Name of work:
1. Constn. of RCC Bridge of span 3x35.00 = 105.00M over river Khowai at Ch. 0.75 Km on
the road from Seoratali to Paharmura under Khowai Block.
2. Constn. of RCC Bridge over river Khowai on the road from Teliamura(Dasamighat) to
Baishgharia under Teliamura Block (Span- 140 M)
3. Replacement of existing causeway over localcherra by RCC bridge on the road from TA
road to Khasiamangal at ch. 1.00 km to 2.00 km.
4. Construction of RCC bridge over river Howrah on the road from Champaknagar to
Bridhibazar via. Balram thakur paraat ch. 0.20 Km.
5. Construction of RCC permanent Bridge over river Cicima (Chainage 1.20 km) on road
from Karaiban(NH 44) Jarulbachai.
Now, if we look at the progress of each project as upto date, it can be seen that work No.
3,4,5 is executed and completed in all respect by the agency and work no. 2 is almost 90%
complete. But if we look at work no. 1, i.e RCC bridge at Seoratali, it is found that work is
suspended since 2011. DPR for the work was approved by the department on October, 2010, with
DPR value Rs. 10,00,90,113.00. As per the clause 9 of MoU, date of completion was October,
2012. A long period of almost 09(Nine) years has already lapsed in between, and till date the work
is merely a negligible percentage complete. After casting one no. abutment well and one no. pier
well upto 7.20 mt. each, agency suspended the work and till today and failed to resume the work.
/conversion/tmp/scratch/485310550.doc
On carefully studying the MoU, it is found that there are 2 (Two) provisions kept for rescind
and termination of work vide clause 11 (iii) and clause 11(iv).
As per clause 11 and its subsequent clauses of MoU, the agency M/S. Simplex Projects
Limited, had already been asked to deposit Rs. 1,00,09,011.00 (Rupees One crore Nine thousand
Eleven) only as vide this office letter No. F 5(84)/EE/TLM/26-29, dated 15/04/2020 (Copy
enclosed) which is yet to be adjusted.
Considering present situation, it is understood that the agency is not interested/unable to
execute the work of Seoratali Bridge in near future.
As such, it is proposed to rescind/terminate the work as per clause of MoU for the interest of
the work.
All related documents/correspondences are placed in file with seriatim.
Recomendation of the competent authority is required.
(Er. M. K. Das)
Executive Engineer, PWD(R&B)
Teliamura Division.