Task Description TIME EARLIEST LATEST SLACK

S 0
A Design 10
B Forecast 14
C Survey 3
D Price 3
E Schedule 7
F Costout 4
G Train 10
FIN 0

PRECEDENCE RELATIONS:
BEFORE AFTER BEFORE AFTER
Design Forecast S A
Design Survey A B
Forecast Price A C
Forecast Schedule B E
Survey Price B D
Schedule Costout C D
Price Train E F
Costout Train D G
F G
G FIN