You are on page 1of 6

2015 IEEE/SICE International Symposium on System Integration (SII)

December 11-13, 2015. Meijo University, Nagoya, Japan

Distribution Control Systems for Data Center


Montri Wiboonrat
College of Graduate Study in Management
Khon Kaen University, Bangkok Campus
Bangkok, Thailand
mwiboonrat@gmail.com, montwi@kku.ac.th

Abstract—System uptime is the crucial objective of data center Strategic planning of data center is not an attempt to
operations. Distribution control system (DCS) proposes design eliminate risk or to forecast what the data center will look like
topologies and attributes for critical network, electrical, and in fifteen years, it is taking action to understand what risks to
mechanical systems to attain these availability. Data center take and what paths will align with the business. Partial
infrastructure management (DCIM) is hardware and software
flexibility concept is advantage the design cost-effective. Tier
tools for monitor, measure, control, manage performance,
utilization and energy consumption through direct digital classification design decision has as impact on the investment
control (DDC) devices. DCIM provides DCS function for all IT- and long-term operations. Designing a cost effective data
related equipment (demand side) and facility infrastructure center is greatly dependent on the mission critical
components (supply side). This paper was derived from applications of the enterprise. Data center design and build
standard changed requirements from Tier Classification which can be classified into 2 concepts, design for scalability or
will be affected data center design in the future. Understanding modular design. For this reason, data center project (DCP)
integrity constraints are the key to optimize demand side and requires different strategic approach [2]. It is differed from
supply side through DCIM distribution control system for data enterprise to enterprises. Without proper DCP, a design and
center. This paper purposes autonomous demand and supply
build project can experience delays, increased costs and
response model through DCS for increasing energy efficiency
and resource utilization while sustains data center operations frustrated team members. Regardless of project size, activities
and protect critical loads. need to be structured and standardized so everyone is on the
same page and the project outcome is predictable. Strong
Keywords—distribution control systems; direct digital control; project management makes sure nothing slips through the
data center; data center infrastructure management cracks or any effort is duplicated. When building or
upgrading a data center’s physical infrastructure, project
I. INTRODUCTION management provides the foundation for a successful result.
Data centers are highly complex things, and complex Its purpose is to structure the project into phases, coordinate
things can quickly become unmanageable [4][5][6]. Modular the work of the entire team and monitor progress. A typical
design allows you to create highly complex systems from team might consist of the end users, consultants, hardware
smaller, more manageable building blocks. These smaller and software providers, general contractor and more.
units are more easily defined and can be more easily replicated The new trend of data center infrastructure management
[7]. They can also be defined by even smaller units, and you (DCIM) was just emerging during the past a few years.
can take this to whatever level of granularity necessary to DCIM solution provides measurable to improved system
manage the design process. Tier IV fault tolerance system is availability, capacity planning for provisioning, energy
designed for autonomous response to a failure and load efficiency, resource utilization, and productivity for remote
demand which is more than just engineering the most management. DCIM as a tool for monitor, measure, manage
technically correct or best system [1][3]. However, customers
and/or control data center utilization and energy consumption
may want is not the best system, they really need is the most
between demand and supply sides of all IT-related equipment
practical system that is focused on and addresses our particular
basics. (such as servers, storage and network switches) and facility
infrastructure components (such as power distribution units
Data center facility infrastructure has performed as the (PDUs) and computer room air conditioners (CRACs).
foundation of information technology that facility This paper was derived problems from the new
infrastructure has been evolutional throughout the last several requirements from Tier Classification [3] subject to; ignoring
years and transformational after the beginning of the 21 st main power utility sources (independence/supply); adding
century. The data center life cycle is around 10-15 years [10]. continuous cooling system by Tier 4 needs to provide makeup
However, within 5 years technology will be changed, thus water up to 12 hours; and autonomous response to a failure
most data center design is flexible and easily upgradable. and critical load. The solution of imply DCIM to adjust
Therefore, it is critical to a successful long-term design.

978-1-4673-7242-8/15/$31.00 ©2015 IEEE 789


demand and supply response was presented in this paper as a 2. Where is the best place to place a new server?
guideline for compliance with Tier Classification or BISCI- 3. Do I have sufficient space, power, cooling and
002 [2]. network connectivity to provide my needs for the next
II. BACKGROUND 6 months? Next year? Next five years?
4. An event occurred in the data center — what
A. Tier Classification happened, what services are impacted, where should
The purpose of data center site infrastructure standard is the technicians go to resolve the issue?
compliant business needs and requirements for design 5. Do I have underutilized resources in my data center?
professionals, facility installation, and operations with 6. Will I have enough power or cooling under fault or
objectives and effectiveness imply for identifying the maintenance conditions?
anticipated performance of different data center site
infrastructure design topologies, as illustrated in Figure 1.

Small Businesses
99.671% Uptime
28.8 Hours Downtime Per Year
No Redundancy
1 12 Hours Engine-Generator Protection

Medium-size Businesses
99.749% Uptime
22 Hours Downtime Per Year
Partial Redundancy in Power and Cooling
Critical Components
2 12 Hours Engine-Generator Protection

Large Businesses
99.982% Uptime
1.6 Hours Downtime Per Year
N+1 Concurrent Maintenance
12 Hours Engine-Generator Protection
3
Enterprise Corporations
99.995% Uptime
2.4 Minutes Downtime Per Year
2N+1 Fully Redundant with Compartment
and Automatic Fault Tolerance
12 Hours Engine-Generator Protection
4 12 Hours Continuous Cooling

Figure 1. New requrements for Tier classification.

1) Tier 3: Concurrently Maintainable Site Infrastructure


A concurrently maintainable data center requires Figure 2. Tier 3 topology.
redundant critical components and multiple independent
distribution paths serving the critical environment. Only one
distribution path is required to serve the critical load at any
time and twelve hours of on-site fuel storage for ‘N’ capacity
[7], as shown in Figure 2.
2) Tier 4: Fault Tolerant Site Infrastructure
A fault tolerant data center requires multiple, independent,
physically isolated systems (compartment) that provide
redundant capacity components and multiple, independent,
device, active distribution paths simultaneously serving the
critical loads. The redundant critical components and diverse
distribution paths shall be configured such that ‘N’ capacity is
providing power and cooling to the critical loads after any
distributed path failure [7], as demonstrated in Figure 3.
B. Data Center Management Components
DCIM is the convergence of previous generations of
purely facilities-oriented power management, physical asset
management, network management, and financial
management and planning solutions for data centers. There are
many benefits for implementing a DCIM solution. The
primary components of data center management consist of:
Figure 3. Tier 4 topology.
design, operations, monitoring, predictive, and planning, as
depicted in Figure 4. One of the primary benefits of DCIM is
the ability to answer questions such as the following [15]:
1. Where is my data center asset located?

790
1.5% of condenser water flow to sustain evaporative cooling
process [9].
C. Data Center Infrastrucutre Management (DCIM)
The autonomous response to a failure and load demand is
one of the newest technologies that apply for monitoring and
control, energy efficiency, and resource utilization inside data
center or called “Data Center Infrastructure Management or
DCIM”. DCIM defines as systems collect and manage data
refer to a data center assets, resource usage, and operational
status throughout data center operational lifecycle. This
information is distributed, integrated, analyzed, and applied
over facilities, networking, and systems in purposes that help
managers or operators meet business and service-oriented
aims and optimize the data center performance, as presented in
Figure 5. DCIM activities are performed through functions of
Figure 4. Data center management components [15]. monitoring and alarming, automation and control, modeling
and simulation, software services, and integrations.
III. NEW STANDARDS COMPLIANCE
In this paper, research was concentrated on Tier 3 and Tier
4. Since 2014, the new requirements of Data Center Tier
Classification was changed by ignoring main power utility
sources (independence) and adding continuous cooling system
by Tier 4 needs to provide makeup water up to 12 hours.
Moreover, the infrastructure controls system demonstrates
autonomous response to a failure while sustaining the critical
loads. Therefore, all new data center infrastructure changes
need to comply if data center owners prefer a certification
body from Uptime Institute.
A. Engine Generators Physical Functional Process
• Asset management
Engine generators and their ratings are governed by •

Power system
Cooling system


Monitoring and alarming
Automation and control


Availability management
Capacity management
International Organization for Standardization (ISO) Standard •

IT space
Security


Modeling and simulation
Software Services,


Change management
Crisis management
8528-1 [12]. This standard covers reciprocating internal • integrations • Integrations •

Financial management,
Integrations
combustion (RIC) engines, alternating current (AC)
generators, and associated systems. Uptime Tier Classification
for Tier III and Tier IV requires only continuous power that Figure 5. The physical layer of data center infrastructure [17].
the maximum power for which an engine-generator is capable
of delivering continuously for a constant load for an unlimited IV. DCIM INTERGRATED TECHNOLOGY
number of hours [8]. Continuous power (COP) means the The integration will provide an increased level of
engine-generator is able to provide power to a non-varying communications between IT Service Management (ITSM) and
load for an unlimited number of hours per year. The average DCIM platforms, providing data center managers with more
power output of the engine-generator is 70-100 percent of the efficient management of data center assets subject to, capacity
rating. The rating is designed to provide 100 percent of the management, automated provisioning, cost management,
rating for 100 percent of the data center operating hours [13]. service catalogs based, analytics and optimization, and
B. Makeup Water availability, as demonstrated in Figure 6.
Since, engine generators are designed for continuous A. DCIM Components and Functions
operations for minimum 12 hours therefore; loss of public The asset management is a key component of DCIM. A
utility power is a design condition rather than a failure mode, data center can contain thousands of assets, from servers,
as the same time, the loss of public utility water must also be storage and network devices to power and cooling
considered as a design condition. This is the critical problem infrastructure equipment. Tracking these assets is an ongoing
for evaporative cooling situations because of the volume of and often monumental task. A DCIM can be hardware-based
water required to maintain functional water level in cooling and/or software-based and is used to monitor a data center or
towers. For assumption each 1 megawatts (MW) of cooling computer room. Direct digital control (DDC) or device
load (approximately 285 refrigeration tons) requires about 855 communication is typically done using SNMP, although some
gallons per minute (gpm) of condenser water flow through the data center monitoring systems can also communicate using
evaporative cooling towers. The estimating evaporation Modbus, IPMI or other protocols, as a part of IEC 61850 [20].
consumes about 1% and 0.5% for drift consumes, thus a This attribute is considered as a real-time monitoring for
source of water is required to replenish, or “makeup” around utilization of hardware component (IT and Infrastructure

791
Systems), as shown in Table I. Moreover, a real-time TABLE II. DCIM SOFTWARE VENDORS [15]
monitoring is not only analyzed capacity planning but also
applied for provisioning and maintenance to reduce mean time
to repair (MTTR) or increasing uptime.

TABLE III. DCIM HARDWARE VENDORS [15]

Figure 6. Integrated DCIM and ITSM infrastructure [16].

TABLE I. DCIM COMPONENT AND FUNCTIOINS

C. Demand and Supply Response through DCIM


Online data collection is a base for DCIM function blocks.
The data is used as input to the other functional areas,
including Asset and Change Management, Environmental
Monitoring, Power and Energy Measuring and Modeling,
Power Management and IT Service and Systems
Management. A data management layer integrates data from
the lower layers to facilitate reporting as well as providing
input to higher level planning, forecasting and optimization
layers, as represented in Figure 7. Figure 8 presents DCIM
distributed systems among facility network, IT management
network, data center network, and enterprise network.

B. DCIM Software and Hardware Vendors


IEC 61850 is a standard for the design of electrical
substation automation [20]. All DCIM vendors must be
complied with this standard. They are many DCIM software
and hardware vendors in the market. However, compatibility
of products is the primary concern when select DCIM
software and equipment rather than investment and Figure 7. Demand and supply response through DCIM [16].
maintenance. Table II and III are listed vendors on this DCIM
business.

792
management and energy management, with a focus on IT
assets and the physical infrastructure needed to support them,
as presented in Figure 9. Tier 4 requires autonomous response
DCIM DCIM
to failure, which encompasses the ability to detect a
fault, isolate the fault and sustain operations with
DCIM
alternate systems that mean real-time monitoring and control
will handle on this data before alert and distributed the signal
DCIM DCIM
to data center managers or other involved persons or other
systems such as building automation system (BAS) increase
of fire alarm or water leak. The function of autonomous
response to failure is not only prevented cascading failure
DCIM
from component to system but also reduced MTTR of
equipment and systems. This is direct function of DCIM
Figure 8. DCIM topology [14]. rather than assess management. The simple test of fault
tolerance for fuel is that ‘N’ or the needed amount of fuel for
V. ANALYSIS DEMAND AND SUPPLY RESPONSE the data center, is available after any failure. Some
Since 2014, the new requirements of Tier Classification failure scenarios of fuel systems include loss of power, leaks,
are changed that effect to the new design of data center which failure of components or fire. Leak detection of fuel systems
require Tier Certification. This research was investigated on is crucial to fault tolerance. Fault detection may be achieved
factors that impact on data center design especially on Tier 4 using a variety of methods, but the chosen method must be
which were required continuous cooling systems and integrated with the system response to isolate the fuel leak.
autonomous response to a failure and load demand. The isolation must limit fuel loss such that the ability of
alternate systems to deliver ‘N’ fuel is not impacted. The
A. Continuous Cooling System Figure 10 shows typical system architecture used for an
Tier 4 is the only one that requires continuous cooling. integrated facility management system that integrates with
Continuous cooling for a chilled water system is generally various network, electrical and mechanical through DDC of
accomplished with thermal energy storage (TES) capability. sub system vendors, and providing a complete building
Secondary pumps and computer room air handlers (CRAHs) management system (BMS), property management system
are required to be on UPS. This can be the IT UPS or a (PMS), and energy management system (EMS) functionality.
separate, concurrently maintainable and fault tolerant,
mechanical UPS system. If the cooling system is in a
primary-direct configuration, then the primary pumps are
required to be on UPS. Moreover, for chilled water system, it
needs to consider makeup water to compensate the
evaporative cooling process. Continuous cooling for direct
exchange (DX) systems requires both the computer room air
conditioners (CRACs) and the external condensers to be on a
concurrently maintainable and fault tolerant UPS system [11].
Table IV shown about heat load of server power trends or Figure 9. DCIM supports on demand and supply response [19].
demand cooling requirements (Racks/Rows/Rooms) for
calculation continuous cooling or cooling supply from
chillers.
TABLE IV. HEAT LOAD OF SERVER POWER TRENDS [18]

B. DCIM for Autonomous Response


DCIM enables IT professionals to understand energy
consumption from a holistic data center perspective subject to
power utilization (watts), heat rejection (watts), space
occupancy, and future resource provisioning. DCIM toots
integrate facets of system management with building
Figure 10. Example of DCIM system configuration through DDC [21].

793
VI. DISCUSSION [2] BICSI-002, Data Center Design and Implementation Best Practices,
BICSI 002-2014, 2014.
DCIM has economic value depends on sizing of monitor [3] TS102120-0812, “Data Center Site Infrastructure Tier Standard:
and control points in data center (number of racks) and Topology,” Uptime Institute, LLC., 2012.
compliant with Tier Standard. This paper reveals Tier 1-3 no [4] M. Wiboonrat, “An Optimal Data Center Availability and Investment
need to comply with fault tolerance procedure only Tier 4 Trade-Offs,” Software Engineering, Artificial Intelligence, Networking,
and Parallel/Distributed Computing,” SNPD 2008, The 9th ACIS
required as statement “site must be designed and operated to International Conference on, pp. 712-719, 2008a.
tolerate the cumulative impact of every site infrastructure [5] M. Wiboonrat, “Transformation of system failure life cycle,” Int. J. of
component, system, and distribution path disrupted by failure Management Science and Engineering Management, Vol. 4, No. 2., pp.
[22],” that implied Tier 4 needs DCIM to define, measure, 143-152, 2008b.
analyze, improve, and control in operation processes. [6] M. Wiboonrat, “An Empirical Study on Data Center System Failure
However, investment in DCIM increases capital expenditure Diagnosis,” The 3rd International Conference on Internet Monitoring
and Protection, pp. 103-108, 2008c.
(CapEx) and long-term operational expenditure (OpEx) that
[7] M. Wiboonrat, “System Reliability of Fault Tolerant Data Center,” The
reflects on total cost of ownership (TCO) and return on 5th International Conference on Communication Theory, Reliability,
investment (ROI). and Quality of Service. Chamonix/ Mont Blanc. France. 29 April- 4
May, 2012.
VII. CONCLUSION
[8] ATD104100-110, “Accredited Tier Designer Technical Paper Series:
Data center design for Tier 3 and Tier 4 Certification Engine-Generator Ratings,” Uptime Institute, LLC., 2010.
needs to comply with all new Uptime Tier Classification [9] ATD101100-110, “Accredited Tier Designer Technical Paper Series:
standard requirements. The three major requirements changed Makeup Water,” Uptime Institute, LLC., 2010.
were; the main power utility sources (independence) is [10] TS106130-0413, “Data Center Site Infrastructure Tier Standard:
Operational Sustainability,” Uptime Institute, LLC., 2013.
generators 2(N+1) with continuous type not power utilities;
[11] UI109110-411, “Accredited Tier Designer Technical Paper Series:
adding continuous cooling system by Tier 4 needs to provide Continuous Cooling,” Uptime Institute, LLC., 2011.
makeup water up to 12 hours, both chiller water (needs [12] ISO Std. 8528-1:2005, Reciprocating Internal Combustion Engine
makeup water) or direct exchange (DX) models; the Drive Alternating Current, Generating Sets, 2005.
infrastructure controls system demonstrates autonomous [13] R. Marfell, “Demystifying Generator Set Ratings,” Caterpillar, October
response to a failure while sustaining the critical loads. These 2012.
three requirements need to fulfill by data center infrastructure [14] Decathlon, “Data center infrastructure management: Operational
management (DCIM) with function of demand and supply intelligence for agile business,” ABB Inc., 2013.
response through distribution control system (DCS) function [15] D. Cole, “Data Center Konwledge Guide to Data Center Infrastructure
Management (DCIM),” Data Center Knowledge, May 2012.
of DCIM. The objectives of DCIM are brings the entire data
[16] A. Lawrence and R. Ascierto, “The DCIM marketplance: Suppliers,
center operation into a unified view while system allows data products and ecosystems,” 451 Research, 2013.
center operators and managers to perceive information across [17] Raritan, “An Introduction to Data Center Infrastructure Management,”
multiple disciplines that enable them to make decisions. Raritan Inc., 2010.
Moreover, DCIM is designed for monitor, measure, manage [18] ASHRAE, “Datacom Equipment Power Trends and Cooling
and/or control data center utilization and energy consumption Application,” 2nd Edition, 2012.
between demand and supply sides to improve power usage [19] Siemens, “Leveraging DCIM to Increase Engergy Efficiency and
Savings,” Siemens AG, August 6, 2013.
effectiveness (PUE). The intelligent functions of DCIM help
[20] IEC 61850, Communication Networks and Systems in Substations,
data center operations subject to resource utilization, energy Technical Committee 57, IEC, 2010.
efficiency, preventive maintenance, improve uptime, reduce [21] Decathlon, “Data Center Infrastructure Management: Decathlon
operation costs, and easy to management. System Guide,” ABB Pte. Ltd., January 11, 2015.
[22] W. P. Turner, J. H. Seader, and V. E. Renaud, “Data Center Site
REFERENCES Infrastructure Tier Standard: Topology,” Uptime Institute, LLC., 2012.
[1] TIA 942, Telecommunications Infrastructure Standard for Data
Centers, Telecommunictions Industry Association (TIA), 2014.

794

You might also like