.m
5
Cement bags 15 numbers
3.0 cu.m
6 Sand
1.062 brass
Number of bricks 5000 numbers
7 Assuming 5% wastage 250 numbers
Total number of bricks 5250 numbers
Cost of Material
Sr. No. Description Quantity Unit Rate

1 Cement 15 number 350


2 Sand 3.0 cu.m 1000
3 Bricks 5250 number 7
Total Cost of Materials
Estimation of Brick Masonry Work- By Prof. Shaikh
(D.C.E., B.E. Civil, ME Structures)
Unite Constructions & Coaching
Youtube Link: Unite Constructions & Unite Coaching