Vessel: XXXXXXXXX
12 December 2012
13 December 2012
14 December 2012
Bill of Lading:
Gross: 500,005 Bbls at 60F Net: 495,005 Bbls at 60F S&W: 1.00%
Stowage in 1 P/S, 2 P/S, 3 P/S, 4 P/S, 5 P/S & 6 P/S cargo tanks
500,450 Bbls at 60F at API 39.4 (as tested from the inspection company) and avg.temp 66.5 deg F
Stowage in 1 P/S, 2 P/S, 3 P/S, 4 P/S, 5 P/S & 6 P/S cargo tanks
ROB : NIL
Shore tanks used were T-10, T-12 and T-15. The floating roofs on both shore tanks were clearly afloat before and after the
delivery, standing pipes were slotted.
The shore line used was the 16” Crude Oil Sea line was used for the loading operation, length about 1 mile, capacity approx
1305 Bbls.
Line displacement conducted on our request. A slack line of 51 Bbls was detected which within tolerance.
DD. ISSUES
Delays:
Vessel waited from 12/01:00 to 12/08:00 for surveyors to come on board for sampling and cargo analysis.
-Direct delays
Surveyors issued a Letter for Apparent discrepancy between B/L and vessel figures