Professional Documents
Culture Documents
2019
SYLLABUS:
(2.1 ) PPC(Production Planning& Control)(PPC) & Stages in PPC,
(2.2) Aggregate Planning,
(2.3) Basics of Project management,
(2.4) Concept of Maintenance Management
(2.1)
PPC(PRODUCTION PLANNING& CONTROL) & STAGES IN PPC…..Text Book Pp 469 to 489
Forecasting is the main base for PPC. ………………………………..Text Book Pp 571 to 606
(i)Statement about future.
(ii)It is the First step in Planning
Demand forecasting:
Estimate of the future demand for products or services are commonly referred to as Sales
Forecasts/Demand Forecasts, which are the starting point for the entire planning in production and
operations management .
Foe eg, material planning, capacity planning, man power planning, financial planning and production
scheduling, all depend on Sales/Demand Forecasting.
Methods:
Quantitative (objective type):
(iv)Causal Models: Trend projection, Linear regression Analysis ,Semi Average Methods etc
2 Common Methods: Linear Regression Method & Semi_Average Methods
F/casting
Regression
Linear method computations
b=(( Sigma(x*y) -n*xavg* yavg ) /
(sigma (x2)- n*xavg2 )
=
(1000-6*5*30 ) / (200-6*5*5)
x is
independen =
dent 100 / 50 = 2.0
y= a+b * x variable
a= (yavg - b * xavg)
= 30 – 2 * 5
= 30 -10
= 20
Period x y x*y X2
(Res Expr) (Profit)
1 2 20 40 4
2 3 25 75 9
3 5 34 170 25
4 4 30 120 16
5 11 40 440 121
6 5 31 155 25
Total 30 180 1000 200
Average 5 30
7 6 ? (Question)
y=a+b*x,
y= 20 + 2 *
x
Equation
y=20+2*7=
34
Answer
Forecasting- examples- semi-average method
F/castin
g
Semi average computations
Method
y=a+b*x x is Y is
independendent dependant
variable variable
Period Sales Semi total Semi Avg
(for 3 years) TrendValue
x y
1997 39
1998 48 152 152/3=50.67 a=50.67
1999 65
2000 78
2001 95
2002 91 298 298/3=99.33 b=(99.33-50.67) / (2002-
1998) = 48.66/4
= 12.165
2003 112
Avg
2004 ? (question)
Equation y=a+b*(x-1998),
where x=2004
Answer y=50.67+12.165*6
=123.66
=124
QUALITATIVE (Judgemental Type):
Jury method .Judgemental
method (DELPHI METHOD) ,
Sales composite method, Market Research method, Others
Forecasting- Delphi Method
For forecasting items of subjective nature,Panel members are to be unknown to each others;Egs:
Technology forecasting, forecasting demand in international competition
Mc language, 1st generation languages(Assembly language), 2nd generation languages(High level
language), 3rd generation languages(Lotus1-2-3), 4 th generation languages(oracle..);Consensus,
otherwise, re-circulate findings to those whose estimates vary by + or -50% of majority finding.
CASE EXAMPLE ON PPC :PRINTING PRESS PROBLEM (Eg ON PPC)
A printing company’s data.
The Co., works on one shift basis ( 8 AM to 4.30PM, with half an hour Lunch break
Business Purpose : Receiving work orders for Text books and Pamphlets/Brochures &
Printing&Despatching to customer.
Products: Text books of 1000 pages (high profit margin) , One page Pamphlets / Brochures Of different
sizes (low profit margin)
RESOURCES:
(i)Machines &Man Power & Their Capacity: Big Printing Machine ( for Text books) : 600
pages/hour);
Small Printing Machine ( for Pamphlets ) : 100 Nos./hour) ;
Cutting ,Trimming&Binding Machine : 5 Books/hour; (Cutting ,Trimming &Binding is not required for
Pamphlets/Brochures ) , Packing and dispatching of Books : 200 Nos./person/Day ;
Packing and dispatching of Pamphlets/Brochures : 1000 Nos./person/Day,
Sales Forecast: : 4500 Books (each of 1000 pages)/year,
5,00,000 Pamphlets/Brochures /year.
To be Worked out :
(1) Sequence of operations,
(2) Production capacities
(3) Machineries & Man power Required
&(4) Comments
Solution :
(1)Sequence of operations:
For Books: (i)Printing (ii) Cutting ,Trimming & Binding & (iii)Packing and dispatching (3 Activities as
per this sequence) (Note:First 2 activities fall under category of Machine Operations and the last one
comes under Manual Operation)
For Pamphlets/Brochures :- (i)Printing (ii)Packing and dispatching…..2 Activities as per this sequence.
(Note:First 2 activity falls under category of Machine Operation and the second one comes under Manual
Operation)
2)Production capacities:
2.1:Production capacities for Books printing : 600 pages/hour (= 0.6 Book/Hour), 8*600=4800
pages/Shift(Day) (=4.8 Books/day) , 4800 X 25= 120000 Pages/month (=120Books / month),
120000 X 12= 1440 000 pages / year
(= 1440 nos.of Books printing / Year)
(Note: The press operates for 1 shift /day. Hence, 1 shift means a day. There are 25 days/ month.& 25 X
12=300 days/Year)
2.2:Production capacities for Books Cutting ,Trimming & Binding : 5 nos./hour, 5X8=40
Nos/Shift(Day) ,40X 25= 1000 nos./month ,1000X12
= 12000 nos. of CTM of Books / year
2.3: Production capacities for Packing and dispatching of Books :200 nos./person/Day ,
200 X 25= 5000 nos./month, 5000 X 12
= 60000 nos. 0f P&D of Books / year
2.4Production capacities for Pamphlets/Brochures printing : 100 nos./hour, 100X8=800
nos./Shift(Day) ,800 X 25….= 20000 nos./month, 20000 12
= 240 000 nos. of P& Bs Printing/ year
Planning: Devising future course of action in advance to realize organizational objectives. It is dynamic
and continuous
Planning varieties:
Strategic (by top management)/ Tactical (by middle management/ operational (by lower level
management)
Respective examples:
Strategic:Plant or Factory/Service Facility- where to locate; production - how to do;
Tactical:product range –what ,plant layout, pricing, maintenance policy, budget, make components or
buy?
Operational: decisions/price discount at field level, maintenance details, man power allocation, production
schedule, inventory control…
Production System is sequence of operations resulting in Output of Product / Service with right
Quantity, Quality , at Required Time, using Best Method & at Cheapest Cost.
STAGES IN PPC:
1.PLANNING: The Choice from SEVERAL ALTERNATIVES of the best means of utilizing the
resources available to achieve the desired OBJECTIVES IN THE MOST EFFICIENT AND ECONOMIC
MANNER.
2.OPERATIONS: Performance in accordance with the details set out in the PRODUCTION PLAN.
3.CONTROL: The monitoring of performance through a feed back by comparing results achieved with
planned targets so as to improve performance through corrective actions .
Hence, PPC may be defined as planning, direction and coordination of the firm’s materials and physical
facilities to meet predetermined objectives in the most economical manner.
PPC can also be referred as Operations planning& Control.
Suppose any other sequence is followed (Say; A,B,C,D,E,F.The computations are as follows.
Job WC1 WC 2
Duratio In time Out Remarks Duratio In Out Remarks
n time n time time
A 2.00 0.00 2.00 1.00 2.00 3.00 Waiting
Upto 2.00
B 4.00 2.00 6.00 2.25 6.00 8.25 Waiting
from 3.00
upto 6.00
C 0.75 6.00 6.75 2.50 8.25 10.75
D 1.50 6.75 8.25 3.00 10.75 13.75
E 2.00 8.25 10.25 4.00 13.75 17.75
F 2.00 10.25 12.25 3.50 17.75 21.25
Tota 12.25 16.25
l
Output Rate = 60/21.25 = 2.823 ,which reduced compared to EARLIER OPTIMUM SEQUENCE of
CDEFBA
ADDITIONAL INFORMATION ON PPC :
PPC-another dimension,
Planning/Action/Control
Planning (What, How):
Optimal schedule, sequencing operations, E.B.Q(Economic Batch Quantity) determination, Despatching
priorities.
Pre Planning;
Forecasting, product design,aggregate planning,master prodn schedule(product wise),order writing for
authorizing,mrp for dependent items
Active Planning ;
Process planning, routing, materials planning,tools planning,loading(mc assigning) & scheduling
( different o.r.techniques, what products&when,what qnty&when,what resources&when, considering
feasibility constraints of resources & technological factors for determining sequence determination & start
and finish time)
Aggregate Planning :
It involves planning the best quantity to produce during time periods in the intermediate range
horizon( Like, 3 months to 1 year) & planning the lowest cost method for the adjustable capacity to
accommodate the production requirements.
Aggregate Planning involves planning work force size, production rate ( in terms of necessary no., of
work hours per week) and managing inventory levels.
operations Planning and Scheduling Systems are concerned with the volume and timing of outputs, the
utilization of operations capacity and balancing outputs with capacity at desired levels of competitive
effectiveness.
Operations Planning and Scheduling Systems,
Business Plan
Operations
Inputs Outputs
Strategic Objectives, Size of work force,
Co., policies, Production Rate (Units/month etc.,),
Demand forecasts, Inventory levels,
Capacity constraints, Units sub contracted,
Financial constraints back-ordered or lost
Steps for Aggregate Planning
1)Determine the Demand ( i.e sales forecast) for each product for each time period(i.e., weeks or months
or quarters) over the planning horizon(6 to 12 months)
2)Determine Aggregate Demand by summing up the demand for individual products.
3) Transform Aggregate Demand for each time period into workers, materials, machines required to
satisfy aggregate demand.
4) Identify Pertinent Company Policies ( on safety stock, stable work force, over time, sub-contracting
etc.,)
5)Determine Unit Costs for regular time, over time, sub-contracting, holding inventories, back orders, lay-
offs etc.,
6)Develop Alternative Resource Plans for providing necessary production capacity to support the
CUMULATIVE aggregate demand and compute the cost of each alternative plan.
7)Select the Resource plan from the Alternatives considered that satisfies Aggregate demand and Best
meets the Objectives of the Firm.
Objectives of MPS:
1) To schedule end items to be completely promptly and when promised to customers
2) To avoid over loading or under loading the production facility so that production capacity is efficiently
utilized and low production cost result.
Method of MPS:
Computerized systems
Example :
Rajasthan saris is a 100% export organisation located at Jaipur.Its sales agency is in Zurich.
In the last week of October, the sales agency provided a forecast of 2000 saris for NOVEMBER.In the last
week of November, it provided the forecast of 3000 saris for DECEMBER. (i.e forecast is done,1 month
in advance.
In October there are 25 workers. Each worker produces 100 saris/month.Salary = Rs 4000 /worker/month.
The co. follows hiring and lay –off policy. The hring cost, including training is Rs 500/person.Thelay off
cost is 20% of the monthly salary( 20 % of 4000= 800/person).The Inventory carrying cost is Rs
10/sari/month.
(Q1)Prepare aggregate plan.(Q2) Suppose the forecasts for the 2 months is known in advance, prepare the
AP.
Qn 1:
Item For Nov Month For Dec Month Total cost,Rs
Units required (Nos.) 2000 3000 5000
Workers on rolls in 25
October (Nos.)
Workers to be 25-20=5 5
Laid off (Nos.)
Qn 2:
Item For Nov For Dec Total cost,Rs
Units reqd (Nos.) 2000 3000 5000
Units prodn plan (Nos.) 2500 2500 5000
Workers on rolls in October 25
(Nos.)
Workers reqd (Nos.) 2500/100=25 2500/100=25
Salary (Rs) 25X4000=100000 25X4000=100000 200000
Workers to be nil nil
Hired (Rs)
Hiring cost (Rs) nil nil
Workers to be nil nil
Laid off (Nos.)
Lay off cost (Rs) nil nil
(2)AP methods
Regular time:
Prodn capacity
(constant work force)
Feature:
Through uniform Production, build inventory& use it in demand peak periods
1.Graphical Method:
Method :Uniform Production Rate : of 365 Units/ Qtr
Quarter (Varying)- Cumulative- Uniform Cumulative
Demand(Nos.) Demand (Nos.) production(Nos.) production(Nos.)
1 270 270 365 365
2 220 490 365 730
3 470 960 365 1095
4 670 1630 365 1460
5 450 2080 365 1825
6 270 2350 365 2190
7 200 2550 365 2555
8 370 2920 365 2920
2920/8 =365
Graphical representation can be made.
(2) Heuristic Method AP :
PURE STRATEGY 1: Varying Work Force:
Rs 150/Unit/Increaseease in production(Hiring), Rs 200/Unit/Decr in production(Firing),&Rs 50
/Unit/Quarter as Inventory carrying cost &Rs 100/Unit/If Sub-Contracted
PURE STRATEGIES
Vayring STRATEGY 1
Work
Force
(Hire/Fire
)
Quarter (Varying) Cumulative Cost of increasing the Cost of decreasing the TOTAL
Demand Demand production production COST
(Nos.) (Nos.) (Rs) (Rs) (Rs)
1 270 270
2 220 490 50 X 200 10000
3 470 960 250 X150 37500
4 670 1630 200 X150 30000
5 450 2080 220 X200 44000
6 270 2350 180 X200 36000
7 200 2550 70 X200 14000
8 370 2920 170 X150 25500
TOTAL 93000 104000 1,97,000
(3) Heuristic Method AP:
PURE STRATEGY 2: Varying Inventory Levels :
System :Let opening Inventory be255 units. Let Constant production rate be365 units. Let Rs 50
/Unit/Quarter be the Inventory carrying cost.
3 470 960 365 1095 135 135 - 240 495-105= 390 390*50
(= - 105)
4 670 1630 365 1460 - 170 - 170 - 135 390-305 =85 85*50
(= - 305)
5 450 2080 365 1825 - 255 - 255+170 85-85= (0) 0
(= --85)
6 270 2350 365 2190 - 160 - 160+255 0+95 =95 95*50
( = 95)
7 200 2550 365 2555 5 5 + 160 95+165= 260 260*50
(=165)
8 370 2920 365 2920 0 0- 5 260-5= 255*50
(= - 5 ) 255
Total 1930*50
=96,500
(4) Heuristic Method AP:
PURE STRATEGY 3: Sub-contracting System & Constant rate of uniform production of 200
units&balance sub-contracting) &Rs 100/unit ,if sub-contracted.
De Uni +/_ OT Ttl Net +/_ Inv Hire / Fire Cost Cost of cost of
m f prod Prod Build up of OT,Rs H / F,Rs
pro Inv, (Rs25/U) (Rs 150/200)
d Rs(Rs
50/U)
C1 c2 c3 c4 c5 C6= c7 C8 C9 C 10 c11
=(c1 =(c2+c4 (c1-c5) Use c6&c7
-c2) )
270 250 20 50 250+50 -30 (surplus) - 30 (Inv) (i) 30*50 50*25
(i) (i)
220 250 -30 0 250 -30 (surplus) - 30-30(inv) 60*50 0
(j) (k) (b)
= (i) + (j)
2.3:
BASICS OF PROJECT MANAGEMENT……………Text Book pp192 to 223
Points:
(i) Concept of a Project
(ii) Common Terms : Activity, Node (or Event), CPM, PERT,
ProjectCrashing, Critical Path, Floats etc.
The word “Project” conjures up a mental picture which is unique,big,multi-agency built, with huge no. of
activities and a composite affair.
eg :Visakhapatnam steel plant, recent space Mars Mission India etc.
In yester years, we had great projects, such as Egyptian pyramids, Tajmahal, Bhakra-NangalDam
,Kalpakkam Atomic Power Project etc.
Exhibit 3 Egyptian Pyramids Exhibit4 Tajmahal
1. Project: Unique one-time operations designed to accomplish a specific set of objectives in a limited
time frame.
Egs: Construction of hospital, ship, R&D for launching a missile, new project, Design &Development of
new product, Chandrayan, preparation for UPSC Exam….
Activities can be interdependent. Eg: Painting work activity for a wall is done only after wall construction)
(called serial activities)
Some activities are done in parallel. Except rarely, the project events are not Sequential in nature
• While wall is under construction, Purchase of paint activity can be done).
Other types of diagrams:
These are Activity on the Arrow System(AOA),which is a Common variety & Activity on Node
system (AON). In network diagram form, generally activity is indicated as Arrow.
These are shown below.
Dummy Activity :
At times, a non-existing & imaginary activity is required to be incorporated. This is called “Dummy
Activity”.
This ensures no loose ends in the network
Completion of Project :
A project is said to be completed, only if all the activities are completed. Some will be serial and some
parallel activities. This is to be visualized,for drawing the project network.
Information required for drawing of (Project) Networks :
(i)List all the activities
(ii)Examining Activity interdependencies
(iii)Making of Time Estimates
Method : Critical Math method (CPM)
Power plant project example :
Activity Activity Activity Activity Time estimate
Code Description Dependency on (most likely) ,” m”
(start &end nodes) (Time,in Months)
A 1-2 Designing of plant Nil 12
F 4-5 Manufacturing C 18
Generator by vendor
G 4-6 Preparation of C 5
opern& maintenance
manuals
H 5-7 Installation of E,F 4
Generator
Arithmetical Total 81
Note: Column (4) gives the dependency relationships of activities. ie, if an activity is to commence after
completion of another activity (in Serial), or 2 (or more) activities can start at the same time( in Parallel),
or an activity can start independently (Eg : Starting activities).
In the eg above, activity (1-2) which is A, does not depend on start or end of any activity. So the project
network is drawn starting with A .
It is seen earlier that an activity has a starting and an ending node (2 nodes).This is as shown .Similarly,
the last Activity(7-8) which is J should appear at the end .
Note : It is seen that , there will always be one start node (initial one) at the beginning end and a finish
node (Final one) at final end.
(B) Project Network :
Method : Program Evaluation and Review Technique (PERT)
F 4-5 Manufacturing C 15 18 30
Generator by vendor
G 4-6 Preparation of C 3 5 8
operations&
maintenance manuals
H 5-7 Installion of E,F 2 4 8
Generator
I 6-7 Train the employees D,G 6 9 12
(c) what is the probability that it will take more than 55 months ?
To determine probabilities of any other completion time , it is required to calculate the variances of the
distribution of completion times along THE ACTIVITIES ON THE CRITICAL PATH, sum them and
estimate Sigma. Sigma= square root of(sigma varience)=sqrt of (1.00+32.11+4.00+1.00+2.78)=6.4
months. Z= (Tx-TE)/Sigma=(55.00-48.00)/6.4=1.09
From Z graph, for normal distribution,P(X>Tx)=0.5000-0.3621=0.1379
Hence, the Probability=0.14
PERT NETWORK -A NOTE:
This probability computation is of utmost importance to top management & Managers to intervene,
if& when needed.
This is how PERT Network is found more useful than CPM Network.
How ever, for simple projects or projects which are repetitive(like building construction projects),CPM
will serve the purpose.
Use : Floats are used to divert resources from “Non-Critical” to “Critical Activities” thereby
ensuring Total Project completion in “Time”.
• Crashing Project Networks: It is meant to reduce the normal project duration to the desired shorter
duration.For this purpose,the activities on the critical path are crashed(reduction of activity
time duration), by the use of additional resources/expenses.
A net work has 4 following activities.The minimum feasible time and for achieving this, the costs to be
incurred/day to crash project duration are as given.If fixed project costs are Rs 90/Day, what is the lowest
cost- time schedule?,
PRACTICE PROBLEM-2 :
CIVIL CONSTRUCTION OF A HOUSE:
(1) Draw “PROJECT NET WORK”,
(2) How many “CRITICAL PATHS” are there ?identify the“CRITICAL PATH / PATHS “
(3) Compute the ESTIMATED COMPLETION TIME (LIKELY COMPLETION DURATION /
PERIOD)
(4) Find & List-out the SUCCESSOR ACTIVITY/ ACTIVITIES for Each Activity.
&(5)Also, INCORPORATE reasonable cost for each ACTIVITY ( in Lakh Rs) and compute TOTAL
PROJECT COST.
Civil construction of a house(along with immediate predecessor details)
Activity Activity This activity Activity
Code Description Depends on: Duration
(No. of days)
A Design/Approval of plan ----- (Nil) 8
B Make foundation/build super structure A 12
C Select &order Electrical & other accessories A 4
D Wiring of the building B 2
E Carpentry works B 8
F Laying of Roof D 2
G Wall plastering/laying floors/Painting E,F 3
H Fixing of fittings(Sanitary, electrical etc) C,G 2
I Giving power and water connections for the site E,F 2
J Final polishing ,testing & handing over I,H 2
PRACTICE PROBLEM-3:
NEW PROJECT LAUNCH OF PRODUCT:
(1) Draw “PROJECT NET WORK”,
(2) How many “CRITICAL PATHS” are there ?identify the“CRITICAL PATH / PATHS “
(3) Compute the ESTIMATED COMPLETION TIME (LIKELY COMPLETION DURATION /
PERIOD)
(4) Find & List-out the SUCCESSOR ACTIVITY/ ACTIVITIES for Each Activity.
&
(5)Also, INCORPORATE reasonable cost for each ACTIVITY ( in Lakh Rs) and compute TOTAL
PROJECT COST.
New Project Launch of Product (along with immediate predecessor details)
PRACTICE PROBLEM-4 :
A Construction Co. has listed down various activities involved in constructing a community hall(along
with immediate predecessor details)
PRACTICE PROBLEM-5 :
PRACTICE PROBLEM-6 :
A PROJECT NETWORK:
(1) Draw “PROJECT NET WORK”.(2) How many “CRITICAL PATHS” are there ?identify
the“CRITICAL PATH / PATHS “(3) Compute the ESTIMATED COMPLETION TIME (LIKELY
COMPLETION DURATION / PERIOD) (4) Find & List-out the SUCCESSOR ACTIVITY/
ACTIVITIES for Each Activity.
A Project network comprises the following activities.
Activity Code Activity Duration(No. of Weeks)
1- 2 2
1- 4 6
1- 3 12
3- 5 4
2- 4 dummy activity
5- 6 2
2- 7 4
5- 7 dummy activity
4- 8 6
6- 8 8
7- 8 8
2.4
(IV)MAINTENANCE MANAGEMENT
Points :
(i) Concept of Maintenance management
(ii) Terminology : %Availability,% Utilisation , Maintenance Crews,(MTBF etc.
(iii) Areas of Maintenance management
(iv)Types of Maintenance management
(v) Preventive Maintenance Vs Breakdown Maintenance
(v) Practical Problems on Maintenance management
(iii) Summary
MAINTENANCE OBJECTIVE : Adding value through Maximisation of Availability of FACILITY.
POINTS :
(i)Types of Maintenance, Costs associated ; Replacement of Facilities, Failure of deterministic type of
items & Stochastic types, Reliability concept;
(ii)Measurement; Preventive Maintenance Hours, Break Down Hours, M.T.B.F(Mean Time Between
Failures)…
(iii)MIS for Maintenance. Management;
(iv)TPM & its Pillars, Organisation chart for Maintenance. Management.
EQUIPMENT AVAILABILITY &UTILIZATION CONCEPTS:
Ex 1:
1 Shift Operation: (1 year old Motor Cycle’s) Use by College student V/s (1 year old Motor Cycle’s) Use
by Medical Sales Representative
AND
Ex 2:
1 Shift operation:(4 years old Car’s) Use by Co.Executive V/s (4 years old Car’s(Cab) Use by Cab
operator.
Note : In the diagrams shown:
Ellipse…………represents Break down period &Rectangle……… represents Break down period.
Ex 3: 3 Shifts operation:
1 year old Cab’s Use
Vs 4 years old Cab’s Use
S. SSH= BDH= MAH= MUH= %A %U %U Co
No Example Stnd Break Mc McUtili =% =% / m
Scheul Down/M Availabl zed Availabil Utilization %A me
ed ntnce e Hours Hours ity nts
Hours
Hours
c1 (c2) (c3) (c4) (c5) (c6) (c7) (c8) (c9) (c1
0)
1 Student, 8 0.083 8-0.083 0.5 (480- 30X100/ (30)X100/4
M/Cy1 Hours Hours =7.917 Hours= 5)X100 480= 75=
yr old = = Hours (30 /480= 6.25% 6.315%
(1Shift (480mi (5 mins) =(480- mins) 98.95%
oprn) ns) 5=475mi
100% ns)
(Base)
2 Med 480m= 30 min 450min 180min (480- 180X100/ (180)X100/
Repr, 30)X100/ 480= 450=
M/Cy1 100% 480= 37.5% 6.315%
yr old 93.75%
(1Shift
oprn)
3 Exec,M/ 480m= 15 min 465min 90min (480- 90X100/ (90)X100/4
Car, 15)X100/ 480= 65=
4 yrs old 100% 480= 18.75% 19.35%
(1Shift 96.87%
oprn)
4 Cab 480m= 60 min 420min 240min (480- 240X100/ (240)X100/
Oprtr 60)X100/ 480= 420=
M/Car, 100% 480= 50.0% 57.15%
4 yrs old 87.5%
(1Shift
oprn)
5 Cab 3X 90 min 1440- (1480- Mc. Available
oprtr, 480= 90=1350 90)X100/ time= 1350 mins,
M/Car, , 1440 min 1440= No. of Br.Downs=
1 yr old m= 93.75% 3Nos.
Hence, MTBF=
(3 Shifts 100% 1350/3=450
Oprn) mins(7.5 hrs). ie,
on the average,
once in 7.5
hours,there is a
Break down.
6 Cab 210 min 1440- (1440- Mc. Available
oprtr, 480m= 210=123 210)X10 time= 1230 mins,
M/Car, 0 min 0/1440= No. of Br.Downs=
5yrs old 100% 85.42% 6Nos.
(3 Shifts Hence, MTBF=
Oprn) 1230/6=450
mins(7.5 hrs). ie,
on the average,
once in 3 hrs 25
mins ,there is a
Break down.
COMPUTATIONS OF SSH,MAH ,MUH & MUH / MAH ,at a Glance
S. Machine Us Sc Shi SSH = BDH = MA = %A MU = %Ut For
N er hed fts/ (Sch (Sch (Break (Brea H (Mac vail H(M (Ma ilisat Top
o ule Da d d Down kDo (Mac hine abil achi chin ion Mgt
y Shift Shift Hours) wnM hine Avail ity ne e =U %U/
Hour Mins ins Avail able =A Utilis Utili % %A
s ) able Mins % ed sed
Hour ) Hour Min
s) s) s)
c1 c2 c3 c4 c5 c6= c7= c8 c9=c C10= c11= C10 c13 c14 C15= C16=c
c5X8 c6X6 8X60 c6-c8 c10X =c1 =c1 c13X 15X10
0 60 0X1 3X6 100/ 0/
00/ 0 c6 C12
c6
1. Mobike, Stu Da 1 8 480 0.083 5 7.917 475
a 1Yr Old den y =8-.0
t 83
2. Mobike, M/ 1 8 480 0.500 30 7.500 450 7.5x 3.00 180 3X10 37.50
a 1Yr Old Re Da =8-.0 100/ /8= X
pr y .5 8= 37.50 100
93.7 /0020
5 93.75
=40.0
2. Mobike, M/ We 6 48 2880 3.000 180 45.00 2700 93.7 18 180 37.50 40.0
b 1Yr Old Re ek( 0=48 5
pr 6d) .0-.3.
0
2. Mobike, M/ Mo 25 200 1200 12.500 750 187.5 1125 93.7 75.00 180 37.50 40.0
c 1Yr Old Re nth 0 00=2 0 5
pr (25 00-
d) 12.5
2. Mobike, M/ Ye 30 2400 1440 150.00 9000 2250. 1350 93.7 900.0 180 37.50 40.0
d 1Yr Old Re ar( 0 00 0 000= 00 5 0
pr 30 2400
0d) -150
3. car,4Yrs 1 8 480 0.250 15 7.750 465 7.75 1.50 90 1.5*1 18.75
a Old Ex Da *10 00/8 X
ec y 0/8= =18. 100 /
96.8 75 96.8=
8 19.4
4. cab,4Yr Ca Da 1 8 480 1.000 60 7.000 420 7X1 4.00 240 4X10 50.0X
a s Old b y 00/8 0/8= 100/8
opt =87. 50.00 7.5=
r 50 57.1
5. cab,4Yr Ca 3 24 1440 1.500 90 22.50 1350 22.5
a s Old b Da 0 X10
opt y 0/24
r =93.
75
6. cab,5Yr Ca 3 24 1440 3.500 210 20.50 1230 20.5
a s Old b Da 0 X10
opt y 0/24
r =85.
42
COMMENTS: More the work (or UTILIZATION) for EQUIPMENT (Stress), the more will be the
BREAK DOWNS.
So, if more emphasis is given to have REGULAR PREVENTIVE MAINTENANCE , the lesser will be
the BREAK DOWNS.
Ex4:MTBF Concept:
Comments:
(i)Maintenance: The function of production management, that is concerned with day -to-day problem of
keeping the physical plant in good working condition.
(ii)Maintenance management: Concerned with planning, organising and directing the resources in order
to control the availability and performance of the industrial plants to some specified level.
1. Minimizing the loss of productive time because of equipment failure (i.e., minimizing idle time of
equipment due to break down).
2. Minimizing the repair time and repair cost.
3. Minimizing the loss due to production stoppages.
4. Efficient use of maintenance personnel and equipments.
5. To keep all productive assets in good working condition.
6. Prolonging the life of capital assets by minimizing the rate of wear and tear.
7. To maximize efficiency and economy in production through optimum use of facilities.
8. To minimize accidents through regular inspection and repair of safety devices.
9. To minimize the total maintenance cost which includes the cost of repair, cost of preventive
maintenance and inventory carrying costs due to spare parts inventory.
10. To improve the quality of products and to improve productivity.
AREAS & TYPES OF MAINTENANCE
AREAS OF MAINTENANCE
(i)Civil Maintenance
(ii)Mechanical Maintenance
(iii)Electrical Maintenance
TYPES OF MAINTENANCE
(i)Break down maintenance or corrective maintenance,
(ii)Preventive maintenance,
(iii)Predictive maintenance,
(iv)Routine maintenance,
(v)Planned maintenance
(i)BREAK-DOWN-MAINTENANCE:
Corrective or remedial maintenance that occurs when or after equipments or machines fail and must be
repaired on an urgent basis.
(ii)PREVENTIVE MAINTENANCE:
Maintenance activities under taken before the machines or equipments fail. Aims to minimise the
possibility of unanticipated or major break-downs.(Inspection, servicing,lubricating,greasing, mnt of
buildings etc.,
(iii)PREDICTIVE MAINTENANCE:
Modern approach to preventive maintenance using sensitive instruments to predict anticipated failure of
machines and equipments.(vibration, temperature, pressures etc.,)
(iv)ROUTINE MAINTENANCE:
This includes activities such as periodic inspection, cleaning, lubrication, and repairs.(Running
maintenance, when m/c is working, Shut down maintenance)
(v)PLANNED MAINTENANCE :
Maintenance activities that are carried out according to a predetermined schedule. Also known as
scheduled maintenance or productive maintenance.(BDs do not occur in a planned manner, but
maintenance work can be planned in advance , which REDUCES sudden BDs needing emergency
maintenance).
MAINTENANCE POLICY:
ECONOMIES OF MAINTENANCE
At the optimal level of maintenance preventive maintenance cost equals breakdown maintenance cost.
TPM Combines total quality management concept with strategic view of maintenance from process and
equipment design to preventive maintenance.
Request arrival Repair time reqd, Repair time Repair time ends M/c down time
time with one begins (clock (clock time) with one crew(idle
crew(mins) time) time +repair
time)=Total time
01:30 60 01:30 02:30 Nil+1.00=1.00
02:00 20 02:30 02:50 0.5+0.33=0.83
04:15 45 04:15 05:00 Nil+0.75=0.75
04:30 120 05:00 07:00 0.5+2.00=2.50
05:30 30 07:00 07:30 1.5+0.50=2.00
07:00 10 07:30 07:40 0.5+0.166=0.666
Total 3.00+4.746=7.75