Professional Documents
Culture Documents
Network Diagrams help justify your time estimate for the project.
Since network diagram of a project shows how activities are
interrelated with each other from the beginning of the project till the
end, it will be very beneficial for calculating the overall project
duration. After the critical path of the project is determined, activities
on the critical path will give us the total duration of the project
respectively.
Network Diagrams aid in planning, organizing and controlling.
Since all project activities are shown in sequence with relevant
interrelationships, the network diagram of a project will help the
project manager and team during planning and organizing. Network
diagram will be useful during project execution as well since it is a
snapshot of the project activities tied with the dependencies.
Here, activity A is a predecessor, and activity B is the successor activity. If something happens to the
predecessor activity, it impacts the successor activities. In this way, successor activity B is a
dependent activity on the predecessor activity A. So, you can see here – A is an independent
activity. Activity A logically comes before activity B in the schedule. The relationships between A and
B activity are either of four types:
Finish-to-start (FS)
Finish-to-finish (FF)
Start-to-start (SS)
Start-to-finish (SF)
We link the predecessor (Activity A) with the first character. It defines the state of processor activity.
And, in the same way, we link successor (Activity B) with the second character. The character defines
the rule which we have to apply on the successor activity.
Let’s discuss these four relationships one by one:
Finish-to-start (FS)
“A logical connection in which a successor venture cannot start until a predecessor activity has
finished.”
If you have a question – which is the most commonly used logical relationship? Yes, Finish to Start is
the most commonly used logical relationship.
You can see, this relation constraint does not impact the independent activity. It only affects the
dependent, so in our case, it is activity B.
Finish-to-start (FS)
From this FS relationship, F shows the finish state of activity A, and at this state, activity B can be
started. The second character ‘S’ is the rule on a successor to make it dependent on the Finish state
of the successor activity.
You cannot start development until you finish the design. Here, development is the dependent
activity on the design activity. Design is the predecessor activity, and its finish state can only start the
development activity.
Start-to-start (SS)
“A logical relationship in which a successor activity cannot start until a predecessor activity has
started.”
So if activity B is bound to this relation, this means it cannot start till the predecessor (independent)
activity A is started. The predecessor activity B start is dependent on the start state of successor
activity A. The start of activity A drives the start of activity B.
Start-to-start (SS)
Example:
The activity of marketing brochure preparation cannot start until user documentation has begun. In
this way, after the commencement of activity A, both A and B can go in parallel.
If you are curious to know in what could be the practical cases to make activity B dependent on the
start state of activity A –
Finish-to-finish (FF)
“A logical relationship in which a successor activity cannot finish until a predecessor activity has
finished.”
So if activity B is bound with this relation it means it cannot finish till the predecessor (independent)
activity A is finished. So, B needs to finish its deliverable and keep working with A till the time A is
not done.
Like, the broadcast of a football match cannot finish until the match is finished. So the match is not
depended in broadcast, but the broadcast is. If the match takes longer than the initially estimated
time broadcast will also continue till that time.
It could be possible that the broadcast is continued even after the match is finished. The broadcast
could be continued to discuss highlights and other things. It means it will end after successor
activities but necessarily immediately.
Start-to-finish (SF)
“A logical connection in which a successor activity cannot finish until a predecessor activity has
started.”
So if activity B is bound to this relation in which it cannot finish till the independent activity A starts.
It looks confusing because in typical cases, predecessor activity gets performed before the successor
activity. But, in this case, the successor is happening first. But even if the successor is happening first,
the predecessor is not at all restricted by successor activity. It is independent. But the successors
(Activity B) cannot finish till the predecessor starts (Activity A starts)
Start-to-finish (SF)
“The initial security guard shift (successor) cannot finish until the second security guard shift
(predecessor) starts.”
It is crucial to understand the basic concepts underlying these four logical relationships or
dependencies between project activities. So, make sure you work on them right from the start and
discuss all the tasks and schedule them accordingly.