You are on page 1of 31

Empl

oyer General
Contractor: Project Manager: Sub-
Subcontr
Abu actor:
CH2MHILL/
Dh KEO

abi Parsons
Brinckerhoff Taahud Sustain
ability
Fut Genera
Special
ure Architect: l
Foster & Contra Projects
MAS Ene Amana/Walb
DAR Partners/WS cting
ridge J.V.
rgy P Co.
Unit

Co.
Document Title: Document No. MAS-
Project Sustainability Plan 1A-PQP- 01
Project Title: Revision
Date:
MIST 1A Ancillary Buildings and No. 0
Infrastructure
22, Oct, Page 1 of
Car Park & Podium (Phase 1B), Abu Dhabi,
2009 31
UAE

Document Title

Project Sustainability Plan

Revision and Approval History


Gen.
Rev. Description / SUBCONTRACTOR Owner Approval
Date Contractor
No. Remarks Status
Prepared Reviewed Approved Approved Approved
0 22.10.2009 Afsar Suleman Karim Nasser Karim Nasser
Contents

Number Description Page Number


- Revision History, Approvals 1
- Index of Contents 2
1.0 INTRODUCTION & PURPOSE 3-4
Scope of Application
Reference Documents and Precedence Level
Issue / Revision Control & Distribution
2.0 DEFINITIONS 4-5

3.0 SUSTAINABILITY POLICY & 6-7


OBJECTIVE
4.0 SUSTAINABILITY MANAGEMENT 8-12
SYSTEM
General
Documentation Requirements
5.0 MANAGEMENT RESPONSIBILITY 12-14
Responsibility. Authority and
Communication Internal
Communication Management Review
6.0 RESOURCE MANAGEMENT 14
Human
Resources
Infrastructure
Work & Environment
7.0 PRODUCT REALIZATION 14-20
Planning of Product Realization
Customer Related Process
Purchasing
Production and Service Provision
Control of Monitoring and Measuring
Devices
8.0 MEASUREMENT, ANALYSIS AND 20-22
IMPROVEMENT
General
Analysis of Data
Improvement - Corrective and Preventive
Actions

9.0 LIST OF ATTACHMENTS 22-30

2
Empl
oyer General
Contractor: Project Manager: Sub-
Subcontr
Abu actor:
CH2MHILL/
Dh KEO

abi Parsons
Brinckerhoff Taahud Sustain
ability
Fut Genera
Special
ure Architect: l
Foster & Contra Projects
MAS Ene Amana/Walb
DAR Partners/WS cting
ridge J.V.
rgy P Co.
Unit

Co.
Document Title: Document No. MAS-
Project Sustainability Plan 1A-PQP- 01
Project Title: Revision
Date:
MIST 1A Ancillary Buildings and No. 0
Infrastructure
22, Oct, Page 3 of
Car Park & Podium (Phase 1B), Abu Dhabi,
2009 31
UAE

1.0 INTRODUCTION & PURPOSE

This document describes The Subcontractor's proposed Sustainability Management Plan applicable to
the project titled,

“MIST 1A Ancillary Buildings and Infrastructure -


Car Park & Podium (Phase 1B), Abu Dhabi, UAE”

As part of Owner's and General Contractor’s commitment to sustainability, this project is covered
by a Project Specific Sustainability Plan in compliance with the relevant elements of the Masdar
Development Construction Environmental Management Plan (CEMP) project 1 for as applicable to
the project. Additionally, this document addresses section 7000 of Fosters and Partners Tender Issue 1
of April 2009.

This Sustainability Plan ensures that Subcontractor has implemented the appropriate environmental
policies and objectives, established a system of procedures to monitor these targets, assigned duties,
delegated authority and set up suitable inspection, examination, reporting and auditing programs to
verify that the requisite standards of Sustainability are achieved. This Sustainability Plan is designed
to accomplish and demonstrate achievement / compliance of / to all contractual sustainability
performance requirements specified by contract and the Owner.

The Project Safety Management System and Quality Control and Assurance are addressed separately by
the specific Project SHE and QAQC Plan documents.

1.1 Scope of Application


This sustainability plan is applicable for the awarded subcontract/project the Architectural
Package for the MIST 1A Ancillary Buildings and Infrastructure Project (Car Park and
Podium). The project works include: -

1. Full mobilization including preparation of the assigned site area and the entire
necessary Subcontractor's site office with related services.

2. The supply and installation of architectural trade works as applicable to the Subcontract and
defined in the Letter of Award dated 7th May 2009. A brief description of work is presented
in document titled “Scope of Work” Section 00210 of tender document dated 22.3.09.

1.2 Reference Documents and Precedence Levels

This Sustainability Plan is overall applicable for the project. The project works include

Reference Documents Precedence Level


Agreement / Contract, Drawings &
1. Agreement / Contract 1
Specs
2. ISO 9001: 2008 2 Project Quality Plan - ISO 9001: 2008
3. Owner's Drawings 3 Inspection and Test Plan

4. Owner's Specifications 4 Method Statements

5. Taahud Sustainability Plan 5 Corporate Procedures


6. 6.

This project Sustainability Plan will be utilized in conjunction with applicable


Subcontractor and Owner/General Contractor procedures as listed in the Attachments.

1.3 Issue / Revision Control & Distribution

This Sustainability Plan is prepared by the Subcontractor and should be approved by the
General Contractor/Owner for implementation on site. It is a controlled document and the
Subcontractor Head Office in Abu Dhabi controls its issue and distribution.

Revisions may be necessary to incorporate General Contractor/Owner Instructions or as a


result of site requirements /corrective actions agreed during internal audits. The
Subcontractor’s Management (delegated to the Lead Sustainability Manager, Afsar Suleman
of KEO Sustainability Special Projects, as required) will conduct all revisions and all
holders of controlled copies will be issued latest revised copies whenever revisions are
effected and approved by General Contractor/Owner.

2.0 DEFINITIONS

4
Empl
oyer General
Contractor: Project Manager: Sub-
Subcontr
Abu actor:
CH2MHILL/
Dh KEO

abi Parsons
Brinckerhoff Taahud Sustain
ability
Fut Genera
Special
ure Architect: l
Foster & Contra Projects
MAS Ene Amana/Walb
DAR Partners/WS cting
ridge J.V.
rgy P Co.
Unit

Co.
Document Title: Document No. MAS-
Project Sustainability Plan 1A-PQP- 01
Project Title: Revision
Date:
MIST 1A Ancillary Buildings and No. 0
Infrastructure
22, Oct, Page 5 of
Car Park & Podium (Phase 1B), Abu Dhabi,
2009 31
UAE

Owner/Employer/Client MASDAR, Abu Dhabi Future Energy Company

General Contractor/Contractor Amana/Walbridge J.V.

Subcontractor Taahud General Contracting Co.

Organization employed by Subcontractor for executing part of the


Sub-Subcontractor/Sub-tiers
works

Organization used by Subcontractor for supply of


Supplier
approved Materials.

CEMP Construction Environmental Management Plan

ITP Inspection and Test Plan

RIT Request for Inspection and Test

TQ or RFI Technical Query or Request for Information

SHE or HSE Health, Safety and Environment

QMS Quality Management System

NCR Non-Conformance Report

RM Restricted Material

VOC Volatile Organic Compound


3.0 SUSTAINABILITY POLICY, OBJECTIVE AND COMMITMENT

Taahud Sustainability Policy

It is our policy to ensure that all projects are executed in accordance with contract
Sustainability standards within the contractual time frame, and in compliance to all legal
requirements so as to provide good value and satisfaction to our Client.

The Sustainability Management system adopted by us to fulfil this objective will comply
with all the applicable requirements of the Masdar Development Construction and
Environmental Management Plan.

This Sustainability Policy requires behaviour modification by employees such as specific


protocol for waste management in site offices and around site off. Prompts signage will be
displayed on all sites, and it is the responsibility of both the management and employees to
be aware of this sustainability policy and the applicable Client’s systems relevant to
one's area of work. Areas of responsibility include

 Appropriate specification of materials that are compliant with Masdar carbon,


recycled materials and eco-toxicity restrictions

 Tracking and logging the material specifications data required by Masdar as part of
their Key Performance Indicators and delivering it in a timely fashion as required to
the General Contractor’s representative

 Following of all waste segregation and materials conservation guidelines

 Following the Masdar CEMP guidelines and promptly reporting any breaches of
policy to appropriate supervisor

 Educating all our employees about Sustainability and providing all employees on site
with proper Masdar Environmental inductions as per requirements of Masdar
representative PB.

The Sustainability Plan will apply to all the construction sites and Departments within
the framework of the agreed contract.

We believe that our clients, employees, suppliers/sub-tiers and the society in general are
important contributors in our business. This fact will be evenly considered in our overall
business dealings vis-à-vis the interests of company management. Additionally, we have a
commitment to exercise appropriate Corporate Social Responsibility in all our endeavours.

Dated June 7th, 2009

Signed..............…..Nadim Nasser, Managing Partner

6
Employer General Contractor: Project Manager: Sub-
Abu
CH2MHILL/ Subcontractor: KEO
Dhabi Taahud International
Future Parsons Brinckerhoff General
Energy Architect: Contracting Sustainability
Foster & Co.
Co. Partners/WSP
Projects Unit
MASDAR Amana/Walbridge J.V.
Document Title:
Document No. MAS-1A-PQP- 01
Project Sustainability Plan
Project Title: Revision No. 0
Date: June 5,
MIST 1A Ancillary Buildings and Infrastructure
2009 Page 7 of 31
Car Park & Podium (Phase 1a), Abu Dhabi, UAE

3.1 Project Sustainability Objectives

1. Carbon & Exemplary compliance in reporting of KPI’s for carbon and


Restricted recycled content in materials
Materials Compliance in adhering to restricted materials list
Tracking Accurate reporting of staff petrol use and mileage for
automobiles and buses
Accurate reporting of onsite energy generation

2. Safety No Fatalities

Frequency Rate: 0-1.5 LTA/ 1 Million Hours

Severity Rate: 0- 2 lost days / 1 Million Hours

Report as many near misses as possible

3. Staff Provide guidance on environmental management during


Eco- Education construction and ensure that staff are aware of the Masdar
CEMP

4. CEMP Work with Environmental Best Practices in mind to safeguard


the environment and to ensure that all works are carried out
without any un significant or unacceptable long term impacts
on the environment.

5. One Planet To uphold principles of One Planet Living as per Masdar’s


Living requirements

To run project and site compliant with General Contractor’s


6. Lean commitment to “Greenwise” and Lean Construction principles.
Construction
4.0 SUSTAINABILITY MANAGEMENT SYSTEM

4.1 General

Subcontractor will implement and maintain the Sustainability Management system for this
project as detailed in this Sustainability plan.

Subcontractor is committed to continually improve the effectiveness of the SMS plan by


rigorous implementation and ongoing participation of staff in Masdar sponsored education.
Ongoing improvements/suggestions and recommendations from the General
Contractor/Owner and KEO Sustainability Consultants will be implemented.
Subcontractor strives for excellence in:
 Upholding environmental best practice
 Pollution prevention on and off site
 Recycling and reclaimed materials use in specifications
 Responsible sourcing of construction materials (certified woods and recycling of
woods)
 Abiding by Environment Agency Abu Dhabi regulations and Masdar CEMP
 Environmental risk and value management
 Site management,
 Carbon minimized supply chain management
 Sustainable construction methods
 Waste minimization
 Protection of water resources

The following will describe how Subcontractor will execute the project the Sustainability plan:

4.1.1 Interaction and Application of the Processes

The key processes are grouped into three main process groups –
Key Process Group (1) Management, Resources and Administration (Sections
5-6)
Key Process Group (2) Project / Construction Operations (section 7)
Key Process Group (3) Measurement, Analysis and Improvement (Section 8)

Process (1) - Management, Resources and Administration covers all the management
activities of planning, implementing and managing the system and determining and providing
those resources needed to operate the system effectively and assure product/service conformity.

Process (1) enables Process (2) - Project/Construction Operations to take place in a planned
and systematic way in order to comply with contract/project requirements and eventually Employer
satisfaction and realization of payments. Process (2) covers all those elements of product and
service realization, those activities pertinent to the sustainability management system which take
place during the planning, purchasing, design, fabrication and installation of the product or
8
Employer General Contractor: Project Manager: Sub-
Abu
CH2MHILL/ Subcontractor: KEO
Dhabi Taahud International
Future Parsons Brinckerhoff General
Energy Architect: Contracting Sustainability
Foster & Co.
Co. Partners/WSP
Projects Unit
MASDAR Amana/Walbridge J.V.
Document Title:
Document No. MAS-1A-PQP- 01
Project Sustainability Plan
Project Title: Revision No. 0
Date: June 5,
MIST 1A Ancillary Buildings and Infrastructure
2009 Page 9 of 31
Car Park & Podium (Phase 1a), Abu Dhabi, UAE

service and related testing and commissioning works.

Process (3) - Measurement, Analysis and Improvement measures and monitors the
effectiveness of Process (1) and Process (2) and provides feedback to those processes for
improvement.

4.2 Documentation Requirements

The project Sustainability Management is documented by this sustainability plan and


associated project procedures as may be developed, together with the sustainability
procedures and project specific method statements that will be developed for the project.

4.2.1 Documentation Structure

The following two levels of documentation will be utilized and maintained to


satisfy the requirements of the Masdar CEMP and Masdar materials assessment
for carbon, restricted and recycled content to ensure adequate control of the
processes.

Level I Sustainability Plan Check lists


Level II Project Specific Procedures
Site Inspections and KEO
Sustainability Consultant Audit Plans
Method Statements

4.2.2 Document & Data Control

Document control will ensure that valid issues of documents related to the
sustainability of the project are available and used in the execution of the work,
and that obsolete documents are promptly removed from all points of use.
Distribution is controlled and is detailed in the Document Distribution Matrix.

A Valid document register indicating contract documents as received from


Owner/General Contractor will be maintained.
Any obsolete document is either destroyed or if need to be retained - these are
clearly marked "SUPERSEDED".
All documents will be uniquely numbered as explained in 4.2.3. Forms within a
procedure are numbered with a prefix FM after the project code. For example
“MAS-1A-PSP-501” is the Project Sustainability Plan and a form belonging to this
procedure / plan is numbered as “MAS-1A-FM-501-10” -Document Distribution
Matrix.

4.2.3 Document Numbering System

Subcontractor's proposed numbering system for sustainability related documents


are explained below. However, Subcontractor may adopt any numbering system
preferred By Owner/General Contractor.

a) Project documents have been categorized with abbreviations as under.


Table 1 - Category of Documents and Project Code

Description of Document Abbreviation


No.
1 Project Specific Procedures FSP
9 Method Statement MS
3 Inspection and Test Plan ITP
4 Sustainability Check-sheets SC
5 Forms FM
6 Project Code MAS-1A

b) Unique series has been allocated for various project management / control
activities. These are reproduced as under:

Table 2 — Project Activity Series (to be developed as required)

Series No. Project Activities


0100 Project Management
0200 Engineering and Design Control (if applicable)
0300 Material, Procurement and Subcontracting
0400 Quality Management
0500 Health, Safety and Environmental Management
1000 Civil Method Statements
The numbering system for all documents described above is a simple alpha-
numeric system giving the category of the document, the project reference, the
serial number (3 digits for Procedures and an extended digit for related Forms and
Quality Check-sheets) within the Procedure/Activity Series.

Table 3 - Numbering System

(The Owner/General Contractor System will be followed)

10
Employer General Contractor: Project Manager: Sub-
Abu
CH2MHILL/ Subcontractor: KEO
Dhabi Taahud International
Future Parsons Brinckerhoff General
Energy Architect: Contracting Sustainability
Foster & Co.
Co. Partners/WSP
Projects Unit
MASDAR Amana/Walbridge J.V.
Document Title:
Document No. MAS-1A-PQP- 01
Project Sustainability Plan
Project Title: Revision No. 0
Date: June 5,
MIST 1A Ancillary Buildings and Infrastructure
2009 Page 11 of 31
Car Park & Podium (Phase 1a), Abu Dhabi, UAE

c. All documents will have full reference to the Project/Subcontract Agreement


Number and will have the document number, revision number and date on which
the document was made.

d. The first submission will have a Revision Number '0' and subsequent submissions
will be followed by A, B, C and so on.

e. Revisions/Changes will be indicated with a vertical line in the left margin. Brief
details necessitating the revision will be indicated in the revision history block on
the first page.

f. Status of submission and approval will be updated every time a submission is


made and Owner/ Project Manager/Consultant/General Contractor comments are
received. Such comments will only be official whenever received from the General
Contractor.

g. The Document Controller will issue a monthly status reports on materials


submissions tracking/approval. Follow up on submissions will be done by
Subcontractor's Project Manager.

h. Approval category legends as approved and implemented by General


Contractor/Owner will be complied with.

4.2.4 Letters, Transmittal and Faxes Numbering

The letter, transmittal and fax numbering system will be as agreed with General
Contractor. The Subcontractor's Project Manager together with the Site
Secretary/Document Controller is responsible for control of all documents and
informing all affected departments/personnel. Whenever possible the
Subcontractor and Subcontractors employees will limit use of paper and instead
use digital communication methods as per Masdar City policy mandates.

Incoming / Outgoing Mail


All incoming mail/correspondence are stamped to indicate date of receipt. The
Subcontractor's Project Manager then reviews and indicates further
distribution (to HO and relevant sub-Subcontractors) and action by others.

Project Specific Correspondence is logged in 'Incoming Mail Register'. Digital


mail will be logged similarly as ‘Incoming Email register.’

The secretary/document controller will track and ensure that Subcontractor's


Sustainability Manager responds to General Contractor Correspondence while on
the other hand remind him of the pending responses to Subcontractor's
correspondence.

4.2.5 Control of Sustainability Records

The following sustainability records will be maintained digitally on and off site by
the Sustainability Manager:

 Materials specifications tracking recycled material content and banned products


list
 Transportation monitoring
 Register of Sustainability training and Masdar environmental inductions of staff
 Daily, weekly and monthly report above items
 Approved inspection and audit plans

Subcontractor copy will be retained for a minimum of 1 year after receipt of Final
Acceptance Certificate. All records are stored for 2 years in the Subcontractor's
Head Office.

5.0 MANAGEMENT RESPONSIBILITY

Subcontractor's management is committed to implement an effective Sustainability Management


system on site. Communication of this commitment will be done daily through visual prompts to
employees and by planned, periodic reminders of the need and importance to meeting Masdar and
EAD regulatory requirements.

Subcontractor will also ensure regular interactions with Owner/General Contractor and shall comply
with Sustainability requirements. Sustainability Manager will be at meetings whenever possible
with owner Project Manager. Commitments made during meetings will be implemented by
Sustainability Manager. Every Tuesday KEO Sustainability Manager and KEO Sustainability QAQC
representative will attend site visits and communicate with Masdar Environmental Project manager.
KEO QAQC representative will be available for four hours each week to communicate with General
Contractor’s Project Manager and any other individuals who have queries of the reporting and auditing
practices of Subcontractor’s Sustainability Management team.

5.1 Responsibility, Authority and Communication

The project will be managed with adequate resources on site for executing contract
requirements for Sustainability Management. Subcontractor has retained Afsar Suleman of
KEO International as consultant Sustainability Manager. Mr Suleman will be on site six days a
12
Employer General Contractor: Project Manager: Sub-
Abu
CH2MHILL/ Subcontractor: KEO
Dhabi Taahud International
Future Parsons Brinckerhoff General
Energy Architect: Contracting Sustainability
Foster & Co.
Co. Partners/WSP
Projects Unit
MASDAR Amana/Walbridge J.V.
Document Title:
Document No. MAS-1A-PQP- 01
Project Sustainability Plan
Project Title: Revision No. 0
Date: June 5,
MIST 1A Ancillary Buildings and Infrastructure
2009 Page 13 of 31
Car Park & Podium (Phase 1a), Abu Dhabi, UAE

week. Additionally, KEO International Director of Corporate Sustainability Holley Chant will
be on site once a week for Quality Control and Quality Assurance supervision of the
Sustainability Manager as detailed in 5.0 above.

5.2 Internal communication:

Subcontractor will ensure all internal communications are effective either verbal or written
format (memo's). Copies of General Contractor correspondence will be copied to relevant
personnel. Site meetings for co-ordination and progress will be held periodically.

Prior to the commencement of major work activities, the Consultant Sustainability Manager and
Sustainability QAQC Manager will partake in induction-training sessions at Masdar. The
Sustainability Manager will periodically repeat the induction training to insure that Subcontractor
is informed of any amendments to Masdar policy.

The Lead Sustainability Manager and Sustainability QAQC Consultant are organizationally
independent from Site Management and as such have the necessary freedom and authority to
carry out the Sustainability Related Activities / duties required for the successful execution of
the project.

5.3 Management Review

Formal Management Reviews of the overall Subcontractor Sustainability System are done at
least quarterly to ensure continuing suitability and effectiveness in satisfying the requirements
of contracts. This review by senior management considers the results of the KEO consultant
sustainability audits, the Owner/General Contractor audits on sites, and the Non
Conformance's and the corrective/preventive and improvement actions are taken.

Evaluations during these reviews form the basis of any changes in the project quality
system. This management review will be recorded either as a report or as minutes and
circulated/maintained by the Lead Sustainability Manager. All recommendations and action
points arising out of this review will be acted upon within agreed times.

The review participants will include the KEO Consultant Sustainability Manager, KEO
Sustainability QAQC consultant, representative Subcontractor's Project Manager and key site
personnel as required.

6.0 RESOURCE MANAGEMENT

Subcontractor will ensure that all resources required for the successful execution of the project are
provided on time for implementing the Sustainability Management system; personnel including
KEO Consultant Sustainability experts, document controller and document control systems.

6.1 Human Resources

Subcontractor will ensure that only competent personnel with sufficient


qualifications/experience and/or training will be utilized on the project site. Subcontractor will
ensure that all proposed key personnel/senior positions are competent to lead this project and
generally comply with the general Contractor/Owner requirements.

Regular training sessions following the initial induction training will be conducted on site to
keep and update the personnel of contract and sustainability technical requirements. The
Project Manager/Lead Sustainability Manager /Lead HSE Engineer will identify training needs
on site. Necessary training for any specialized activity shall be provided to personnel as
applicable. Any other training for specialist operations on site will be provided.

6.2 Infrastructure

All equipment deployed on site will be fit for use on site as per Masdar’s CEMP
requirements. Authority requirements/Legal requirements/Owner requirements for vehicles,
lifting equipment and tackles will be complied with. Fuel usage of all vehicles will be reported
to KEO Sustainability manager and recorded appropriately for carbon tracking purposes.

6.3 Work Environment

Proper infrastructure, Safety Tools and Tackles, necessary rest/ablution facilities and other
requirement to provide a safe and sustainable conducive work environment will be provided.
Necessary sustainability prompts, safety procedures and relevant contract requirements will be
posted at pertinent locations.

All the Subcontractor's Sustainability and Health Safety and Environment requirements will be
proactively implemented onsite, to ensure safe working environment and to successful
execution of the project with as little environmental impact as possible, no fatalities, lost time
accidents and lost time.

7.0 PRODUCT SUSTAINABILITY REALIZATION

7.1 Planning of Product Sustainability Realization

The project will be executed strictly in accordance with the contract Sustainability specifications,
14
Employer General Contractor: Project Manager: Sub-
Abu
CH2MHILL/ Subcontractor: KEO
Dhabi Taahud International
Future Parsons Brinckerhoff General
Energy Architect: Contracting Sustainability
Foster & Co.
Co. Partners/WSP
Projects Unit
MASDAR Amana/Walbridge J.V.
Document Title:
Document No. MAS-1A-PQP- 01
Project Sustainability Plan
Project Title: Revision No. 0
Date: June 5,
MIST 1A Ancillary Buildings and Infrastructure
2009 Page 15 of 31
Car Park & Podium (Phase 1a), Abu Dhabi, UAE

approved environmental procedures, schedules and Sustainability mandates. Only Owner/


approved materials will be utilized in the project. Sub-Subcontractors will comply with all
Sustainability Mandates and are subject to Masdar Environmental Inductions requirements.

Subcontractor will adhere and fulfil all Sustainability Requirement as per the Contract relevant
clauses of the Sustainability and Environmental Section.

The whole process of Project/Construction operations can be split as:

> Contract review - which is done at tender stage and immediately after award

> Design Control –. Sustainable materials approvals reporting and tracking will be submitted
in a timely fashion to General Contractor Project Manager.

> Purchasing Control - use of approved materials and Sub-Subcontractors and store control.
Specific requirements related to sustainable material/products should be observed and
implemented wherever possible.

> Inspection and Testing - including receiving inspection, in process inspections and
testing, inspections at vendor premises (if required) and testing.

> Handover/Close Out.

All the above processes forming the Project/Construction operations are covered by
Subcontractor’s procedures and/or project specific procedures. Records required to demonstrate
compliance are indicated in each of the procedures, which will be verified during internal
audits. Data relating to sustainability will be submitted on a monthly basis and then again as a
compilation for handover at the end of the project.

Method Statements will be submitted to ensure planning of the detailed construction activities
including sustainability specification requirements and environmental impact controls that need
to be in place for a Masdar CEMP compliant operation.

7.2 Customer Related Processes

Subcontractor has reviewed the Sustainability contractual requirements in detail at tender, the
time of post-tender negotiations and on award of contract. All addenda and bulletins issued
during tender period, post tender clarifications and other queries are all retained as contractual
documents.
Where requirements are not clear, the General Contractor will be contacted by the KEO
Consultant Sustainability Manager and clarifications will be sought. Records are kept of all
reviews and any exchange of correspondence on contractual requirements is also filed as
evidence of contract review.

The post award contract review is done in Subcontractor's Head Office and attended by the
Managing Partner, the Lead Consultant Sustainability Manager and Sustainability QAQC
Consultant and the Project Manager.

7.2.1 Clarifications on Site

Any clarifications on drawings, scope of works, Sustainability contractual requirements


or technical queries are assessed by means of “Request for Information” or "Technical
Query". All RFIs or TQs are treated as contractual documents and will form part of the
final hand over documentation. Owner/General Contractor responses will be copied to
relevant departments/personnel.

7.3 Purchasing

Materials and Sub-Subcontractors to be used in the works shall be first submitted for
Owner/General Contractor approval. Consideration will be given on quality, sustainability,
price, delivery, reliability and service. Criteria for selection of Sub-Subcontractors and
Suppliers/Vendors besides complying with Specifications and legal/local Authority
registrations are; organizational structure, prior Sustainable Construction experience,
Quality and HSE systems, compliance with sustainability requirements, past performance,
previous experience with Owner/General Contractor, current workload and adequate
expertise/experience in the particular service shall be considered and complied with. Where
there are proprietary items and the above criteria cannot be adhered to, Owner/General
Contractor would be placed on the actual picture with details during submission for approvals.
Material approval and deliveries will be tracked and reported in progress reports. Material is
purchased only from the approved sources. Material requisitions are sent from site, detailing
the requirements. All materials to be permanently incorporated into the project will be
subjected to receiving checks by KEO Consultant Sustainability Manager, Lead QA/QC
Inspector / Project Manager and Storekeeper.

All Sub-Subcontractors used in the project are subjected to the same project Sustainability
requirements as applicable to Subcontractor. Subcontract agreements are made on a back-to-
back basis, thus making all Sub-Subcontractors bound to the main contract requirements.

7.4 Production and Service Provision

Subcontractor understands the critical operations involved during the construction works. As
such, coordination, use of dated and approved drawings, and strict compliance to safety
and sustainability requirements and approved method statement will be ensured.

7.4.1.A Control of Production and Service for Sustainability

16
Employer General Contractor: Project Manager: Sub-
Abu
CH2MHILL/ Subcontractor: KEO
Dhabi Taahud International
Future Parsons Brinckerhoff General
Energy Architect: Contracting Sustainability
Foster & Co.
Co. Partners/WSP
Projects Unit
MASDAR Amana/Walbridge J.V.
Document Title:
Document No. MAS-1A-PQP- 01
Project Sustainability Plan
Project Title: Revision No. 0
Date: June 5,
MIST 1A Ancillary Buildings and Infrastructure
2009 Page 17 of 31
Car Park & Podium (Phase 1a), Abu Dhabi, UAE

The construction activities shall be controlled by the use of this Sustainability Plan,
HSE Plan, Master Construction Schedule, Inspection and Test Plans, Project
Specific Procedures/Method Statements and Check sheets together with the contract
drawings and specifications.

Familiarity and knowledge of contract specifications/drawings and strict adherence


to Sustainability mandates together with the regular interaction/monitoring/in-process
inspections will ensure that work is executed to contract requirements.

The Subcontractor's Project Manager, Consultant Sustainability Manager and


Sustainability QAQC Consultant together with his site team will ensure that the
work is executed in line with the relevant procedures, suitable equipment are used
and the work is monitored at various stages as required by specifications and identified
in the Inspection and Test Plans and relevant procedures.

Contract Requirements on Sustainability Management will be complied with. The


following protocol is followed for Material Reviews by the KEO Consultant
Sustainability Manager:

The KEO Consultant’s initial focus on the material reviews has been to address
existing materials tracking issues on hand, as identified by General Contractor’s
Project Manager in comments on the Material submittals thus far. This process
involves:
 Communicating with the suppliers to obtain necessary data missing in the
initial submission,
 Investigating possible alternatives,
 Discussing the usage of renewable/ recycled raw material,
 Inquiring on their outlook, goals and sustainable practices within their factory
etc.

For new specifications Consultant Sustainability Manager will evaluate materials as


identified in the Masdar Technical Reference Sheet. All building products need be
evaluated subject to their use within the building and on their sustainable features
defined by Masdar and generally acceptable green practices as outlined below:
 Compliance to restricted Materials list, as established by Masdar. (Yes/No,
with a brief write up on issues therein)
 Proximity of Source : set limits within 800 km of the project (Yes/No, with a
brief write on source availability)
 Percentage of recycled content of material
 Sustainable sourcing of materials: mostly pertaining to wood, but also based
on material abundance can be suggestive for other materials as well. (FSC
certificate/ or brief write up on sustainable sourcing)
 Available manufacturer’s data of Embodied Carbon for the material.
(Co2/tone)
 Sustainable manufacturing practices: Although this has not been laid down as
a criteria Consultant Sustainability team suggest looking at sustainable
practices (Yes/No)
 Material Delivery and Packaging- One on one discussion with supplier will be
undertaken material delivery optimization and for possible reduction or
packaging.
 Material durability and life cycle impacts.( Avg./Good/ Excellent)
 Future recycling, down cycling of environmental impacts of demolished
materials.(note possible issues)

Submittal Forms on the above basis are developed summarizing documentation


compliance. Material Submittals will be further substantiated with necessary proof of
compliance by means of certifications, manufacturer’s statements, technical data
sheets etc.

In the absence of a database of sustainable companies and products within the UAE,
emphasis is with Subcontractor to name 3 companies whose products comply with the
Consultants Architectural Specifications. Subcontractor uses the Ecospecifier system
for specification alternatives. Discussions will be undertaken with General Contractor
and the project Consultant’s as required to facilitate the material approval process.

A data base will be created tracking all technical correspondence and the
sustainability component of all outgoing material submittals.

Construction Carbon Tracking:


Site Carbon Tracking will be documented as outlined in the Masdar Sustainability
Data Collection Form. The tracking forms include the following tables:
 Materials
 Deliveries
 Employee Travel
 Flights
 Waste
 Water Use
 Electricity Purchased
 On site fuel use
18
Employer General Contractor: Project Manager: Sub-
Abu
CH2MHILL/ Subcontractor: KEO
Dhabi Taahud International
Future Parsons Brinckerhoff General
Energy Architect: Contracting Sustainability
Foster & Co.
Co. Partners/WSP
Projects Unit
MASDAR Amana/Walbridge J.V.
Document Title:
Document No. MAS-1A-PQP- 01
Project Sustainability Plan
Project Title: Revision No. 0
Date: June 5,
MIST 1A Ancillary Buildings and Infrastructure
2009 Page 19 of 31
Car Park & Podium (Phase 1a), Abu Dhabi, UAE

The tracking form is required to be submitted monthly to General Contractor but to


maintain best practice and efficient recording of information Subcontractor has
charged KEO Sustainability Manager to record data weekly.

It is understood that waste management is under General Contractor scope and will
not require assessment; similarly any fuel bought directly from General Contractor
does not require accounting. As is customary for commercial and logistic reasons,
most of the necessary data for the carbon tracking can be availed from Subcontractor’s
document control, in the absence of such records internal tracking forms will be
created as required.

Sustainability Management Work Progress is monitored on a daily/weekly basis and


progress reporting is done as per contract requirements. Suitable actions shall be
taken to accelerate progress and avoid slippages. Where required, the schedules will
be modified as agreed with the General Contractor.

7.4.2 Product Identification and Traceability

The product - in this case the architectural finishes to the buildings and other structures
in the scope of work of the subcontractor, are visually identifiable as to the status of
work and the numbering as indicated in the approved drawings and the Owner
preferred numbering system.

Incoming materials are correctly identified for sustainability requirements and stored.
Most of the construction materials are identifiable by means of labels and packaging
by the manufacturer/supplier. Where not available, materials will be suitably
identified by using coloured markers and or tags. All materials coming out of store
shall be either traceable by marking/labels, store records, test certificate, etc.

7.4.3 Customer Property

Any material obtained from dismantling/demolition will be considered as Owner’s


property and will be returned/disposed off as per Owner/General Contractor
instructions and contract agreement. Correct sustainability and environmental
considerations will be adhered to when disposal is the required action.

Care will be taken of Owner property by complying with all sustainability, safety
and security requirements. Subcontractor also understands the confidentiality of
drawings and the property contained therein and will only exchange information as
required for the project.

7.4.4 Preservation of Product

Material received on site for permanent incorporation in the project, are subject to
Receiving Inspection by Sustainability Manager, Lead QA/QC Engineer/Project
Manager and Storekeeper. Presence of Owner/General Contractor will be as per
contract requirements and as indicated in the ITP's. Acceptable materials are listed
on the Site Receipts and logged into the database of Sustainability records. Store data
is continuously updated on receipt and issue to site.

8. MEASUREMENTS, ANALYSIS AND IMPROVEMENT

8.1 General

Subcontractor will plan and implement assessment methods to demonstrate conformity with
the contract Sustainability requirement (as detailed in above section 7), process
performance objectives, conformity of the planned quality management system, and for the
continuous improvement of the Sustainability management system.

The assessment methods for Sustainability Management are indicated below -


> Customer Satisfaction - use of the Customer Satisfaction Survey Questionnaire at
least once during the project duration.
> Internal Audit - to check compliance and effectiveness of the Sustainability
management system and processes
> Monitoring of the Processes (Employer level)

8.2 Analysis of Data

8.2.1 Weekly Sustainability Report (Internal to Subcontractor)

The Lead Consultant Sustainability Manager in coordination with the Document


Controller will prepare and submit on a weekly basis a report to the Subcontractor's
Project Manager and Managing Partner, indicating issues detailed below:

Weekly Sustainability Reports will be submitted by every Saturday or Sunday to


Subcontractor's Project Manager. Following issues will be covered in the weekly
report as a minimum.
a) Updated Status of Sustainability Documentation Submittals and approval
status with Highlights of Changes during the week.
b) Status of Request for Further Information for Sustainability documentation.
20
Employer General Contractor: Project Manager: Sub-
Abu
CH2MHILL/ Subcontractor: KEO
Dhabi Taahud International
Future Parsons Brinckerhoff General
Energy Architect: Contracting Sustainability
Foster & Co.
Co. Partners/WSP
Projects Unit
MASDAR Amana/Walbridge J.V.
Document Title:
Document No. MAS-1A-PQP- 01
Project Sustainability Plan
Project Title: Revision No. 0
Date: June 5,
MIST 1A Ancillary Buildings and Infrastructure
2009 Page 21 of 31
Car Park & Podium (Phase 1a), Abu Dhabi, UAE

c) Summary Status of Internal Audits and Non Conforming Materials if any.


d) Sustainability Meetings Summary and list of outstanding actions if any.
e) Log of cumulative mileage travelled by employees and alerts issued for delinquent
employee reporting.
f) Sustainability inductions and training conducted if any.
g) Any other issues.

8.2.2 Monthly Sustainability Report

A monthly Sustainability Management report will be submitted to the General


Contractor using the same contents as above in the weekly report. Cut off date for the
monthly report will follow the same as progress reporting as agreed with the General
Contractor during execution.

8.2.3 Safety, Health and Environment (SHE) Data

An additional Project HSE Plan covers all aspects of SHE control on site. All
reporting required shall be as per the SHE Plan and Owner’s SHE contractual
documents.

8.3 Improvement

Subcontractor will strive to continually improve the effectiveness of the Sustainability


Management system through the use of the expertise of the KEO Sustainability
Consultants and analysis of data as indicated above, and undertaking corrective and
preventive actions resulting from management review decisions and/or Owner/General
Contractor instructions/audits.

8.3.1 Corrective and Preventive Action

In issues of Sustainability Material Specifications non-conformance, corrective action


is started as soon as it is practically possible after approval of proposed corrective
action from the Owner/General Contractor. The corrective actions taken are recorded
on the Non Conformance report and/or the relevant check sheets or by a letter.

The Lead Sustainability Manager will ensure all agreed corrective actions have been
completed and related Non Conformance Reports closed out.
The Subcontractor's Sustainability Manager is responsible to initiate suitable
preventive action to ensure the Non Conformances do not repeat. Preventive actions
like project documentation and method statements together with the control measures
required are already documented. Compliance with these will ensure that potential
non-conformities will be prevented from occurring.

9.0 List of Attachments


1.0 Project/Site Organization Chart
2.0 Responsibilities of Key Personnel
3.0 Format/Template
3.1 Method Statement Format
3.2 Form – Training Record
3.3 Form – Weekly/Monthly Sustainability Report
3.4 Form – Material Sustainability Non-Conformance Report
3.5 Various Sustainability Forms

22
Employer General Contractor: Project Manager: Sub-
Abu
CH2MHILL/ Subcontractor: KEO
Dhabi Taahud International
Future Parsons Brinckerhoff General
Energy Architect: Contracting Sustainability
Foster & Co.
Co. Partners/WSP
Projects Unit
MASDAR Amana/Walbridge J.V.
Document Title:
Document No. MAS-1A-PQP- 01
Project Sustainability Plan
Project Title: Revision No. 0
Date: June 5,
MIST 1A Ancillary Buildings and Infrastructure
2009 Page 23 of 31
Car Park & Podium (Phase 1a), Abu Dhabi, UAE

1.0 Project /Site Organization Chart


(Official nomination of key personnel will be addressed in separate correspondence)

2.0 Responsibilities of Sustainability Personnel

SUSTAINABILITY MANAGER
Reports to : Site Manager/Project Manager

Major Responsibility : Ensure that construction complies with the sustainability principle,
administration, Coordination with General Contractor and coordination of
procurement activities and site activities and reporting to Site Agent.

Related Responsibilities:

a) Ensure that all contractual requirements of Owner and local authority requirements for
Sustainability, Quality, Health Safety & Environment (HSE) requirements are complied with
b) Ensure that all temporary and permanent materials/products comply with the Construction
Products Directive (CPD) or acceptable equivalent directive and properly labelled with CE or
equivalent marking.
c) Ensure that materials and products are from sustainable sources.
d) Keep a database of all materials and products that comply with sustainable construction
requirements.
e) Follow up with suppliers/vendors and product/material sources to obtain all necessary data
related to sustainability and fill in all necessary tabulations and issue relevant
daily/weekly/monthly reports to the General Contractor and Owner as required by the Contract.
f) Coordinate closely with the General Contractor Sustainability Manager and daily basis.
g) Ensure that workmanship/fabrication/installation/transportation methods etc are in line with
sustainable construction requirements and meets requirements of US Green Building Council
(wherever applicable).
h) Obtain, verify and appraise quotations for materials and products and obtain material/product
data that is needed and that has to be tabulated and related to the sustainability program assigned
to the project by Owner.
a) Ensuring site activities are all coordinated to meet sustainability programme requirements
and that work activities are properly planned to ensure work is completed as per the
construction work schedule.
i) Monitor, control and coordinate work with Sub-Subcontractor.
j) Ensuring works are done in strict compliance to Environmental requirements.
k) Ensuring and coordinating ordering of all approved materials.
l) Interact with responsible engineer and ensure all materials are approved, ordered and
available on site.
m) Coordinating with the independent testing laboratory together with QA/QC and ensuring
necessary resources are provided.
n) Coordinating the interface between other Subcontractor's secondary Sub-Subcontractors on
site.
o) Implementing and coordinating corrective actions to arrest slippages are being implemented.
p) Ensuring Non-Conformance's if any are closed and taking timely preventive and corrective
actions
q) Responsible for completing of all punch items and project close out & handover
documentation.
r)Responsible for reporting to KEO QAQC Consultant for performance and administrational review
once a week and when any situation warrants third party advise.

24
Employer General Contractor: Project Manager: Sub-
Abu
CH2MHILL/ Subcontractor: KEO
Dhabi Taahud International
Future Parsons Brinckerhoff General
Energy Architect: Contracting Sustainability
Foster & Co.
Co. Partners/WSP
Projects Unit
MASDAR Amana/Walbridge J.V.
Document Title:
Document No. MAS-1A-PQP- 01
Project Sustainability Plan
Project Title: Revision No. 0
Date: June 5,
MIST 1A Ancillary Buildings and Infrastructure
2009 Page 25 of 31
Car Park & Podium (Phase 1a), Abu Dhabi, UAE

3.1 Method Statement Format


Project Title

MIST 1A Ancillary Buildings and Infrastructure Tender Package 0400


Car Park & Podium (Phase 1B), Abu Dhabi, UAE

Document Title

Method Statement for


Xyz

Revision and Approval History


Re General Approval
Description / SUBCONTRACTOR Owner
v. Date Contractor Status
Remarks
No. Prepared Reviewed Approved Approved Approved

1.0 PURPOSE

2.0 SCOPE

3.0 REFERENCES

4.0 DEFINITIONS
5.0 RESPONSIBILITIES

6.0 EQUIPMENT

7.0 PROCEDURE

8.0 DOCUMENTATION

3.2 Form –Sustainability Training & Induction Record


Please pass copy to Sustainability Manager, when completed.

Taahud General Contracting Co.

SUSTAINABILITY TRAINING & INDUCION RECORD

Training / Seminar Title: Date:

Names & Designations of Personnel Trained: (Use additional Sheet if required) No. of Personnel Trained:

Project Site / Venue:

Total Time Taken:

Reason for training:

Brief details of topics covered: (Use additional sheets as required)

Handouts / Technical Literature given: Yes No

Remarks if any:

Training Conducted By: Signature: Date:

Acknowledgement of Training: Post Training comment on Effectiveness of Training if any:

26
Employer General Contractor: Project Manager: Sub-
Abu
CH2MHILL/ Subcontractor: KEO
Dhabi Taahud International
Future Parsons Brinckerhoff General
Energy Architect: Contracting Sustainability
Foster & Co.
Co. Partners/WSP
Projects Unit
MASDAR Amana/Walbridge J.V.
Document Title:
Document No. MAS-1A-PQP- 01
Project Sustainability Plan
Project Title: Revision No. 0
Date: June 5,
MIST 1A Ancillary Buildings and Infrastructure
2009 Page 27 of 31
Car Park & Podium (Phase 1a), Abu Dhabi, UAE

3.3 Form – Weekly / Monthly Sustainability Report


Masdar-Ch2-Suite-Rep Sustainability Data Form v. 3 will be used for reporting.

1.0 Sustainability Personnel on Site

SI. No. Name of Personnel Designation


1 Afsar Suleman: KEO Sustainability Manager Consultant
2 International
Holley Chant: KEO Sustainability QAQC Consultant
3

2.0 Sustainability Documents Submission Status

Status of Sustainability Documents Submission


This Week Cumulative
Approved Su Approved
Document Type Sub Document Type
A B C b. A B C
Weekly/Monthly
Sustainability Procedure
Report
Method
Method Statement
Statement
Quality Cont.
Quality Cont. Proc
Proc
Inspection & Test Inspection & Test
Plan Plan

2.1 Sustainability Compliance Sheet


3.0 Sustainability Non Conformance Log and Close-Out Details
PROJECT ARCHITECTURAL PACKAGE MAIN CONTRACTOR: CLIENT: - CONSULTANT
MANAGEMENT:- CONTRACTOR:- - :-
Status of NCR as on aa.bb.ccTAAHUD
This Week
General Cumulative
NCR's Issued
Owner ContractinClosed Issued Open Closed

General Contractor g Co. LLC


Project Title: -
Subcontractor Project No.:-
Total
MASDAR Project 1 Phase A MIST1A Ancillary Buildings And
MIST1A
Infrastructure
Document Title: -

MAR Ref. MIST1A-


Sustainability Compliance Sheet No
MAR-022
Material Trade Name

Compliance
Specificati
N
on Clause Remarks
o Requirements Proposed Material Specification
Reference
Yes No.

Does the product contain


Section None of the items listed are
1 materials on the banned
00910 used in the proposed materials
item list?

Does the product contain


Section None of the items listed are
2 materials on the
00910 used in the proposed materials
restricted item list?

Material is to supplied
Section No material is coming from
3 from an 800km radius
00910 Europe
zone

Section What is the recycled


4 No information on the same
00910 content of the material

Notes / Comments:

Material is approved in MIST 1

Reviewed By and Date:

Note:

28
Employer General Contractor: Project Manager: Sub-
Abu
CH2MHILL/ Subcontractor: KEO
Dhabi Taahud International
Future Parsons Brinckerhoff General
Energy Architect: Contracting Sustainability
Foster & Co.
Co. Partners/WSP
Projects Unit
MASDAR Amana/Walbridge J.V.
Document Title:
Document No. MAS-1A-PQP- 01
Project Sustainability Plan
Project Title: Revision No. 0
Date: June 5,
MIST 1A Ancillary Buildings and Infrastructure
2009 Page 29 of 31
Car Park & Podium (Phase 1a), Abu Dhabi, UAE

4.0 Updated Status of Sustainability Query (SQ)

This Week Cumulative


Remarks
Submitted Responded Submitted Responded

5.0 Summary Status of Client / Internal Audits and Corrective Action Request

No of No of Status of
Total No of No of Audit Corrective Corrective Corrective
Audited By Audits Conducted Action Action /
Conducted This Week Request Request Preventive
Issued Closed actions
Owner/General
Contractor
Internal-
Subcontractor

6.0 Sustainability Training Conducted if any during this Week

Type of Training
Total Number of Training Conducted

This Week
Cumulative
Quality Tool Box

Sustainability Induction
Job Skill

Quality System

Safety

Special Application

TOTAL

7.0 Form – Non-Conformance Sustainability Report

Owner:

MASDAR
General Contractor:

Amana/Walbridge J.V.
Subcontractor:

Taahud General Contracting Co.


Document Title:
Non-Conformance Report
Sustainability Management Procedure: Sustainability Audits-Compliance Record
Project:
Job No.:
Audit Reference / Verification Stage:
Auditors / Verifier:
NCR No.:
Department / Site:
Auditee/Process:
Date:
Applicable Document/Standard/Procedure:

Clause No.:
Non Conformity Description:

Acknowledge of Non Conformity / Auditee / Process:


Signature:
Name Date:
Proposed/Agreed Corrections/Remedial
30
Employer General Contractor: Project Manager: Sub-
Abu
CH2MHILL/ Subcontractor: KEO
Dhabi Taahud International
Future Parsons Brinckerhoff General
Energy Architect: Contracting Sustainability
Foster & Co.
Co. Partners/WSP
Projects Unit
MASDAR Amana/Walbridge J.V.
Document Title:
Document No. MAS-1A-PQP- 01
Project Sustainability Plan
Project Title: Revision No. 0
Date: June 5,
MIST 1A Ancillary Buildings and Infrastructure
2009 Page 31 of 31
Car Park & Podium (Phase 1a), Abu Dhabi, UAE

Actions:

Proposed completion Date:

Signature:
Name: Date:
Acceptance and Verification of Corrections/Remedial actions:

Actual completion Date:

Signature:
Name: Date:
Corrective actions taken to prevent recurrence of Non conformity:

Planned Completion Date:


Actual Completion Date:
Signature:
Name: Date:
Post Audit Review By Management
Reviewed:
Signature:
SITE SUSTAINABILITY PLAN

Taahud

You might also like