Lesson: Understanding New Implementation S/4HANA On Premise

Workstream Artifact Specifics


Extensibility Project Procedure - Custom Code Management process in SAP Solution
Custom Code Man- Manager shall be ready and SAP Solution Manager
agement Standard shall be configured before starting development into
SAP S/4HANA On-Premise system landscape.

Data Manage- Master Data Catalog It is important to create full list of Master Data Ob-
ment jects which are in scope of migration and assign
Business Data Owner and Master Data Manager to
each to ensure efficient data cleansing and success-
ful migration.

Technical Ar- System Setup (Devel- Development system is installed and technically con-
chitecture opment) - System figured. Based on results from Fit-Gap workshop
and Infra- Configuration Scope Items are activated. System is assigned to
structure Landscape Management within SAP Solution Manag-
er.

Table 49: Realize


Workstream Artifact Specifics
Solution Adop- Value Audit Report Value Expert shall verify whether decisions and ef-
tion forts are spent on priorities set for the project.

Testing “Functional Test %”, According to recommendations from Agile method-


“Integration Test %” ologies (for example, SCRUM) automated function-
al tests shall be developed for any configuration
change or customization. It is recommended to use
BPCA tools for narrowing down testing scope to
changed functions only.

Data Manage- “Training Data %” It is important to prepare data, which shall be used
ment for training End-Users. Define scope and volumes
Data Migration for
required for successful testing.
test data (Legacy--
>QAS) – Plan When testing new or configured functions with busi-
ness data (e.g. Unit Test is done without it) this data
shall comply with requirements of stakeholders,
who will make decision on success or failure of
these tests.

Technical Ar- System Setup (Pro- It is important to safeguard identical configuration


chitecture and ductive System) - for DEV-to-QAS-to-PRD systems. All transportable
Infrastructure System Configuration changes shall be transported and manual configura-
tion should be verified.
“Performance Test
%” Performance test should verify Sizing used to pur-
chase HW. In case actual realization of business re-
quirements led to high HW resources consumption
risk budget shall be used for expanding HW.