The Contractor shall notify the Owner of his intention to undertake any site investigation and
submit details of the proposed methods and tests to the Owner before commencing work

SECTION 3

TOPOGRAPHICAL SURVEY

General

The Topographical Survey Report can be requested from the owner. This Supplementary
Information of the Bidding Document provides site data and information to serve as reference of
the Contractor for the project’s civil works final design. Similarly, the Contractor could opt if
deemed necessary, and at his own cost, to perform additional topographical survey to
investigate the topographical profiles and features of the proposed plant site including all
existing structures. The Contractor shall furnish the Owner a copy of the study for its review and
reference, in case the Contractor opted to do so

Notification

The Contractor shall notify the Owner of his intention to undertake any site investigation and
submit details of the proposed methods and tests to the Owner before commencing work

SECTION 4

SITE CONSTRUCTION

4.1 Temporary Construction Facilities

Site Security during Construction

The Contractor shall provide appropriate security arrangements to protect the site from \\

Notification

The Contractor shall notify the Owner of his intention to undertake any site investigation and
submit details of the proposed methods and tests to the Owner before commencing work
SECTION 3

TOPOGRAPHICAL SURVEY

General

The Topographical Survey Report can be requested from the owner. This Supplementary
Information of the Bidding Document provides site data and information to serve as reference of
the Contractor for the project’s civil works final design. Similarly, the Contractor could opt if
deemed necessary, and at his own cost, to perform additional topographical survey to
investigate the topographical profiles and features of the proposed plant site including all
existing structures. The Contractor shall furnish the Owner a copy of the study for its review and
reference, in case the Contractor opted to do so

Notification

The Contractor shall notify the Owner of his intention to undertake any site investigation and
submit details of the proposed methods and tests to the Owner before commencing work

SECTION 4

SITE CONSTRUCTION

4.1 Temporary Construction Facilities

Site Security during Construction

The Contractor shall provide appropriate security arrangements to protect the site from
malicious or accidental damage or loss throughout the construction and commissioning
Notification

The Contractor shall notify the Owner of his intention to undertake any site investigation and
submit details of the proposed methods and tests to the Owner before commencing work

SECTION 3

TOPOGRAPHICAL SURVEY

General
The Topographical Survey Report can be requested from the owner. This Supplementary
Information of the Bidding Document provides site data and information to serve as reference of
the Contractor for the project’s civil works final design. Similarly, the Contractor could opt if
deemed necessary, and at his own cost, to perform additional topographical survey to
investigate the topographical profiles and features of the proposed plant site including all
existing structures. The Contractor shall furnish the Owner a copy of the study for its review and
reference, in case the Contractor opted to do so

Notification

The Contractor shall notify the Owner of his intention to undertake any site investigation and
submit details of the proposed methods and tests to the Owner before commencing work

SECTION 4

SITE CONSTRUCTION

4.1 Temporary Construction Facilities

Site Security during Construction

The Contractor shall provide appropriate security arrangements to protect the site from

Notification

The Contractor shall notify the Owner of his intention to undertake any site investigation and
submit details of the proposed methods and tests to the Owner before commencing work

SECTION 3

TOPOGRAPHICAL SURVEY

General

The Topographical Survey Report can be requested from the owner. This Supplementary
Information of the Bidding Document provides site data and information to serve as reference of
the Contractor for the project’s civil works final design. Similarly, the Contractor could opt if
deemed necessary, and at his own cost, to perform additional topographical survey to
investigate the topographical profiles and features of the proposed plant site including all
existing structures. The Contractor shall furnish the Owner a copy of the study for its review and
reference, in case the Contractor opted to do so
Notification

The Contractor shall notify the Owner of his intention to undertake any site investigation and
submit details of the proposed methods and tests to the Owner before commencing work

SECTION 4

SITE CONSTRUCTION

4.1 Temporary Construction Facilities

Site Security during Construction

The Contractor shall provide appropriate security arrangements to protect the site from
malicious or accidental damage or loss throughout the construction and commissioning
Notification

The Contractor shall notify the Owner of his intention to undertake any site investigation and
submit details of the proposed methods and tests to the Owner before commencing work

SECTION 3

TOPOGRAPHICAL SURVEY

General

The Topographical Survey Report can be requested from the owner. This Supplementary
Information of the Bidding Document provides site data and information to serve as reference of
the Contractor for the project’s civil works final design. Similarly, the Contractor could opt if
deemed necessary, and at his own cost, to perform additional topographical survey to
investigate the topographical profiles and features of the proposed plant site including all
existing structures. The Contractor shall furnish the Owner a copy of the study for its review and
reference, in case the Contractor opted to do so

Notification

The Contractor shall notify the Owner of his intention to undertake any site investigation and
submit details of the proposed methods and tests to the Owner before commencing work
SECTION 4

SITE CONSTRUCTION

4.1 Temporary Construction Facilities

Site Security during Construction

The Contractor shall provide appropriate security arrangements to protect the site from
malicious or accidental damage or loss throughout the construction and commissioning
Notification

The Contractor shall notify the Owner of his intention to undertake any site investigation and
submit details of the proposed methods and tests to the Owner before commencing work

SECTION 3

TOPOGRAPHICAL SURVEY

General

The Topographical Survey Report can be requested from the owner. This Supplementary
Information of the Bidding Document provides site data and information to serve as reference of
the Contractor for the project’s civil works final design. Similarly, the Contractor could opt if
deemed necessary, and at his own cost, to perform additional topographical survey to
investigate the topographical profiles and features of the proposed plant site including all
existing structures. The Contractor shall furnish the Owner a copy of the study for its review and
reference, in case the Contractor opted to do so

Notification

The Contractor shall notify the Owner of his intention to undertake any site investigation and
submit details of the proposed methods and tests to the Owner before commencing work

SECTION 4

SITE CONSTRUCTION

4.1 Temporary Construction Facilities


Site Security during Construction

The Contractor shall provide appropriate security arrangements to protect the site from
malicious or accidental damage or loss throughout the construction and commissioning
Notification

The Contractor shall notify the Owner of his intention to undertake any site investigation and
submit details of the proposed methods and tests to the Owner before commencing work

SECTION 3

TOPOGRAPHICAL SURVEY

General

The Topographical Survey Report can be requested from the owner. This Supplementary
Information of the Bidding Document provides site data and information to serve as reference of
the Contractor for the project’s civil works final design. Similarly, the Contractor could opt if
deemed necessary, and at his own cost, to perform additional topographical survey to
investigate the topographical profiles and features of the proposed plant site including all
existing structures. The Contractor shall furnish the Owner a copy of the study for its review and
reference, in case the Contractor opted to do so

Notification

The Contractor shall notify the Owner of his intention to undertake any site investigation and
submit details of the proposed methods and tests to the Owner before commencing work

SECTION 4

SITE CONSTRUCTION

4.1 Temporary Construction Facilities

Site Security during Construction

The Contractor shall provide appropriate security arrangements to protect the site from
malicious or accidental damage or loss throughout the construction and commissioning
Notification
The Contractor shall notify the Owner of his intention to undertake any site investigation and
submit details of the proposed methods and tests to the Owner before commencing work

SECTION 3

TOPOGRAPHICAL SURVEY

General

The Topographical Survey Report can be requested from the owner. This Supplementary
Information of the Bidding Document provides site data and information to serve as reference of
the Contractor for the project’s civil works final design. Similarly, the Contractor could opt if
deemed necessary, and at his own cost, to perform additional topographical survey to
investigate the topographical profiles and features of the proposed plant site including all
existing structures. The Contractor shall furnish the Owner a copy of the study for its review and
reference, in case the Contractor opted to do so

Notification

The Contractor shall notify the Owner of his intention to undertake any site investigation and
submit details of the proposed methods and tests to the Owner before commencing work

SECTION 4

SITE CONSTRUCTION

4.1 Temporary Construction Facilities

Notification

The Contractor shall notify the Owner of his intention to undertake any site investigation and
submit details of the proposed methods and tests to the Owner before commencing work

SECTION 3

TOPOGRAPHICAL SURVEY
General

The Topographical Survey Report can be requested from the owner. This Supplementary
Information of the Bidding Document provides site data and information to serve as reference of
the Contractor for the project’s civil works final design. Similarly, the Contractor could opt if
deemed necessary, and at his own cost, to perform additional topographical survey to
investigate the topographical profiles and features of the proposed plant site including all
existing structures. The Contractor shall furnish the Owner a copy of the study for its review and
reference, in case the Contractor opted to do so

Notification

The Contractor shall notify the Owner of his intention to undertake any site investigation and
submit details of the proposed methods and tests to the Owner before commencing work

SECTION 4

SITE CONSTRUCTION

4.1 Temporary Construction Facilities

Site Security during Construction

The Contractor shall provide appropriate security arrangements to protect the site from
malicious or accidental damage or loss throughout the construction and commissioning
Notification

The Contractor shall notify the Owner of his intention to undertake any site investigation and
submit details of the proposed methods and tests to the Owner before commencing work

SECTION 3

TOPOGRAPHICAL SURVEY

General

The Topographical Survey Report can be requested from the owner. This Supplementary
Information of the Bidding Document provides site data and information to serve as reference of
the Contractor for the project’s civil works final design. Similarly, the Contractor could opt if
deemed necessary, and at his own cost, to perform additional topographical survey to
investigate the topographical profiles and features of the proposed plant site including all
existing structures. The Contractor shall furnish the Owner a copy of the study for its review and
reference, in case the Contractor opted to do so

Notification

The Contractor shall notify the Owner of his intention to undertake any site investigation and
submit details of the proposed methods and tests to the Owner before commencing work

SECTION 4

SITE CONSTRUCTION

4.1 Temporary Construction Facilities

Site Security during Construction

The Contractor shall provide appropriate security arrangements to protect the site from
malicious or accidental damage or loss throughout the construction and commissioning Site
Security during Construction

The Contractor shall provide appropriate security arrangements to protect the site from
malicious or accidental damage or loss throughout the construction and commissioning
malicious or accidental damage or loss throughout the construction and commissioning
malicious or accidental damage or loss throughout the construction and co
Notification

The Contractor shall notify the Owner of his intention to undertake any site investigation and
submit details of the proposed methods and tests to the Owner before commencing work

SECTION 3

TOPOGRAPHICAL SURVEY

General

The Topographical Survey Report can be requested from the owner. This Supplementary
Information of the Bidding Document provides site data and information to serve as reference of
the Contractor for the project’s civil works final design. Similarly, the Contractor could opt if
deemed necessary, and at his own cost, to perform additional topographical survey to
investigate the topographical profiles and features of the proposed plant site including all
existing structures. The Contractor shall furnish the Owner a copy of the study for its review and
reference, in case the Contractor opted to do so
Notification

The Contractor shall notify the Owner of his intention to undertake any site investigation and
submit details of the proposed methods and tests to the Owner before commencing work

SECTION 4

SITE CONSTRUCTION

4.1 Temporary Construction Facilities

Site Security during Construction

The Contractor shall provide appropriate security arrangements to protect the site from
malicious or accidental damage or loss throughout the construction and commissioning
Notification

The Contractor shall notify the Owner of his intention to undertake any site investigation and
submit details of the proposed methods and tests to the Owner before commencing work

SECTION 3

TOPOGRAPHICAL SURVEY

General

The Topographical Survey Report can be requested from the owner. This Supplementary
Information of the Bidding Document provides site data and information to serve as reference of
the Contractor for the project’s civil works final design. Similarly, the Contractor could opt if
deemed necessary, and at his own cost, to perform additional topographical survey to
investigate the topographical profiles and features of the proposed plant site including all
existing structures. The Contractor shall furnish the Owner a copy of the study for its review and
reference, in case the Contractor opted to do so

Notification

The Contractor shall notify the Owner of his intention to undertake any site investigation and
submit details of the proposed methods and tests to the Owner before commencing work
SECTION 4

SITE CONSTRUCTION

4.1 Temporary Construction Facilities

Site Security during Construction

The Contractor shall provide appropriate security arrangements to protect the site from
malicious or accidental damage or loss throughout the construction and commissioning
mmissioning