300266 Project schedule submitted/Drawing – waiting for
Project dept
OXYDENTAL approval from client
2 300266
70% materials has been procured Project dept Before production
OXYDENTAL
3 Level switch received – arrived in ACE ENGG. Bring it
300231 T LAB Project dept 1 DAY
to RAK
4
300231 T LAB Roof leak test must be done QAQC 1 DAY
5
300231 T LAB As built drawing to submit ENGG DEPT 1 DAY
6
300231 T LAB Punch point clearance to be done Production dept 1 DAY
7 300181 SAGAR
Cable cutout size required ENGG DEPT Soon
SAMARAT
16 Production dept
300256(UES) Production activity behind schedule
17 Projects dept
300256(UES) Man hour report to be received from production
18 Projects dept
300256(UES) Planed delivery date as per schedule – 17‐11‐14
19 Projects dept
300260 Painting system yet to be confirmed
20 300245 ONGC
Projects dept 17‐11‐14
Free issued material will be received on 17‐11‐14
21 300245 ONGC Free issued materials (FIM) delivery date has been
delayed by client. Update the same FIM issue date in Projects dept Soon
schedule and submit the same to client
22 300245 ONGC
All Fabrications drawings are issued for production Projects dept
28 300244 ‐ C220kVa
Retesting to be done on 16‐11‐14 Project Dept
29 300244 ‐ C220kVa
Ventilation space must be increased as per required Project Dept
31 300244 ‐ C220kVa
Dispatch to be done on 17‐11‐14 Project Dept
32 Petrofac ‐ 300221
As built drawings to be submitted ENGG DEPT Before delivery
33 Petrofac ‐ 300221
Punch point clearance in progress. Production dept
34 Petrofac ‐ 300221
Photos need to be sent to client Project Dept
38 300241‐ GYM
container Panel work in progress Production dept
40 300235‐NMPJ
Canopy arrival today Project dept
41 300270
Electrical work separate job – Check Electrical Dept
42 Office container
Job no and budget need to be added in Server Project dept
43 General
Safety and electrical dept must shift upstairs – Bay2