Professional Documents
Culture Documents
Activity 1 can start immediately and has an estimated duration of three weeks.
Activity 2 can start after activity 1 is completed and has an estimated duration of
three weeks.
Activity 3 can start after activity 1 is completed and has an estimated duration of
six weeks.
Activity 4 can start after activity 2 is completed and has an estimated duration of
eight weeks.
Activity 5 can start after activity 4 is completed and after activity 3 is completed.
This activity takes four weeks.
1 -- 3
2 1 3
3 1 6
4 2 8
5 4,3 4
Network Diagram
1. A1 A2 A4A5 = 18weeks. here we got the total duration of path by adding
the duration of all activities such as A1, A2, A4, A5 (3 + 3 + 8 + 4) = 18.
Questions:
Critical Path: The critical path is the longest path through the network diagram
and establishes the shortest time to complete the project. The total float of every
activity in the critical path is zero.
Float: Float is also known as total float its nothing but how long an activity can be
postponed, without delaying the project completion date. On the critical path, the
total float is zero. Total float is often known as slack.
Total float = Late Start time (LST) – Early Start Time (EST)
and
8 6 14
The slack time of Activity 3 = 5 without delaying the completion of the project.
Total float = Critical path – longest Path of Activity 3 which is (18 – 13 = 5).
and
3 A2 6 Float = 0
3 3 6
Total Float of Activity 2 (A2) = LST- EST which is (3 - 3 = 0).
and
Here as the Activity 2 (A2) is in the Critical Path, the float for Activity 2 is zero. Where
the float in the Critical path is always Zero.
The critical path is the longest path through the network diagram, i.e. a sequence
of activities that defines the validity of the start and end dates of the project and
has no slack time which means the float is always “zero” in critical path.
But from the network diagram above we observed that the second route A1, A3,
A5 is not a critical route, which means that it has a slowdown time of 5 weeks
compared to the critical route. In this diagram, activity 3 is delayed by 5 weeks
from the completion of the first A1 activity. But here it did not cause any
difference or delay in completing the project, as both A3 and A4 activities were
completed within the 14th week
Float of the path (A1A3A5) = duration of the critical path – duration of path
Which means (18 – 13) =5
Where Duration of critical path= 18.
Duration of second (non-critical path) = 13.
Acc