Concrete Pouring of Footing Foundation

4Bagger Mixer Output = 15 m3/hr

Volume of Footing Foundation t be concrete poured = 210 m3

Time Comparison

No. of Hours of Concrete Pouring using C3 Pump Mixer = 14Hrs + 2 Hrs (Finishing) = 16 Hrs (almost 2 Shift)

No. of Hours of Concrete Pouring by Sahara = 4 Hrs

Manpower Needed Using 4-Bagger Mixer

1 - Foreman @ P 700/shift for 8hrs = P 700 x 2 shifts = P 1,400.00

2 - Mason @ P 600/shift for 8hrs = P 600 x 2 shifts = P 1,200.00

2 - Steel Man as Cement Bagger @ P 550/shift for 8hrs = P 550 x 2 shifts = P 1,100.00

2 - Steel Man as Sand Loader @ P 550/shift for 8hrs = P 550 x 2 shifts = P 1,100.00

2 - Steel Man as Gravel Loader @ P 550/shift for 8hrs = P 550 x 2 shifts = P 1,100.00

2 - Steel Man as Finisher @ P 550/shift for 8hrs = P 550 x 2 shifts = P 1,100.00

2 - Steel Man as Line Pump @ P 550/shift for 8hrs = P 550 x 2 shifts = P 1,100.00

2 - Labor for Concrete Vibrator @ P 500/shift for 8hrs = P 500 x 2 shifts = P 1,000.00

1 - Mixer Operator @ P600/shift for 8hrs = P 600 x 2 shifts = P 1,200.00

1 - Loader Operator @ P700/shift for 8hrs = P 700 x 2 shifts = P 1,400.00

Total Labor Cost c/o VRB = P 11,700.00

Material Cost Comparison

* Using C3 Mixer
CEMENT MIXING RATIO: 1:2:3
To produce a cubic meter of 4000 psi concrete, you have to to adjust
the concrete mixing ratio to: 1659
277 kg of cement
553 kg of sand
830 kg of gravel SAY:
Price of Cement per bag ₱ 500.00
therefore total required; Price of Sand per cbm ₱ 800.00
in KGS ` ` Price of Gravel per cbm ₱ 900.00
CEMENT 58,170 kg CEMENT 1,454 per 40-kg bag Price of Bostik per pc ₱ 35.00
SAND 116,130 kg SAND 77 cbm COST ESTIMATES:
GRAVEL 174,300 kg GRAVEL 112 cbm
ADMIX 1,454 pcs (consider BOSTIK) CEMENT ₱ 727,125.00
Note: SAND ₱ 61,936.00
Density of Cement 1440 kg/m3 GRAVEL ₱ 101,206.45
Sand Density 1,450 - 1500 kg/m3 ADMIX ₱ 50,898.75
Density of Aggregate 1,450-1550 kg/m3 TOTAL PRICE ₱ 941,166.20

* Sahara Price of 4000psi @ 28days = P 5,100/m3

= P 5,100/m3 x 210m3 = P 1,071,000.00

Saving if we use C3 Mixer = P 129,833.73

However, 100% compressive strength is not achievable because of material mix is not fully calibrated. Quality
might be sacrificed unlike if it is batch by Sahara mix, they are responsible for the attainment of 4000psi
compressive strength.

By Sahara, concreting will just take 4-5hrs

By C3 Mixer (4bagger) it will take 14 - 16 hrs


TO : Sir Jerry, Sir Jerome
SUBJECT : Comparative Analysis of Ready Mix Concrete and Site Mixed Concrete

Foundation should be stable and expected to withstand huge amount of loadings, if the design
is ok but the implementation and execution of work is not in accordance to good engineering
practice then failure might occur specially on compressive strength. This is risky when we
are talking of structural stability and integrity, we don't need to sacrifice because in the end
what we expect is its reliability and rigidity, thus a lifetime structure that will carry heavy
loadings of chemical products. Always expect the worst case scenario.

Factor Being
Ready-Mix Concrete Site-Mixed Concrete
Considered
Consistent quality, Mix batch
Continuous supervision is for consistency
Quality/ of sand/gravel calibrated thru
among batches. Setting time may vary due to
Consistency weighing scale as well as the
inconsistency affecting the quality.
water/cement ratio
Difficult to attain once we overlooked the
Required compressive strength
mixture affecting the required compressive
of 4000psi is definitely
Criticality/ strength 4000psi. Note: This is highly Class
attainable and certified. Should
Accountability A structures so we should follow what is
there be any failure we can
required as plan in accordance to engineering
have them accountable
standards
Delivered ready to use and less Slower process due to multiple steps,
Time
time-consuming. formulas and the setting time.
Does not require equipment at Requires a weigh batch mixer to make
Equipment
the construction site. concrete on-site.
Requires a controlled storage space, to
Storage Does not require additional
manage and protect materials like cement
Requirements storage space for raw materials
and aggregates
Material waste at the site is There is some material loss during storage
Waste
minimal and mixing
Skilled labor is required only to Requires more man-hours to prepare
Work force
pour and compact the concrete. concrete at the project site.
Requires a suitable access for Requires space for material storage and
Space
the concrete mixer truck. batch mixers.