PROJECT : THE BIG BOX

TITLE : THE BIG BOX CONTRACTOR-CONSULTANT


COORDINATION MEETING NO.01 (CCCM MOM 02)

DATE : 28-Feb-17

TIME : 9.45AM - 10.45AM

VENUE : MEETING ROOM, CITRINE SITE OFFICE

PRESENT : Mr. Yabe Akira SCSB /


Mr. Kevin Lee Kok Thang SCSB /
Mr. Low Ting Hai SCSB /
Mr. Teoh Ming Hui SCSB /
Mohd Alhafiz Abdullah SCSB /
Nathan Murugasan SCSB x

Ms. Nadiah Ghani SAA /


Mr. Joseph SAA x

Ir. Goh Wei Hong JRK /


Ms. Thiu Soo Phui JRK /

Ir. Daniel Lim ADC /


Mr. Jonathan ADC x

Ms. Nabila JRD /


Mr. Kamil JRD /

Minuted by,
Mohd Alhafiz Abdullah
Sunway Construction Sdn Bhd.

Reviewed by,
Kevin Lee Kok Thang
Sunway Construction Sdn Bhd.
The Big Box Contractor-Consultant-Coordination Meeting No.2
Minutes of Meeting (CCCM MOM 02)

No Agenda Action by Date Required

1 Authoroties Submission Matters

1.1 Discussion with IRDA / MPJBT held on 20-Feb-17.


P&D
Planner to resubmitted pre-PDRC plan by 26-Feb-17

1.2 SMSB informed Pre-PDRC Meeting schedule on 27-Feb-17. Info

1.3 Authorities submission timeline refer attachment.

2 Civil & Structural Matters

2.1 Piling Work

a Piling package budget approved.


Target to start work on 6-Mar-17. SC 3-Mar-17
SC will proceed to award piling contractor

b SAA to demarcate hotel footprint and forward to all, in order for JRK to
exclude Hotel area from piling work.
SAA 28-Feb-17
SAA advise to follow KM plan, at the same time SAA will email the
softcopy of KM plan to JRK

c JRK request the size and location for loading / unloading area, to proceed
with piling load design.
Retail to confirm. SAA 28-Feb-17
SMSB inform to follow current layout location. SC advise JRK to follow
current design. SAA to forward detail to JRK.

d SAA requested to confirm Arcade layout & cinema, as the layout will
affect the pile location.
Info
SAA inform no comment received from Retail team.
SAA advise JRK to follow current design.

e JRK request heavy traffic route to cater heavy vehicle access. SAA to
advise and forward the drawing to all. SAA 28-Feb-17
Clarified verbally by SAA. SAA to forward detail drawing to JRK.

f JRK request loading allocation for façade signage.


SC proposed to get info from Sunway Velocity signage loading. JRK / Retail 26-Feb-17
SAA informed there will be not heavy signage.

g JRK request cross-section at interface area between building footprint


and carpark.
Info
SAA to provide drawing and forward to JRK.
JRK informed drawing received for review.
The Big Box Contractor-Consultant-Coordination Meeting No.2
Minutes of Meeting (CCCM MOM 02)

h ADC confirmed the size of RC gutter for M&E services 2.5m width, 1.2m
Info
height (1.7m height façade wall).

i SC to notify SMSB to start piling work with current design and pile
location.
Any changes / late confirmation receive after 26-Feb-17 will be an Info
additional and will be revise later.
Letter sent on 24-Feb-17

j SC request for piling construction drawing issuance from consultant.


JRK to provide drawing and forward to SC.
JRK inform construction drawing for pile will be issued 2 phase
JRK 28-Feb-17
Block 1-3 : 1-Mar-17
Block 4-10 : 3-Mar-17

2.2 Substructure / Pile cap / RC Work


2.2.1 Carpark

a JRK request routine for M&E services - pipe sleve / opening. 24-Feb-17
ADC
ADC to advise. (Pending 1)

b JRK request outlet for RWDP connection and discharge location. 22-Feb-17
SAA
SAA to advsie with drawing, and forward to all. (Pending 1)

c SC inform interlocking paver for carpark lower ground and upper ground.
Info

2.2.2 Building

a SC request SAA to finalize floor finish level (FFL) and forward finalize
SAA 28-Feb-17
drawings to all for coordination.

b Load for water tank, ADC to advice 24-Feb-17


ADC
(Pending 1)

c SAA confirmed loading bay area is 6m height with RC slab. Info

d SAA confirmed toilet 6m height, with celing board to cover M&E


info
services.

e ADC confirmed mechanical room to be 6m height RC slab, and electrical


info
room to be 4.5m height RC slab.

2.2.3 SC request construction drawing for RC and structural work.


JRK 17-Mar-17
JRK to issue construction drawing before RC contractor award.
The Big Box Contractor-Consultant-Coordination Meeting No.2
Minutes of Meeting (CCCM MOM 02)

2.2.4 SC confirm to proceed structural construction drawing without


Info
intermediate road structural design

3 Architectural Matters

3.1 SC request SAA to feedback on inquiry No. 5, 6, 7.


SAA to advise. Info
SC informed all queries replied.

3.2 SAA request supplier list for sanitary equipment from SC.
SAA 28-Feb-17
SC advice SAA to use M1 supplier list for reference.

3.3 SAA advice to to relocate chiller room.


ADC agreed. SAA / SMSB 7-Mar-17
SAA to confirm with SMSB and revise the layout.

3.4 ADC informed standard requirement for electrical room and


chiller/pump room.
Electrical room FFL 150mm heigher from external FFL SAA 7-Mar-17
Chiller/pump room FFL 100mm lower from external FFL.
SAA to incorporate in FFL drawing.

4 M&E Matters

4.1 ADC informed that earthing lighting spike will be exposed on the roof
top.
ADC 28-Feb-17
SAA request ADC to highlight the location of lighting spike, with
specification and size of equipment.

4.2 SC request ADC to compile all latest M&E drawing, and forward to all for 24-Feb-17
ADC
coordination. (Pending 1)

5 Landscape Matters

5.1 SC request JRD to submit BQ for softscape work, for costing study and
preparation. Info
Email received on 25-Feb-17

5.2 JRD are advise to follow original tree's position from SAA layout
drawings.
For any changes / proposal from landscape side, JRD required to Info
demarcate in layout, and forward to SAA for further coordination.

6 Others
The Big Box Contractor-Consultant-Coordination Meeting No.2
Minutes of Meeting (CCCM MOM 02)

6.1 SC informed MPC for substructure target on 17-Mar-17 SC 17-Mar-17

6.2 SC to establish standard flow chart format for sample submission /


SC 28-Feb-17
approval