HOME PRACTICE

A DRAW CPM DIAGRAM AND IDENTIFY CRITICAL PATH


Activity Preceding Activity Time Days

A Nil 2
B Nil 3
C A 4
D B 6
F B 9
E C,D 5
G E,F 3

B.DRAW CPM IDENTIFY CRITICAL PATH


Activity Preceding Time Days
A Nil 2
B Nil 3
C A 3
D A 4
E B 5
F B 2
G C 4
H D,E 6
I D,E 3
J F 4
K G,H 5
L I,J 3
M K,L 3
D Following is the work break down structure of a project
Activity code Activity Description Preceding activity Time(days)
A Implementation plan Nil 2
B Team formation Nil 2
C Office set up Nil 2
D Procurement of A 3
recycling plant
E Construction work A 4
G Training of project B 7
staff
H Complete B 6
procurement of
machines
I Complete waste D,E 4
recycling plant
J Complete cable C 10
fittings
K Complete installation H,J 3
L Trial run and G,I,K 4
handover

Draw a CP diagram and identify the critical path showing all the slack activities
(may require dummy activity, more than one critical path can come).